S06 - 0004 - Att1 - Vendor QA.xlsx

XLSX spreadsheet 28 KB Posted

Attached to
Construct EHRM Infrastructure Upgrades | Wilkes-Barre, PA Federal contract opportunity
Solicitation number
36C77625R0056_1
Issued by
Department of Veterans Affairs Technology Acquisition Center Austin

About this file

This file is a vendor Q&A document (S06 - 0004 - Att1 - Vendor QA.xlsx) for a competitive Service-Disabled Veteran-Owned Small Business (SDVOSB) set-aside solicitation for infrastructure upgrades at the Wilkes-Barre VA Medical Center. The project, valued between $20-50 million, involves constructing EHRM (Electronic Health Record Modernization) infrastructure upgrades, including mechanical, electrical, data, and civil infrastructure work in an occupied medical facility with complex phasing and utility tie-ins.

Key details include a solicitation closing date of 8/1/25 at 4 PM ET, requirements for technical capability demonstrations using past project examples, and extensive specifications for work in telecommunications rooms, hallways, and medical facility spaces. The project involves precise coordination with VA staff, including OIT escorts for telecom rooms, ICRA (Infection Control Risk Assessment) protocols, and specific working hour restrictions. Technical requirements encompass fiber optic cabling, security systems integration, fire suppression, and infrastructure modifications, with careful attention to maintaining hospital operations during construction.

View the file

Other files for this federal contract opportunity

Other files attached to Construct EHRM Infrastructure Upgrades | Wilkes-Barre, PA, newest first.
File Type Posted
S06 - 0007 - Att1 - Wage Determination.txt TXT text file
S06 - 0007 - 36C77625R0056 0007.pdf PDF
S06 - 0006 - 36C77625R0056 0006.pdf PDF
S06 - 0005 - Att2 - General Requirements ASI-1.pdf PDF
S06 - 0005 - Att1 - Vendor QA Updated 7.25.25.xlsx XLSX spreadsheet
S06 - 0005 - Att5 - Wage Determination.txt TXT text file
S06 - 0005 - Att3 - Drawing Index ASI-1.pdf PDF
S06 - 0005 - Att4 - Specification TOC ASI-1.pdf PDF
S06 - 0005 - 36C77625R0056 0005.pdf PDF
S06 - 0004 - Att2 - HazMat Report.pdf PDF
S06 - 0004 - 36C77625R0056 0004.pdf PDF
S06 - 0004 - Att4 - Building Drainage Report.pdf PDF
S06 - 0004 - Att3 - GeoTech Report.pdf PDF
S06 - 0003 - Att4 - Infection Control Construction Project Compliance.pdf PDF
S06 - 0003 - Att2 - Geotech Report 2024.pdf PDF
S06 - 0003 - Att3 - GPRS Findings.pdf PDF
S06 - 0003 - Att1 - Geotech Report 2013.pdf PDF
S06 - 0003 - 36C77625R0056 0003.pdf PDF
S06 - 0002 - Site Visit Sign-In Sheet.pdf PDF
S06 - 0002 - Site Visit Agenda.doc DOC document
S06 - 0002 - 36C77625R0056.pdf PDF
S06 - 0001 - 36C77625R0056.pdf PDF
S02 - Att1 - 693-22-700 - Drawings pt2of2.zip ZIP file
S02 - 36C77625R0056.pdf PDF
S02 - Att2 - Zip File Content.docx DOCX document
S02 - Att8 - Design Alerts.pdf PDF
S02 - Att1 - 693-22-700 - Drawings pt1of2.zip ZIP file
S02 - Att9 - Redacted JA.pdf PDF
S02 - Att5 - Limitations on Subcontracting - Construction.docx DOCX document
S02 - Att3 - CD Specifications FINAL.pdf PDF
S02 - Att7 - ICRA.pdf PDF
S02 - Att6 - PCRA.pdf PDF
S02 - Att4 - Wage Determination.txt TXT text file
Show all 33

