36C78619B0021-011.pdf
PDF 6 MB Posted
- Solicitation number
- 36C78619B0021
About this file
36C78619B0021 835CM3036 - CNC Admin and Maintenace Bldg - Specifications Vol 1 - Bid Documents 6-28-19.pdf
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C78619B0021-0006001.jpg | JPG image | |
| 36C78619B0021-0006000.docx | DOCX document | |
| 36C78619B0021-0005000.docx | DOCX document | |
| 36C78619B0021-0005001.xlsx | XLSX spreadsheet | |
| 36C78619B0021-0004000.docx | DOCX document | |
| 36C78619B0021-0004001.docx | DOCX document | |
| 36C78619B0021-0003001.pdf | ||
| 36C78619B0021-0003000.docx | DOCX document | |
| 36C78619B0021-0002000.docx | DOCX document | |
| 36C78619B0021-0001000.docx | DOCX document | |
| 36C78619B0021-013.pdf | ||
| 36C78619B0021-009.pdf | ||
| 36C78619B0021-006.docx | DOCX document | |
| 36C78619B0021-016.pdf | ||
| 36C78619B0021-014.pdf | ||
| 36C78619B0021-015.pdf | ||
| 36C78619B0021-008.pdf | ||
| 36C78619B0021-012.pdf | ||
| 36C78619B0021-007.pdf | ||
| 36C78619B0021-010.docx | DOCX document | |
| 36C78619B0021-000.docx | DOCX document |
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Chattanooga National Cemetery Renovate Administration and Maintenance Buildings
June 28, 2019 Specifications Volume 1
U.S. DEPARTMENT OF VETERANS AFFAIRS
National Cemetery Administration VA Project No: 835CM3036 Task Order No: 36C78618N0562
Chattanooga National Cemetery Project No. 835CM3036 Renovate Administration and Maintenance Buildings 28 June 2019
00 01 10-1
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
Volume 1
DIVISION 00 - SPECIAL SECTIONS
00 01 15 List of Drawing Sheets
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 01 32 17 Network Analysis Schedule 01 33 23 Shop Drawings, Product Data, and Samples 01 42 19 Reference Standards 01 45 29 Testing Laboratory Services 01 57 19 Temporary Environmental Controls 01 74 19 Construction Waste Management 01 81 13 Sustainable Construction Requirements 01 91 00 General Commissioning Requirements
DIVISION 02 – EXISTING CONDITIONS
02 41 10 Demolition 02 41 10A Building Demolition 02 82 13A Environmental Testing Laboratory Services 02 82 13B Asbestos Abatement 02 83 33 Lead Paint Safe Work Practices
DIVISION 03 – CONCRETE
03 30 53A (Short-Form) Architectural Cast-in-Place Concrete 03 33 53B (Short-Form) Site Civil Cast-in-Place Concrete
DIVISION 04 – MASONRY
04 01 00 Maintenance of Masonry 04 05 13 Masonry Mortaring 04 05 31 Masonry Tuck Pointing 04 20 00 Unit Masonry 04 43 00 Natural Stone Veneer
DIVISION 05 – METALS
05 40 00 Cold-Formed Metal Framing 05 50 00 Metal Fabrications
DIVISION 06 – WOOD,PLASTICS AND COMPOSITES
06 10 00 Rough Carpentry 06 20 00 Finish Carpentry 06 20 10 Capped PVC Finish System 06 41 16.0010 Laminate Clad Casework 06 61 16 Solid Surface Fabrications
00 01 10-2
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 08 00 Facility Exterior Closure Commissioning 07 31 13 Asphalt Shingle 07 31 26 Slate Shingles 07 60 00 Flashing and Sheet Metal 07 84 00 Firestopping 07 92 00 Joint Sealants
DIVISION 08 - OPENINGS
08 11 13 Hollow Metal Doors and Frames 08 14 00 Interior Wood Doors 08 31 13 Access Doors and Frames 08 33 00 Coiling Doors and Grilles 08 41 13 Aluminum-Framed Entrances and Storefronts 08 51 13 Aluminum Windows 08 71 00 Door Hardware 08 71 13.11 Low Energy Power Assist Door Operators 08 80 00 Glazing 08 90 00 Louvers and Vents
DIVISION 09 – FINISHES
09 06 00 Schedule for Finishes 09 22 16 Non-Structural Metal Framing 09 29 00 Gypsum Board 09 30 13 Tiling 09 51 00 Acoustical Ceilings 09 65 13 Resilient Base and Accessories 09 68 00 Carpeting 09 91 00 Painting
DIVISION 10 – SPECIALTIES
10 14 00 Exterior Signage 10 14 05 Interior Signage 10 21 13 Toilet Compartments 10 28 00 Toilet and Bath Accessories 10 44 13 Fire Extinguisher Cabinets 10 51 13 Metal Lockers 10 56 13 Steel Shelving
DIVISION 12 – FURNISHINGS
12 24 00 Window Shades
Volume 2
DIVISION 22 – PLUMBING
