This is a Geotechnical Investigation Report for the CLC Phase 3 project at the VA Medical Center in Big Spring, Texas, prepared by Enprotec/Hibbs & Todd, Inc. The investigation was authorized in April 2022 and provides foundation and floor slab design information along with construction recommendations for a proposed single-story building of approximately 7,500 square feet with steel framing and brick veneer.

The site is underlain by moderate strength, low expansive sandy clays further underlain by clayey and silty sands and cemented sands. The Potential Vertical Rise (PVR) is estimated to be less than one-half inch. Foundation design recommendations include a shallow foundation system with continuous wall footings for load-bearing walls and spread footings for building columns, designed for maximum net allowable bearing pressures of 2.5 to 3.0 kips per square foot based on dead load plus design live load. The slab-on-grade should be supported on properly compacted existing soils or select fill used to raise site grades to provide a PVR of less than one-half inch, with a minimum 5-inch thick concrete slab reinforced with #4 rebar 18 inches on center. Critical construction recommendations include site clearing requiring removal of moderately organic topsoil and Portland cement concrete pavement; proofrolling to locate soft or unstable areas; compaction of select fill to minimum 95 percent Standard Proctor density at not less than 2 percent below optimum moisture content; installation of a vapor barrier below the slab-on-grade in moisture sensitive areas; excavation observation by a geotechnical engineer; and utility trench plugging with low permeability materials. The report specifies minimum testing and sampling frequencies during construction including Proctor tests, Atterberg limits tests, and concrete cylinder testing.

View the file

Other files

File Type Posted
Tech Questions Tracker - Big Spring CLC Phase III Minor - 16 OCT 26 Responses.pdf PDF
36C77626B0011 0019.docx DOCX document
36C77626B0011 0018.docx DOCX document
Tech Questions Tracker - Big Spring CLC Phase III Minor - 08 OCT 26 Responses.pdf PDF
36C77626B0011 0017.docx DOCX document
36C77626B0011 0016.docx DOCX document
36C77626B0011 0015.docx DOCX document
Tech Questions Tracker - Big Spring CLC Phase III Minor - 16 SEP 26 Responses.pdf PDF
36C77626B0011 0014.docx DOCX document
Wage Determination - Howard County TX - 5-18-26.pdf PDF
36C77626B0011 0013.docx DOCX document
36C77626B0011 0012.docx DOCX document
Tech Questions Tracker - Big Spring CLC Phase III Minor - 01 SEP 26 Responses.pdf PDF
Big Spring VA CLC Ph3 - 22 63 00 GAS SYSTEMS FOR LABORATORY AND HEALTHCARE FACILITIES.pdf PDF
Brand Name Justification - Big Spring CLC Phase III - Redacted.pdf PDF
519-371-28 _Big Springs_CLC Phase 3_Issue For Bid_Drawings REVISED 26 AUG26.pdf PDF
519-371-28 _Big Springs_CLC Phase 3_Issue for Bid Specifications 26AUG26.pdf PDF
36C77626B0011 0011.docx DOCX document
Tech Questions Tracker - Big Spring CLC Phase III Minor - 26 AUG 26 Responses.pdf PDF
RFI 117 - Electrical Fire Place Cutsheet.pdf PDF
RFI 110 - PATIENT LIFT - P-440_User_Manual_WGS_21DEC20101.pdf PDF
09 67 23.60 - Resinous Urethane and Epoxy Mortar Flooring RES-6A AND RES-6B.pdf PDF
36C77626B0011 0010.docx DOCX document
C - 52.212-4 - Construction.docx DOCX document
36C77626B0011 0009.docx DOCX document
36C77626B0011 0008.docx DOCX document
36C77626B0011 0007.docx DOCX document
36C77626B0011 0006.docx DOCX document
36C77626B0011 0005.docx DOCX document
36C77626B0011 0004.docx DOCX document
36C77626B0011 0003.docx DOCX document
36C77626B0011 0002.docx DOCX document
36C77626B0011 0001.docx DOCX document
CLC Phase 3 Sign-In Sheet.pdf PDF
Attachment 3 - PCRA CLC Phase 3.pdf PDF
Attachment 5 - Redacted Brand Name Justification.pdf PDF
Attachment 6 - Wage Determination - Howard County TX - 1-2-26.pdf PDF
Attachment 7 - Site Visit Instructions.docx DOCX document
36C77626B0011_1.docx DOCX document
Attachment 1 - Specifications - REV2 25FEB26.pdf PDF
Attachment 4 - Limitations on Subcontracting - Construction.docx DOCX document
Attachment 2 - Drawings.pdf PDF
Show all 42

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .