Revised Specs - Mountain Home EHRM - Vol. 1.pdf

PDF 11 MB Posted

Attached to
Y1DA--EHRM Infrastructure Upgrade Construction - Mountain Home Federal contract opportunity
Solicitation number
36C77624B0024
Issued by
Department of Veterans Affairs Technology Acquisition Center Austin

About this file

This document is a comprehensive set of technical specifications for the EHRM Infrastructure Upgrades project at the James H. Quillen VA Medical Center in Mountain Home, Tennessee. The specifications cover multiple technical divisions including architectural, mechanical, electrical, plumbing, fire protection, and communications systems upgrades for various buildings on the medical center campus. The project involves infrastructure improvements across Buildings 3, 5, 8, 37, 160, 162, 200, 204, and 205, with a focus on modernizing existing facilities.

The specifications detail precise requirements for demolition, construction, materials, installation, and commissioning of building systems. Key components include thermal insulation, firestopping, joint sealants, access doors, interior wood doors, hollow metal doors and frames, and blast-resistant glazing systems. The project emphasizes sustainable construction practices, with requirements for recycled content, low-pollutant emitting materials, and energy efficiency. The contract number is 36C77622C0129, with a project completion date of May 22, 2025, and is being executed through the Department of Veterans Affairs Technology Acquisition Center in Austin.

View the file

Other files for this federal contract opportunity

Other files attached to Y1DA--EHRM Infrastructure Upgrade Construction - Mountain Home, newest first.
File Type Posted
Redacted Bid Opening Abstract Statement - Mountain Home EHRM.pdf PDF
36C77624B0024 0011.docx DOCX document
Bid Opening Attendees List.docx DOCX document
36C77624B0024 0010.docx DOCX document
36C77624B0024 0009.docx DOCX document
Updated Technical Question Tracker - Mountain Home EHRM.xlsx XLSX spreadsheet
36C77624B0024 0008.docx DOCX document
Corrected Revised Specs - Mountain Home EHRM - Vol. 2.pdf PDF
Corrected Revised Specs - Mountain Home EHRM - Vol. 1.pdf PDF
Corrected Revised Drawings - Mountain Home EHRM - Vol. 2.pdf PDF
36C77624B0024 0007.docx DOCX document
Revised Drawings - Mountain Home EHRM - Vol. 1.pdf PDF
36C77624B0024 0006.docx DOCX document
Revised Specs - Mountain Home EHRM - Vol. 2.pdf PDF
Revised Drawings - Mountain Home EHRM - Vol. 2.pdf PDF
Attachment 12 - RFI 39 - WAO Pricing.docx DOCX document
Technical Question Tracker - Mountain Home EHRM.xlsx XLSX spreadsheet
Revised Attachment 10 - Rooms Descoped From Project.docx DOCX document
36C77624B0024 0005.docx DOCX document
36C77624B0024 0004.docx DOCX document
36C77624B0024 0003.docx DOCX document
Attachment 12 - Redacted Brand Name Justification.pdf PDF
Attachment 8 - Wage Determination - Washington County TN - 6-6-2025.pdf PDF
36C77624B0024 0002.docx DOCX document
S06 - 36C77624B0024 0001.docx DOCX document
S06 - Site Visit Sign In Sheet.pdf PDF
36C77624B0024.docx DOCX document
Attachment 2 - EHRM_IFB_Spec_Vol2_05222025 1.pdf PDF
Attachment 4b - EHRM_Moutain Home_EHRM_IFB_Dwgs VOL 2b.pdf PDF
Attachment 7 - Asbestos Survey Report 2.pdf PDF
Attachment 1 - EHRM_IFB_Spec_Vol1_05222025 1.pdf PDF
Attachment 10 - Rooms Descoped From Project.docx DOCX document
Attachment 4a - EHRM_Moutain Home_EHRM_IFB_Dwgs VOL 2a.pdf PDF
Attachment 11 - Site Visit Instructions.docx DOCX document
Attachment 8 - Construction Wage Rates - Washington County TN - 5-2-25.pdf PDF
Attachment 9 - Limitations on Subcontracting - Construction.docx DOCX document
Attachment 3a - EHRM_Moutain Home_EHRM_IFB_Dwgs VOL 1a.pdf PDF
Attachment 3b - EHRM_Moutain Home_EHRM_IFB_Dwgs VOL 1b.pdf PDF
Attachment 5 - List of TRs and TEs 5.20.2025.pdf PDF
Attachment 6 - Mtn Home Port List Report.xlsx XLSX spreadsheet
Show all 40

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Specifications

James H. Quillen VA Medical Center

Lamont Street & Veterans Way

Johnson City, TN 37684

EHRM Infrastructure Upgrades

ISSUED FOR BID

Volume 1

Divisions 00-02, 04, 06-10, 13

May 22, 2025

Chris Carter

BICSI ID # 136803

EXPIRES 12-31-27

L

I

C

E N

S

E

D

P

R

O

F

E

SS

I O

N

A

L

E

N

G

I N

E

E

R

O

K

L

AH

O

M

A

DIVISION 00

EHRM Infrastructure Upgrades

Bancroft Architects + Engineers

01-01-21

Contract No. 36C77622C0129

Station Project No. 621-22-700

Bancroft-AE Project No. 22-114 05/22/2025

00 01 10-1

Table of Contents

DEPARTMENT OF VETERANS AFFAIRS

VHA MASTER SPECIFICATIONS

TABLE OF CONTENTS

Section 00 01 10

SECTION NO. DIVISION AND SECTION TITLES DATE

DIVISION 00 - SPECIAL SECTIONS

00 01 10 Table of Contents 01-21

00 01 15 List of Drawing Sheets 05-20

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 General Requirements 01-21

01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build) 03-20

01 33 23 Shop Drawings, Product Data, and Samples 05-17

01 33 24 Electronic Submittal Procedures (Web-based Service) 01-21

01 35 26 Safety Requirements 07-20

01 42 19 Reference Standards 11-20

01 45 29 Testing Laboratory Services 11-18

01 45 35 Special Inspections 03-19

01 57 19 Temporary Environmental Controls 01-21

01 58 16 Temporary Interior Signage 07-15

01 74 19 Construction Waste Management 01-21

01 81 13 Sustainable Construction Requirements 10-17

01 91 00 General Commissioning Requirements 10-15

DIVISION 02 – EXISTING CONDITIONS

02 41 00 Demolition 08-17

DIVISION 03 – CONCRETE (NOT USED)

DIVISION 04 – MASONRY

04 01 00 Maintenance of Masonry 01-21

DIVISION 05 – METALS (NOT USED)

DIVISION 06 – WOOD, PLASTICS AND COMPOSITES

06 10 00 Rough Carpentry 10-17

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 01 50.19 Preparation for Re-Roofing 01-21

EHRM Infrastructure Upgrades

Bancroft Architects + Engineers

01-01-21

Contract No. 36C77622C0129

Station Project No. 621-22-700

Bancroft-AE Project No. 22-114 05/22/2025

00 01 10-2

Table of Contents

SECTION NO. DIVISION AND SECTION TITLES DATE

07 08 00 Facility Exterior Closure Commissioning 01-21

07 21 13 Thermal Insulation 01-21

07 81 00 Applied Fireproofing 10-17

07 84 00 Firestopping 01-21

07 92 00 Joint Sealants 10-17

DIVISION 08 - OPENINGS

08 11 13 Hollow Metal Doors and Frames 01-21

08 14 00 Interior Wood Doors 01-21

08 31 13 Access Doors and Frames 01-21

08 56 53 Blast Resistant Windows 12-22

08 71 00 Door Hardware 01-21

DIVISION 09 – FINISHES

09 05 16 Subsurface Preparation for Floor Finishes 01-21

09 22 16 Non-Structural Metal Framing 06-18

09 29 00 Gypsum Board 04-20

09 51 00 Acoustical Ceilings 12-18

09 65 13 Resilient Base and Accessories 01-21

09 65 19 Resilient Tile Flooring 05-18

09 65 20 Conductive Electro-Static Dissipative Resilient Tile

Flooring

09 68 00 Carpeting 01-21

09 91 00 Painting 01-21

DIVISION 10 – SPECIALTIES

10 14 00 Signage 01-21

10 26 00 Wall and Door Protection 01-21

10 44 13 Fire Extinguisher Cabinets 08-18

DIVISION 11 – EQUIPMENT (NOT USED)

DIVISION 12 – FURNISHINGS (NOT USED)

DIVISION 13 - SPECIAL CONSTRUCTION

13 05 41 Seismic Restraint Requirements for Non-Structural

Components

01-14

DIVISION 14– CONVEYING EQUIPEMENT (NOT USED)