22 05 11 Common Work Results for Plumbing 22 05 23 General-Duty Valves for Plumbing Piping 22 07 11 Plumbing Insulation 22 08 00 Commissioning of Plumbing Systems 22 11 00 Facility Water Distribution 22 13 00 Facility Sanitary and Vent Piping 22 33 00 Electric Domestic Water Heaters 22 40 00 Plumbing Fixtures
00 01 10-3
DIVISION 23 – HEATING, VENTILATING, AND AIR CONDITIONING
(HVAC)
23 05 11 Common Work Results for HVAC 23 05 12 General Motor Requirements for HVAC Equipment 23 05 41 Noise and Vibration Control for HVAC Piping and Equipment 23 05 93 Testing, Adjusting, and Balancing for HVAC 23 07 11 HVAC Insulation 23 08 00 Commissioning of HVAC Systems 23 11 23 Facility Natural Gas Piping 23 23 00 Refrigerant Piping 23 31 00 HVAC Ducts and Casings 23 34 00 HVAC Fans 23 36 00 Air Terminal Units 23 37 00 Air Outlets and Inlets 23 55 23 Gas-Fired Radiant Heaters 23 81 00 Unitary HVAC Equipment 23 82 39 Unit Heaters
DIVISION 26 – ELECTRICAL
26 05 11 Requirements for Electrical Installations 26 05 19 Low-Voltage Electrical Power Conductors and Cables 26 05 26 Grounding and Bonding for Electrical Systems 26 05 33 Raceway and Boxes for Electrical Systems 26 05 41 Underground Electrical Construction 26 05 73 Overcurrent Protective Device Coordination Study 26 08 00 Commissioning of Electrical Systems 26 24 16 Panelboards 26 27 26 Wiring Devices 26 29 21 Enclosed Switches and Circuit Breakers 26 41 00 Facility Lightning Protection 26 51 00 Interior Lighting 26 56 00 Exterior Lighting
DIVISION 27 – COMMUNICATIONS
27 05 00 Common Work Results for Communication 27 05 11 Requirements for Communications Installations 27 05 26 Grounding and Bonding for Communications Systems 27 05 33 Conduits and Backboxes for Communication Systems 27 08 00 Commissioning of Communication Systems 27 10 00 Structured Cabling 27 11 00 Communications Equipment Room Fittings
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
28 08 00 Commissioning of Electronic Safety and Security Systems 28 10 00 Access Control 28 20 00 Video Surveillance 28 31 00 Intrusion Detection 28 46 00 Fire Detection and Alarm
DIVISION 31 – EARTHWORK
31 20 11 Earthwork (Short Form)
00 01 10-4
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 05 23 Cement and Concrete for Exterior Improvements 32 12 16 Asphalt Paving 32 17 23 Pavement Markings 32 31 13 Chain Link Fences and Gates 32 90 00 Planting
DIVISION 33 – UTILITIES
33 10 00 Water Utilities 33 30 00 Sanitary Sewer Utilities 33 40 00 Storm Sewer Utilities 33 41 13 Foundation Drainage
SIGNATURE - 1
SIGNATURE PAGE
Lead Consultant/ Landscape Architect:
JG&A
Sections covered by this seal include:
00 01 15, 01 00 00, 01 32 17, 01 33 23, 01 42 19,01 45 29, 01 74 19, 01 81 13, 32 30 00, 32 90 00, Civil Engineer:
Atrirax
Sections covered by this seal include:
01 57 19. 02 41 10, 03 30 53B, 04 01 00, 31 20 11, 32 05 23, 32 12 16, 32 17 23, 32 21 13, 33 10 00, 33 33 00, 33 40 00, 33 41 13
Architect:
Wood LLC
Sections covered by this seal include:
01 91 00, 02 41 10A, 02 82 13A, 02 82 13B, 02 83 33, 03 30 53A, 04 05 13, 04 05 31, 04 20 00, 04 43 00, 05 40 00, 05 50 00, 06 10 00, 06 20 00, 06 20 10, 06 41 16, 06 61 16, 07 08 00, 07 31 13, 07 31 26, 07 60 00, 07 84 00, 07 92 00, 08 11 13, 08 14 00, 08 31 13, 08 33 00, 08 41 13, 08 51 13, 08 71 00, 08 71 13.11, 08 80 00, 08 90 00, 09 06 00, 09 22 16, 09 29 00, 09 30 13, 09 51 00, 09 65 13, 09 68 00, 09 91 00, 10 14 00, 10 14 05, 10 21 13, 10 28 00, 10 44 13, 10 51 13, 10 56 13, 12 24 00
SIGNATURE - 2
Mechanical Engineer:
22 05 11, 22 05 23, 22 07 11, 22 08 00, 22 11 00, 22 13 00, 22 33 00, 22 40 00, 23 05 11, 23 05 12, 23 05 41, 23 05 93, 23 07 11, 23 08 00, 23 11 23, 23 23 00, 23 31 00, 23 34 00, 23 36 00, 23 37 00, 23 55 23, 23 81 00, 23 82 39
Electrical Engineer:
26 05 11, 26 05 19, 26 05 26, 26 05 33, 26 05 41, 26 05 73, 26 08 00, 26 24 16, 26 27 26, 26 29 21, 26 41 00, 26 51 00, 26 56 00, 27 05 00, 27 05 11, 27 05 26, 27 05 33, 27 08 00, 27 10 00, 27 11 00, 28 08 00, 28 10 00, 28 20 00, 28 31 00, 28 46 00
00 01 15 - 1
SECTION 00 01 15
LIST OF DRAWINGS
The drawings listed below accompanying this specification form a part of the contract.
