36C78619Q0011-003.pdf
PDF 572 KB Posted
- Attached to
- FY19 New Contract - Cemetery Grounds and Facilities Maintenance Service - Dayton National Cemetery
- Solicitation number
- 36C78619Q0011
About this file
36C78619Q0011 36C78619Q0011 DNC PWS FY19 Grounds and Facilities Maintenance.pdf
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C78619Q0011-0004000.docx | DOCX document | |
| 36C78619Q0011-0003000.docx | DOCX document | |
| 36C78619Q0011-0002000.docx | DOCX document | |
| 36C78619Q0011-0001000.docx | DOCX document | |
| 36C78619Q0011-002.pdf | ||
| 36C78619Q0011-000.docx | DOCX document | |
| 36C78619Q0011-001.pdf | ||
| 36C78619Q0011-004.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Department of Veterans Affairs Dayton/Camp Chase National Cemetery National Cemetery Administration Performance Work Statement
General Information
a) Title of Project: Cemetery Grounds and Facilities Maintenance Services
b) Scope of Work: The contractor shall provide all resources necessary to accomplish the deliverables described in this Performance Work Statement, except as otherwise specified.
a) This is a service contract for cemetery grounds and facilities maintenance services at the Dayton National Cemetery, Dayton, OH and Camp Chase Confederate Cemetery, hereafter referred to as “Cemetery.” The overall responsibility of the Contractor is to plan, coordinate, organize, manage, and perform the activities described herein, which are required to maintain an acceptable appearance of the cemetery grounds and facilities.
b) National cemeteries are a resting place for our nation's heroes and as such, the standards for management, maintenance and appearance of these cemeteries have been established by the National Cemetery Administration to reflect this nation's concern and respect for those interred there. The National Cemetery Administration (NCA) mission: the NCA honors veterans with a final resting place and lasting memorials that commemorate their service to our nation.
c) Background:
a) The Dayton National Cemetery is located at 4400 West Third Street, Dayton, OH 45417. The phone number is (937) 268-2221. The Camp Chase Confederate Cemetery is located at 2900 Sullivant Ave, Columbus, OH 43204. There is no phone or cemetery employees at Camp Chase Confederate Cemetery, it is a closed cemetery dating back to the 1860’s.
b) Dayton Site features consist of preset and conventional casket sections and cremation burials.
Camp Chase Site only consists of conventional caskets.
c) The Dayton National Cemetery comprises 106 acres of land. Camp Chase Confederate
Cemetery consists of 1.8 acres.
d) Dayton Site features include a main entrance with floral beds, administration building, maintenance building, 2 committal shelters, columbarium with floral beds, extensive landscaping with turfgrass, trees, shrubs and ground cover. Camp Chase Site is the cemetery, surrounding stonewall and a rostrum.
e) National Cemeteries are National Shrines. The standards of maintenance and appearance at these cemeteries must reflect this nation's concern for those interred there. For this reason, strict adherence to the specifications is required as well as National Cemetery Administration standards.
d) Performance Period: The term of this contract shall be for a period from October 1st, 2018 through
September 30, 2019 plus 4, One-year options, if exercised. Contractor shall submit an invoice at the end of each month. Delivery of all items under this contract is FOB Destination and is subject to inspection and acceptance by the NCA Contracting Officer’s Representative (COR).
e) Type of Contract: Firm Fixed Price
B. Contract Award Meeting
a) The contractor shall not commence performance of the tasks in this Performance Work Statement until the contracting officer has conducted a “kick-off” meeting or has advised the contractor that a “kick-off” meeting is waived.
C. Specific Mandatory Tasks and Associated Deliverables:
a) Description of Tasks and Associated Deliverables: The contractor shall provide the specific deliverables described below within the performance period stated in Section C thru F and Attachments A thru N of this Performance Work Statement.
b) NCA Standards and Measures:
a) Standard 6.1: Daily grounds maintenance activities do not detract from the dignity and solemnity of the cemetery.
(1) Measure 6.1: The number of complaints that are received because of operations, noise, equipment, etc. that intruded on the visitor’s experience.
(2) Target 6.1: 0 complaints.
b) Standard 6.2: All areas where cemetery operations have been conducted are neat, clean and free of debris and equipment at the end of the workday.
(1) Requirement 6.2a: Debris, equipment, tools and supplies are removed at the conclusion of each task or at the end of the workday.
(2) Requirement 6.2b: Roads, walkways, shelters and burial sections are free of grounds maintenance debris by the end of the workday.
(3) Target 6.2: 100% compliant.
c) Description of Services:
a) The contractor shall provide all personnel, equipment, tools, supplies, supervision, and other items and services necessary to ensure that total cemetery maintenance is performed at Dayton National Cemetery and Camp Chase Confederate Cemetery in a manner that will maintain healthy grass, trees, shrubs, and plants and present a clean, neat, and professional appearance throughout.
b) Services include, but are not limited to maintenance of grounds and facilities, regular mowing, trimming, edging, removal of leaves and debris, as well as, sweeping roads and sidewalks, maintenance of gravesites and headstones, and the alignment and washing of headstones, headstone maintenance, turf maintenance, irrigation system maintenance, plant and tree maintenance, planting bed maintenance, sunken grave or cremains repair and trash removal.
c) All work will be done during normal Federal workdays. Contractor shall accomplish all work in accordance with the technical specifications that have been provided as Attachments A through N to this solicitation. Overall work will conform to the NCA Operational Standards and Measures.
d) The Contractor shall be responsible for:
(1) Grounds and Facilities Maintenance; Grounds Maintenance Services Dayton National Cemetery to include mowing, trimming and edging, pesticide and herbicide, irrigation winter shut down and spring start-up.