DIVISION 21- FIRE SUPPRESSION

21 08 00 Commissioning of Fire Suppression System 11-16

21 13 13 Wet-Pipe Sprinkler Systems 06-15

EHRM Infrastructure Upgrades

Bancroft Architects + Engineers

01-01-21

Contract No. 36C77622C0129

Station Project No. 621-22-700

Bancroft-AE Project No. 22-114 05/22/2025

00 01 10-3

Table of Contents

DIVISION 22 – PLUMBING

22 05 11 Common Work Results for Plumbing 09-20

22 08 00 Commissioning of Plumbing Systems 11-16

22 11 00 Facility Water Distribution 11-19

22 13 00 Facility Sanitary and Vent Piping 09-20

DIVISION 23 – HEATING, VENTILATING, AND AIR

CONDITIONING (HVAC)

23 05 11 Common Work Results for HVAC 02-20

23 05 12 General Motor Requirements for HVAC Equipment 02-20

23 05 41 Noise and Vibration Control for HVAC Piping and

Equipment

02-20

23 05 93 Testing, Adjusting, and Balancing for HVAC 02-20

23 07 11 HVAC Insulation 02-20

23 08 00 Commissioning of HVAC Systems 02-20

23 09 23 Direct-Digital Control System for HVAC 09-11

23 21 13 Hydronic Piping 02-20 23 23 00 Refrigerant Piping 02-20

23 31 00 HVAC Ducts and Casings 02-20

23 36 00 Air Terminal Units 02-20

23 37 00 Air Outlets and Inlets 02-20

23 81 00 Decentralized Unitary HVAC Equipment 03-20

DIVISION 25 – INTEGRATED AUTOMATION (NOT USED)

DIVISION 26 – ELECTRICAL

26 05 11 Requirements for Electrical Installations 01-16

26 05 19 Low-Voltage Electrical Power Conductors and Cables 01-17

26 05 26 Grounding and Bonding for Electrical Systems 01-17

26 05 33 Raceway and Boxes for Electrical Systems 01-18

26 05 36 Wireways for Radiology Equipment 01-18

26 05 39 Underfloor Raceways for Electrical Systems 01-18

26 05 41 Underground Electrical Construction 01-17

26 09 23 Lighting Controls 01-18

26 22 00 Low-Voltage Transformers 01-18

26 24 16 Panelboards 01-18

EHRM Infrastructure Upgrades

Bancroft Architects + Engineers

01-01-21

Contract No. 36C77622C0129

Station Project No. 621-22-700

Bancroft-AE Project No. 22-114 05/22/2025

00 01 10-4

Table of Contents

SECTION NO. DIVISION AND SECTION TITLES DATE

26 26 00 Power Distribution Units for Static Uninterruptible

Power Systems

01-18

26 27 26 Wiring Devices 01-18

26 33 53 Static Uninterruptible Power Supply 01-17

26 51 00 Interior Lighting 01-18

DIVISION 27 – COMMUNICATIONS

27 05 26 Grounding and Bonding for Communications Systems 01-22

27 05 33 Raceways and Boxes for Communications Systems 01-22

27 05 36 Cable Trays for Communications Systems 01-22

27 05 53 Identification for Communications Systems 01-22

27 10 00 Structured Cabling 01-22

27 11 16 Communications Cabinets, Racks, Frames and Enclosures 01-22

27 11 19 Communications Terminations Blocks and Patch Panels 01-22

27 11 26 Communications Rack Mounted Power Protection and Power

Strips

01-22

27 13 13 Communications Copper Backbone Cabling 01-22

27 13 13.13 Communications Copper Splicing and Terminations 01-22

27 13 23 Communications Optic Backbone Cabling 01-22

27 13 23.13 Communications Optic Splicing and Terminations 01-22

27 15 13 Communications Copper Horizontal Cabling 01-22

27 15 19 Communications Patch Cords, Station Cords, and Cross

Connect Wire

01-22

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

28 05 00 Common Work Results for Electronic Safety and Security 04-18

28 05 13 Conductors and Cables for Electronic Safety and

Security

10-18

28 05 26 Grounding and Bonding for Electronic Safety and

Security

09-11

28 05 28.33 Conduits and Backboxes for Electronic Safety and

Security

09-11

28 08 00 Commissioning of Electronic Safety and Security Systems 11-16

28 13 00 Physical Access Control System 10-11

28 16 00 Intrusion Detection System 10-11

28 23 00 Video Surveillance 09-11

28 31 00 Fire Detection and Alarm 10-11

DIVISION 31 – EARTHWORK

31 20 00 Earthwork 07-16

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 05 23 Cement and Concrete for Exterior Improvements 08-16

32 12 16 Asphalt Paving 09-15

32 17 23 Pavement Markings 08-16

EHRM Infrastructure Upgrades

Bancroft Architects + Engineers

01-01-21

Contract No. 36C77622C0129

Station Project No. 621-22-700

Bancroft-AE Project No. 22-114 05/22/2025

00 01 10-5

Table of Contents

32 90 00 Planting

DIVISION 33 – UTILITIES (NOT USED)

DIVISION 34 – TRANSPORTATION (NOT USED)

DIVISION 48 – Electrical Power Generation (NOT USED)

Appendix A

Appendix A – Structural Calculations

Mountain Home, TN 37684

Bancroft Architects + Engineers

05-01-20

Contract No. 36C77622C0129

Station Project No. 621-22-700

Bancroft-AE Project No. 22-114 05/22/2025 00 01 15 - 1

SECTION 00 01 15

LIST OF DRAWING SHEETS

The drawings listed below accompanying this specification form a part of the contract.

Drawing No. Title

GENERAL

G001 GENERAL - COVER SHEET

G002A GENERAL - DRAWING INDEX (1 OF 3)

G002B GENERAL - DRAWING INDEX (2 OF 3)

G002C GENERAL - DRAWING INDEX (3 OF 3)

GI001 GENERAL - CONTRACTOR & BOD PROTOCOL NOTES

GI002 GENERAL - PROTECTION PROTOCOLS AND MISCELLANEOUS NOTES

GI003 GENERAL - ABBREVIATIONS, SYMBOLS, LEGENDS AND MOUNTING HEIGHTS

GI101 GENERAL - INFECTION CONTROL CLASS IV AND GENERAL NOTES

GI102 GENERAL - INFECTION CONTROL - SAMPLE PCRA & ILSM FORMS

GI201 GENERAL - SITE ORIENTATION PLAN

GI301A GENERAL - TRAFFIC MANAGEMENT & STAGING PLAN - AREA A

GI301B GENERAL - TRAFFIC MANAGEMENT & STAGING PLAN - AREA B

GI301C GENERAL - TRAFFIC MANAGEMENT & STAGING PLAN - AREA C

CIVIL

CU100 CIVIL - OVERALL UTILITY PLAN

CU101 CIVIL - UTILITY PLAN (SHEET 1 OF 6)

CU102 CIVIL - UTILITY PLAN (SHEET 2 OF 6)

CU103 CIVIL - UTILITY PLAN (SHEET 3 OF 6)

CU104 CIVIL - UTILITY PLAN (SHEET 4 OF 6)

CU105 CIVIL - UTILITY PLAN (SHEET 5 OF 6)

CU106 CIVIL - UTILITY PLAN (SHEET 6 OF 6)

CD101 CIVIL – DETAIL SHEET (SHEET 1 OF 2)

CD102 CIVIL – DETAIL SHEET (SHEET 2 OF 2)

