This file contains details of a federal contract opportunity for expanding sterile processing space in Building 200 at the Hines VA Medical Center. The related solicitation seeks proposals to conduct a study of available space in Building 200 to accommodate an expansion of the sterile processing department. The Department of Veterans Affairs Technology Acquisition Center Austin will award a contract under solicitation number 36C77623R0126 with an opportunity type listed as a pre-solicitation and name C1DA--578-375 Expand Sterile Processing - Hines for Building 200. Offerors should study the available 19MB file attached regarding the scope of work for the space study at the Hines VA Medical Center to determine available space for sterile processing expansion in Building 200, with responses due on the date specified in the solicitation.

View the file

Other files

File Type Posted
SF330 amendment 0001.docx DOCX document
P01 - 14 OIT Horizontal Cable Requirements.pdf PDF
P01 - 12 Contractor Parking.pdf PDF
P01 - 13 AE Design Checklist.pdf PDF
P01 - 16 No Smoking Policy 10-1-19.pdf PDF
P01 - 19b SOW Final Study of SPS Space in Building 200.pdf PDF
P01 - 08 Pre-Construction Risk Assessment (PCRA).docx DOCX document
P01 - 10 Infection Control Risk Assessment (ICRA).docx DOCX document
P01 - 05 Cutting Welding and Other Hot Work.pdf PDF
P01 - 09 Interim Life Safety Measures (ILSM).docx DOCX document
P01 - 19c SOW Final Study of SPS Space in Building 200.pdf PDF
P01 - 02 Hines Underground Utility Plan.pdf PDF
P01 - 21 VHA Directive 1116(2) dated 3-23-16.pdf PDF
P01 - 04 Safety and Health During Construction Activities.pdf PDF
P01 - 15 Fire Protection Code Reviews.pdf PDF
P01 - 03 Pre-Construction Checklist.pdf PDF
P01 - 07 Above Ceiling Entry and Wall Construction Permits.pdf PDF
P01 - 06 Dig Permit SOP Form.pdf PDF
P01 - 19d SOW Final Study of SPS Space in Building 200.pdf PDF
P01 - 20 Sterile Processing Service Design Guide 9-1-22.pdf PDF
P01 - 11 Contractor PIV Instructions and Form.pdf PDF
P01 - 01 SPS Expansion Plans.pdf PDF
Design SOW 578-375 Expand SPS for Building 200 -Final.pdf PDF
36C77623R0126.docx DOCX document
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BUILDING 200

TRIPP AVENUE

SOUTH 9TH AVENUE

R O

O S E V

E L T R

O A

D

S C

O T T D

R

IV

E

BUILDING 1

BUILDING 128

BUILDING 113

BUILDING 228

BUILDING 14

BUILDING 13

BUILDING 12

EDWARD HINES, JR. VAMC HINES, IL

578-20-003 STUDY OF SPS 100% SUBMISSION

September 21, 2022

BUILDING 200

iii

Table of Contents

Part 1 - Executive Summary 7

Part 2 - Space Allocation Matrix 13 Existing SPS Analysis 13

SPS VA SEPS Room by Room Program 21

SPS VA SEPS Large Equipment List 23

Part 3 - Site Analysis 27

Part 3 - 10 Siting Options : Options 1-5 30

Part 3 - 10 Siting Options : Options 6-9 31

Part 3 - 1- Siting Options : Option 10 32 Site Analysis Score Card 33

Siting Option 1 38

Siting Option 2 44

Siting Option 3 50

Siting Option 4 56

Siting Option 5 62

Siting Option 6 68

Siting Option 7 74

Siting Option 8 80

Siting Option 9 86

Siting Option 10 92

Recommendation of 3 Concept Siting Options 98

Part 4 - Concept Design 101 Concept Design | Option 3 102

Concept Design | Option 8 106

Concept Design | Option 9 110

Part 5 - Reuse Study After SPS Is Relocated 119

Part 5 - Reuse Study 121

Part 5 - Reuse Study 123

Part 6 - A/E SOW for Follow-on Design 127 Appendix A : VA SEPS Equipment List 135

Appendix B : VA Mechanical Drawings w/ Siting Analysis 140

Appendix C : Basis of Design Equipment Cut Sheets 150

Edward Hines, Jr. VA Medical Center | iv

Page Intentionally left Blank

Executive Summary

. E

X C

U T

IV

E

S U

M M

A R

Y

The scope of this feasibility report is to identify possible re-location options for the SPS department to align with modern workfl ow, regulatory compliance, special processing requirements, and workfl ow effi ciencies.