Grounds Maintenance Services for Camp Chase National Cemetery to include mowing, trimming and edging, pesticide and herbicide, trash and storm damage clean-up, snow and ice removal, leaf removal, turf maintenance over seeding, repair sunken graves, raise and realign/bump and run headstones, pressure wash headstones, markers, wall, entry column, archway.
(2) Turf Maintenance, Dayton and Camp Chase; Fertilization; Soil Testing; herbicide applications, including spot spraying. Another pest Control as required. Aeration, overseeding, and maintaining and adjusting grade as required.
(3) Irrigation System Management, Dayton; seasonal startup and shutdown.
(4) Gravesite Maintenance; Sunken grave Repair (Camp Chase only). Repair of damaged turf. Mowing and trimming of gravesites (Dayton and Camp Chase).
e) Provide a safe working environment for Contractor, cemetery staff and general public.
f) Ensuring all work conforms to the NCA’s established National Standards.
d) Standards of Employee Conduct:
a) Contractor and Contractor personnel shall be required to adhere to the following standards of dress and conduct while performing work in the National Cemetery. These standards and regulations are enforceable under Title 38, U.S.C., Part I, Chapter 9, Section 901.
(1) Be fully clothed at all times in matching uniforms, to include long slacks or pants and shirt, buttoned up from neck to waist. Clothing shall be clean each day. Any soiled clothing should be cemetery work-related that day. T-shirts and/or tank tops and short pants as outer garments are prohibited. Shoes/boots will have no holes or loose soles. Steel-toed shoes or equivalent will be required in accordance with OSHA requirements. Contractor employees will maintain personal hygiene.
(2) Shall not engage in loud or boisterous behavior or use profane or abusive language. Shall show proper reverence during committal services.
(3) Shall neither eat nor drink beverages (except water or non-alcoholic drinks) in the work areas, nor in sight of committal shelter during a service. Use of intoxicating beverages and/or drugs is strictly prohibited.
(4) Contractor personnel shall not lean, sit or stand on or against headstones or monuments.
No tools, equipment or other items will be placed or leaned on headstones or monuments.
(5) The only designated smoking area for contract personnel of the Dayton National Cemetery is located by the maintenance building. All other areas are designated as NO
SMOKING.
(6) Contracted personnel are required to report the damaging of any cemetery facility, equipment, grounds or headstones to the COR as soon as occurs.
e) Parking and VA Regulations:
a) Contractor employees may park privately owned vehicles in the area designated for parking by the COR. It is the responsibility of the Contractor to ensure his employees park in the appropriate designated parking areas. Smoking is prohibited inside any buildings at the
Cemetery. Possession of weapons is prohibited. Enclosed containers, including tool kits, shall be subject to search. Violations of VA regulations may result in citation answerable in the United States (Federal) District Court, not a local district, state, or municipal court.
b) All contractor personnel operating vehicles on government property must possess a valid state driver’s license.
f) Use of Cemetery Facilities:
a) The Government shall not be responsible for any loss, damage, or theft of Contractor items.
Contractor shall be responsible for acceptable standards of housekeeping and custodial maintenance of Cemetery facilities used by Contractor's employees.
b) The Government will not furnish a storage building at the cemetery site for use by the
Contractor to store supplies and equipment. The Government will not be responsible for any damage to or loss of the Contractor's equipment and supplies stored on the Government's premises. The Contractor shall be responsible for maintaining fire extinguishers and other safety equipment.
c) The Contractor will be responsible for safely storing any chemicals, pesticides, herbicides, cleaning solutions, etc. in accordance with manufacturers recommendations. An SDS (Safety Data Sheet) is required for all chemicals, with a copy provided to the COR, pesticides, herbicides and cleaning solutions. Additionally, copies of pesticide applicators license (if required) will be provided to the COR.
d) Electricity and phone service will NOT be furnished by the Government for the contractor’s work area. However, government will provide all electricity and water used on and for the cemetery facility.
e) Contractor employees will not be allowed to use cemetery staff or public restrooms. Contractor must provide restroom facilities for their employees.
g) Inspection and Cleaning of Cemetery Facilities:
a) The Contractor will perform a weekly inspection. During this inspection the appearance of the cemetery will be observed, and any deficiencies noted within the scope of the contract will be corrected as soon as practicable. Items that need correcting outside the scope of the contract will be reported to the Contracting Officer or his representative (COR).
b) The Contractor will be required to submit daily inspection reports/checklists and work accomplished to the Contracting Officer Representative weekly. The Contracting Officer Representative is located at Dayton National Cemetery, Dayton, OH for both locations. The inspection forms/checklists shall be provided to the Contractor.
h) Performance Evaluation Meeting
a) The issuance of a Contract Discrepancy Report (CDR) may be cause for the scheduling of a meeting among the Contractor, Contracting Officer, and the Contracting Officer Representative. A mutual effort will be made to resolve all problems identified. The Government will prepare written minutes of the meeting. The Contractor, Contracting Officer, and the Contracting Officer Representative will sign minutes of the meeting (s).