Contract No. 36C77622C0129

Station Project No. 621-22-700

Bancroft-AE Project No. 22-114 05/22/2025 00 01 15 - 2

HAZARDOUS MATERIALS

HA-3-100 HAZARDOUS ABATEMENT – BLDG 3 – GROUND FLOOR & ENLARGED PLANS

HA-3-101 HAZARDOUS ABATEMENT – BLDG 3 – FIRST FLOOR & ENLARGED PLANS

HA-3-102 HAZARDOUS ABATEMENT – BLDG 3 – SECOND FLOOR & ENLARGED PLANS

HA-5-100 HAZARDOUS ABATEMENT – BLDG 5 – GROUND FLOOR & ENLARGED PLANS

HA-5-101 HAZARDOUS ABATEMENT – BLDG 5 – FIRST FLOOR & ENLARGED PLANS

HA-5-102 HAZARDOUS ABATEMENT – BLDG 5 – SECOND FLOOR & ENLARGED PLANS

HA-8-100 HAZARDOUS ABATEMENT – BLDG 8 – GROUND FLOOR & ENLARGED PLANS

HA-8-101 HAZARDOUS ABATEMENT – BLDG 8 – FIRST FLOOR & ENLARGED PLANS

HA-8-102 HAZARDOUS ABATEMENT – BLDG 8 – SECOND FLOOR & ENLARGED PLANS

HA-8-103 HAZARDOUS ABATEMENT – BLDG 8 – THIRD FLOOR & ENLARGED PLANS

HA-34-100 HAZARDOUS ABATEMENT – BLDG 34 – BASEMENT & ENLARGED PLANS

HA-34-101 HAZARDOUS ABATEMENT – BLDG 34 – FIRST FLOOR & ENLARGED PLANS

HA-37-100 HAZARDOUS ABATEMENT – BLDG 37 – GROUND FLOOR & ENLARGED PLANS

HA-37-101 HAZARDOUS ABATEMENT – BLDG 37 – FIRST FLOOR & ENLARGED PLANS

HA-37-102 HAZARDOUS ABATEMENT – BLDG 37 – SECOND FLOOR & ENLARGED PLANS

HA-77-100 HAZARDOUS ABATEMENT – BLDG 77 – BASEMENT LEVEL OVERALL PLAN

HA-77-101 HAZARDOUS ABATEMENT – BLDG 77 – LEVEL 1 PLAN OVERALL

HA-77-102 HAZARDOUS ABATEMENT – BLDG 77 – LEVEL 2 PLAN OVERALL

HA-77-103 HAZARDOUS ABATEMENT – BLDG 77 – LEVEL 3 PLAN OVERALL

HA-160-101 HAZARDOUS ABATEMENT – BLDG 160 – FIRST FLOOR PLAN

HA-160-102 HAZARDOUS ABATEMENT – BLDG 160 – SECOND FLOOR PLAN

HA-160-103 HAZARDOUS ABATEMENT – BLDG 160 – LEVEL 3 PLAN OVERALL

HA-160-104 HAZARDOUS ABATEMENT – BLDG 160 – LEVEL 4 PLAN OVERALL

HA-162-101 HAZARDOUS ABATEMENT – BLDG 162 – LEVEL 1 PLAN OVERALL

HA-162-102 HAZARDOUS ABATEMENT – BLDG 162 – LEVEL 2 PLAN OVERALL

HA-200-100 HAZARDOUS ABATEMENT – BLDG 200 – BASEMENT OVERALL

HA-200-101 HAZARDOUS ABATEMENT – BLDG 200 – LEVEL 1 OVERALL

HA-200-102 HAZARDOUS ABATEMENT – BLDG 200 – LEVEL 2 OVERALL

HA-201-101 HAZARDOUS ABATEMENT – BLDG 200 – LEVEL 1 PLAN OVERALL

HA-204-100 HAZARDOUS ABATEMENT – BLDG 204 – GROUND LEVEL PLAN

Contract No. 36C77622C0129

Station Project No. 621-22-700

Bancroft-AE Project No. 22-114 05/22/2025 00 01 15 - 3

HA-204-101 HAZARDOUS ABATEMENT – BLDG 204 – LEVEL 1 PLAN

HA-204-102 HAZARDOUS ABATEMENT – BLDG 204 – LEVEL 2 PLAN

ARCHITECTURAL

A-001 ARCHITECTURAL - GENERAL NOTES AND SYMBOLS

A-3-10G ARCHITECTURAL - BLDG 3 -GROUND FLOOR OVERALL & ENLARGED PLANS

A-3-101 ARCHITECTURAL - BLDG 3 - FIRST FLOOR OVERALL & ENLARGED PLANS

A-3-102 ARCHITECTURAL - BLDG 3 - SECOND FLOOR OVERALL & ENLARGED PLANS

A-5-10G ARCHITECTURAL - BLDG 5 - GROUND FLOOR OVERALL & ENLARGED PLANS

A-5-101 ARCHITECTURAL - BLDG 5 - FIRST FLOOR OVERALL & ENLARGED PLANS

A-5-102 ARCHITECTURAL - BLDG 5 - SECOND FLOOR OVERALL & ENLARGED PLANS

A-8-10G ARCHITECTURAL - BLDG 8 - GROUND FLOOR OVERALL & ENLARGED PLANS

A-8-101 ARCHITECTURAL - BLDG 8 - FIRST FLOOR OVERALL & ENLARGED PLANS

A-8-102 ARCHITECTURAL - BLDG 8 - SECOND FLOOR OVERALL & ENLARGED PLANS

A-8-103 ARCHITECTURAL - BLDG 8 - THIRD FLOOR OVERALL & ENLARGED PLANS

A-15-10B ARCHITECTURAL - BLDG 15 - BASEMENT PLAN

A-17-10B ARCHITECTURAL - BLDG 17 - BASEMENT & SECOND FLOOR PLAN

A-19-10B ARCHITECTURAL - BLDG 19 - BASEMENT PLAN

A-34-10B ARCHITECTURAL - BLDG 34 - BASEMENT & ENLARGED PLANS

A-34-101 ARCHITECTURAL - BLDG 34 - FIRST FLOOR & ENLARGED PLANS

A-34-102 ARCHITECTURAL - BLDG 34 - SECOND FLOOR PLAN

A-35-10B ARCHITECTURAL - BLDG 35 - BASEMENT PLAN

A-35-101 ARCHITECTURAL - BLDG 35 - FIRST FLOOR PLAN

A-36-10B ARCHITECTURAL - BLDG 36 - BASEMENT PLAN

A-37-10G ARCHITECTURAL - BLDG 37 - GROUND FLOOR & ENLARGED PLANS

A-37-101 ARCHITECTURAL - BLDG 37 - FIRST FLOOR & ENLARGED PLANS

A-37-102 ARCHITECTURAL - BLDG 37 - SECOND FLOOR & ENLARGED PLANS

A-39-10B ARCHITECTURAL - BLDG 39 - BASEMENT PLAN

A-40-10B ARCHITECTURAL - BLDG 40 - BASEMENT PLAN

A-41-10B ARCHITECTURAL - BLDG 41 - BASEMENT PLAN

A-42-10B ARCHITECTURAL - BLDG 42 - BASEMENT PLAN

Contract No. 36C77622C0129

Station Project No. 621-22-700

Bancroft-AE Project No. 22-114 05/22/2025 00 01 15 - 4

A-43-10B ARCHITECTURAL - BLDG 43 - BASEMENT PLAN

A-44-10B ARCHITECTURAL - BLDG 44 - BASEMENT PLAN

A-45-10B ARCHITECTURAL - BLDG 45 - BASEMENT PLAN

A-46-10B ARCHITECTURAL - BLDG 46 - BASEMENT PLAN

A-47-10B ARCHITECTURAL - BLDG 47 - BASEMENT PLAN

A-53-10B ARCHITECTURAL - BLDG 53 - BASEMENT PLAN

A-69-10G ARCHITECTURAL - BLDG 69 - GROUND FLOOR & ENLARGED PLANS

A-69-101 ARCHITECTURAL - BLDG 69 - FIRST FLOOR & ENLARGED PLANS

A-69-102 ARCHITECTURAL - BLDG 69 - SECOND FLOOR & ENLARGED PLANS

A-69-103 ARCHITECTURAL - BLDG 69 - THIRD FLOOR & ENLARGED PLANS

A-77-10G ARCHITECTURAL - BLDG 77 - GROUND FLOOR PLAN OVERALL

A-77-101 ARCHITECTURAL - BLDG 77 - FIRST FLOOR PLAN OVERALL

A-77-102 ARCHITECTURAL - BLDG 77 - SECOND FLOOR PLAN OVERALL

A-77-103 ARCHITECTURAL - BLDG 77 - THIRD FLOOR PLAN OVERALL

A-77-401 ARCHITECTURAL - BLDG 77 - ENLARGED PLANS - GROUND FLOOR

