36C78619B0021-0004001.docx
DOCX document 14 KB Posted
- Solicitation number
- 36C78619B0021
About this file
36C78619B0021 0004 36C78619B0021 - P0004.docx
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C78619B0021-0006001.jpg | JPG image | |
| 36C78619B0021-0006000.docx | DOCX document | |
| 36C78619B0021-0005000.docx | DOCX document | |
| 36C78619B0021-0005001.xlsx | XLSX spreadsheet | |
| 36C78619B0021-0004000.docx | DOCX document | |
| 36C78619B0021-0003001.pdf | ||
| 36C78619B0021-0003000.docx | DOCX document | |
| 36C78619B0021-0002000.docx | DOCX document | |
| 36C78619B0021-0001000.docx | DOCX document | |
| 36C78619B0021-013.pdf | ||
| 36C78619B0021-009.pdf | ||
| 36C78619B0021-006.docx | DOCX document | |
| 36C78619B0021-016.pdf | ||
| 36C78619B0021-011.pdf | ||
| 36C78619B0021-014.pdf | ||
| 36C78619B0021-015.pdf | ||
| 36C78619B0021-008.pdf | ||
| 36C78619B0021-012.pdf | ||
| 36C78619B0021-007.pdf | ||
| 36C78619B0021-010.docx | DOCX document | |
| 36C78619B0021-000.docx | DOCX document |
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Chattanooga National Cemetery - 36C78619B0021 – P0004
Question: There is a conflict in the plans regarding placement of the concrete - Shot blast or pour new concrete slab in the maintenance building at the new managers office see page AC101 Note 5 and page AC102 Note 10 for the conflict. Please advise on the preferred concrete method.
Answer: Both. The existing floor is currently (or have in the past) being used as a ‘garage’. The shot blasting method is use to clean and prepare the surface to receive the new 4” concrete slab for the new office. This ‘raised floor’ also protects against water intrusion, and ties back into the existing exterior curb.
Question: Are the lockers all single or double tier?
Answer: To be Single Tier.
Question: What is the lock mechanism that we will be using (lockers)? There are four specified.
1. Combination Lock Built-In
1. Combination Lock Built-In
1. Key Lock Built-In
1. Padlocks
1. Positive Automatic and Pre-locking
Answer: Lock mechanism to be Padlocks.
Question: Will the lockers in the maintenance building be on a 4” slab or will they be on a wood base? Specs (10 51 13) and drawings (AC301 Detail 10 / AA102 note 6 ) are showing both.
Answer: Lockers to be on 4” Concrete Slab.
Question: Can we get more information on finishes:
1. Carpet – Type, brand, squares, rolled goods?
1. Ceramic Tile – Type, brand, sizes?
1. Pavers (Admin Building) – Type, brand, size?
1. Countertops – Type?
Answer: consult approved color boards.