No. Drawing No. Title
1 G-101 COVER SHEET
2 X-001 CLIN INDEX
3 X-101 CONSTRUCTION ACCESS AND STAGING PLAN
4 X-102 ENLARGED CONSTRUCTION ACCESS AND STAGING PLAN
CIVIL
5 C-101 OVERALL SITE PLAN
6 C-102 OVERALL PAVING PLAN
7 C-103 ENLARGED PAVING PLANS
8 C-104 SPOILS YARD
9 C-105 MAINTENANCE BUILDING
10 C-106 POND REPAIR PLAN
11 C-107 ENLARGED SITE PLANS 1 OF 2
12 C-108 ENLARGED SITE PLANS 2 OF 2
13 C-501 SITE DETAILS 1 OF 2
14 C-502 SITE DETAILS 2 OF 2
SIGNAGE
15 L-101 SITE SIGNAGE PLAN
16 L-501 SITE SIGNAGE DETAILS
ARCHITECTURAL
17 A-100 ARCHITECTURAL LEGEND, ABBREVIATIONS AND NOTES
18 AA101 ADMINISTRATION BUILDING DEMOLITION FLOOR PLANS AND NOTES
19 AA102 ADMINISTRATION BUILDING RENOVATION FLOOR PLAN AND NOTES
20 AA103 ADMINISTRATION BUILDING REFLECTED CEILING PLAN AND NOTES
21 AA104 ADMINISTRATION BUILDING ROOF PLAN AND NOTES
22 AA105 ADMINISTRATION BUILDING LIFE SAFETY PLAN
23 AA201 ADMINISTRATION BUILDING RENOVATION ELEVATIONS
24 AA301 ADMINISTRATION BUILDING INTERIOR ELEVATIONS
25 AA601 ADMINISTRATION BUILDING SCHEDULES AND DETAILS
26 AA602 ADMINISTRATION BUILDING WINDOWS, DOOR ELEVATIONS AND DOORS
27 AB101 PUBLIC RESTROOM BUILDING DEMOLITION FLOOR PLAN AND NOTES
28 AB102 PUBLIC RESTROOM BUILDING RENOVATION FLOOR PLAN AND NOTES
29 AB103 PUBLIC RESTROOM BUILDING ROOF PLAN AND NOTES
30 AB104 PUBLIC RESTROOM INTERIOR ELEVATIONS, SCHDULES AND DETAILS
31 AB105 PUBLIC RESTROOM LIFE SAFETY PLAN
32 AC101 MAINTENANCE BUILDING DEMOLITION FLOOR PLAN AND NOTES
33 AC102 MAINTENANCE BUILDING RENOVATION FLOOR PLAN AND NOTES
34 AC103 MAINTENANCE BUILDING REFLECTED CEILING PLAN AND NOTES
35 AC104 MAINTENANCE BUILDING ROOD PLAN AND NOTES
36 AC105 MAINTENANCE BUILDING LIFE SAFETY PLAN
00 01 15 - 2
37 AC201 MAINTENANCE BUILDING RENOVATION ELEVATIONS
38 AC301 MAINTENANCE BUILDING RENOVATION INTERIOR ELEVATIONS
39 AC601 MAINTENANCE BUILDING SCHEDULES AND DETAILS
40 AE101 COMMITTAL SERVICE SHELTER A FLOOR PLAN AND REFLECTED CEILING PLAN
ELECTRICAL
41 E-001 ELECTRICAL LEGEND, ABBREVIATIONS AND NOTES
42 E-101 ELECTRICAL SITE PLAN 1 OF 2
43 E-102 ELECTRICAL SITE PLAN 2 OF 2
44 EA101 ADMINISTRATION BUILDING POWER AMD LIGHTING DEMOLITION PLANS
45 EA102 ADMINISTRATION BUILDING POWER AND LIGHTING NEW WORK PLANS
46 EA103 ADMINISTRATION BUILDING TELECOM PLAN
47 EB101 PUBLIC RESTROOM BUILDING POWER AND LIGHTING DEMOLITION PLANS
48 EB102 PUBLIC RESTROOM BUILDING POWER AND LIGHTING NEW WORK PLANS
49 EC101 MAINTENANCE BUILDING POWER AND LIGHTING DEMOLITION PLANS
50 EC102 MAINTENANCE BUILDING LIGHTING NEW WORK PLAN
51 EC103 MAINTENANCE BUILDING POWER NEW WORK PLAN
52 ED101 COMMITTAL SHELTER A ELECTRICAL PLANS
53 EE101 LIGHTNING PROTECTION PLANS
54 E-501 ELECTRICAL DETAILS 1 OF 2
55 E-502 ELECTRICAL DETAILS 2 OF 2
56 E-601 SINGLE LINE DIAGRAM