SPS would like to add two additional cart washers for redundancy and requires re-confi guration of workfl ow to separate its internal processes to align with current operating regulations. The Hines VA provides surgical and procedural care for inpatient and outpatient services. The Sterile Processing Department (SPS) serves not only the Surgery Department, but also Radiation Therapy, GU Clinic, Eye Clinic, Radiology, Medical Intensive

Care Unit, Surgery Intensive Care Unit, Surgery, Dental Clinic, Digestive/Endoscopy Clinic, and Pulmonology/

Respiratory Care Clinic. The SPS gathers and distributes instruments throughout the building, with the second fl oor surgery department being the primary location served. The goals to drive the modernization of the SPS are defi ned and have been provided by the SPS leadership team, they are as follows:

• Resolve Vertical Circulation, reduce travel time and cross traffi c with public and other services.

• Upgrade equipment and utility services, including water treatment.

• Modernize departmental workfl ow and staff effi ciency and accuracy.

The new department shall be programmed to provide appropriate staff support areas such as staff lockers, restrooms with shower, staff break room, conference room, workstations, and two offi ces. The processing area shall be provided appropriate separation and fl ow of materials and personnel. The infrastructure shall provide modern air circulation, air supply, dehumidifi cation, treated water, sanitary and emergency electrical supply. Within this study a space program is provided that is created through the VA’s Space Planning Criteria

SEPS software based on the SPS’s provided input data. The program supports a new SPS department at

8,300 net square foot, for a range of 12,000-15,000 building gross square footage. The building gross square footage will vary depending on circulation, structural and utility effi ciencies each option is able to provide.

This program provides the base line for the ten location options in the initial exercise and a development of three concept space layouts from the top three ranking siting options. The concepts incorporate the leadership goals and correct the following FCA defi ciencies:

SPS FCA Defi ciencies to be Corrected:

• Record No. 42259 for equipment that is graded “D”

• Record No. 161422 for fi nishes that are graded “D”

• Record No. 363893 for water infi ltration graded “D”

• Record No. 363898 for water infi ltration graded “D”

• Record No. 363216 for outdated/missing PIV access control graded “D”

The scope of the study includes the identifi cation, analysis, and evaluation through a scoring matrix of fourteen criteria to either expand Building 200 through the construction of an addition, renovate interior space for relocation, or a combination of addition and renovation. All options are required to be attached to or within Building 200. Each location is described, indicated in plan, and outlined 3-dimensionally in its relationship to Building 200. Each option is also scored based on the Assessment Factors further outlined in this report. The Assessment Factors have been provided by the VA, along with the scoring levels. Each of the ten options address the outline below in narrative form and by scoring levels. A comparative matrix of all the options is also provided to provide a location where all the scores for each option may be reviewed.

A project estimate for each concept is provided to communicate magnitude of cost for each option and their relationship to each other. Concept space plans are created for the preferred three relocation options.

The feasibility study concludes with a descriptive statement of work for VA use in procuring design and engineering services.

Ten Options

The ten options reviewed and broken down for further analysis are the following:

Option 1: Relocate SPS to West Roof/Renovate Existing Storage

Option 2: Relocate SPS and OR Sterile Storage to East Roof/ Relocate OR Waiting to OR Storage

Option 3: Relocate SPS to OR Core/ Reconfi gure OR Storage

Option 4: New Two Story SPS Space North Face of Building 200 and Between Building 128

Option 5: Relocate SPS to 15th Floor

Option 6: Relocate SPS to OR PACU/ Relocate PACU and Reconfi gure OR Storage

Option 7: New Two Story SPS Space Southwest Face of Building 200

Option 8: Expand Existing SPS and Reconfi gure Ambulatory Surgery (Basement)

Option 9: New Two Story SPS Space South Face of Building 200/ Reconfi gure South Circle Drop-off

Option 10: Relocate SPS to Orthopedic OR Core/ Relocate Orthopedic OR Services to Ambulatory Surgery

Part 1 - Executive Summary

Edward Hines, Jr. VA Medical Center | 8

Assessment Factors

1. Architecture: Each option shall be rated on its impact to the architecture of the Campus and Building 200.

The highest scores are given to those projects with the least impact to the exterior of the building. An addition would impact the overall look of the building and require more complex construction to connect new construction to the existing building.