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

#QuestionAnswerBy
1Does the clean agent fire suppression require a connected reserve cylinder and agent?A/E notes that reserve cylinder(s) and agent are not required by NFPA 2001.A&E
2Are the EPO buttons for the CRAC unit shutdowns and UPS shutdowns apart of a system such as the FIKE EPSMS that has a Bypass for testing?Maintenance bypass switches are shown on detail sheet EP512. As long as EPO System matches the functionality per drawings and specification, the system may be acceptable upon review.A&E
3Electrical work within existing Buildings, can this be done during normal working hours or off-shift?Work can be done during normal business hours if normal hospital operations can be maintained. In instances where it will affect operations and coordination with the affected department is not possible, after-hours work would be required.A&E
4Regarding FE per Detail 3/A-605, if FE needs to be installed because existing is not present within 75’ of new TR, what size shall the new FE be? Please confirm these will be clean agent FE.In accordance with the requirements of NFPA 75 and NFPA 10, the minimum rating for
each required individual portable extinguisher should be a 5lb, 2A:10B:C, carbon dioxide or clean agent fire extinguishers are appropriate.A&E
5MV Sectionalizer switches shown on One-line but there is no spec for them.Sectionalizer switches are included in Specifciation 26 12 19 - PAD-MOUNTED, LIQUID FILLED, MEDIUM-VOLTAGE TRANSFORMERS section 2.9 SECTIONALIZING CABINET.A&E
6"Division 26 metering is shown internal to the electrical equipment, however, it is specified to be by div 25. This vendor can either provide standard meters with modbus OR we can provide standard equipment with no provisions for metering, and the div 25 contractor provides wall mount remote products like EMON, SATEC or other.Provide equipment with integral meters as specificed in specifciation 26 24 16 - PANELBOARDS section 2.5 DIGITAL POWER METERS (DPM). This applies to panelboards and switchboards where indicated on drawings.A&E
7Specification Section 27.06.00 is referenced in the Drawings but not provided, please advise.Reference Specification Section 01 00 00, section I. PHASING for phasing plans.A&E
8Please confirm location of lay-down area and stock piling.Per Specification SECTION 01 00 00-
GENERAL REQUIREMENTS, part 1.6 OPERATIONS AND STORAGE AREAS. Specific area will be determined when details on requirements are provided.Site
9Flag Mount Fire Extinguisher ID signs: a. Do we defer to specs in the VA Sign Design manual for this particular sign? b. If not – are there pictures or samples of existing signs we are to match?Details for Flag mounted Fire Extinguisher Indentification provided on sheet AW001A&E
10Window vinyls: a. Interior or exterior. B. 1st or 2nd surface?A. interior B. seciond surfaceA&E
11Will any interior ADA signs be on glass? If so, do you want a blank acrylic panel, cut to size/shape to match, on the backside of the glass to hide the double sided tape and silicone showing on the other side of the glass? This blank panel would be painted to match.No.A&E
12Regarding the FE in the new Data Center, what size are required, please advise.5lb, 2A:10B:C, clean agent fire extinguishersA&E
13For the new Telecom Rooms, these are Phased per Floor, may the Contractor work on several Floors concurrently or just one Floor at a time?Contractors may work on several floors concurrently. However, any deviations from the contract documents must be approved by the VA before starting work.A&E
14If qualified, may the Project Manager also be the SSHO?Per Specification SECTION 01 35 26-
SAFETY REQUIREMENTS, part 1.7.Site
15Regarding the duct-bank work, there are many concrete sidewalks/curbs that will be impacted by the duct-bank work, may the Contractor go back and patch these areas once the duct-bank has been completed or does it have to be patching as the duct-bank work is being done?Impacted concrete sidewalks in high traffic areas would have to be replace soon after that work is completed to allow for pedestrian traffic to use that walkway.Site