57 E-602 ELECTRICAL SCHEDULES 1 OF 2
58 E-603 ELECTRICAL SCHEDULES 2 OF 2
MECHANICAL
59 M-001 MECHANICAL LEGEND, ABBREVIATIONS AND NOTES
60 MA101 ADMINISTRATION BUILDING MECHANICAL PLAN
61 MB101 PUBLIC RESTROOM BUILDING MECHANICAL PLAN
62 MC101 MAINTENANCE BUILDING MECHANICAL DEMOLITION PLAN
63 MC102 MAINTENANCE BUILDING MECHANICAL NEW WORK PLAN
64 M-501 MECHANICAL DETAILS
65 M-601 MECHANICAL SCHEDULES
PLUMBING
66 P-001 PLUMBING LEGEND, ABBREVIATIONS AND NOTES
67 PA101 ADMINISTRATION BUILDING PLUMBING DEMOLITION PLAN
68 PA102 ADMINISTRATION BUILDING PLUMBING NEW WORK PLAN
69 PB101 PUBLIC RESTROOM BUILDING PLUMBING PLAN
70 PC101 MAINTENANCE BUILDING PLUMBING DEMOLITION PLAN
71 PC102 MAINTENANCE BUILDING PLUMBING NEW SANITARY WASTE PLAN
72 PC103 MAINTENANCE BUILDING NEW WATER PIPING PLAN
73 PC601 MAINTENANCE BUILDING PLUMBING RISER DIAGRAMS
74 P-501 PLUMBING DETAILS
75 P-601 PLUMBING SCHEDULES
- - - E N D - - -i
SECTION 01 00 00
GENERAL REQUIREMENTS
TABLE OF CONTENTS
1.1 GENERAL INTENTION
1.2 STATEMENT OF BID ITEM(S)
1.3 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
1.4 CONSTRUCTION SECURITY REQUIREMENTS
1.5 OPERATIONS AND STORAGE AREAS
1.6 ALTERATIONS
1.7 DISPOSAL AND RETENTION
1.8 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT,
UTILITIES, AND IMPROVEMENTS
1.9 RESTORATION
1.10 PHYSICAL DATA
1.11 PROFESSIONAL SURVEYING SERVICES
1.12 LAYOUT OF WORK
1.13 AS-BUILT DRAWINGS
1.14 USE OF ROADWAYS
1.15 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT
1.16 TEMPORARY TOILETS
1.17 AVAILABILITY AND USE OF UTILITY SERVICES
1.18 NEW TELEPHONE EQUIPMENT
1.19 TESTS
1.20 INSTRUCTIONS
1.21 GOVERNMENT-FURNISHED PROPERTY
1.22 CONSTRUCTION SIGN
1.23 SAFETY SIGN
1.24 PHOTOGRAPHIC DOCUMENTATION
1.25 FINAL ELEVATION Digital Images
ii
1.26 HISTORIC PRESERVATION
01 00 00 -1
SECTION 01 00 00
GENERAL REQUIREMENTS
1.1 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for the renovation of the
Administration, Public Restroom and Maintenance Storage Buildings and
Spoils Shed. Repair and renovations to Architectural structures, monuments, entrance gates, walls, fencing, and memorials. Site improvements including paving repair, signage, correction of erosion condition at pond and other improvements as required by drawings and specifications.
C. Offices of John Gallup & Associates (JG&A), as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the
Government without affirmations by Contracting Officer (CO) or his duly authorized representative.
D. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.
E. Training:
1. All employees of general contractor or subcontractors shall have the
10-hour OSHA certified Construction Safety course and /or other relevant competency training, as determined by VA CP.
