This document is a Price/Cost Schedule (Section B.2) for a Department of Veterans Affairs (VA) solicitation for Jacksonville Initial Outfitting Transition and Activation (IOTA) Services, RFQ 36C77625Q0253. The pricing schedule outlines a 36-month base period from 10-10-2025 to 10-09-2028 for pre-activation IOTA services and associated travel, with optional tasks including warehousing, activation services, and additional travel. The optional tasks can be exercised as needed according to the project schedule, with potential additional 6-month periods from 09-15-2028 to 04-09-2029. The document provides a structured pricing framework with line items for different service components, allowing space for unit pricing to be filled in by the offeror, with a grand total to be calculated at the time of proposal submission.

View the file

Other files

File Type Posted
A0002 - ATTACHMNET S - Jacksonville Area CBOCs.pdf PDF
Questions and Answers - Jacksonville MSOC IOTA.pdf PDF
A0002 - ATTACHMENT R- Pricing Worksheet - Jacksonville.xlsx XLSX spreadsheet
S06 - 36C77625Q0253 0002.docx DOCX document
36C77625Q0253 0001.docx DOCX document
ATTACHMENT R- Pricing Worksheet - Jacksonville.xlsx XLSX spreadsheet
ATTACHMENT Q - Rooms Content list Jacksonville NC OPC.xlsx XLSX spreadsheet
ATTACHMENT O - VSC Security Package 7.15.2025.pdf PDF
ATTACHMENT I - Equipment Inventory_ReUse and Disposal Plan Template.xlsx XLSX spreadsheet
ATTACHMENT H - Integrated Move Plan Template.xlsx XLSX spreadsheet
ATTACHMENT F - WBS Template.pdf PDF
ATTACHMENT J - Proposed FTE Report.xlsx XLSX spreadsheet
ATTACHMENT G - Contents Acq Plan Template 9.21.2023.xlsx XLSX spreadsheet
ATTACHMENT D - Risk Management Plan and Register Template.xlsx XLSX spreadsheet
ATTACHMENT C - Contract Staff Roster.pdf PDF
ATTACHMENT M - QASP.pdf PDF
ATTACHMENT L - Procurement Package Template and 6500 5.20.2025.pdf PDF
ATTACHMENT K - Furniture IDIQ Templates.pdf PDF
ATTACHMENT E - Change Management Plan and Log Template.xlsx XLSX spreadsheet
ATTACHMENT P - Wage Determination.pdf PDF
ATTACHMENT N - PDAT Summary - IOTA.pdf PDF
ATTACHMENT B - Travel Authorization Request.pdf PDF
ATTACHMENT A - FINAL IOTA PWS Jacksonville MSOC.pdf PDF
36C77625Q0253_1.docx DOCX document
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

B.2 PRICE/COST SCHEDULE

ITEM INFORMATION

ITEM NUMBER
DESCRIPTION OF SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
36.00
MO
_________________
_________________

Pre-Activation IOTA Services IAW PWS Sections 16.1, 16.2, 16.3, 16.4, and 16.5

* Period of Performance is based on an estimated date of award. 36-month Period of Performance to be finalized at time of award.

Contract Period: Base POP Begin: 10-10-2025 POP End: 10-09-2028

36.00
MO
_________________
_________________

Travel - Pre-Activation

* Period of Performance is based on an estimated date of award. 36-month Period of Performance to be finalized at time of award.

Contract Period: Base POP Begin: 10-10-2025 POP End: 10-09-2028

6.00
MO
_________________
_________________

Optional Task: Warehousing & Warehousing Management Services IAW PWS Section 17.1 *Optional Tasks are exercised at time of need according to the project schedule. The Period of Performance begin date is 6 months.

Contract Period: Option 1 POP Begin: 09-15-2028 POP End: 03-14-2029

6.00
MO
_________________
_________________

Optional Task: Activation Services IAW PWS Section 16.1, 17.2, 17.3, and 17.4

* Optional Tasks are exercised at time of need according to the project schedule. 6-month Period of Performance to be finalized at time of award.

Contract Period: Option 1 POP Begin: 10-10-2028 POP End: 04-09-2029

6.00
MO
_________________
__________________

Optional Task: Travel Activation

* Optional Tasks are exercised at time of need according to the project schedule. 6-month Period of Performance to be finalized at time of award.

Contract Period: Option 2 POP Begin: 10-10-2028 POP End: 04-09-2029

GRAND TOTAL
__________________

36C77625Q0253

Page 1 of Page 1 of