This document is Amendment 0002 to Solicitation 36C77625R0021 for a Design-Build project to construct a parking structure at the VA Northern California Health Care System in Mather, California. The amendment makes several key changes to the original solicitation, including revising Phase I technical qualification requirements and extending the relevant project experience timeframe to 8 years due to COVID-19 impacts.
The revised technical qualifications section now requires detailed documentation for key personnel, including resumes for specific roles such as Design-Build Project Manager, Construction Project Manager, Quality Control Specialist, and various engineering leads. Offerors must provide an organizational chart, list of consultants and subcontractors, personnel capacity, current project details, and descriptions of management approaches, peer review techniques, and quality assurance plans. The amendment also removes previous language about personnel experience evaluation and includes attachments addressing Request for Information (RFI) responses, as-built record drawings, and contractor-related documents.
View the file
Other files
Show all 30
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Amendment 0002 posting for 36C77625R0021
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) 612-165 36C776 Department of Veterans Affairs Program Contracting Activity Central 6100 Oak Tree Blvd, Suite 490 Independence
OH
44131 36C776 Department of Veterans Affairs Program Contracting Activity Central 6100 Oak Tree Blvd, Suite 490 Independence
OH
44131 To all Offerors/Bidders
36C77625R0021 05-19-2025
X X X See continuation page for details of amendment 0002 to 36C77625R0021
William Henkel Contracting Officer
CONTINUATION PAGE
The purpose of amendment 0002 to RFP 36C77625R0021 is the following:
1. To answer RFI’s from industry contained in attachment 1
2. The following change has been made to Phase I criteria in Section 2.7 Proposal Requirements, Part B. Factor 2 technical Qualifications is hereby revised it its entirety to the following:
The Offeror shall submit an organizational chart and indicate the prime responsible firm (or firms, if a J/V) and individuals, as well as the roles and responsibilities of individuals proposed as consultants and subcontractors. Provide a list of all consultants and all proposed major subcontractors, including telephone number, address, and name of contact.
The Offeror shall provide resumes that describes the design build team’s qualifications, to include education and/or certification(s), of the following personnel (page limitation, two (2) pages per requested resume):
| • | Design-Build Project Manager |
| • | Construction Project Manager/Site Superintendent |
| • | On-site Quality Control Specialist |
| • | Lead Architect |
| • | Lead Structural Engineer |
| • | Lead MEP Engineer |
| • | Lead Civil Engineer |
| • | Fire Protection Engineer |
*Dual hatting will not be allowed. There is no preprinted form for this submittal.
For each of these required key personnel, the offeror shall identify the available capacity and any current projects they are working along with the anticipated completion dates.
The Offeror shall describe its approach for managing performance under this solicitation, including techniques for management of work coordination with subcontractors and measures/corrective action that will be taken for substandard performance. The Offeror shall describe proposed Design-Build Peer Review techniques along with the Quality Assurance/Quality Control Plan.
Evaluation Methodology: Technical Qualifications will evaluate the relevant management, required technical personnel, and subcontractor capabilities and qualifications of the team to provide the required planning, implementation, and completion of the project. The VA will consider education and certifications, as well as relevant experience in an operational health care facility. The VA will also evaluate how the Offeror organized personnel for this project, and the lines of authority between the construction firm, design firm, and key subcontractors
3. The following language is removed from Phase I criteria in Section 2.7 Proposal Requirements, Part B. Factor 3 Past Performance:
“The evaluation shall consider the specific experience (minimum of five years) and qualifications (i.e., education, training, registration, certifications, overall relevant experience, and longevity with the firm as full-time employees) of personnel proposed for assignment to the project, and their record of working together as a team when evaluating professional qualifications.”
In response to the inquiry regarding the limited project activity during the COVID era, the Government agrees to extend the allowable timeframe for relevant project experience and past performance submissions. Offerors may now include projects completed within the last 8 years from the date of this solicitation
See attached document: 0002 Attachment 1 Answers to RFIs Martinez CA 6.3.25.
See attached document: 0002 Attachment 2 as built Record drawings.
See attached document: 0002 Attachment 3 WMC Contractor Request FEB 2025.
See attached document: 0002 Attachment 4 VHA COR Contractor Security Presentation April 2025 Final.
End of Document
File details come from the government source that posted it. Updated .