2. Submit training records of all such employees for approval before the start of work.
F. Working Hours: Working Hours: Contractor shall be permitted to work between the hours of 8:00 am and 4:30pm unless approved by CO/COR and
Cemetery Director. Coordinate with Cemetery staff on the schedule of services each week and any required adjustments to working hours.
01 00 00 -2
1.2 STATEMENT OF BID ITEM(S)
A. ITEM I,GENERAL CONSTRUCTION: Installation of all work shown on the plans and described in the specifications including but not limited to:
general construction, alterations, road paving, walks, grading, storm drainage, site furnishings, site signage and pond bank stabilization.
1.3 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense,.
1.4 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
B. Security Procedures:
1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. Before starting work the General Contractor shall give one week’s notice to the Contracting Officer so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.
3. No photography of VA premises is allowed without written permission of the Contracting Officer.
4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.
C. Key Control:
01 00 00 -3
1. The General Contractor shall provide duplicate keys and lock combinations to the Contracting officers representative (COR)for the purpose of security inspections of every area of project including tool boxes and parked machines and take any emergency action.
E. Document Control:
1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of
“sensitive information”.
2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.
3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”.
Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.
4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting
Officer.
5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.
6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.
7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document
Management Software (EDMS).
a. Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the
EDMS system.
01 00 00 -4
b. “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.
H. Motor Vehicle Restrictions
1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.
1.5 OPERATIONS AND STORAGE AREAS
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the
Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the
Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the
Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the Contracting
Officer, the buildings and utilities may be abandoned and need not be removed.
C. The Contractor shall, under regulations prescribed by the Contracting
Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting
Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The
Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
(FAR 52.236-10)
01 00 00 -5
D. Working space and space available for storing materials shall be as shown on the drawings.
E. Workmen are subject to rules of Cemetery applicable to their conduct.
F. Construction Fence: Before construction operations begin, Contractor shall provide a chain link construction fence, 1.8m (Six feet) minimum height, around the construction area indicated on the drawings. Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum 375mm (15 inches). Bottom of fences shall extend to 25mm (one inch) above grade. Remove the fence when directed by COR
G. Utilities Services: Maintain existing utility services for Cemetery at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services. Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by Resident Engineer COR.
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR. Electrical work shall be accomplished with all affected circuits or equipment de-energized.
When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the Cemetery Director’s prior knowledge and written approval. Refer to specification Sections 26 05 11, REQUIREMENTS FOR
ELECTRICAL INSTALLATIONS, and 27 05 11 REQUIREMENTS FOR
COMMUNICATIONS INSTALLATIONS for additional requirements.
2. Contractor shall submit a request to interrupt any such services to
COR, in writing, 7 days n advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.
3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least
01 00 00 -6 inconvenience to operations of Cemetery. Interruption time approved by Cemetery may occur at other than Contractor's normal working hours.
4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the Resident Engineer COR.
5. In case of a contract construction emergency, service will be interrupted on approval of Resident Engineer COR. Such approval will be confirmed in writing as soon as practical.
6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
L. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, which are to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.
M. To minimize interference of construction activities with flow of
Cemetery traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles. Wherever excavation for new utility lines cross existing roads, at least one lane must be open to traffic at all times with approval.
2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.
N. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.
01 00 00 -7
O. Coordination of Construction with Cemetery Director: The burial activities at a National Cemetery shall take precedence over construction activities. The Contractor must cooperate and coordinate with the Cemetery Director, through the Resident COR in arranging construction schedule to cause the least possible interference with cemetery activities in actual burial areas. Construction noise during the interment services shall not disturb the service. Trucks and workmen shall not pass through the service area during this period:
1. The Contractor is required to discontinue his work sufficiently in advance of Easter Sunday, Mother's Day, Father's Day, Memorial Day, Veteran's Day and/or Federal holidays, to permit him to clean up all areas of operation adjacent to existing burial plots before these dates.
2. Cleaning up shall include the removal of all equipment, tools, materials and debris and leaving the areas in a clean, neat condition.
1.6 ALTERATIONS
A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR and a representative of VA Supply Service, of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by all three, to the
Contracting Officer. This report shall list by rooms and spaces:
1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of buildings.
2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.
3. Shall note any discrepancies between drawings and existing conditions at site.
4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and COR.
01 00 00 -8
B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of
Resident Engineer COR and/or Supply Representative, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by Contractor with new items in accordance with specifications which will be furnished by Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled
"DIFFERING SITE CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR 52.243-4 and VAAR 852.236-88).
C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:
1. Re-survey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of
Contractor to restore damage caused by Contractor's workmen in executing work of this contract.
D. Protection: Provide the following protective measures:
1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.
2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.
3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.
01 00 00 -9
1.7 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
1. Reserved items which are to remain property of the Government are noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by Resident Engineer COR.
2. Items not reserved shall become property of the Contractor and be removed by Contractor from Cemetery.
3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.
1.8 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND
IMPROVEMENTS
A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workmen, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting Officer.
B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall repair any damage to those
01 00 00 -10 facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the
Contractor fails or refuses to repair the damage promptly, the
Contracting Officer may have the necessary work performed and charge the cost to the Contractor.
(FAR 52.236-9)
C. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, for additional requirements on protecting vegetation, soils and the environment. Refer to Articles, "Alterations", "Restoration", and
"Operations and Storage Areas" for additional instructions concerning repair of damage to structures and site improvements.
D. Refer to FAR clause 52.236-7, "Permits and Responsibilities," which is included in General Conditions. A National Pollutant Discharge
Elimination System (NPDES) permit is required for this project. The
Contractor is considered an "operator" under the permit and has extensive responsibility for compliance with permit requirements. VA will make the permit application available at the office. The apparent low bidder, contractor and affected subcontractors shall furnish all information and certifications that are required to comply with the permit process and permit requirements. Many of the permit requirements will be satisfied by completing construction as shown and specified.
Some requirements involve the Contractor's method of operations and operations planning and the Contractor is responsible for employing best management practices. The affected activities often include, but are not limited to the following:
- Designating areas for equipment maintenance and repair;
- Providing waste receptacles at convenient locations and provide regular collection of wastes;
- Locating equipment wash down areas on site, and provide appropriate control of wash-waters;
- Providing protected storage areas for chemicals, paints, solvents, fertilizers, and other potentially toxic materials; and
- Providing adequately maintained sanitary facilities.//
01 00 00 -11
1.9 RESTORATION
A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the
COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
B. Upon completion of contract, deliver work complete and undamaged.
Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workmen to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.
D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES"
(FAR 52.243-4 and VAAR 852.236-88) and "DIFFERING SITE CONDITIONS" (FAR
52.236-2).
1.10 PHYSICAL DATA
A. Data and information furnished or referred to below is for the
Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.
1. The indications of physical conditions on the drawings and in the specifications are the result of site investigations by Wood
01 00 00 -12
Environmental & Infrastructure Solutions, Inc., 1075 Big Shanty Rd., Suite 100, Kennesaw, Ga 30144.
(FAR 52.236-4)
B. Government does not guarantee that other materials will not be encountered nor that proportions, conditions or character of several materials will not vary from those indicated by explorations. Bidders are expected to examine site of work and logs of borings; and, after investigation, decide for themselves character of materials and make their bids accordingly. Upon proper application to Department of
Veterans Affairs, bidders will be permitted to make subsurface explorations of their own at site.
1.11 PROFESSIONAL SURVEYING SERVICES
A registered professional land surveyor or registered civil engineer whose services are retained and paid for by the Contractor shall perform services specified herein and in other specification sections.
The Contractor shall certify that the land surveyor or civil engineer is not one who is a regular employee of the Contractor, and that the land surveyor or civil engineer has no financial interest in this contract.
1.12 LAYOUT OF WORK
A. The Contractor shall lay out the work from Government established base lines and bench marks, indicated on the drawings, and shall be responsible for all measurements in connection with the layout. The
Contractor shall furnish, at Contractor's own expense, all stakes, templates, platforms, equipment, tools, materials, and labor required to lay out any part of the work. The Contractor shall be responsible for executing the work to the lines and grades that may be established or indicated by the Contracting Officer. The Contractor shall also be responsible for maintaining and preserving all stakes and other marks established by the Contracting Officer until authorized to remove them.
If such marks are destroyed by the Contractor or through Contractor's negligence before their removal is authorized, the Contracting Officer may replace them and deduct the expense of the replacement from any amounts due or to become due to the Contractor.
(FAR 52.236-17)
01 00 00 -13
B. Establish and plainly mark and such other lines and grades that are reasonably necessary to properly assure that location, orientation, and elevations established for each such structure and/or addition, roads, parking lots, are in accordance with lines and elevations shown on contract drawings.
C. Following completion of general mass excavation and before any other permanent work is performed, establish and plainly mark (through use of appropriate batter boards or other means) sufficient additional survey control points or system of points as may be necessary to assure proper alignment, orientation, and grade of all major features of work. Survey shall include, but not be limited to, location of lines and grades of footings, exterior walls, center lines of columns in both directions, major utilities and elevations of floor slabs:
1. Such additional survey control points or system of points thus established shall be checked and certified by a registered land surveyor or registered civil engineer. Furnish such certification to the Resident Engineer COR before any work (such as footings, floor slabs, columns, walls, utilities and other major controlling features) is placed.
D. Whenever changes from contract drawings are made in line or grading requiring certificates, record such changes on a reproducible drawing bearing the registered land surveyor or registered civil engineer seal, and forward these drawings upon completion of work to OR.