A-77-411 ARCHITECTURAL - BLDG 77 - ENLARGED PLANS - FIRST FLOOR

A-77-421 ARCHITECTURAL - BLDG 77 - ENLARGED PLANS - SECOND FLOOR

A-77-431 ARCHITECTURAL - BLDG 77 - ENLARGED PLANS - THIRD FLOOR

A-160-10G ARCHITECTURAL - BLDG 160 - GROUND FLOOR PLAN OVERALL

A-160-101 ARCHITECTURAL - BLDG 160 - FIRST FLOOR PLAN OVERALL

A-160-102 ARCHITECTURAL - BLDG 160 - SECOND FLOOR PLAN OVERALL

A-160-103 ARCHITECTURAL - BLDG 160 - THIRD FLOOR PLAN OVERALL

A-160-104 ARCHITECTURAL - BLDG 160 - FOURTH FLOOR PLAN OVERALL

A-160-105 ARCHITECTURAL - BLDG 160 - FIFTH FLOOR & ENLARGED PLANS

A-160-106 ARCHITECTURAL - BLDG 160 - ROOF PLAN

A-160-401 ARCHITECTURAL - BLDG 160 - ENLARGED PLANS - GROUND FLOOR

A-160-411 ARCHITECTURAL - BLDG 160 - ENLARGED PLANS - FIRST FLOOR

A-160-421 ARCHITECTURAL - BLDG 160 - ENLARGED PLANS - SECOND FLOOR

A-160-431 ARCHITECTURAL - BLDG 160 - ENLARGED PLANS - THIRD FLOOR

A-160-441 ARCHITECTURAL - BLDG 160 - ENLARGED PLANS - FOURTH FLOOR

A-162-101 ARCHITECTURAL - BLDG 162 - FIRST FLOOR PLAN OVERALL

Contract No. 36C77622C0129

Station Project No. 621-22-700

Bancroft-AE Project No. 22-114 05/22/2025 00 01 15 - 5

A-162-102 ARCHITECTURAL - BLDG 162 - SECOND FLOOR PLAN OVERALL

A-162-103 ARCHITECTURAL - BLDG 162 - ROOF PLAN

A-162-411 ARCHITECTURAL - BLDG 162 - ENLARGED PLANS - FIRST FLOOR

A-162-421 ARCHITECTURAL - BLDG 162 - ENLARGED PLANS - SECOND FLOOR

A-200-10G ARCHITECTURAL - BLDG 200 - GROUND FLOOR PLAN

A-200-101 ARCHITECTURAL - BLDG 200 - FIRST FLOOR PLAN

A-200-102 ARCHITECTURAL - BLDG 200 - SECOND FLOOR PLAN

A-200-103 ARCHITECTURAL - BLDG 200 - ROOF PLAN

A-200-401 ARCHITECTURAL - BLDG 200 - ENLARGED PLANS - GROUND FLOOR

A-200-402 ARCHITECTURAL - BLDG 200 - ENLARGED PLANS - GROUND FLOOR

A-200-411 ARCHITECTURAL - BLDG 200 - ENLARGED PLANS - FIRST FLOOR

A-200-412 ARCHITECTURAL - BLDG 200 - ENLARGED PLANS - FIRST FLOOR

A-200-421 ARCHITECTURAL - BLDG 200 - ENLARGED PLANS - SECOND FLOOR

A-200-422 ARCHITECTURAL - BLDG 200 - ENLARGED PLANS - SECOND FLOOR

A-201-101 ARCHITECTURAL - BLDG 201 - FIRST FLOOR PLAN

A-204-10G ARCHITECTURAL - BLDG 204 - GROUND FLOOR PLAN

A-204-101 ARCHITECTURAL - BLDG 204 - FIRST FLOOR PLAN

A-204-102 ARCHITECTURAL - BLDG 204 - SECOND FLOOR PLAN

A-204-103 ARCHITECTURAL - BLDG 204 - ROOF PLAN

A-204-401 ARCHITECTURAL - BLDG 204 - ENLARGED PLANS - GROUND FLOOR

A-204-411 ARCHITECTURAL - BLDG 204 - ENLARGED PLANS - FIRST FLOOR

A-204-421 ARCHITECTURAL - BLDG 204 - ENLARGED PLANS - SECOND FLOOR

A-205-10B ARCHITECTURAL - BLDG 205 - BASEMENT FLOOR PLAN

A-205-101 ARCHITECTURAL - BLDG 205 - FIRST FLOOR PLAN

A-205-102 ARCHITECTURAL - BLDG 205 - SECOND FLOOR & ENLARGED PLAN

A-205-411 ARCHITECTURAL - BLDG 205 - ENLARGED PLANS - FIRST FLOOR

A-206-101 ARCHITECTURAL - BLDG 206 - FIRST FLOOR PLAN OVERALL

A-208-101 ARCHITECTURAL - BLDG 208 - FIRST FLOOR PLAN OVERALL

A501 ARCHITECTURAL - PARTITION TYPES

A502 ARCHITECTURAL - DETAILS

A503 ARCHITECTURAL - WINDOW INFILL

Contract No. 36C77622C0129

Station Project No. 621-22-700

Bancroft-AE Project No. 22-114 05/22/2025 00 01 15 - 6

A504 ARCHITECTURAL - DETAILS

A601 ARCHITECTURAL - DOOR SCHEDULE

A602 ARCHITECTURAL – DOOR DETAILS

AF-601 ARCHITECTURAL - FINISH SCHEDULE

AF-602 ARCHITECTURAL - FINISH SCHEDULE

AF-603 ARCHITECTURAL - FINISH LEDGEND

AS-601 ARCHITECTURAL - SIGNAGE SCHEDULE

AS-602 ARCHITECTURAL - SIGNAGE DETAILS

FIRE SUPRESSION

FX-001 FIRE PROTECTION - GENERAL NOTES

FX-002 FIRE PROTECTION - GENERAL SYMBOLS

FX-B3-401 FIRE PROTECTION - BUILDING 3 - GROUND ENLARGED PLANS

FX-B3-411 FIRE PROTECTION - BUILDING 3 - FIRST FLOOR ENLARGED PLANS

FX-B3-421 FIRE PROTECTION - BUILDING 3 - SECOND FLOOR ENLARGED PLANS

FX-B5-401 FIRE PROTECTION - BUILDING 5 - GROUND ENLARGED PLANS

FX-B5-411 FIRE PROTECTION - BUILDING 5 - FIRST FLOOR ENLARGED PLANS

FX-B5-421 FIRE PROTECTION - BUILDING 5 - SECOND FLOOR ENLARGED PLANS

FX-B8-401 FIRE PROTECTION - BUILDING 8 - GROUND FLOOR ENLARGED PLANS

FX-B8-411 FIRE PROTECTION - BUILDING 8 - FIRST FLOOR ENLARGED PLANS

FX-B8-421 FIRE PROTECTION - BUILDING 8 - SECOND FLOOR ENLARGED PLANS

FX-B8-431 FIRE PROTECTION - BUILDING 8 - THIRD FLOOR ENLARGED PLANS

FX-B34-401 FIRE PROTECTION - BUILDING 34 - GROUND FLOOR PLAN

FX-B34-411 FIRE PROTECTION - BUILDING 34 - FIRST FLOOR PLAN

FX-B34-421 FIRE PROTECTION - BUILDING 34 - SECOND FLOOR PLANS

FX-B35-411 FIRE PROTECTION - BUILDING 35 - FIRST FLOOR PLANS

FX-B37-401 FIRE PROTECTION - BUILDING 37 - GROUND FLOOR PLANS

FX-B37-411 FIRE PROTECTION - BUILDING 37 - FIRST FLOOR PLANS

FX-B37-421 FIRE PROTECTION - BUILDING 37 - SECOND FLOOR PLANS

FX-B69-421 FIRE PROTECTION - BUILDING 69 - SECOND FLOOR PLANS

FX-B69-431 FIRE PROTECTION - BUILDING 69 - THIRD FLOOR PLANS

Contract No. 36C77622C0129

Station Project No. 621-22-700

Bancroft-AE Project No. 22-114 05/22/2025 00 01 15 - 7

FX-B77-401 FIRE PROTECTION - BUILDING 77 - GROUND FLOOR PLANS

FX-B77-411 FIRE PROTECTION - BUILDING 77 - FIRST FLOOR PLANS

FX-B77-421 FIRE PROTECTION - BUILDING 77 - SECOND FLOOR PLANS

FX-B77-431 FIRE PROTECTION - BUILDING 77 - THIRD FLOOR PLANS