16Please verify if a Geotechnical Report is available for the site and Data Center, indicating the locations and depths of rock. Drawing S-001 "Foundations - Item 1 indicates a Geotechnical report" was prepared. If so, please issue.Geotechnical Reports are avalable and will be distributed to the contractor at the VA's discretion.Site
17Per the Drawing Index on Drawing G-002, there appears to be 2 sets of Civil Drawing Pages for the project with the same sheet name, pages 4-23 and 24-43. (i.e Pages 8 & 28 are both titled "CS-200 DC Building Site Plan"). Please verify if there are 2 sets of drawings and which set is to be use for bidding.There is only one set of civil drawings, VA has been provided the latest Civil set in and sheet index has been revised.A&E
18Please confirm location for Expansion Joint Cover Assemblies, Specification Section 07.95.13.Spec Section 07 95 13 will be removed from contract documents, it was a holdover from scope that has since been removed from the project.A&E
19What is the current firmware version on the current CCTV system?4.36.0.16 (d3811948)Security
20Is the CCTV on the VA network or standalone network?StandaloneSecurity
21Is the CCTV using FIPS Servers?Security
22For the SECURITY ACCESS, PANNING CAMERA TRAVERSE ANGLE (TN002), does the VA like the multi-head vs the fisheye?It all depends on where the camera is located. Example: We like the Multiheaded at hallway intersections. Fisheyes are good when covering a large area where we can PTZ.Security
23Are PACS and CCTV currently integrated with each other?NoSecurity
24Are PACS and IDS currently integrated with each other?NoSecurity
25Are the TR's getting IDS installed (intrusion)?No Intrusion detection is included in TRsA&E
26There was a reader without power on an IT closet during the walkthrough. Are we responsible for replacing the reader or any other readers or other hardware/devices that may be out on IT closets/TR's that work is being performed?Card readers shall be relocated, replaced, or upgraded as indicated on drawings.A&E
27What is the current version of software for the PACS?C-Cure 9000 version 3.00.3 (Build 3188.188)Security
28Is the PACS on the VA network or a standalone network?VA NetworkIT
29Is the PACS a 75 bit or 200 bit system?200-bitSecurity
30How much advanced notice will be required for OIT escort coverage of TR rooms?The more escorts needed at one time, the more advance notice would be required. A schedule and regular look- ahead meetings with the Facility staff will allow for scheduling the required number of escorts.
Site / IT
31What constitutes the need for OIT escorts? Is an escort required any time the doors are open to a TR room?When accessing any active TR. Yes, an escort is required ant time a TR door is open. When a new TR buildout reaches a point where VA network gear is installed, then escorts will be required, not before.Site / IT
32How many OIT escorts will be available at any given time?A schedule and regular look- ahead meetings with the Facility staff will allow for scheduling the required number of escorts.Site
33Will on-site parking be available for contractor personnel?Per Specification SECTION 01 00 00-
GENERAL REQUIREMENTS, part 1.5, E Motor Vehicle Restrictions.Site
34How many new TR room buildouts can be requested at one time?This depends on where the worked TRs are located and the affect each has on daily operations. Also see Phasing Plan.Site
35What specific tasks are intended to be scheduled at night/day?In the Medical Center- Per Specification SECTION 01 00 00-
GENERAL REQUIREMENTS, part 1.6, F & G. Outside areas will typically be during the daylight hours.Site
36Working Hours – What are the precise hours for double shifts and weekends? For instance, o 1st Shift: 7:00 AM - 4:00 PM o 2nd Shift: 4:00 PM - 10:00 PM o Weekends: 7:00 AM - 5:00 PMPer Specifications SECTION 01 00 00-
GENERAL REQUIREMENTS, part 1.6 G.Site
37Will there be conflict with current construction next to the new server building being built?No.Site
38On office spaces being demoed to become a TR, are the ceiling tiles being removed?Refer to demo RCPs for scope. For example on sheet 01-A-400b, Keynote #5 - "DEMOLISH EXISTING ACT COMPLETELY INCLUDING ALL