E. The Contractor shall perform the surveying and layout work of this and other articles and specifications in accordance with the provisions of
Article "Professional Surveying Services".
1.13 AS-BUILT DRAWINGS
A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.
B. All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built drawings shall be made available for the COR review, as often as requested.
01 00 00 -14
C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.
D. Paragraphs A, B, & C shall also apply to all shop drawings.
1.14 USE OF ROADWAYS
A. For hauling, use only established public roads and roads on Cemetery property and, when authorized by the COR, such temporary roads which are necessary in the performance of contract work. Temporary roads shall be constructed and restoration performed by the Contractor at
Contractor's expense. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.
B. When certain buildings (or parts of certain buildings) are required to be completed in advance of general date of completion, all roads leading thereto must be completed and available for use at time set for completion of such buildings or parts thereof.
1.15 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT
A. Use of new installed mechanical and electrical equipment to provide heat, ventilation, plumbing, light and power will be permitted subject to written approval and compliance with the following provisions:
1. Permission to use each unit or system must be given by COR in writing. If the equipment is not installed and maintained in accordance with the written agreement and following provisions, the
Resident COR will withdraw permission for use of the equipment.
2. Electrical installations used by the equipment shall be completed in accordance with the drawings and specifications to prevent damage to the equipment and the electrical systems, i.e. transformers, relays, circuit breakers, fuses, conductors, motor controllers and their overload elements shall be properly sized, coordinated and adjusted.
Installation of temporary electrical equipment or devices shall be in accordance with NFPA 70, National Electrical Code, (2014
Edition), Article 590, Temporary Installations. Voltage supplied to each item of equipment shall be verified to be correct and it shall
01 00 00 -15 be determined that motors are not overloaded. The electrical equipment shall be thoroughly cleaned before using it and again immediately before final inspection including vacuum cleaning and wiping clean interior and exterior surfaces.
3. Units shall be properly lubricated, balanced, and aligned.
Vibrations must be eliminated.
4. Automatic temperature control systems for preheat coils shall function properly and all safety controls shall function to prevent coil freeze-up damage.
5. The air filtering system utilized shall be that which is designed for the system when complete, and all filter elements shall be replaced at completion of construction and prior to testing and balancing of system.
6. All components of heat production and distribution system, metering equipment, condensate returns, and other auxiliary facilities used in temporary service shall be cleaned prior to use; maintained to prevent corrosion internally and externally during use; and cleaned, maintained and inspected prior to acceptance by the Government
B. Prior to final inspection, the equipment or parts used which show wear and tear beyond normal, shall be replaced with identical replacements, at no additional cost to the Government.
C. This paragraph shall not reduce the requirements of the mechanical and electrical specifications sections.
D. Any damage to the equipment or excessive wear due to prolonged use will be repaired replaced by the contractor at the contractor’s expense.
1.16 TEMPORARY TOILETS
A. Provide where directed, (for use of all Contractor's workmen) ample temporary sanitary toilet accommodations with suitable sewer and water connections; or, when approved by Resident Engineer COR , provide suitable dry closets where directed. Keep such places clean and free from flies, and all connections and appliances connected therewith are to be removed prior to completion of contract, and premises left perfectly clean.
01 00 00 -16
A*. Contractor may have for use of Contractor's workmen; such toilet accommodations as may be assigned to Contractor by Cemetery. Contractor shall keep such places clean and be responsible for any damage done thereto by Contractor's workmen. Failure to maintain satisfactory condition in toilets will deprive Contractor of the privilege to use such toilets.
1.17 AVAILABILITY AND USE OF UTILITY SERVICES
A. The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract. The amount to be paid by the Contractor for chargeable electrical services shall be the prevailing rates charged to the Government. The Contractor shall carefully conserve any utilities furnished without charge.
B. The Contractor, at Contractor's expense and in a workmanlike manner, in compliance with code and as satisfactory to the Contracting Officer, shall install and maintain all necessary temporary connections and distribution lines, and all meters required to measure the amount of electricity used for the purpose of determining charges. Before final acceptance of the work by the Government, the Contractor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia and repair restore the infrastructure as required.
C. Contractor shall install meters at Contractor's expense and furnish the
Cemetery a monthly record of the Contractor's usage of electricity as hereinafter specified.
D. Heat: Furnish temporary heat necessary to prevent injury to work and materials through dampness and cold. Use of open salamanders or any temporary heating devices which may be fire hazards or may smoke and damage finished work, will not be permitted. Maintain minimum temperatures as specified for various materials:
1. Obtain heat by connecting to Cemetery heating distribution system.
E. Electricity (for Construction and Testing): Furnish all temporary electric services.
01 00 00 -17
1. Obtain electricity by connecting to the Cemetery electrical distribution system. The Contractor shall meter and pay for electricity required for electric cranes and hoisting devices, electrical welding devices and any electrical heating devices providing temporary heat. Electricity for all other uses is available at no cost to the Contractor.
