Amendment 0002 Attachment 1 Additional RFIs 7 9 24.docx
DOCX document 32 KB Posted
- Solicitation number
- 36C77624R0079_1
About this file
This document is an amendment to a Request for Information (RFI) related to a federal contract opportunity for the expansion of a Mental Health Clinic at the Wilkes-Barre VA Medical Center.
The amendment provides responses to three questions received regarding the project. The questions cover concrete patching methods, the need for shotcrete, and the requirements for temporary shoring. The government responses clarify that two concrete patching methods are acceptable, no shotcrete is required, and temporary shoring is not needed unless conditions vary from the provided record documents. The related federal contract opportunity is a competitive Service-Disabled Veteran-Owned Small Business (SDVOSB) set-aside solicitation for the Wilkes-Barre VA Medical Center expansion project. The contractor will be required to provide all labor, project management, materials, tools, supplies, and equipment necessary to complete the work as specified in the drawings and documents.
View the file
Other files
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ITEM
NO.
| DATE QUESTION RECEIVED |
| DATE QUESTION ANSWERED |
| QUESTION |
| GOVERNMENT RESPONSE |
| 1. |
| 6/18/2024 |
| 7/09/2024 |
| Regarding concrete patching the floor from through floor Plumbing demolition, may the method be tapcon into the underside of the existing floor, caulk perimeter then concrete patch from above? |
| Yes – we listed two acceptable methods, the method stated above and another system that can be filled from the floor the hole is on. |
| 2. |
| 6/18/2024 |
| 7/09/2024 |
| There are Shotcrete Specifications, please clarify where this work is on the Drawings. |
| No shotcrete is required. |
| 3. |
| 6/18/2024 |
| 7/09/2024 |
| Please provide load requirements, detail and exactly clarify where the temporary shoring is required for this project. |
Temporary shoring is not required. Design accounts for existing conditions as provided in record documents. Should conditions vary upon construction, notify the EOR.