b) Should the Contractor not concur with the minutes, he will state in writing to the Contracting
Officer within ten calendar days any areas he does not concur and explain the reasons for non-concurrence. The Contracting Officer will review and consider the reasons submitted for the Contractor's non-concurrence and make a decision. The Contracting Officer will notify the Contractor of the decision in writing within ten calendar days.
i) Actions
a) Normally, the Contracting Officer Representative will verbally advise or give a written inspection report to the Contractor of discrepancies the first time they occur and ask the Contractor to correct the problem. A notation will be made on the COR checklist of the date and the time the deficiency was discovered and the date and time the Contractor was notified.
b) If the Government created any of the discrepancies, these will not be counted against the Contractor's performance. When the Government has caused the Contractor to perform in an unsatisfactory manner, a letter must be written to the responsible organizational element requesting corrective action is taken.
c) When the Contractor is not meeting the limits of satisfactory performance, a CDR will be issued to the Contractor. The seriousness of the failures should govern whether to issue CDR at the end of the period, or as soon as the limits of satisfactory performance are exceeded.
d) When a CDR is issued for a service, the Contracting Officer must deduct from the periodic payment, a percentage of that payment as indicated in the Service Delivery System (SDS) as attached hereto.
e) If the Contractor does not achieve satisfactory performance by the end of the next period or agreed suspense date, another CDR will be issued and the appropriate amount deducted from the periodic payment.
f) A third CDR will be the cause for a Cure Notice. However, the Contracting Officer may issue a Cure Notice at any time he/she deems appropriate.
g) Depending on the overall performance of the Contractor, an unsatisfactory reply to the Cure Notice should require a Show Cause letter to be issued, followed by consideration of termination of the contract.
j) Supervision, Work Hours and Training:
a) Project Manager: A competent and experienced “Project Manager” shall be provided by the Contractor for not less than two (2) hours per day whenever work is being performed. In the absence of the Project Manager, the Contractor will appoint a crew foreman or employee who will be responsible to ensure that the work is (i) being accomplished in an expeditious manner,
(ii) performed in accordance with the contract specifications, and (iii) progress is being made without undue delay. The Project Manager must have no less than two (2) years’ experience as a direct supervisor of a commercial construction operation that includes surveying, soil excavation, and site construction in industrial, commercial and/or public sites. The Project Manager will ensure all specifications are being met, ensure contract work does not conflict with ceremonies and funerals, and ensure employees are adequately supervised and proper conduct is maintained. BOTH PROJECT MANAGER AND CREW FOREMAN ARE
REQUIRED TO BE FLUENT IN ENGLISH. AT ALL TIMES DURING THE WORK DAY,
A PROJECT MANAGER OR CREW FOREMAN ARE TO BE PRESENT WITH THE
ABILITY TO MAKE DECSIONS AS NEEDED AT THE DAYTON NATIONAL
CEMETERY AND THE CAMP CHASE CONFEDERATE CEMETERY.
b) Work Hours: Work may be performed between the hours of 7:30 a.m. to 4:00 p.m., Monday through Friday unless otherwise directed by the COR. At the Contractor’s request, and with the written permission of the COR, work may also be permitted to be scheduled for weekends and / or Holidays. In emergency situations caused by the Contractor, or when severe adverse weather prohibits work during the week, the Contractor shall arrange with the COR to work on weekends and/or holidays to meet performance time frames. The Government shall not compensate the Contractor for any alternate work schedules needed for the Contractor to complete all contract work within the specified project duration. No work will be permitted during Memorial Day or Veteran’s Day weekend activities. Notwithstanding, if any work under this contract will be required outside of the VA's normal working hours (7:30 a.m. to 4:00 p.m.
Monday through Friday), the Contractor shall request for a deviation in writing to the COR at least 24 hours in advance. The COR will notify the appropriate individuals regarding Contractor's anticipated schedule and will provide written approval or disapproval to the Contractor.
(1) FEDERAL HOLIDAYS
(a) New Year’s Day (January)
(b) Martin Luther King’s Birthday (January)
(c) President’s Day (February)
(d) Memorial Day (May)
(e) Fourth of July (July)
(f) Labor Day (September)
(g) Columbus Day (October)
(h) Veterans Day (November)
(i) Thanksgiving Day (November)
(j) Christmas Day (December)
c) The Contractor shall be responsible for maintaining satisfactory standards of personnel conduct and work performance and shall administer disciplinary action as required. The Contractor shall remove employees for cause, to include, but not limited to, misconduct in performance of duty under these specifications and/or conduct contrary to the best interests of the Government.
d) The Contractor shall also be responsible for training and safety precautions for Contractor employees performing work under these specifications. OSHA standards shall be observed by the Contractor in all work performed. Appropriate safety equipment shall be furnished by the Contractor to Contractor personnel and shall be used as prescribed by OSHA standards, including hard hats, safety shoes, safety glasses, and hearing protection devices. The following OSHA and NFPA standards and codes are to be adhered to:
(1) National Fire Protection Association (NFPA): 10-1998 Standard for Portable Fire
Extinguishers
(2) Occupational Safety and Health Administration (OSHA) 29 CFR 1910 Safety and Health
Regulations for Personal Protection, Safety Color Codes, Portable Power Tools, Electrical Safety and Portable Electric Equipment.