F. Water (for Construction and Testing): Furnish temporary water service.
1. Obtain water by connecting to the Cemetery water distribution system. Provide reduced pressure backflow preventer at each connection as per code. Water is available at no cost to the
Contractor.
2. Maintain connections, pipe, fittings and fixtures and conserve water-use so none is wasted. Failure to stop leakage or other wastes will be cause for revocation (at COR discretion) of use of water from Cemetery's system.
G. Fuel: Natural and LP gas and burner fuel oil required for boiler cleaning, normal initial boiler-burner setup and adjusting, and for performing the specified boiler tests will be furnished by the
Government. Fuel required for prolonged boiler-burner setup, adjustments, or modifications due to improper design or operation of boiler, burner, or control devices shall be furnished and paid by the
Contractor at Contractor's expense.
1.18 NEW TELEPHONE EQUIPMENT
The contractor shall coordinate with the work of installation of telephone equipment by others. This work shall be completed before the building is turned over to VA.
1.19 TESTS
A. As per specification section 23 05 93 the contractor shall provide a written testing and commissioning plan complete with component level, equipment level, sub-system level and system level breakdowns. The plan will provide a schedule and a written sequence of what will be tested, how and what the expected outcome will be. This document will be submitted for approval prior to commencing work. The contractor
01 00 00 -18 shall document the results of the approved plan and submit for approval with the as built documentation.
B. Pre-test mechanical and electrical equipment and systems and make corrections required for proper operation of such systems before requesting final tests. Final test will not be conducted unless pre-tested.
C. Conduct final tests required in various sections of specifications in presence of an authorized representative of the Contracting Officer.
Contractor shall furnish all labor, materials, equipment, instruments, and forms, to conduct and record such tests.
D. Mechanical and electrical systems shall be balanced, controlled and coordinated. A system is defined as the entire system which must be coordinated to work together during normal operation to produce results for which the system is designed. For example, air conditioning supply air is only one part of entire system which provides comfort conditions for a building. Other related components are return air, exhaust air, steam, chilled water, refrigerant, hot water, controls and electricity, etc. Another example of a system which involves several components of different disciplines is a boiler installation. Efficient and acceptable boiler operation depends upon the coordination and proper operation of fuel, combustion air, controls, steam, feedwater, condensate and other related components.
E. All related components as defined above shall be functioning when any system component is tested. Tests shall be completed within a reasonably period of time during which operating and environmental conditions remain reasonably constant and are typical of the design conditions.
F. Individual test result of any component, where required, will only be accepted when submitted with the test results of related components and of the entire system.
1.20 INSTRUCTIONS
A. Contractor shall furnish Maintenance and Operating manuals (hard copies and electronic) and verbal instructions when required by the various sections of the specifications and as hereinafter specified.
01 00 00 -19
B. Manuals: Maintenance and operating manuals and one compact disc (four hard copies and one electronic copy each) for each separate piece of equipment shall be delivered to the COR coincidental with the delivery of the equipment to the job site. Manuals shall be complete, detailed guides for the maintenance and operation of equipment. They shall include complete information necessary for starting, adjusting, maintaining in continuous operation for long periods of time and dismantling and reassembling of the complete units and sub-assembly components. Manuals shall include an index covering all component parts clearly cross-referenced to diagrams and illustrations. Illustrations shall include "exploded" views showing and identifying each separate item. Emphasis shall be placed on the use of special tools and instruments. The function of each piece of equipment, component, accessory and control shall be clearly and thoroughly explained. All necessary precautions for the operation of the equipment and the reason for each precaution shall be clearly set forth. Manuals must reference the exact model, style and size of the piece of equipment and system being furnished. Manuals referencing equipment similar to but of a different model, style, and size than that furnished will not be accepted.
C. Instructions: Contractor shall provide qualified, factory-trained manufacturers' representatives to give detailed training to assigned
Department of Veterans Affairs personnel in the operation and complete maintenance for each piece of equipment. All such training will be at the job site. These requirements are more specifically detailed in the various technical sections. Instructions for different items of equipment that are component parts of a complete system, shall be given in an integrated, progressive manner. All instructors for every piece of component equipment in a system shall be available until instructions for all items included in the system have been completed.
This is to assure proper instruction in the operation of inter-related systems. All instruction periods shall be at such times as scheduled by the COR and shall be considered concluded only when the COR is satisfied in regard to complete and thorough coverage. The contractor shall submit a course outline with associated material to the COR for review and approval prior to scheduling training to ensure the subject matter covers the expectations of the VA and the contractual
01 00 00 -20 requirements. The Department of Veterans Affairs reserves the right to request the removal of, and substitution for, any instructor who, in…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it.