FX-B160-401 FIRE PROTECTION - BUILDING 160 - BASEMENT FLOOR PLANS

FX-B160-411 FIRE PROTECTION - BUILDING 160 - FIRST FLOOR PLANS

FX-B160-421 FIRE PROTECTION - BUILDING 160 - SECOND FLOOR PLANS

FX-B160-431 FIRE PROTECTION - BUILDING 160 - THIRD FLOOR PLANS

FX-B160-441 FIRE PROTECTION - BUILDING 160 - FOUTH FLOOR PLANS

FX-B160-451 FIRE PROTECTION - BUILDING 160 - FIFTH FLOOR PLANS

FX-B162-411 FIRE PROTECTION - BUILDING 162 - FIRST FLOOR PLANS

FX-B162-421 FIRE PROTECTION - BUILDING 162 - SECOND FLOOR PLANS

FX-B200-401 FIRE PROTECTION - BUILDING 200 - BASEMENT FLOOR PLANS

FX-B200-411 FIRE PROTECTION - BUILDING 200 - FIRST FLOOR PLANS

FX-B200-421 FIRE PROTECTION - BUILDING 200 - SECOND FLOOR PLANS

FX-B204-401 FIRE PROTECTION - BUILDING 204 - BASEMENT FLOOR PLANS

FX-B204-411 FIRE PROTECTION - BUILDING 204 - FIRST FLOOR PLANS

FX-B204-421 FIRE PROTECTION - BUILDING 204 - SECOND FLOOR PLANS

FX-B205-401 FIRE PROTECTION - BUILDING 205 - BASEMENT FLOOR PLANS

FX-B205-411 FIRE PROTECTION - BUILDING 205 - FIRST FLOOR PLANS

FX-500 FIRE PROTECTION DETAILS

PLUMBING

P-001 PLUMBING - GENERAL NOTES, ABREVIATIONS, SYMBOLS

P-B5-401 PLUMBING - BUILDING 5 - BASEMENT FLOOR ENLARGED PLANS

P-B5-411 PLUMBING - BUILDING 5 - FIRST FLOOR ENLARGED PLANS

P-B35-

PLUMBING - BUILDING 35 - FIRST FLOOR PLANS

P-B69-

PLUMBING - BUILDING 69 - THIRD FLOOR ENLARGED PLANS

P-B162-

PLUMBING - BUILDING 162 - FIRST FLOOR ENLARGED PLANS

Contract No. 36C77622C0129

Station Project No. 621-22-700

Bancroft-AE Project No. 22-114 05/22/2025 00 01 15 - 8

P-B162-

PLUMBING - BUILDING 162 - SECOND FLOOR ENLARGED PLANS

P-B200-

PLUMBING - BUILDING 200 - BASEMENT ENLARGED PLANS

P-B200-

PLUMBING - BUILDING 200 - FIRST FLOOR ENLARGED PLANS

P-B200-

PLUMBING - BUILDING 200 - SECOND FLOOR ENLARGED PLANS

MECHANICAL

M001 MECHANICAL - GENERAL NOTES

M-3-10G MECHANICAL - BUILDING 3 - GROUND FLOOR PLANS

M-3-101 MECHANICAL - BUILDING 3 - FIRST FLOOR PLANS

M-3-102 MECHANICAL - BUILDING 3 - SECOND FLOOR PLANS

M-5-10G MECHANICAL - BUILDING 5 - GROUND FLOOR PLANS

M-5-101 MECHANICAL - BUILDING 5 - FIRST FLOOR PLANS

M-5-102 MECHANICAL - BUILDING 5 - SECOND FLOOR PLANS

M-8-10G MECHANICAL - BUILDING 8 - GROUND FLOOR PLANS

M-8-101 MECHANICAL - BUILDING 8 - FIRST FLOOR PLANS

M-8-102 MECHANICAL - BUILDING 8 - SECOND FLOOR PLANS

M-8-103 MECHANICAL - BUILDING 8 - THIRD FLOOR PLANS

M-34-10G MECHANICAL - BUILDING 34 - GROUND FLOOR PLANS

M-34-101 MECHANICAL - BUILDING 34 - FIRST FLOOR PLANS

M-37-10G MECHANICAL - BUILDING 37 - GROUND FLOOR PLANS

M-37-101 MECHANICAL - BUILDING 37 - FIRST FLOOR PLANS

M-37-102 MECHANICAL - BUILDING 37 - SECOND FLOOR PLANS

M-77-10G MECHANICAL - BUILDING 77 - GROUND FLOOR PLANS

M-77-101 MECHANICAL - BUILDING 77 - FIRST FLOOR PLANS

M-77-102 MECHANICAL - BUILDING 77 - SECOND FLOOR PLANS

M-77-103 MECHANICAL - BUILDING 77 - THIRD FLOOR PLANS

M-77-104 MECHANICAL - BUILDING 77 - ROOF PLANS

M-160-10G MECHANICAL - BUILDING 160 - GROUND FLOOR PLANS

M-160-101 MECHANICAL - BUILDING 160 - FIRST FLOOR PLANS

Contract No. 36C77622C0129

Station Project No. 621-22-700

Bancroft-AE Project No. 22-114 05/22/2025 00 01 15 - 9

M-160-102 MECHANICAL - BUILDING 160 - SECOND FLOOR PLANS

M-160-103 MECHANICAL - BUILDING 160 - THIRD FLOOR PLANS

M-160-104 MECHANICAL - BUILDING 160 - FOURTH FLOOR PLANS

M-160-105 MECHANICAL - BUILDING 160 - FIFTH FLOOR PLANS

M-162-101 MECHANICAL - BUILDING 162 - FIRST FLOOR PLANS

M-162-102 MECHANICAL - BUILDING 162 - SECOND FLOOR PLANS

M-162-103 MECHANICAL - BUILDING 162 - ROOF PLANS

M-200-10G.A MECHANICAL - BUILDING 200 - GROUND FLOOR PLAN - A WING

M-200-10G.B MECHANICAL - BUILDING 200 - GROUND FLOOR PLAN - B WING

M-200-10G.C MECHANICAL - BUILDING 200 - GROUND FLOOR PLAN - C WING

M-200-10G.E MECHANICAL - BUILDING 200 - GROUND FLOOR PLAN - E WING

M-200-101.A MECHANICAL - BUILDING 200 - FIRST FLOOR PLAN - A WING

M-200-101.B MECHANICAL - BUILDING 200 - FIRST FLOOR PLAN - B WING

M-200-101.C MECHANICAL - BUILDING 200 - FIRST FLOOR PLAN - C WING

M-200-101.E MECHANICAL - BUILDING 200 - FIRST FLOOR PLAN - E WING

M-200-102.A MECHANICAL - BUILDING 200 - SECOND FLOOR PLAN - A WING

M-200-102.B MECHANICAL - BUILDING 200 - SECOND FLOOR PLAN - B WING

M-200-102.C MECHANICAL - BUILDING 200 - SECOND FLOOR PLAN - C WING

M-200-102.E MECHANICAL - BUILDING 200 - SECOND FLOOR PLAN - E WING

M-200-103 MECHANICAL - BUILDING 200 - ROOF PLANS

M-204-10G MECHANICAL - BUILDING 204 - GROUND FLOOR PLANS

M-204-101 MECHANICAL - BUILDING 204 - FIRST FLOOR PLANS

M-204-102 MECHANICAL - BUILDING 204 - SECOND FLOOR PLANS

M-204-103 MECHANICAL - BUILDING 204 - ROOF PLANS

M501 MECHANICAL - DETAILS

M502 MECHANICAL - DETAILS

M601 MECHANICAL - SCHEDULES

M602 MECHANICAL - SCHEDULES

M603 MECHANICAL - SCHEDULES

M701 MECHANICAL - CONTROLS

Contract No. 36C77622C0129

Station Project No. 621-22-700

Bancroft-AE Project No. 22-114 05/22/2025 00 01 15 - 10

G003 GENERAL - COVER SHEET VOLUME 2

G004A GENERAL - DRAWING INDEX (1 OF 3)

G004B GENERAL - DRAWING INDEX (2 OF 3)

G004C GENERAL - DRAWING INDEX (3 OF 3)