2. Civil Engineering and Existing Site Conditions: Each option shall be rated on its impact to the existing Campus.

All projects will require contractor parking and logistics site use. The projects were scored on their lasting impact on the site. Those projects impacting utilities or physical security off sets were ranked the lowest.

3. Constructability: Each option shall be rated based on the disruption to the hospital and Campus operations during construction. This rating shall also consider the sites diffi culty or ease of construction. Projects were ranked based on the impact of construction on fl oors above and below, number of phases, and requirements of relocation of existing services. Those with the most disruptions where ranked the lowest.

4. Cost Estimation for Design and Construction: A cost estimate shall be provided for each option broken out by CSI Divisions which is to include a line-item cost for design services.

5. Electrical: Each option shall be rated based on its impact on the existing and future electrical systems.

The electrical service in the building, upon initial investigation is assumed to support relocation of the department without need to upgrade the service to Building 200. The service to the building is also assumed to support a branch to any new addition.

6. Energy: Each option shall be rated based on effi ciency of energy use. More energy effi cient options are rated higher. Additions require additional energy to operate and rank less than interior renovations where additional space to heat and cool is not provided.

7. Environmental Design: Each option shall be rated based on the environmental impact, such as permeable pavement and re-use of building elements. The additions have the greatest impact on the site and increase stormwater run-off will need to be managed.

8. Function and Adjacencies: Each option is to be rated based on the location’s adjacencies to SPS clients, determines if the location allows for an effi cient fl oor plan, and supports effi cient hospital operations.

Options that create direct adjacencies with the 2nd Floor are ranked the highest while those options furthest from the 2nd fl oor ranked the lowest.

9. Infection Control: Each option shall be rated based on how positively or negatively it impacts the hospital’s infection control eff orts. The options that are proposed with the greatest number of construction phases, cross traffi c with public corridors and which increase transportation time of the instruments for processing rank the lowest.

10. Mechanical: Each option shall be rated based on its impact on the existing and any future mechanical systems. The mechanical system in the building, on initial investigation, require a new air handler unit and exhaust capacity be provided whether it’s an addition or an interior renovation.

11. Phasing of Construction/Schedule Development: Each option shall be rated on the ease of phasing construction to minimize costs and disruption to the hospital and campus’ operations. The projects with no relocation of other services and that proposed the fewest construction phases for completion are ranked highest.

12. Plumbing: Each option shall be based on its impact on the existing and future plumbing systems. The plumbing in the building, upon initial investigation, is assumed to support relocation of the department without need to upgrade the service to Building 200. The plumbing service to the building is also assumed to support a water supply to any new addition. Localized water treatment in all options will be required.

13. Security: Each option shall be rated on the ease of physical security. Additions require alignment with the

VA’s Physical Security Design Guide. One key aspect of that design guide is that all new construction shall maintain a 50’ setback from any vehicular movement, which would require civil work to re-align drop off s and access drives. Interior options would require security access control, which would be through the use of door and card reader access.

14. Structural: Each option shall be rated on the structural effi ciency and impact of each site.

Assessment Scoring Levels

5 Points - Exceptional: One or more strong points that will signifi cantly benefi t the VA. No weak points.

4 Points - Very Good: One or more strong points that will benefi t the VA. Weak points, if any, are minor.

Strong points outweigh any minor weak points.

3 Points - Satisfactory: Few or no strong points that will benefi t VA. Strong and weak points are off setting or will have little impact on performance.

2 Points - Marginal: One or more weak points that are not off set by strong points.

1 Points - Unsatisfactory: No strong points. Weak points/numerous weak points exist.

0 Points – not an acceptable solution to the category. This eff ectively eliminates an option from consideration.

Part 1 - Executive Summary

3 Concepts

The Hines VA facility group assessed the ten options with the design team and three options were identifi ed for conceptual development based on the Score Card cumulative score and meeting the needs of the facility.