(3) Site and Building Access: Maintain free and unobstructed access to facility emergency services and for fire, police and other emergency response forces in accordance with NFPA 241.
k) Work Scheduling and Maintenance During Cemetery Functions:
a) The Contractor shall coordinate a work schedule with the COR(s) daily to ensure that no work is being performed at the immediate site of a scheduled interment. These daily meetings are also an opportunity for the Contractor to ask questions and ensure he/she understands the off-limit areas, which may vary, depending on the event. Contractor personnel shall not operate motorized equipment or conduct other commercial activities during interment services. The COR or his/her representative shall furnish the Contractor with a schedule of all interments and/or ceremonies no later than the close of business of the day prior to the scheduled internment, and a minimum of three (3) days before any ceremonial events. The Contractor is solely responsible for ensuring that no contract work causes any funeral, ceremony, procession or visitation to be delayed, altered, or otherwise impacted in such a way that the dignity or security of the event is compromised. The Contractor is solely responsible for staying abreast of all such upcoming events and when in doubt, he/she must ask the COR(s). The Contractor shall meet with the COR at the end of each day to determine work completed and ensure that work is on schedule. In the absence of the COR, the Contractor shall meet with the Alternate
COR.
l) Historic Preservation:
Where the Contractor or any of the Contractor's employees, prior to, or during the service work, are advised of or discover any possible archeological, historical and/or cultural resources, the Contractor shall immediately notify the COR verbally, and then with a written follow up.
D. Schedule for Deliverables
a) If for any reason any deliverable cannot be delivered within the scheduled time frame the contractor is required to explain why in writing to the contracting officer, including a firm commitment of when the work shall be completed. This notice to the contracting officer shall cite the reasons for the delay, and the impact on the overall project. The contracting officer will then review the facts and issue a response in accordance with applicable regulations.
b) Contract period will consist of a base period from October 1, 2018 through September 30, 2019, with four one-year options to extend the term of the contract through September 30, 2023. Units and services to be in accordance with Performance Work Statement, attached technical specifications, and the terms and conditions contained in this solicitation.
Schedule of Deliverables
E. Changes to The Performance Work Statement
a) Any changes to this Performance Work Statement shall be authorized and approved only through written correspondence from the contracting officer. A copy of each change will be kept in a project folder along with other products of the project. Costs incurred by the contractor through the actions of parties other than the contracting officer shall be borne by the contractor.
F. Reporting Requirements
a) The Contractor shall meet with the Contracting Officer’s Representative (COR) at the end of each day to determine work completed and ensure that work is on schedule. In the absence of the COR, the Contractor shall meet with the Alternate COR. The COR shall require documentation of headstones installed, sunken grave, etc. on forms or checklists provided by the COR.
b) The contractor is required to provide the COR with monthly written progress reports. These are due to the COR by the second workday following the end of each calendar month throughout the project’s duration. The COR is required to provide monthly progress reports to the contracting officer.
c) The progressive report shall cover all work completed during the preceding month and shall present the work to be accomplished during the subsequent month. This report shall also identify any problems that arose and a statement explaining how the problem was resolved. This report shall also identify any problems that have arisen but have not been completely resolved with an explanation.
G. Government Responsibilities
a) The Government will provide a staging area on site for contractor storage unit (conex box) at
Dayton National Cemetery only. Camp Chase Confederate Cemetery does NOT have a storage area available and the contractor will have to bring and remove all needed tools and equipment daily.
b) The Government will not be responsible for any loss, damage, or theft of Contractor items.
Contractor shall be responsible for acceptable standards of housekeeping and custodial maintenance of Cemetery facilities used by Contractor's employees.
c) The Government will not furnish a storage building at the cemetery site for use by the Contractor to store supplies and equipment. The Government will not be responsible for any damage to or loss of the Contractor's equipment and supplies stored on the Government's premises. The Contractor shall be responsible for maintaining fire extinguishers and other safety equipment.
d) The Contractor will be responsible for safely storing any chemicals, pesticides, herbicides, cleaning solutions, etc. in accordance with manufacturers recommendations. An SDS (Safety Data Sheet) is required for all chemicals, pesticides, herbicides and cleaning solutions.
e) Electricity and phone service will NOT be furnished by the Government for the contractor’s work area. However, government will provide all electricity and water used on and for the cemetery facility.
H. Contractor Experience Requirements
a) Offers will be considered only from contractors who are regularly established in the business called for and who in the judgment of the Contracting Officer are financially responsible and able to show evidence of their reliability, ability, experience, equipment, facilities and personnel directly employed or supervised by them to render prompt and satisfactory service. All services are expected to be performed by competent technicians, trained and qualified to complete the specific services required. All work performed shall be done in a first-class manner and in accordance with good commercial practices.
b) Contractors must provide evidence of their experience and ability to perform the tasks describe in this Performance Work Statement.
a) Performing grounds maintenance activities in a high-profile environment.
b) Operation of equipment in the vicinity of headstones.