ELECTRICAL

E001 ELECTRICAL - GENERAL NOTES

E-002 ELECTRICAL - SYMBOLS AND ABBREVIATION

E-003 ELECTRICAL - ENLARGED TYPICAL TR ROOMS LIGHTING AND POWER

E-004 ELECTRICAL - POWER ELEVATION AND SCHEMATIC FOR RACK TR

EP-B3-10G ELECTRICAL - BUILDING 3 - GROUND FLOOR PLAN

EP-B3-101 ELECTRICAL - BUILDING 3 - FIRST FLOOR PLAN

EP-B3-102 ELECTRICAL - BUILDING 3 - SECOND FLOOR PLAN

EP-B5-10G ELECTRICAL - BUILDING 5 - GROUND FLOOR PLAN

EP-B5-101 ELECTRICAL - BUILDING 5 - FIRST FLOOR PLAN

EP-B5-102 ELECTRICAL - BUILDING 5 - SECOND FLOOR PLAN

EP-B8-10G ELECTRICAL - BUILDING 8 - GROUND FLOOR PLAN

EP-B8-101 ELECTRICAL - BUILDING 8 - FIRST FLOOR PLAN

EP-B8-102 ELECTRICAL - BUILDING 8 - SECOND FLOOR PLAN

EP-B8-103 ELECTRICAL - BUILDING 8 - THIRD FLOOR PLAN

EP-B15-10B ELECTRICAL - BUILDING 15 - BASEMENT FLOOR PLAN

EP-B17-10B ELECTRICAL - BUILDING 17 - BASEMENT FLOOR PLAN

EP-B19-10B ELECTRICAL - BUILDING 19 - BASEMENT FLOOR PLAN

EP-B34-10B ELECTRICAL - BUILDING 34 - BASEMENT FLOOR PLAN

EP-B34-101 ELECTRICAL - BUILDING 34 - FIRST FLOOR PLAN

EP-B34-102 ELECTRICAL - BUILDING 34 - SECOND FLOOR PLAN

EP-B35-10B ELECTRICAL - BUILDING 35 - BASEMENT FLOOR PLAN

EP-B35-101 ELECTRICAL - BUILDING 35 - FIRST FLOOR PLAN

EP-B36-10B ELECTRICAL - BUILDING 36 - BASEMENT FLOOR PLAN

EP-B36-101 ELECTRICAL - BUILDING 36 - FIRST FLOOR PLAN

EP-B37-10F ELECTRICAL - BUILDING 37 - SECURITY GATES POWER PLAN

Contract No. 36C77622C0129

Station Project No. 621-22-700

Bancroft-AE Project No. 22-114 05/22/2025 00 01 15 - 11

EP-B37-10G ELECTRICAL - BUILDING 37 - GROUND FLOOR PLAN

EP-B37-101 ELECTRICAL - BUILDING 37 - FIRST FLOOR PLAN

EP-B37-102 ELECTRICAL - BUILDING 37 - SECOND FLOOR PLAN

EP-B39-10B ELECTRICAL - BUILDING 39 - GROUND FLOOR PLAN

EP-B39-101 ELECTRICAL - BUILDING 39 - FIRST & SECOND FLOOR PLANS

EP-B40-10B ELECTRICAL - BUILDING 40 - BASEMENT FLOOR PLAN

EP-B40-101 ELECTRICAL - BUILDING 40 - FIRST & SECOND FLOOR PLANS

EP-B41-10B ELECTRICAL - BUILDING 41 - BASEMENT FLOOR PLAN

EP-B41-101 ELECTRICAL - BUILDING 41 - FIRST & SECOND FLOOR PLANS

EP-B42-10B ELECTRICAL - BUILDING 42 - BASEMENT FLOOR PLAN

EP-B43-10B ELECTRICAL - BUILDING 43 - BASEMENT FLOOR PLAN

EP-B44-10B ELECTRICAL - BUILDING 44 - BASEMENT FLOOR PLAN

EP-B45-10B ELECTRICAL - BUILDING 45 - BASEMENT FLOOR PLAN

EP-B46-10B ELECTRICAL - BUILDING 46 - BASEMENT FLOOR PLAN

EP-B47-10B ELECTRICAL - BUILDING 47 - BASEMENT FLOOR PLAN

EP-B53-10B ELECTRICAL - BUILDING 53 - BASEMENT FLOOR PLAN

EP-B69-10G ELECTRICAL - BUILDING 69 - GROUND FLOOR PLAN

EP-B69-101 ELECTRICAL - BUILDING 69 - FIRST FLOOR PLAN

EP-B69-102 ELECTRICAL - BUILDING 69 - SECOND FLOOR PLAN

EP-B69-103 ELECTRICAL - BUILDING 69 - THIRD FLOOR PLAN

EP-B77-10G ELECTRICAL - BUILDING 77 - GROUND FLOOR PLAN

EP-B77-101 ELECTRICAL - BUILDING 77 - FIRST FLOOR PLAN

EP-B77-102 ELECTRICAL - BUILDING 77 - SECOND FLOOR PLAN

EP-B77-103 ELECTRICAL - BUILDING 77 - THIRD FLOOR PLAN

EP-B77-104 ELECTRICAL - BUILDING 77 - ROOF PLAN

EP-B160-10G ELECTRICAL - BUILDING 160 - GROUND FLOOR PLAN

EP-B160-101 ELECTRICAL - BUILDING 160 - FIRST FLOOR PLAN

EP-B160-102 ELECTRICAL - BUILDING 160 - SECOND FLOOR PLAN

EP-B160-103 ELECTRICAL - BUILDING 160 - THIRD FLOOR PLAN

EP-B160-104 ELECTRICAL - BUILDING 160 - FOURTH FLOOR PLAN

EP-B160-105 ELECTRICAL - BUILDING 160 - FIFTH FLOOR & ENLARGED PLANS

Contract No. 36C77622C0129

Station Project No. 621-22-700

Bancroft-AE Project No. 22-114 05/22/2025 00 01 15 - 12

EP-B162-101 ELECTRICAL - BUILDING 162 - FIRST FLOOR PLAN

EP-B162-102 ELECTRICAL - BUILDING 162 - SECOND FLOOR PLAN

EP-B200-10G ELECTRICAL - BUILDING 200 - GROUND FLOOR PLAN

EP-B200-10G.A ELECTRICAL - BUILDING 200 - GROUND FLOOR PLAN - A WING

EP-B200-10G.B ELECTRICAL - BUILDING 200 - GROUND FLOOR PLAN - B WING

EP-B200-10G.C ELECTRICAL - BUILDING 200 - GROUND FLOOR PLAN - C WING

EP-B200-10G.D ELECTRICAL - BUILDING 200 - GROUND FLOOR PLAN - D WING

EP-B200-10G.E ELECTRICAL - BUILDING 200 - GROUND FLOOR PLAN - E WING

EP-B200-101 ELECTRICAL - BUILDING 200 - FIRST FLOOR PLAN

EP-B200-101.A ELECTRICAL - BUILDING 200 - FIRST FLOOR PLAN - A WING

EP-B200-101.B ELECTRICAL - BUILDING 200 - FIRST FLOOR PLAN - B WING

EP-B200-101.C ELECTRICAL - BUILDING 200 - FIRST FLOOR PLAN - C WING

EP-B200-101.D ELECTRICAL - BUILDING 200 - FIRST FLOOR PLAN - D WING

EP-B200-101.E ELECTRICAL - BUILDING 200 - FIRST FLOOR PLAN - E WING

EP-B200-102 ELECTRICAL - BUILDING 200 - SECOND FLOOR PLAN

EP-B200-102.A ELECTRICAL - BUILDING 200 - SECOND FLOOR PLAN - A WING

EP-B200-102.B ELECTRICAL - BUILDING 200 - SECOND FLOOR PLAN - B WING

EP-B200-102.C ELECTRICAL - BUILDING 200 - SECOND FLOOR PLAN - C WING

EP-B200-102.D ELECTRICAL - BUILDING 200 - SECOND FLOOR PLAN - D WING

EP-B200-102.E ELECTRICAL - BUILDING 200 - SECOND FLOOR PLAN - E WING

EP-B200-103 ELECTRICAL - BUILDING 200 - ROOF PLAN

EP-B201-101 ELECTRICAL - BUILDING 201 - FIRST FLOOR PLAN

EP-B204-10B ELECTRICAL - BUILDING 204 - BASEMENT FLOOR PLAN

EP-B204-101 ELECTRICAL - BUILDING 204 - FIRST FLOOR PLAN

EP-B204-102 ELECTRICAL - BUILDING 204 - SECOND FLOOR PLAN

EP-B204-103 ELECTRICAL - BUILDING 204 - ROOF PLAN

EP-B205-10B ELECTRICAL - BUILDING 205 - BASEMENT FLOOR PLAN

EP-B205-101 ELECTRICAL - BUILDING 205 - FIRST FLOOR PLAN

EP-B205-102 ELECTRICAL - BUILDING 205 - SECOND FLOOR PLAN

EP-B206-101 ELECTRICAL - BUILDING 206 - FIRST FLOOR PLAN

EP-B208-101 ELECTRICAL - BUILDING 208 - FIRST FLOOR PLAN

Contract No. 36C77622C0129

Station Project No. 621-22-700

Bancroft-AE Project No. 22-114 05/22/2025 00 01 15 - 13

E-501 ELECTRICAL - DETAILS

E-600 ELECTRICAL - PANEL SCHEDULES

E-600-1 ELECTRICAL - PANEL SCHEDULES

E-600-2 ELECTRICAL - PANEL SCHEDULES

E-600-3 ELECTRICAL - PANEL SCHEDULES

E-600-4 ELECTRICAL - PANEL SCHEDULES

E-600-5 ELECTRICAL - PANEL SCHEDULES

E-601 ELECTRICAL - ELECTRICAL EQUIPMENT SCHEDULE

E-701 ELECTRICAL - SINGLE LINE, BLDG 15, 39, 46

E-702 ELECTRICAL - SINGLE LINE, BLDG 17, 40, 41

E-703 ELECTRICAL - SINGLE LINE, BLDG 36, 42, 43, 115

E-704 ELECTRICAL - SINGLE LINE, BLDG 77

E-705 ELECTRICAL - SINGLE LINE, BLDG 160

E-706 ELECTRICAL - SINGLE LINE, BLDG 200

TELECOMMUNICATIONS

TT-000 ICT - GENERAL NOTES

TT1.01 COMMUNICATIONS PATHWAY SITE PLAN

TT5.01 ICT - DETAILS 1

TT-5.02 ICT - DETAILS 2

TT-6.01 OVERALL SITE RISER DIAGRAM

TT-6.02 OVERALL SITE RISER DIAGRAM

TT-6.03 OVERALL SITE RISER DIAGRAM

TT-6.04 OVERALL SITE RISER DIAGRAM

TT-6.05 OVERALL SITE RISER DIAGRAM

TT-7.01 OVERALL SITE SPLICING DIAGRAM

TT-7.02 OVERALL SITE SPLICING DIAGRAM

TT-7.03 OVERALL SITE SPLICING DIAGRAM

TT-B3-10B ICT - BUILDING 3 - BASEMENT PLAN OVERALL

TT-B3-101 ICT - BUILDING 3 - LEVEL 1 PLAN OVERALL

TT-B3-102 ICT - BUILDING 3 - LEVEL 2 PLAN OVERALL

TT-B3-201 ICT - BUILDING 3 RACK ELEVATIONS

Contract No. 36C77622C0129

Station Project No. 621-22-700

Bancroft-AE Project No. 22-114 05/22/2025 00 01 15 - 14

TT-B3-202 ICT - BUILDING 3 RACK ELEVATIONS

TT-B5-10B ICT - BUILDING 5 - BASEMENT PLAN OVERALL

TT-B5-101 ICT - BUILDING 5 - FIRST FLOOR PLAN OVERALL

TT-B5-102 ICT - BUILDING 5 - SECOND FLOOR PLAN OVERALL

TT-B5-201 ICT - BUILDING 5 RACK ELEVATIONS

TT-B5-202 ICT - BUILDING 5 RACK ELEVATIONS

TT-B8-10B ICT - BUILDING 8 - LEVEL 1 PLAN OVERALL

TT-B8-101 ICT - BUILDING 8 - FIRST FLOOR PLAN OVERALL

TT-B8-102 ICT - BUILDING 8 - SECOND FLOOR PLAN OVERALL

TT-B8-103 ICT - BUILDING 8 - THIRD FLOOR PLAN OVERALL

TT-B8-201 ICT - BUILDING 8 RACK ELEVATIONS

TT-B8-202 ICT - BUILDING 8 RACK ELEVATIONS

TT-15-10B ICT - BUILDING 15 - BASEMENT PLAN OVERALL

TT-B17-10B ICT - BUILDING 17 - BASEMENT FLOOR PLAN OVERALL

TT-B19-10B ICT - BUILDING 19 - BASEMENT PLAN OVERALL

TT-B34-10G ICT - BUILDING 34 - BASEMENT PLAN OVERALL

A-34-101 ICT - ENLARGED PLANS - FIRST FLOOR PLAN

TT-B34-102 ICT - BUILDING 34 - LEVEL 2 PLAN OVERALL

TT-B34-201 ICT - BUILDING 34 RACK ELEVATIONS

TT-B35-101 ICT - BUILDING 35 - FIRST FLOOR PLAN OVERALL

TT-B36-10B ICT - BUILDING 36 - BASEMENT PLAN OVERALL

TT-B37-10B ICT - BUILDING 37 - BASEMENT PLAN OVERALL

TT-B37-101 ICT - BUILDING 37 - FIRST FLOOR PLAN OVERALL

TT-B37-102 ICT - BUILDING 37 - SECOND FLOOR PLAN OVERALL

TT-B37-201 ICT - BUILDING 37 RACK ELEVATIONS

TT-B39-10B ICT - BUILDING 39 - BASEMENT PLAN OVERALL

TT-B40-10B ICT - BUILDING 40 - BASEMENT PLAN OVERALL

TT-B41-10B ICT - BUILDING 41 - BASEMENT PLAN OVERALL

TT-B42-10B ICT - BUILDING 42 - BASEMENT PLAN OVERALL

TT-B43-10B ICT - BUILDING 43 - BASEMENT PLAN OVERALL

TT-B44-10B ICT - BUILDING 44 - BASEMENT PLAN OVERALL

Contract No. 36C77622C0129

Station Project No. 621-22-700

Bancroft-AE Project No. 22-114 05/22/2025 00 01 15 - 15

TT-B45-10B ICT - BUILDING 45 - BASEMENT PLAN OVERALL

TT-B46-10B ICT - BUILDING 46 - BASEMENT PLAN OVERALL

TT-B47-10B ICT - BUILDING 47 - BASEMENT PLAN OVERALL

TT-53-10B ICT - BUILDING 53 -BASEMENT PLAN OVERALL

TT-B160-10B ICT - BUILDING 160 - BASEMENT PLAN OVERALL

TT-B160-101 ICT - BUILDING 160 - FIRST FLOOR PLAN OVERALL

TT-B160-102 ICT - BUILDING 160 - SECOND FLOOR PLAN OVERALL

TT-B160-103 ICT - BUILDING 160 - LEVEL 3 PLAN OVERALL

TT-B160-104 ICT - BUILDING 160 - FOURTH FLOOR PLAN OVERALL

TT-B160-105 ICT - BUILDING 160 - FIFTH FLOOR PLAN OVERALL

TT-B160-106 ICT - BUILDING 160 - RISER DIAGRAM

TT-B160-201 ICT - BUILDING 160 - RISER DIAGRAM

TT-B160-202 ICT - BUILDING 160 - RISER DIAGRAM

TT-B160-203 ICT - BUILDING 160 - RISER DIAGRAM

TT-B160-204 ICT - BUILDING 160 - RISER DIAGRAM

TT-B160-205 ICT - BUILDING 160 - RISER DIAGRAM

TT-B160-206 ICT - BUILDING 160 - RISER DIAGRAM

TT-162-101 ICT - BUILDING 162 - LEVEL 1 PLAN OVERALL

TT-162-102 ICT - BUILDING 162 - LEVEL 2 PLAN OVERALL

TT-162-102 ICT - BUILDING 162 RACK ELEVATIONS

TT-201-101 ICT - BUILDING 201 - LEVEL 1 PLAN OVERALL

TT-B206-101 ICT - BUILDING 206 - LEVEL 1 PLAN OVERALL

TT-B208-101 ICT - BUILDING 208 - LEVEL 1 PLAN OVERALL

TT-BB-00 ICT - BUILDINGS - 69 - 77 - 200 - 204 -205 - BASEMENT PLAN

TT-BB-01 ICT - BUILDINGS - 69 - 77 - 200 - 204 -205 - LEVEL 1 PLAN

TT-BB-02 ICT - BUILDINGS - 69 - 77 - 200 - 204 -205 - LEVEL 2 PLAN

TT-BB-03 ICT - BUILDINGS - 69 - 77 - 200 - 204 -205 - LEVEL 3 PLAN

TT-BB-04.1 ENLARGED PLANS

TT-BB-04.2 ENLARGED PLANS

TT-BB-04.3 ENLARGED PLANS

TT-BB-04.4 ENLARGED PLANS

Contract No. 36C77622C0129

Station Project No. 621-22-700

Bancroft-AE Project No. 22-114 05/22/2025 00 01 15 - 16

TT-BB-04.5 ENLARGED PLANS

TT-BB-04.6 ENLARGED PLANS

TT-BB-04.7 ENLARGED PLANS

TT-BB-05 ICT - BUILDINGS - 69 - 77 - 200 - 204 -205 - RISER DIAGRAMS

TT-BB-06.1 ENTRANCE DIAGRAMS

TT-BB-06.2 ENTRANCE DIAGRAMS

TT-BB-06.3 ENTRANCE DIAGRAMS

TT-BB-07.1 RACK ELEVATIONS

TT-BB-07.2 RACK ELEVATIONS

TT-BB-07.3 RACK ELEVATIONS

TT-BB-07.4 RACK ELEVATIONS

TT-BB-07.5 RACK ELEVATIONS

TT-BB-07.6 RACK ELEVATIONS

TT-BB-07.7 RACK ELEVATIONS

TT-BB-07.8 RACK ELEVATIONS

TT-BB-07.9 RACK ELEVATIONS

TT-BB-07.10 RACK ELEVATIONS

TT-BB-07.11 RACK ELEVATIONS

- - - END - - -

Contract No. 36C77622C0129

Station Project No. 621-22-700

Bancroft-AE Project No. 22-114 05/22/2025 00 01 15 - 17

- - - E N D - - -

DIVISION 01

11-01-21

Contract No. 36C77622C0129

Station Project No. 621-22-700

Bancroft-AE Project No. 22-114 05/22/2025 01 00 00 -1

General Requirements

SECTION 01 00 00

GENERAL REQUIREMENTS

1.1 SAFETY REQUIREMENTS

A. Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.

1.2 GENERAL INTENTION

A. Contractor shall completely prepare site and perform the necessary work for a fully operational electronic health records infrastructure system, including demolition and removal of existing structures and systems (including mechanical, electrical, fire-protection, plumbing and information technology infrastructure), installation of structures and systems (including mechanical, electrical, fire-protection, plumbing and information technology infrastructure). This shall include the furnishing of all necessary labor and materials as required to provide for fully operational systems for the James H. Quillen VA

Medical Center – EHRM Infrastructure Upgrades – 621-22-700 as required by drawings and specifications.

B. Visits to the site by Bidders may be made in accordance with what is listed in the solicitation and at the discretion of the Contracting

Officer.

C. Offices of Bancroft Architects + Engineers (BAE), as Architect-Engineer of Record, will render certain technical services during construction.

Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer or their duly authorized representative.

D. Before placement and installation of work subject to tests by testing laboratory retained by General Contractor and approved by VA, the

Contractor shall notify the COR in sufficient time to enable personnel to be present at the site in time for witnessing taking and testing of

Contract No. 36C77622C0129

Station Project No. 621-22-700

Bancroft-AE Project No. 22-114 05/22/2025 01 00 00 -2

General Requirements specimens and field inspection. Such prior notice shall be not less than seven workdays unless otherwise designated by the COR.

E. All employees of general contractor and subcontractors shall comply with VA security management program.

F. Contractor Work Hours

1. Normal working hours for this contract will be from

7:00AM to 4:30PM (local time) Monday through Friday except for weekends and established Federal Holidays.

2. Performing on-site work outside normal working hours will be required in patient care areas and at no additional cost to the Government. Performing work outside normal working hours will require approval from the Contracting

Officer and the COR. Requests shall be submitted via email at least 72 hours prior to the requested date and at no additional cost to the Government. Approvals are subject to the availability of on-site staff.

1.3 STATEMENT OF BID ITEM(S)

A. ITEM I,BASE BID: Work includes general construction, alterations and demolition, Site alternations (roads, walks, grading, drainage), necessary removal of existing structures and construction of certain other items as required for a fully operational electronic health records infrastructure system.

1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

A. Electronic drawings and contract documents may be obtained from the website where the solicitation is posted. Hard copies will be at

Contractor's expense.

1.5 CONSTRUCTION SECURITY REQUIREMENTS

A. Security Plan:

Contract No. 36C77622C0129

Station Project No. 621-22-700

Bancroft-AE Project No. 22-114 05/22/2025 01 00 00 -3

General Requirements

1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.

2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.

3. VA Directive 6500 requires that contractors working in IT spaces must be escorted by personnel with a VA issued PIV badge authorized by the OIT regional manager to be in the IT spaces.

B. Security Procedures:

1. General Contractor’s employees shall not enter the project site without an appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.

2. Before starting work the General Contractor shall give three week’s notice to the Contracting Officer so that security and escort arrangements can be provided by the Station. This notice is separate from any notices required for utility shutdown described later in this section.

3. No photography of VA premises is allowed without written permission of the Contracting Officer. Patients and staff are not to be photographed at any time.

4. VA reserves the right to close or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.

C. Key Control:

1. The General Contractor shall turn over all permanent lock cylinders to the VA Station locksmith for permanent installation. See Section

08 71 00, DOOR HARDWARE, and coordinate.

1.6 OPERATIONS AND STORAGE AREAS (FAR 52.236-10)

A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by

Contract No. 36C77622C0129

Station Project No. 621-22-700

Bancroft-AE Project No. 22-114 05/22/2025 01 00 00 -4

General Requirements the Contracting Officer. The Contractor shall hold and save the

Government, its officers, and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.

B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the

Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the

Contractor and shall be removed by the Contractor at its expense upon completion of the work.

C. The Contractor shall, under regulations prescribed by the Contracting

Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting

Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The

Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.

D. Working space and space available for storing materials shall be as determined by the COR.

E. Workers are subject to rules of the Mountain Home Medical Center applicable to their conduct.

F. Execute work in such a manner as to interfere as little as possible with work being done by others. Keep roads clear of construction materials, debris, standing construction equipment and vehicles at all times.

G. Execute work so as to interfere as little as possible with normal functioning of the Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not

Contract No. 36C77622C0129

Station Project No. 621-22-700

Bancroft-AE Project No. 22-114 05/22/2025 01 00 00 -5

General Requirements permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space.

1. Do not store materials and equipment in other than assigned areas.

2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of

Veterans Affairs in quantities sufficient for not more than two workdays. Provide unobstructed access to Medical Center areas required to remain in operation.

3. Where access by the Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.

H. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR. All such actions shall be coordinated with the COR and Utility Company involved:

I. Phasing:

1. The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur.

It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks.

2. To ensure such executions, Contractor shall furnish the COR with a schedule of approximate phasing dates on which the Contractor intends to accomplish work in each specific area of site, buildings, or portions thereof. In addition, Contractor shall notify the COR three weeks in advance of the proposed date of starting work in each specific area of site, buildings, or portions thereof. Arrange such

Contract No. 36C77622C0129

Station Project No. 621-22-700

Bancroft-AE Project No. 22-114 05/22/2025 01 00 00 -6

General Requirements phasing dates to ensure accomplishment of this work in successive phases mutually agreeable to COR and Contractor.

3. Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical Centers operations will not be hindered. Contractors shall permit access to Department of

Veterans Affairs personnel and patients through other construction areas which serve as routes of access to such affected areas and equipment. These routes, whether access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces, lighting etc. to facilitate patient and staff access.

Coordinate alteration work in areas occupied by the Department of

Veterans Affairs so that Medical Center operations will continue during the construction period.

4. Immediate areas of alterations not mentioned in preceding

Subparagraph 1 will be temporarily vacated while alterations are performed.

J. Construction Fence: Before construction operations begin, Contractor shall provide a chain link construction fence, 2.1m (seven feet) minimum height, around the construction area indicated on the drawings.

Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum 375mm (15 inches). Bottom of fences shall extend to 25mm

(one inch) above grade. Remove the fence when directed by COR.

K. When a building and/or construction site is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:

1. The contractor shall maintain a minimum temperature of 4 degrees C

(40 degrees F) at all times, except as otherwise specified.

Contract No. 36C77622C0129

Station Project No. 621-22-700

Bancroft-AE Project No. 22-114 05/22/2025 01 00 00 -7

General Requirements

2. The contractor shall maintain in operating condition existing fire protection and alarm equipment.

L. Utilities Services: Maintain existing utility services for the Medical

Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services.

Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.

1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR Electrical work shall be accomplished with all affected circuits or equipment de-energized.

2. Contractor shall submit a request to interrupt any such services to

COR, in writing, 21 days in advance of proposed interruption.

Request shall state reason, date, exact time of, and approximate duration of such interruption.

3. Contractor will be advised of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center. Interruption time approved by Medical

Center may occur at other than Contractor's normal working hours at no added cost to the government.

4. Major interruptions of any system must be requested, in writing, at least 21 calendar days prior to the desired time and shall be performed as directed by the COR.

5. In case of a contract construction emergency, service will be interrupted on approval of COR.

M. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, shall be removed back to their source. Those which are indicated to be abandoned but are not required to be entirely removed, shall be sealed, capped, or plugged at the main, branch or panel they originate from. The lines

Contract No. 36C77622C0129

Station Project No. 621-22-700

Bancroft-AE Project No. 22-114 05/22/2025 01 00 00 -8

General Requirements shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.

N. To minimize interference of construction activities with flow of

Medical Center traffic, comply with the following:

1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles. Wherever excavation for new utility lines cross existing roads, at least one lane must be open to traffic at all times with approval.

2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.

O. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.

P. Coordination of Construction with Cemetery Director: The burial activities at a National Cemetery shall take precedence over construction activities. The Contractor must cooperate and coordinate with the Cemetery Director, through the COR, in arranging construction schedules to cause the least possible interference with cemetery activities in actual burial areas. Construction noise during the interment services shall not disturb the service. Trucks and workers shall not pass through the service area during this period:

1. The Contractor is required to discontinue his work sufficiently in advance of Easter Sunday, Mother's Day, Father's Day, Memorial Day, Veteran's Day and/or Federal holidays, to permit him to clean up all areas of operation adjacent to existing burial plots before these dates.

2. Cleaning up shall include the removal of all equipment, tools, materials, and debris and leaving the areas in a clean, neat condition.

Contract No. 36C77622C0129

Station Project No. 621-22-700

Bancroft-AE Project No. 22-114 05/22/2025 01 00 00 -9

General Requirements

1.7 ALTERATIONS

A. Survey: Before any work is started, the Contractor shall make a…