GRIDS, SUPPORTING WIRES, CLIPS, AND PERIMETER

WALL ANGLES TO EXPOSE UNDERSIDE OF STRUCTURE

ABOVE. PATCH WALLS WHERE CEILING IS REMOVED.

PATCH AND REPAIR REMAINING CEILING GRID AND TILES

WHERE NEW WALLS ARE BEING INSTALLED."A&E
39Drawing CU 300 shows communication duct banks A & B as does the legend on multiple drawings. Drawing CU500 & CU501 shows (4) different duct bank details with no identification as to where each detail is used, please advise.The duct bank details provided are typical in nature for all EHRM projects.

The contractor is to determine the applicable ductbank based on the fiber counts required on each run.

In general for the smaller VA sites, it's anticipated that the campus fiber ductbank will utilize the 4 conduit ductbank (separate ductbanks for A and B sides), and the building connections will utilize the 3 conduit ductbank.A&E
40Drawing 05-TN101 shows Fiber to IT Room 5-203. Should Fiber go to 5-201.Yes, Fiber should route to 5-201.A&E
41How much work can be done above ceilings in existing Hospital during Normal working hours? 7am-3:30pm.Per Specifications SECTION 01 00 00-
GENERAL REQUIREMENTS, part 1.6 G. Work outside those hours depends on the location and activity in the Medical Center. The ICRA Level will be a factor in this.. Above ceiling permits will be required for any work/inspections being completed within the facility. The IC SOP will address the number of ceiling tiles allowed out in one area. Refer to safety for above the ceiling work permits.ICRA
42Will Auto-CAD Drawings of the duct-bank layout be provided?CAD documents for all Construction Drawing sheets have been provided by the AE to the VA. It is at the VA's discretion if these will be provided to the contractor. CAD documents are supplemental only and are not considered construction documents. Any CAD provided to the contractor are to be used at the contractor's discretion.A&E
43Drawing S-541, Detail F1, please advise where this is located on a Plan View.This is a typical detail for support of the mechanical units. Refer to mechancial plans for proposed locations.A&E
44Will the sign-in sheet from site visit be available in addendum?Posted on SAM.gov.Site
45Please clarify if a superintendent can be a dual hat to cover the requirements of SSHO?Per Specification SECTION 01 35 26-
SAFETY REQUIREMENTS, part 1.7.Site
46If no to the question above, will the SSHO need to be full-time for this project?Per Specification SECTION 01 35 26-
SAFETY REQUIREMENTS, part 1.7.Site
47Please clarify if a superintendent can be a dual hat to cover the requirements of QA/QC?Per Specification SECTION 01 45 00-
QUALITY CONTROL, part 3 EXECUTION.Site
48If no to the question above, will the QA/QC need to be full time for this project?Per Specification SECTION 01 45 00-
QUALITY CONTROL, part 3 EXECUTION.Site
49Can a superintendent be a triple hat to cover the requirements of SSHO and QA/QC?Per Specification SECTION 01 45 00-
QUALITY CONTROL, part 3 EXECUTION.Site
50Please confirm if tax should be included in our proposal?See 52.229-3 FEDERAL, STATE, AND LOCAL TAXES and Special Notes regarding FAR 52.229-3.Contracting
51Please provide the latest wage determination for this project’s county.Wage determination as of 7/17/2025 has been included.Contracting
52Please confirm if the current prevailing wages will be consistent for the life of the project with no escalation?Wage Rates will remain the same for the life of the project.Contracting
53Please confirm the current design documents meet current VA TIL guidelines.Yes.Site / A&E
54Who is responsible for contracting the commissioning agent?Contractor is required to be familiar with contract documents - Specification section 01 91 00 1.8 identifies the following:

B. Members Appointed by Contractor:

1. Contractor’ Commissioning Manager: The designated person, company, or entity that plans, schedules and coordinates the commissioning activities for the construction team.

2. Contractor’s Commissioning Representative(s): Individual(s), each having authority to act on behalf of the entity he or she represents, explicitly organized to implement the commissioning process through coordinated actions.

C. Members Appointed by VA:

1. Commissioning Agent: The designated person, company, or entity that plans, schedules, and coordinates the commissioning team to implement the commissioning process. The VA