The selected options are the following:

Option 3 which is the reconfi guration and consolidation of surgery support spaces to accommodate the relocation of SPS services to the Second fl oor.

Option 8 which is the expansion of SPS services in place in the Basement which involves correcting existing building infrastructure issues and re-confi guring ambulatory surgery to increase the SPS footprint.

Option 9 which is the expansion of Building 200 with an addition on the south side and reconfi guration of the existing drive and drop of, which also corrects existing physical security defi ciencies.

These three options are presented with concept fl oor plans, all three of which align with the VA SEPS generated program presented in the Space Allocation section of this report. The three concepts are also presented with a refi ned project cost.

Reuse Study

Two of the presented concepts will leave a vacated space available for future renovation and relocation or expansion of other service areas on campus. Upon conversations with the hospital’s planning staff , the following uses for the vacated areas are reviewed within this report.

1. Inpatient Pharmacy

2. Eye Clinic Consolidated with adjacent Ambulatory Surgery

3. Caregiver Support and Respite

4. Facility Central Locker, Lounge and Touchdown Space

Option 1 to relocate Inpatient Pharmacy to the basement fl oor from the fi rst fl oor would vacate critical space on the fi rst fl oor which can be used for patient facing care clinics.

Option 2 to relocate the Eye Clinic would consolidate the Eye Clinic next to Ambulatory Surgery where

Ophthalmology provides procedures and surgeries.

Option 3 for creating a central Caregiver Support and Respite Clinic would fi ll a patient care need that had been identifi ed as being needed for the population of veterans at this location. This would be a new space within the hospital.

Option 4 to provide facility lockers and central staff support staff would fi ll a need that is not provided and is a core support for staff in the hospital. The central lockers and lounge would provide a place for logistics, EMS, Facilities, Nutrition, and other services a place to go for a break and to change before and after work. The space would also be provided with touchdown workstations to support computer access for email, training, and an onsite location for remote workers when they come to the building. Training and conference rooms would also be provided and available to staff working in Building 200 and on campus.

A/E Scope of Work

The report includes narrative language for the VA to include within their Scopes of Work to solicit for design and engineering services. There is a scope of work narrative provided for each of the three concept design options that outlines program needs, proposed consultant needs, scope of work and important information needed for a fi rm to provide an appropriate fee for design and construction administrative services.

Edward Hines, Jr. VA Medical Center | 10

Page Intentionally left Blank

SPACE ALLOCATION MATRIX

. S p a c e

A llo c a tio n

M a trix

The basis of study for this section are the current conditions aff ecting the state of workfl ow and compliance issues for the SPS. The review includes observations of the existing site’s physical condition, equipment, utilities, and workfl ow defi ciencies. The SPS requires additional space for separation of processes between low temperature instrument, standard instrument, and scope processing. The SPS department needs staff support facilities such as workstations, break area, and locker rooms.

This study also includes an analysis of SPS services provided throughout the hospital, space programming needs for a modern department, equipment needs, and review of the existing campus for potential building expansion.

The existing SPS footprint is approximately 7,000 sf, an equivalent modern department with segregated workfl ow and staff areas based on VA standards would be around 8,300 sf net square footage. A gross building square footage need of approximately 12,000-15,000 sf total would be required for a new location. An area’s shape and proportions infl uence the gross building square footage depending on number of corridors, mechanical chase, and such to support a new area, thus the reason for the range in gross building square footage.

Part 2 - Space Allocation Matrix

��
���
��
���
����
����� ����
�����������
��
���
����
��
�����������
��
�����������
��
�����������
��
�����������
��
�����������
��
�����������
��
�����������
��
�����������
��
�+���
��

Existing SPS Analysis

Existing SPS Analysis - Basement Floor

Congestion at elevators, none are dedicated to transport dirty or clean materials, cross traffi c is an issue.