I. Confidentiality and Nondisclosure
It is agreed that:
a) The preliminary and final deliverables and all associated working papers, application source code, and other material deemed relevant by VA which has been generated by the contractor in the performance of this task order are the exclusive property of the U.S. Government and shall be submitted to the contracting officer at the conclusion of the task order.
b) The contracting officer will be the sole authorized official to release verbally or in writing, any data, the draft deliverables, the final deliverables, or any other written or printed materials pertaining to this task order. No information shall be released by the contractor. Any request for information relating to this task order presented to the contractor shall be submitted to the contracting officer for response.
c) Press releases, marketing material or any other printed or electronic documentation related to this project, shall not be publicized without the written approval of the contracting officer.
J. Operations During Cemetery Functions
Contractor personnel shall not operate motorized equipment or conduct other commercial activities within a designated area during interment services. The COR will identify the designated area. The COR or his/her representative will furnish the Contractor with a schedule of all interments and/or ceremonies no later than the close of business of the day prior to the scheduled interment, and a minimum of three (3) days before any ceremonial events.
H. Contractor’s Responsibilities and Insurance Requirements
The Contractor shall obtain all necessary licenses and/or permits required to perform this work. The Contractor shall take all precautions necessary to protect persons and property from injury or damage during the performance of this contract. The Contractor shall be responsible for any injury to himself, his employees, or others, as well as for any damage to personal or public property that occurs during the performance of this contract that is caused by his or her employees’ fault or negligence. Further, it is agreed that any negligence of the Government, its officers, agents, servants and employees, will not be the responsibility of the Contractor hereunder with the regard to any claims, loss, damage, injury, and liability resulting there-from. The Contractor shall maintain workmen’s compensation, personal liability, automobile liability, and property damage insurance, as prescribed by the laws of the state of Ohio, and in accordance with FAR 52.228-5. Evidence of coverage is required before commencing work under this contract (copy of Certificate of Insurance), and it may not be changed or cancelled without thirty calendar days prior written notice to the Contracting Officer.
I. Damage to Government property
The Contractor shall be responsible for repair or replacement of any contractor damaged cemetery structure, to include: turf, curb, road pavement, headstones or markers, valve boxes, grid monument control markers, trees, plant beds, etc., which are chipped, marred, damaged and/or ruined at the fault of the Contractor and shall bear all costs associated with replacement and reinstallation. Any such damage shall be brought to the immediate attention of the appointed Contracting Officer’s Representative (COR) prior to repair/replacement/installation. The Contractor shall be responsible for cleaning cemetery structures, headstones, monuments, and roadways that are soiled or stained because of Contractor’s performance. The Contractor shall wash-down with water all soiled or stained structures, headstones, and monuments at the end of each workday. Roadways shall be cleaned with a street sweeper each day, as needed, to keep the existing roads free from dirt and mud resulting from all operations. No hazardous chemicals shall be used at any time on Government property. The Contractor shall bear all costs associated with washing and cleaning. Any such washing/cleaning shall be brought to the immediate attention of the COR prior to washing/cleaning.
At the end of each day the Contractor shall remove all debris from the cemetery site resulting from the work. The Contractor shall ensure always that rubbish and trash generated by the Contractor is kept clear of vehicular and pedestrian traffic throughout the site. The Government will not provide receptacle(s) for disposal of debris related to this contract. The Contractor will be permitted to place his trash receptacle dumpsters in the COR approved “Contractor Staging Area”.
Adequate warning devices, barricades, guards, flagmen or other necessary precautions shall be provided by the Contractor at work site to eliminate hazards and for the protection, safety, and warning of all public visitors, pedestrians, cemetery employees, and vehicular traffic within the area.
The Government may undertake or award other contracts for additional work at or near the site of work for this contract. The Contractor shall fully cooperate with any other contractors and with Government employees and shall carefully adapt scheduling and performance of work, and needing any direction, it will be provided by the COR(s). The Contractor shall be responsible for reporting to the COR(s) any problems or questions that may arise with any other personnel on site during the period of performance of this contract. The Contractor shall not take it upon him or herself to resolve any problems or issues with other on-site contractors or employees, but rather shall leave it to the COR(s) to resolve the issue.
The Contractor (including his or her employees, subcontractors, consultants or the like) shall not operate trucks, tractors, and other heavy equipment on any turf area except as provided in this contract to perform work or as authorized by the COR. The Contractor shall be responsible for repairing turf damage caused by the Contractor‘s equipment and staff at no additional cost to the Government.
H. Safety
Matters related to safety, and any actions of the Contractor, shall meet all safety requirements of the COR, Safety Officer, Department of Veterans Affairs, OSHA, and the State. It is incumbent upon the Contractor to be familiar with these requirements. "Safety" shall also include the Contractor having a safety representative who maintains regular and routine contact with the Safety Officer at Dayton National Cemetery.
I. Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements
The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workmen, the Contractor shall trim those limbs or branches with a clean cut and remove and properly dispose of from the site as defined herein.
The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall immediately notify the COR of any such occurrence and repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.
M. Restoration
Upon completion of contract, deliver work complete and undamaged. Existing cemetery features (lawns, paving, roads, walks, etc.) disturbed or removed because of performing required new work, will be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work. All restoration work shall be accomplished without undue delay.
The Contractor shall be responsible for restoration and the Contractor shall bear all costs associated with restoration. Any such restoration to service and repair because of damage caused by Contractor’s workmen/subcontractors to existing cemetery infrastructure shall be brought to the immediate attention of the appointed Contracting Officer’s Representative (COR) prior to restoration.