will engage the CxA under a separate contract.A&E
55Is the use of temporary plastic wall panels (such as STARC panels) acceptable to meet ICRA requirements?YesICRA
56Will shutdowns be required to be done during off hours or weekends?Per Specification SECTION 01 00 00-
GENERAL REQUIREMENTS, part 1.6.Site
57Please confirm if there is assumed asbestos or lead that is to be removed whether underground or within manholes or buildings?Hazardous materials report provided to the VA, this can be distributed to the contractors at the VA's discretion.A&E
58Will telecommunications rooms, mechanical rooms, work areas, etc. be cleared of all stored items prior to the contractor entering those areas?Conditions will vary. Mechanical spaces, existing TRs and working spaces will often need to remain functional before and after contractor work. In these cases, It is not feasible to remove and replace the contents of the rooms. Although, when the function of the space has changed completely (such as converting an office to a TR) coordination and planning of clearing the space can be made.Site
59Will a full-time fire watch be required during activities such as cutting, brazing, and welding? How long after such activities are completed?A Fire Watch is required during cutting, brazing, and welding activities and 30-minutes after the activity is completed. A Hot work permit is required and issued by WB VA Safety and this process will determine if the person performing the cutting, brazing, and welding activities can the Fire Watch or a dedicated Fire Watch is required.Site
60Will any existing glycol be required to be removed and disposed of by the contractor? If so, can the total volume of glycol be provided?Contractor is responsible for verifying glycol percentage of existing hydronic systems and disposing of any glycol associated with the demolition and removal of the existing fan coil units and hydronic piping as shown on the contract documents.A&E
61With regards to underground utility work how much open trenching is allowed at a time?The amount of open trenching allowed at a time will be dependent on the location and the ability to maintain access to vehicles and pedestrians. All trenchs will need to be closed or protected by the end of the work shift.Site
62Have test pits or exploratory excavations been completed along the proposed fiber duct bank routing? Please provide reports if available.No. Geotechnical Reports around the Data Center are available and posted on SAM.gov.Site
63After backfilling, topsoil and seed have been applied who is responsible for watering? If the contractor is responsible will water be provided by the facility?Contractor is responsible for watering the seed until it sprouts and grass is established. Water will be made available by the facility.Site
64On all underground utility work please confirm if excavated material is acceptable for re-use as backfill?Clean excavated material is acceptable for re-use as backfill.Site
65Please confirm if the contractor is responsible for any rock removal that is encountered. If so, what is the assumed elevations and quantity of rock material?Yes. Unknown. See Specification SECTION 31 20 11- EARTHWORK, part 1.6 B. A new fire main loop was installed on the campus a few years ago.Site
66Please confirm if a unit price can be established for rock removal as opposed to carrying in bid?No. The bid is all inclusive.Site / Contracting
67If an extreme amount of rock is encountered/removed, please confirm if extra time will be added to the contract completion date?Specification SECTION 31 20 11- EARTHWORK, part 1.6 B.Site / Contracting
68Please confirm if there is a separate staging area onsite for fill material to be stockpiled for re-use?There is an area on-site to stage fill material.Site
69Please confirm if an onsite arborist is required for any tree removal or tree protection?Per Specification SECTION 01 00 00-
GENERAL REQUIREMENTS, part 1.9, A.Site
70Please advise if the site contains any contaminated soil that needs to be removed.No contaminated soil is anticipated.Site
71If the underground site package requires removal of contaminated soils. Will the site contractor be required to have operators trained and certified in all various levels of contamination handling?If contaminated soil is found, then a company that is certified to remove/dispose of it would be required.Site
72Please confirm if we will be allowed to keep a locked storage container or Conex box within the grounds.Yes, space for a locked storage container or Conex box will be available. Per Specification SECTION 01 00 00-
GENERAL REQUIREMENTS, part 1.6 D.Site
73Who is responsible for final terminations and integration to the existing data system?When terminations are installed, tested, and validated, a VA OIT technician will make the final connections from patch panel to network switch.IT
74To allow sufficient time to review responses and prepare our bid we kindly request that you please extend the bid date.Solicitation closing date has been extended to 8/1/25, 4PM ET.Contracting
75Must past performance examples be from the offeror acting as the Prime Contractor, or will subcontractor experience be accepted?Past performance is not an evaluation factor for this solicitation. Factor 1, Technical Capability (Technical) may be satisfied by the prime or proposed subcontractor.Contracting
76Will the Government consider ongoing multi-year contracts (e.g., service contracts or BPAs with completed task orders) if they include scopes of work relevant to the solicitation? If so, are there specific requirements for documentation (e.g., percent complete, task summaries, interim CPARs)?In regard to Factor 1, Technical Capability (Technical) all examples must be of at least 90% completed projects.Contracting
77If subcontractor past performance is used, are Letters of Commitment or Subcontractor Consent Forms required at time of submission? If so, is there a preferred format?Past performance is not an evaluation factor for this solicitation.Contracting
78Are there any specific formatting requirements for presenting subcontractor experience (e.g., prime vs. sub role, dollar share, duration)?All formatting should follow the "Instructions to Offerors"Contracting
79The solicitation defines relevant experience as:-----------
80“Construction or complete renovation of a data center in an occupied medical facility involving mechanical, electrical, data, and civil infrastructure, tying-in to existing structure, project phasing, and interruptions of facility utilities.”Within the two to five project limit, all technical evaluation factor criteria must be met in some combination of different examples. It is not necessary to meet all criteria in a single example.Contracting
81Will the Government accept projects that involve occupied VA or healthcare facilities with MEP and utility tie-ins, but not a dedicated data center, as relevant?Contracting
82May offerors submit a combined portfolio of projects that collectively meet all requirements? For example, one project demonstrating medical MEP/phasing, and another demonstrating telecom/data infrastructure?Yes, examples provided must meet each requirement listed under Factor One at least twice across any combination of the examples provided.Contracting
83Will the Government consider data infrastructure upgrades (e.g., MDF/IDF rooms, telecom cabling, IT support spaces, or EMCS controls) as meeting the “data center” criterion?Contractor shall detail the specific work activities accomplished and explain their relevancy to the project requirements.Contracting
84For the civil infrastructure component, would trenching, duct banks, utility tie-ins, or similar site utility work satisfy the requirement?Yes, examples provided must meet each requirement listed under Factor One at least twice across any combination of the examples provided.Contracting
85Does the “occupied medical facility” requirement apply to the entire project scope, or may equivalent work in occupied federal facilities (e.g., DoD or FAA) also qualify?Other experience can be listed, however at least two examples of work performed in an occupied medical facility must be provided.Contracting
86Would projects performed in hospital support buildings (e.g., dietary, laundry, logistics) be considered within the definition of “active healthcare environment”?Yes, examples provided must meet each requirement listed under Factor One at least twice across any combination of the examples provided.Contracting
87Must every project submitted for Past Performance meet the $20M minimum, or is it acceptable to submit two or more $20M+ projects and use smaller projects to fulfill the remaining technical criteria?It is acceptable to submit two or more $20M+ projects and use smaller projects to fulfill the remaining technical criteria.Contracting
88Will the Government accept IDIQ contracts whose total value exceeds $20M, even if no single task order exceeds that amount?Projects submitted may be under $20M, but at least two projects must have a value of at least $20M to meet technical factor criteria.Contracting
89Can projects performed individually by JV members be combined to meet evaluation criteria, even if no single project includes all elements?Yes, examples provided must meet each requirement listed under Factor One at least twice across any combination of the examples provided.Contracting
90We and another company are approved participants in an SBA Mentor-Protégé Agreement (MPA), with us as the protégé and the other company as the mentor. If a protégé in an approved SBA Mentor-Protégé Agreement submits the proposal as the prime contractor under the MPA, with the mentor providing substantial contributions (e.g., key personnel, management support, or subcontracted scope), will the mentor’s past performance be fully considered under 13 CFR § 125.9(d)(1)(iii)? Also, will documentation of the MPA and a narrative of roles/responsibilities will be sufficient to justify this consideration?Past performance is not an evaluation factor for this solicitation.Contracting
91The following existing equipment is requested to provide new breakers :