DECOMTAM

SIDE

CLEAN

SIDE

DISPATCH

Single entry/ ante-room into SPS

Scope processing area

Bank of 5 sterilizers

Packet sterilizers

Existing elevator shaft through all fl oors of

Building 200. Option to use 1 shaft for new cart elevator conveyor system to transport dirty materials between fl oors. Access would need to be provided at fl oors B, 1, 2, 12, 13 and

14. The EHRM project for new telecom rooms utilizes these vertical chases.

Edward Hines, Jr. VA Medical Center | 14

Part 2 - Space Allocation Matrix

��
���
��
���
����
����� ����
�����������
��
���
����
��
�����������
��
�����������
��
�����������
��
�����������
��
�����������
��
�����������
��
�����������
��
�����������
��
�+���
��

Photo Views- Basement Floor

F

G

H

E D

C

AB

Key workfl ow defi ciencies identifi ed within the department include the following:

• Outside access through ante rooms to dirty and clean areas for donning and doffi ng PPE, as well as receiving vendors and their equipment.

• Scope processing is completed in the decontamination area with an ineffi cient manner to process scopes and to transfer them to the clean side of SPS for distribution.

• Defi cient separation of low temperature processing of eye instruments from standard instrument processing.

• Lack of instrument and scope sterile supply storage in a central area. All the supplies are stored wherever a cabinet will fi t, thus creating an ineffi cient workfl ow for compiling sterile packets.

• Defi cient HVAC air exchanges and exhaust of the space, thus the space is challenged to meet requirements for air exchanges, exhaust, and humidity control.

• Distribution issue with transporting materials to and from the area in the building due to elevator traffi c congestion.

A & B Clean workroom, workstation and instruction storage

C. D & E Case cart assembly and dispatch area

F, G, & H Existing sterilizers

Existing Photos

A

B

C

D

E

F

G

H

Edward Hines, Jr. VA Medical Center | 16

U T

IL

IT

Y

L E G E N D

U E

B U R

IE

D

E L E C T R

IC

B T

B U R

IE

D

T E L E P H O N E

F O C

B U R

IE

D

F

IB

E R

O P T

IC

C A B L E

C T V

B U R

IE

D

C A B L E

T V

G A S

G A S

W A T E R

S T M

S T E A M

U N K

B U R

IE

D

U N K N O W N

U T

IL

IT

Y

F L

F U E L

L

IN

E

O X Y G E N

L

IN

E

S S

S A N

IT

A R Y

S E W E R

S T

S T O R M

S E W E R

C

IV

IL

E

N G

IN

E

E R

IN

G

* T R

A N

S P

O R

T A

T

IO

N

* E

N V

IR

O

N M

E N

T A

L

* P

L A

N N

IN

G

* U T

IL

IT

Y E

N G

IN

E

E R

IN

G

/L O

C A

T

IN

G

E L E C T R

IC

P E D E S T A L

M E T E R

S T O R M

IN

L E T

S T O R M

M A N H O L E

M A N H O L E

M A N H O L E

M A N H O L E V A U L T

S A N

IT

A R Y

M A N H O L E

M E T E R

V A U L T

H A N D H O L E

VA Hines Utility Map

EXPANSION

AREA A

EXPANSION

AREA B

EXPANSION

AREA C EXPANSION

AREA E

EXPANSION

AREA D

BUILDING

BUILDING

BUILDING

BUILDING 13

B U

IL

D

IN

G

B U

IL

D

IN

G

The exterior site was reviewed around the perimeter of Building 200 to identify possible locations to provide a new two-story addition to accommodate a new SPS department. All two-story additions would require having a connector over the existing roof of Building 200 to connect the new addition to the second fl oor. Connectors on the fi rst fl oor would disrupt patient clinics with material being transported through the spaces or the clinics would be reduced in size to accommodate new corridor construction.

Area A is set between Building 200 and Building 128. There is a drive directly to the west for support and delivery vehicles to Building 200.

This drive would require a security gate, bollards, and other security provisions to align with the VA Physical Security requirements. The open area has a linear accelerator and photon therapy vault underground that a new addition would have to be constructed over.

Area B is adjacent to the current Emergency Department and a second fl oor addition would remove exterior patient windows, which are a requirement for patient rooms. The addition would decommission intensive care rooms, cause disruptions, and possible emergency room shutdowns. Due to these critical confl icts, an option in this area will not be further explored in this study.

Area C is an open space with an area well where the main water, steam and electrical services come into Building 200. To construct in this area would require construction over or relocation of utilities, which could require utility shutdowns to portions of Building 200. This area will be further explored in this study to understand utility impacts of an addition.

Area D would require the shutdown of the south entry and reconfi guration of the existing drive to align with the VA Physical Security Manual. Utilities can be relocated or constructed over. This location has been determined as a possible location to support an addition and will be further explored in the study.

Area E has been assigned to house an emergency generator farm and is currently a design and construction project. This area is not available for further study.

Existing SPS Site

ACS SPECIALTY CARE

COMMON SPACE

EDUCATION

ENGINEERING

ENVIRONMENTAL MGMT

LINEN SERVICE

NURSING SVC ADMIN

NUTRITION/FOOD

PATHOLOGY

RADIATION THERAPY

REHAB MEDICINE

SPD SERVICE

SURGICAL

UNASSIGNED VACANT SPACE

VERTICAL SPACE

TO BLDG.

OPEN TO

BELOW

TO BLDG.

OPEN

OPEN

SURGICAL

RECOVERY

A001

1,919 SF

SURGICAL

SUPPLY

STORAGE

A001F

111 SF

SURGICAL

STORAGE

A001E

108 SF

SURGICAL

LOUNGE

A001C

161 SF

SURGICAL

SPECIMEN

ROOM

A001D

157 SF

SURGICAL

OFFICE

A002

192 SF

SURGICAL

OPERATING ROOM

A003

380 SF

UNASSIGNED VACANT SPACE

OPERATING ROOM

A004

368 SF

SURGICAL

OPERATING ROOM

A005

528 SF

UNASSIGNED VACANT SPACE

OPERATING ROOM

A006

361 SF

UNASSIGNED

VACANT SPACE

STORAGE

A007

101 SF

SURGICAL

SUPPLY STORAGE

A009

429 SF

UNASSIGNED VACANT SPACE

OPERATING ROOM

A010

387 SF

SURGICAL

OPERATING ROOM

A011

561 SF UNASSIGNED VACANT SPACE

STORAGE

A012

374 SF

UNASSIGNED

VACANT SPACE

STORAGE

A013

108 SF

UNASSIGNED VACANT SPACE

OPERATING ROOM

A015

386 SF

SURGICAL

EQUIPMENT

STORAGE

A017

97 SF

SURGICAL

OPERATING ROOM

A018

364 SF

UNASSIGNED

VACANT SPACE

H.A.C.

A020

46 SF

UNASSIGNED VACANT SPACE

OXYGEN TANK STORAGE

A029

64 SF

SURGICAL

CHASE

RCCB03C

7 SF

UNASSIGNED

VACANT SPACE

CHASE

RCCB04C

8 SF

SURGICAL

CHASE

RCCB05C

17 SF

UNASSIGNED

VACANT SPACE

CHASE

RCCB06C

7 SF

SURGICAL

CHASE

RCCB08C

8 SF

SURGICAL

CHASE

RCCB07C

9 SF

SURGICAL

CHASE

RCCB10C

8 SF

UNASSIGNED

VACANT SPACE

CHASE

RCCB09C

7 SF

SURGICAL

CHASE

RCCB11C

15 SF

COMMON

SPACE

RCCB01R

7 SF

SURGICAL

CHASE

RCCB01C

93 SF

SURGICAL

CHASE

RCCB02C

12 SF

COMMON SPACE

CORRIDOR

RCCB02R

1,685 SF

COMMON SPACE

CORRIDOR

RCCB03R

1,319 SF

SPD SERVICE

PUMP ROOM STORAGE

A021

236 SF

SPD SERVICE

GAS CONTAINER STORAGE

A022B

45 SF

SPD SERVICE

EQUIPMENT STORAGE

A023C

1,529 SF

SPD SERVICE

LINEN

A023D

280 SF

SPD SERVICE

H.A.C.

A023E

40 SF

SPD SERVICE

CART WASH

A025C

112 SF

SPD SERVICE

LINEN

A023F

348 SF

ENVIRONMENTAL

MGMT

H.A.C.

A025B

29 SF

ENVIRONMENTAL

MGMT

H.A.C.

A025D

48 SF

SPD SERVICE

SUPPLY STORAGE

A024C

85 SF

ENVIRONMENTAL

MGMT

LOCKER ROOM

A024A

144 SF

SPD SERVICE

STERILE

PROCESSING

A023I

244 SF

SPD SERVICE

STORAGE

RCCB04R

37 SF

SPD SERVICE

PREPERATION &

STERILIZATION

A025

3,808 SF

ENVIRONMENTAL MGMT

LOCKER ROOM

A024B

125 SF

SPD SERVICE

OFFICE

A023G

155 SF

COMMON SPACE

MECHANICAL ROOM

A023J

70 SF

ENVIRONMENTAL

MGMT

CHASE

RCCB12C

7 SF

ENVIRONMENTAL

MGMT

CHASE

RCCB13C

7 SF

COMMON

SPACE

RCCB05R

3 SF

SPD SERVICE

CHASE

RCCB14C

9 SF

SPD SERVICE

STORAGE

RCCB06R

37 SF

COMMON SPACE

CORRIDOR

RCCB07R

60 SF

SURGICAL

ANESTHESIA WORK ROOM

B003

478 SF

SURGICAL

H.A.C.

B006

62 SF

LINEN SERVICE

LINEN

B006B

144 SF

SURGICAL

BLOOD GAS ANALYSIS

B008A

117 SF

COMMON

SPACE

RCCB08R

19 SF

SURGICAL

OFFICE

B009

174 SF

SURGICAL

LOCKER ROOM

B010

322 SF

SURGICAL

TOILET

B010A

143 SF

SURGICAL

LOUNGE

B011

291 SF

SURGICAL

COPY ROOM

B012

259 SF

SURGICAL

LOCKER ROOM

B014

385 SF

SURGICAL

TOILET

B014A

139 SF

SURGICAL

CHASE

RCCB15C

45 SF

COMMON

SPACE

RCCB09R

4 SF

COMMON SPACE

CORRIDOR

RCCB10R

363 SF

COMMON SPACE

CORRIDOR

RCCB11R

471 SF

COMMON SPACE

CORRIDOR

RCCB12R

268 SF

VERTICAL

SPACE

STAIR

RCCB13R

141 SF

SURGICAL

PATIENT HOLDING

B016

583 SF

SURGICAL

SOILED UTILITY

B017

81 SF

SURGICAL

TOILET

B016B

36 SF

SURGICAL

CHASE

RCCB16C

12 SF

SURGICAL

CONFERENCE ROOM

B018

265 SF

SURGICAL

CHASE

RCCB17C

10 SF

COMMON SPACE

CORRIDOR

RCCB14R

1,423 SF

SURGICAL

OFFICE

B019

836 SF

SURGICAL

OFFICE

B019B

88 SF

SURGICAL

OFFICE

B019C

93 SF

SURGICAL

TOILET

B020B

46 SF

COMMON SPACE

CORRIDOR

RCCB15R

174 SF

SURGICAL

TOILET

B020A

38 SF

SURGICAL

RECEPTION

B020

715 SF

SURGICAL

EXAM

B022A

99 SF

SURGICAL

EXAM

B022B

84 SF

SURGICAL

EXAM

B022C

83 SF

SURGICAL

EXAM

B022D

82 SF

SURGICAL

EXAM

B022E

76 SF

SURGICAL

EXAM

B022F

77 SF

SURGICAL

EXAM

B022G

131 SF

SURGICAL

URODYNAMIC

LAB

B022H

192 SF

SURGICAL

TOILET

B022I

37 SF

SURGICAL

UTILITY

B023D

48 SF

COMMON SPACE

CORRIDOR

RCCB16R

520 SF

SURGICAL

CHASE

RCCB19C

7 SF

SURGICAL

TOILET

B024A

30 SF

SURGICAL

TOILET

B023C

30 SF

SURGICAL

TOILET

B023B

33 SF

SURGICAL

STORAGE

B026

133 SF

SURGICAL

PROCEDURE

ROOM

B027

260 SF

SURGICAL

LOCKER ROOM

B024

163 SF

SURGICAL

RECOVERY

B023

1,353 SF

SURGICAL

DRESSING

ROOM

B024B

34 SF

SURGICAL

DRESSING

ROOM

B024C

34 SF

SURGICAL

H.A.C.