N. Disposal of Waste
The Contractor shall not dispose of any waste materials at any location on the cemetery premises. All waste materials shall be removed from cemetery property and disposed of in full accordance with local and state requirements at the contractor’s expense.
List of Attachments
ATTACHMENT A: HEADSTONE REALIGNMENT
ATTACHMENT B: IRRIGATION SERVICES – START UP, SHUT DOWN
ATTACHMENT C: HEADSTONE MAINTENANCE AND CLEANING
ATTACHMENT D: LAWN MAINTENANCE: FERTILIZATION, WEED CONTROL
ATTACHMENT E: LAWN MAINTENANCE: SODDING/SEEDING/CORE
AERIFICATION/OVERSEEDING
ATTACHMENT F: LAWN MAINTENANCE: MOWING, TRIMMING & EDGING
ATTACHMENT G: PLANT MATERIAL MAINTENANCE
ATTACHMENT H: GROUNDS REPAIR AND REFILLING OF SUNKEN GRAVE OR CREMAINS
ATTACHMENT I: TRASH AND DEBRIS REMOVAL
ATTACHMENT J: SNOW AND ICE REMOVAL
ATTACHMENT K: PLACEMENT OF FLAGS
ATTACHMENT L: QUALITY ASSURANCE SURVEILLANCE PLAN (QASP)
ATTACHMENT M: WEEKLY INSPECTION REPORTS
ATTACHMENT N: SERVICE DELIVERY SYSTEM (SDS)
ATTACHMENT O: WORK SUMMARY & PROGRESS REPORT
ATTACHMENT P: CONTRACT DISCREPANCY REPORT (CDR)
ATTACHMENT Q: QUALITY ASSESSMENT MONITORING FORM – CUSTOMER
COMPLAINT INVESTIGATION
ATTACHMENT A
HEADSTONE REALIGNMENT (CAMP CHASE ONLY)
A. SCOPE:
1. NCA STANDARD AND MEASURES:
a) STANDARD 4.2: Proper height, alignment, and plumb of each headstone or marker is maintained.
b) MEASURE 4.2: The percent of headstones and markers that are properly aligned.
2. Work shall consist of adjusting alignment of headstones already in place that have shifted out of vertical or horizontal alignment. Fine tuning of headstone alignment, or “Bump and run,” shall be ongoing to keep stones plumb and aligned, and those headstones that are below or above allowable grade shall be fixed to proper height.
B. GENERAL REQUIREMENTS:
1. In areas where smaller than standard size headstones occur (Civil War type), coordinate the measurements, dimensions, and layout of these headstones with COR. Typically the Civil War type headstones are set at 18-20 inches above grade and located by aligning the faces of the headstones along the rows and aligning the centerline of the headstones down the columns. Minor deviations in the less than nominal height is permissible to provide a uniform appearance in the top line to compensate for slight ground rises or depression within a burial section. Where a considerable number of adjacent stones are set or reset in a section, and ground conditions are known to require an allowance for vertical settlement, an extra inch may be permissible in the above ground projection when the stone is initially set.
2. Minor realignment, consisting merely of straightening the headstone, is called fine tuning, or bump and run, and may be accomplished by one person by hand or with a wooden tamping/pry stick, but is usually more efficient with one or two others to sight along headstone rows and columns to guide the adjustment.
3. If a headstone needs to be removed from its socket to adjust its height, it shall not be removed from the gravesite and shall not be left unattended. It shall be removed only briefly so an adequate amount of moistened, crushed limestone can be added to and compacted, or removed from, the bottom of the socket for proper height adjustment, then the headstone shall be replaced.
No more than one headstone shall be removed from its socket at one time in a section.
4. The contractor is responsible to protect headstones from damage or being discolored from contact with dirt, soil or other contaminants during realignment or other maintenance operations.
5. HEADSTONES SHALL NOT BE REMOVED FROM THEIR RESPECTIVE
GRAVESITES.
6. See ATTACHMENT D, HEADSTONE SETTING AND ALIGNMENT for drawing diagrams and layout diagram drawings.
ATTACHMENT B
IRRIGATION SYSTEM START UP, SHUT DOWN (DAYTON ONLY)
A. SCOPE: Work consists of cover spring start-up and fall winterization of diagnostic.
1. DESCRIPTION: The work specified herein shall be provided to facilitate the successful operation of startup in the spring and shutdown in the fall.
WORK NOT INCLUDED UNDER THIS AGREEMENT
a. Maintenance service shall not include the performance of any work required because of improper use, accidents, or negligence for which the contractor is not directly responsible.
b. Underground repairs to piping and wiring are not included in this contract. If such repairs are required, and the COR requests the Contractor to make repairs, said repairs shall be performed and billed under a separate agreement or purchase order.
IRRIAGATION WINTERIZATION:
a. Shut down Irrigation service at street.
b. Contact city water department to inform them water meter is out of service till spring.
c. Completely drain down pump station and meter vault.
d. Evacuate water from main line piping, lateral piping, valves and heads with compressed air.
e. Provide necessary air compressors and hoses.
f. Drain down all flower watering stations connected to irrigation system.
g. While blowing system down visually inspect basic system operation and prepare a maintenance report as needed.
h. Secure central control computer, weather station and all controllers for winter.
i. Warranty system against any freeze damage caused by improper winterization.
j. Access to Toro Sentinel remote radios during winterization.
IRRIAGATION SPRING START-UP:
a. Contact City Water Department to coordinate turning service and meter on, if necessary.
b. Pressurize pump station and bring on-line.
c. Slowly fill mainline to remove all air in pipes.
d. Test all Flower Watering Stations.
e. Test Pump station operations at all flow ranges.
f. Run through entire system, operating each valve one at a time.
g. Visually inspect each zone for proper operation and head adjustment.
h. Make minor adjustments to heads or valves if required.
i. Prepared a maintenance report noting any required repairs or work.
j. Bring central control system on-line and test basic operation, including weather station and pump monitoring systems.
k. Access to Toro Sentinel remote radios during start-up.
l.
ATTACHMENT C
HEADSTONE MAINTENANCE AND CLEANING (CAMP CHASE ONLY)
B. SCOPE:
1. NCA Standards and Measures:
a) Standard 4.1: Headstones, markers, and niche covers are clean, free of debris and objectionable accumulations.
b) Measure 4.1a: 95% of headstones, markers, and niche covers do not show evidence of debris or objectionable accumulations.
2. Work consists of cleaning all headstones as specified by the Contracting Officers Representative
(COR).
3.
4. DEFINITION: “Clean” under this contract means: The headstones will contain NO discoloration due to environmental deposits, mold, mildew, moss, algae, lichen, dirt/mud, grass clippings, grass marks, bird droppings, etcetera.
C. GENERAL REQUIREMENTS: All headstones shall be cleaned prior to Memorial Day and Veteran’s
Day and any other time as determined by the Contracting Officer Representative (COR). The natural surfaces shall be retained. They shall not be painted, white washed or calcimined. Any headstones that have any dirt splash up or grass debris from mowing/trimming will be promptly cleaned when found.
D. HEADSTONE CLEANING PROCESS
a) All in-ground vases, temporary markers, floral, commemorative, or other types of decorations (arrangements) causing interference with the cleaning of the headstones or flat markers operation shall be carefully, and in an orderly manner, moved from and after completion of the work, moved back to all gravesites by the Contractor. Prior to removal, the contractor shall verify the numbering sequence and location of the headstone and associated decorations or vases.
b) Cleaning techniques shall demonstrate a clear understanding of, and the sensitivity to, such environmental issues as ground water contamination, wetlands, etc., and shall be consistent and fully compliant with all applicable Federal, State, and County laws, ordinances and regulations.
(1) “D/2 Biological Solution” is the only authorized cleaner for headstones at National
Cemeteries.
(2) Clean water shall be used to wet the stone prior to washing, to apply the cleaning product and to rinse the stone after washing. Once the stone is wet, cleaning techniques with water shall include low pressure water spraying with the wand affixed with a fan tip. The distance between the fan tip and the headstone surface shall be a minimum of 12”.
(3) Camp Chase headstones are older (1860’s), when water under pressure is used, such pressure shall not be greater than 200 psi and work shall be accomplished in a manner that does not cause any etching of the stone surface to occur. A test cleaning shall be done in an inconspicuous area of a headstone (based on age and or style) and approved by the COR prior to cleaning all like headstones and markers.
(4) Hand scrubbing may be used as needed. If manual agitation is necessary to remove soiling, only a soft bristle (synthetic or natural) brush shall be used; metal or stiff plastic shall not be used because it can scratch the stone.
(5) Rinsing: Thoroughly rinse the headstone or marker surface using clean, clear water under low pressure or without pressure.
(6) Site disturbance: If water used in cleaning should soften the soil around the base of the headstone or marker so it is loosened, care will be taken not to tip the headstone out of plumb or alignment.
(7) Care shall be taken to protect the turf area from damage. Any turf damaged by the contractor shall be restored at Contractor’s expense. Upright headstones shall be set and anchored firmly in place with no movement from forces subjected by the COR or inspector after cleaning has been completed.
c) APPLICATION OF “D/2 BIOLOGICAL SOLUTION”
(1) After wetting the headstone in accordance with paragraph 2 above, apply a heavy spray application of undiluted “D/2 Biological Solution” cleaner to all sides of the headstone.
Do not dilute the cleaner with water.
(2) Do not rinse: allow D/2 to soak into the stone. Do not irrigate for 12 hours, and if significant rain occurs within 12 hours reapply the D/2. Heavy stains or deposits should be scrubbed with a soft bristle brush 10-15 minutes after D/2 application, keeping the surface wet with additional D/2 or a light water mist as needed.
(3) The effect of using D/2 Biological Solution will not be immediate. It will take 2 to 3 weeks for the full appearance of a clean stone to become apparent. For this reason, re-treatment should not occur within (3) three weeks of the first cleaning and only with the concurrence of the COR.
(4) Headstones that have been cleaned but become marked, discolored, dirt covered, or muddied, etc., after initial cleaning has been completed but prior to overall project completion shall be re-cleaned at no additional cost to the government. All headstones shall be clean at the time of project completion final inspection.
(5) The result of this service is that the Contractor shall provide the Government “CLEAN” headstones/markers, as defined above.
ATTACHMENT D
LAWN MAINTENANCE: FERTILIZATION, WEED CONTROL
(CAMP CHASE ONLY)
a) Standard 1.1: All maintenance activities are included in a current Cemetery Grounds Management Plan.