A SWBD (page 01-EP604) B SWBD (page 01-EP605) Panel MDP (page 06-EP601) SWBD EMDP 1 (page 27-EP601) SWBD MDS (page 27-EP603) Can you please confirm the original equipment manufacturer for each of the above, and if possible the nameplate information? A SWBD (page 01-EP604) -- GE – AKD-8 Switch Gear – AKRU – 60 breaker type B SWBD (page 01-EP605) -- GE – AKD-8 Switch Gear – AKRU – 60 breaker type Panel MDP (page 06-EP601)- Panel MDP (page 06-EP601) – SIEMENS – Cat No. F1C75ML600ATS Breaker Type I.T.E Vacu-Break – Series A SWBD EMDP 1 (page 27-EP601) GE – Spectra Series Switchboard – Breaker model # SGLA36AT

SWBD MDS (page 27-EP603) Square D – Power Style Switch Board - CAT No – 44-72805-1 Type SW-3Elec Shop
92Is the contractor to assume ceilings in hallways are ACT drop ceilings unless noted otherwise?Contractor to review RCP plans in construction documents - ceiling information is provided.A&E
93Please confirm, are all horizontal interior fiber backbone conduit pathways existing to be reused, or is the contractor to assume these are all to be provided as new?All fiber pathways are to be provided.A&E
94Please confirm, is all work in hallways and work areas to be done during off hours (nights / weekends) so as not to disturb normal facility operations?Per Specification SECTION 01 00 00-
GENERAL REQUIREMENTS, part 1.6 F and G. Not all work will necessary have to be during these hours. There are hallways and work areas that can be worked during normal business hours 7AM-5PM. The ICRA Level will be a factor in this.Site
95Please confirm, is the contractor responsible for providing maxwell 3-cell innerduct for all new fiber backbone cable installed in new conduit?Yes, Innerduct shall be installed in all fiber filled conduits.Site
96Please confirm, the designated SSHO must be a separate individual from both the designated superintendent and QCM?Per Specification SECTION 01 35 26-
SAFETY REQUIREMENTS, part 1.7.Site
97Is the contractor required to hire an SIOR to oversee all special inspections?Yes. Per 01 45 35 - B Statement of Special InspectionsSite / Contracting
98Is the contractor required to hire a 3rd-party firestopping inspector as part of this contract?Per Specification SECTION 07 84 00-
FIRESTOPPING, Part 1.5 QUALITY ASSURANCE.Site
99Is the contractor required to hire a 3rd party geotechnical engineer as part of this project?Geotechnical reports are available.Geotechnical reports will be distributed to the contractor at the VA's discretion. Contractor is responsible for Special Inspections per specifications - the inspector for soil conditions must be qualified as indicated in specification section 01 45 35. There are multiple ways the contractor may meet these requirements.Site
100Is the contractor responsible for any abatement of asbestos or hazardous material beyond quantities provided in the specifications?No. An approved Change Order would be required before any abatement of asbestos or removal of hazardous material beyond quantities provided in the specifications.Site
101Will the contractor be limited to the amount of rooms / work areas that can be accessed simultaneously? Or will the contractor be allowed to sequence work areas as they see fit to best move the project along to meet the schedule?The faculty will work with the contractor to allow as many rooms/areas to be worked as possible, without affecting the operations of the hospital. The contractor can also sequence the work areas. See Phasing Plan.Site
102If room-specific phasing constraints are to be anticipated, for bidding purposes, please provide an approximate amount of rooms that will be turned over to the contractor at a time. For example, in past EHRM projects, bidders have been advised to assume access to only 3-4 Telecom Rooms, with work in each required to be completed in full before contractors would be permitted to advance to the next work area.This depends on where the work is being performed. Once a preliminary schedule is provided to the VA, it can be reviewed with the affected department and adjustments made if necessary. Also see Phasing Plan.Site
103Would HEPA carts be considered a sufficient means of infection control for contractors to use while working above ceilings in hallways?Yes, especially in patient care areas. A review of the cart will be made to assure it meets the facilities requirements, as this facility would not provide carts.ICRA
104Is the contractor permitted to utilize plastic barrier containments to isolate hallway sections during above ceiling hallway work? If so, must this work be done on off-hours so as not to disturb facility operations?Refer to Safety cause this will involve egress clearance requirements. ICRA barriers/carts may be setup during normal business hours but egress must be always maintained. In addition, noise must be kept to a minimum to avoid disruptions. Clearence requirements will change based on the area.Safety
105Is the contractor to assume new fire sleeves are required at all new through-wall cable penetrations at work areas calling for new cat6a cable drop locations?Yes. All penetrations shall have all new fire sleeves.Safety / A&E
106Is the contractor responsible for providing all new WAPs where shown on the T-drawings, or are these existing devices to receive new cable connections only?WAPs are existing and require recabling unless otherwise noted.Site
107Is there an existing proprietary fire alarm contractor at the facility? If so, please provide company name and point of contact.Yes, Johnson Controls is the proprietary vendor. Scott W Eyerman scott.william.eyerman@jci.com or Glenn Porpiglia d.glenn.porpiglia@jci.comSafety
108Is there an existing proprietary controls contractor at the facility? If so, please provide company name and point of contact.Yes, Johnson Controls is the proprietary BMS controls vendor. Scott W Eyerman scott.william.eyerman@jci.com or Glenn Porpiglia d.glenn.porpiglia@jci.comSafety
109Is there an existing proprietary PACS and/or CCTV contractor at the facility? If so, please provide company name and point of contact.Yes, HID Global is the proprietary vendor for PACS. Yes, Avigilon Video Surveillance is the proprietary vendor for CCTV.Security
110Where disturbed by construction, is grass area to be restored using seed or sod?Seed is acceptable.Site
111Is the contractor responsible for maintenance and watering for an establishment period of a predetermined duration after initial grass restoration? If so, how long is this establishment period?Contractor is responsible for watering the seed until it sprouts and grass is established. Water will be made available by the facility.Site
112Is this project Tax Exempt?Yes.Contracting
113Please confirm that all firestopping must be either installed by an FM global approved contractor, or a UL qualified firestop contractor certified.Per Specification SECTION 07 84 00-
FIRESTOPPING, Part 1.5 QUALITY ASSURANCE.Site
114If rooms are required to be isolated in phases, will there be any downtime in the schedule between phases to allow the VA time for relocation of staff / equipment / devices? If so, how much downtime should the contractor anticipate for this?This depends on where the work is being performed and the affected department. Once a preliminary schedule is provided to the VA, it can be reviewed with the affected department and adjustments made if necessary.Site
115Please confirm the contractor will be required to submit post award the requested information that the telecommunications contractor shall be a BICSI licensed Contractor with a minimum of five (5) years’ experience installing and servicing systems of similar scope and complexity. The Contractor shall provide four (4) current references from clients with systems of similar scope and complexity which became operational in the past three (3) years. At least three (3) of the references shall be utilizing the same system components, in a similar configuration as the proposed system. The references must include a current point of contact, company or agency name, address, telephone number, complete system description, date of completion, and approximate cost of the project.Please refer to the instructions to offerors for all requirements pertaining to this project.Contracting
116Please confirm that the telecommunications contractor must submit copies of system manufacturer certification for all technicians. The Contractor shall provide proof project superintendent with BICSI Certified Commercial Installer Level 1, Level 2, or Technician to provide oversight of the project.Specifications SECTION 28 13 53

