Amendment 0002 Attachment 1 Additional RFIs 7 9 24.docx

DOCX document 32 KB Posted

Attached to
Z2DA--Expand Mental Health Clinic Construction Wilkes Barre (VA-24-00034565)
Solicitation number
36C77624R0079_1
Issued by

About this file

This document is an amendment to a Request for Information (RFI) related to a federal contract opportunity for the expansion of a Mental Health Clinic at the Wilkes-Barre VA Medical Center.

The amendment provides responses to three questions received regarding the project. The questions cover concrete patching methods, the need for shotcrete, and the requirements for temporary shoring. The government responses clarify that two concrete patching methods are acceptable, no shotcrete is required, and temporary shoring is not needed unless conditions vary from the provided record documents. The related federal contract opportunity is a competitive Service-Disabled Veteran-Owned Small Business (SDVOSB) set-aside solicitation for the Wilkes-Barre VA Medical Center expansion project. The contractor will be required to provide all labor, project management, materials, tools, supplies, and equipment necessary to complete the work as specified in the drawings and documents.

View the file

Other files

File Type Posted
Amendment 0003 36C77624R0079.pdf PDF
Amendment 0002 36C77624R0079.pdf PDF
Amendment 0002 Attachment 2 6007 Wilkes-Barre Geotechnical Report.pdf PDF
Amendment 0001 Attachment 3 -VA Signage Design Manual.pdf PDF
Amendment 0001 36C77624R0079.pdf PDF
Amendment 0001 Attachment 1 RFIs - Expand Mental Health Wilkes-Barre Final.docx DOCX document
Amendment 0001 Attachment 4 - Const Wage Determination Luzern 6.28.24.pdf PDF
Amendment 0001 Attachment 5 -Site Visit SIgn In Sheet.pdf PDF
Amendment 0001 Attachment 2 -Adendum 01.zip ZIP file
Attachment 9 -Site Visit Instructions Wilkes-Barre.docx DOCX document
36C77624R0079_1.pdf PDF
Attachment 11- Site Map.pdf PDF
Attachment 3- Drawings - EMHC - Part 2 of 4.pdf PDF
Attachment 12 - Limitations on Subcontracting - Construction.docx DOCX document
Attachment 2- Drawings - EMHC - Part 1 of 4.pdf PDF
Attachment 7- Construction Wage Determination 5.31.pdf PDF
Attachment 1- Specs - EMHC.pdf PDF
Attachment 4- Drawings - EMHC - Part 3 of 4.pdf PDF
Attachment 9 -Site Visit Instructions Wilkes-Barre.docx DOCX document
Attachment 5- Drawings - EMHC - Part 4 of 4.pdf PDF
Attachment 8- Service Wage Determination.pdf PDF
Attachment 10- Brand Name_Redacted.pdf PDF
Attachment 6- Asbestos Reports - Wilkes-Barre.pdf PDF
Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ITEM

NO.

DATE QUESTION RECEIVED
DATE QUESTION ANSWERED
QUESTION
GOVERNMENT RESPONSE
1.
6/18/2024
7/09/2024
Regarding concrete patching the floor from through floor Plumbing demolition, may the method be tapcon into the underside of the existing floor, caulk perimeter then concrete patch from above?
Yes – we listed two acceptable methods, the method stated above and another system that can be filled from the floor the hole is on.
2.
6/18/2024
7/09/2024
There are Shotcrete Specifications, please clarify where this work is on the Drawings.
No shotcrete is required.
3.
6/18/2024
7/09/2024
Please provide load requirements, detail and exactly clarify where the temporary shoring is required for this project.

Temporary shoring is not required. Design accounts for existing conditions as provided in record documents. Should conditions vary upon construction, notify the EOR.

image1.emf