(1) Measure 1.1a: The percent of national cemeteries that have a written, current Cemetery
Grounds Management Plan that includes all maintenance activities and schedules for that cemetery.
Target 1.1a: 100%
(2) Measure 1.1b: The percent of Cemetery Grounds Management Plans that are reviewed and updated on an annual basis.
Target 1.1b: 100%
(3) Measure 1.1c: The percent of National Cemeteries that are accomplishing all activities in their Cemetery Grounds Management Plan.
Target 1.1c: 100%
The contractor shall follow the Dayton National Cemetery and the Camp Chase Cemetery Grounds Management Plan, and recommend changes to it as needed, in coordination with the COR and District Agronomist, to reflect current and ongoing needs.
b) Standard 2.1: Visually prominent areas have a well-established, healthy stand of turf.
(1) Requirement 2.1a: Visually prominent areas are generally weed free.
(2) Requirement 2.1b: Visually prominent areas with established turf are generally free of bare areas.
c) Standard 3.2: Grounds are maintained in a manner that avoids safety hazards for visitors and staff.
(1) Measure 3.2a: 100% of safety hazards (holes, pests, hazardous trees and branches, sprinkler heads, etc.) that are identified have corrective action initiated within the same workday in which they are identified.
The contractor shall maintain the turf area of the Cemetery and the immediate area surrounding of the Cemetery in a healthy condition by proper application of fertilizers and other plant health care products (including pesticides, particularly herbicides, as needed). Turf in burial areas shall be generally weed free, meaning “the population of weeds is very widely scattered and visually insignificant when the total expanse of the cemetery is observed. They in no way distract from the visual attractiveness of the landscape.”
Attractive, healthy turf shall cover at least 95 percent of the area. The turf is to be aerated with a core aerator in September.
B. EQUIPMENT AND SUPPLIES:
1. The Contractor is to supply all necessary applicators, hoses and other equipment.
2. The contractor shall have soil tested at a certified facility. Copy of results shall be provided to the COR. Test results will show any deficiencies and the needed corrections.
3. The Contractor shall furnish all required chemicals, fertilizers and any other supplies. The
Contractor shall determine the necessary formulation of fertilizers and the required amount of lime as indicated by the soil tests.
4. Water will be furnished by the Government for Contractor use at the Cemetery.
C. GENERAL REQUIREMENTS:
1. The Contractor shall be responsible for taking all precautions to prevent damage to the cemetery, in any manner, including headstones, markers, monuments, flower bases, trees and other structures during maintenance operations. The Contractor shall be charged current replacement costs for headstones/markers, other cemetery structures or property damaged because of actions by contractor personnel. Any damage must be reported to the COR immediately.
2. Fertilizer: Shall be applied at a rate of one pound of nitrogen per 1,000 square feet three times each year: late May/early June, early September, and late October (or about the time of the final mowing for the season). It shall be applied with a properly adjusted and calibrated spreader. Overlap of spread pattern from adjacent passes shall be adequate to ensure uniform application. Streaks appearing in turf any time during the year because of non-uniform application are not acceptable.
Fertilizer deposited impervious surfaces (walks/pavement) shall be removed or blown onto the turf immediately following application. Fifty percent or more of the nitrogen in the fertilizer shall be in a slow or controlled release form. The fertilizer potash (K) content shall be one third to one half that of the nitrogen content, and the phosphate (P) content shall be one fourth or more that of the nitrogen content, e.g., 24-6-8, or 26-9-13. It shall contain no iron. Variations of this regime may be approved by the COR, in consultation with the District Agronomist, if needed based on soil test results or extreme weather conditions. (See ‘5.’ Below for an additional option about the May-June application.)
3. Soil Testing: The Contractor shall collect soil samples and have them analyzed at a qualified university or commercial laboratory once every three years from each cemetery section. Tests shall include at least the basic macronutrients (except nitrogen), CEC, pH, and texture. Approximately one third of the sections shall be tested each year, and results shall be submitted to the COR.
4. Spraying Broadleaf Weeds: In addition to proper fertilization and mowing to enhance turfgrass competitiveness against weeds, weeds shall also be controlled with appropriate use of herbicides.
Broadleaf weeds shall be controlled by spraying turfgrass areas with the proper type and rate of herbicide that will control the weeds present (typically clover, dandelion, plantain, oxalis, chickweed, henbit, etc.). Spraying of all turfgrass areas will be done twice each year: in early-mid May to clean up weeds prior to Memorial Day, and in October to have maximum effect on perennial weeds and reduce winter-annual weed establishment. Contractor is also expected to spot spray at other times as needed to control localized weed populations that may develop.
5. Pre-emergence Herbicide shall be applied twice per year to prevent annual grassy weed establishment. Applications shall be in April when soil temperature approaches that necessary for crabgrass germination, and again approximately 7 weeks later. Either dithiopyr (e.g., Dimension) or prodiamine (e.g., Barricade) shall be used at the maximum label rate allowed for the site. (If approved by the COR in consultation with the District Agronomist, the spring fertilizer application may be combined with the pre-emergence herbicide applications, if (1) the April application contains less than one half pound of nitrogen per 1,000 square feet, and the overall “late May to early June” fertilizer requirements regarding controlled release and ratio in ‘2.’, above, are met, or
(2) the entire “late May to early June” fertilizer quantity may be applied with the April pre-emergence herbicide IF the nitrogen in the…