SECURITY ACCESS DETECTION, Part 1.3 F. SECTION 28 23 00 VIDEO SURVEILLANCE, part 1.4 F and SECTION 28 13 00

PHYSICAL ACCESS CONTROL SYSTEM, part 1.3 E.Site
117Please confirm cable installer must have on staff a Registered Communication Distribution Designer (RCDD) certified by Building Industry Consulting Service International (BICSI).Specifications SECTION 28 13 53

SECURITY ACCESS DETECTION, Part 1.3 F. SECTION 28 23 00 VIDEO SURVEILLANCE, part 1.4 F and SECTION 28 13 00

PHYSICAL ACCESS CONTROL SYSTEM, part 1.3 E.Site
118Please confirm this project must meet the buy American act requirements.Yes.Contracting
119Please confirm level 4 finish for all finished gypsum board including patchesPer Specification section 09 29 00-Gypsum Board -230409, part 3.5 Finishing of Gypsum Board.Site
120Are we required to use plenum rated cabling for all areas? Can we use riser rated cabling in non plenum spaces?Per Specification section 27 15 13-
COMMUNICATIONS COPPER HORIZONTAL CABLING, part 2.1 GSite
121Will flexible metal conduit be allowed?Flexible metal conduit is acceptable when making connections to motors or vibrating loads per NEC.A&E
122Please confirm the VA will be working and scheduling with the subsystem vendors on scheduling network outages.Prime Contractor is resp. to schedule with all sub-contractors.Site / IT
123Please confirm the normal working hours of this contract are to be assumed as normal working hours; 7:00 am-5:00 pmSpecifications SECTION 01 00 00-
GENERAL REQUIREMENTS, part 1.6 G.Site
124Please confirm per section 01 00 00 that contractor is to provide a commercial photographer/subcontractor and that indexing/navigation will use AutoCAD drawings to be interactive online. Typically this has been waived on most other VA projects as most facilities do not have the capabilities to utilize AutoCAD.Part 1.33 of Spec Section 01 00 00 appears to have not been used.Site
125Can the contractor QC manager serve as the photographer if they meet the requirement of having experience photographing construction projects. The term “Commercial Photographer” is vague, has no licensing requirements or any other information required.Specifications SECTION 01 91 00
GENERAL COMMISSIONING REQUIREMENTS, Part 3.9 OPERATION AND MAINTENANCE TRAINING REQUIREMENTS. Paraghaph C.2 and D.3.Site
126Is it anticipated that unsuitable soil will be encountered on this project? If so, is the contractor responsible for removal and disposal of any unsuitable soils?No unsuitable soil is anticipated. Yes, contractor would be responsible for removal and disposal of any unsuitable soils. An approved Change Order would be required before any unsuitable soils were removed and disposed of.Site
127Please confirm, is the prime contractor required to directly hire the controls system integrator?The controls system integrator does not have to be a direct subcontractor of the prime contractor.Site
128Will there be PLA requirements on this project?Contracting
129Please confirm, are all new cat6a cables to be factory terminated?Per Specification section 27 15 13-

COMMUNICATIONS COPPER HORIZONTAL CABLING, part 2.1 D & E and SECTION 27 13 13.13- COMMUNICATIONS COPPER CABLE SPLICING AND TERMINATIONS, part 3. Site