B024F

26 SF

SURGICAL

CHASE

RCCB20C

13 SF

SURGICAL

CHASE

RCCB21C

12 SF

SURGICAL

LOCKER ROOM

B024D

57 SF

SURGICAL

LOCKER ROOM

B024E

47 SF

SURGICAL

DECONTAMINATION

ROOM

B025A

48 SF

SURGICAL

SOILED UTILITY

B025B

48 SF

SURGICAL

CLEAN ROOM

B029B

95 SF

SURGICAL

PROCEDURE ROOM

B028

350 SF

SURGICAL

PROCEDURE ROOM

B029

346 SF

COMMON SPACE

CORRIDOR

RCCB17R

470 SF

SURGICAL

CHASE

RCCB22C

8 SF

SURGICAL

CHASE

RCCB24C

20 SF

SURGICAL

CHASE

RCCB23C

14 SF

SURGICAL

CHASE

RCCB25C

7 SF

SURGICAL

CHASE

RCCB27C

7 SF

SURGICAL

CHASE

RCCB26C

18 SF

SURGICAL

ANESTHESIA STORAGE

B036

717 SF

SURGICAL

OFFICE

B036A

96 SF

ENVIRONMENTAL

MGMT

H.A.C.

B030

50 SF

NURSING SVC ADMIN

WHEEL CHAIR STORAGE

B031

2,144 SF

ENVIRONMENTAL

MGMT

TOILET

B032

57 SF

ENGINEERING

ELEVATOR MACHINE ROOM

B033

114 SF

SURGICAL

ELECTRICAL CLOSET

B037A

50 SF

COMMON SPACE

CORRIDOR

RCCB18R

1,147 SF

COMMON

SPACE

RCCB19R

23 SF

COMMON SPACE

CORRIDOR

RCCB21R

1,004 SF

COMMON

SPACE

RCCB20R

25 SF

SURGICAL

C005A

3 SF

ENVIRONMENTAL

MGMT

CHASE

RCCB28C

12 SF

VERTICAL SPACE

ELEVATOR

RCCB29C

81 SF

ENGINEERING

COMMUNICATIONS

B040

1,114 SF

ENGINEERING

BED REPAIR

B039

1,338 SF

SURGICAL

ANESTHESIA STORAGE

B037

1,061 SF

SURGICAL

TELEPHONE CLOSET

B037C

12 SF

SURGICAL

COMPUTER

ROOM

B037B

14 SF

SURGICAL

ELECTRICAL CLOSET

B037D

23 SF

COMMON

SPACE

RCCB22R

2 SF

ACS-SPECIALTY CARE

WAITING ROOM

B038

527 SF

ACS-SPECIALTY CARE

EXAM

B038C

127 SF

ACS-SPECIALTY CARE

EXAM

B038D

143 SF

ACS-SPECIALTY CARE

EXAM

B038E

143 SF

ACS-SPECIALTY

CARE

EXAM

B038F

92 SF

ACS-SPECIALTY CARE

EXAM

B038G

92 SF

ACS-SPECIALTY CARE

OFFICE

B038H

154 SF

ENVIRONMENTAL MGMT

TOILET

B038I

38 SF

VERTICAL SPACE

STAIR

RCCB30C

156 SF

ENGINEERING

COMMUNICATIONS

B040A

69 SF

SPD SERVICE

OXYGEN TANK

STORAGE

C003

67 SF

NUTRITION/FOOD

ELECTRICAL CLOSET

C003A

229 SF

ENGINEERING

STORAGE

C004

140 SF

VERTICAL SPACE

CHASE

C004a

49 SF

VERTICAL

SPACE

CHASE

RCCB31C

25 SF

VERTICAL SPACE

CHASE

C099

68 SF

SURGICAL

OFFICE

C005

124 SF

SURGICAL

OFFICE

C006

144 SF

REHAB MEDICINE

OFFICE

C007

132 SF

ENVIRONMENTAL

MGMT

TOILET

C008

40 SF

SURGICAL

OFFICE

C009

261 SF

NUTRITION/FOOD

OFFICE

C010

230 SF

SURGICAL

CHASE

RCCB32C

12 SF

ENVIRONMENTAL

MGMT

CHASE

RCCB33C

9 SF

ENGINEERING

TOILET

C021

508 SF

ENGINEERING

CHASE

RCCB39C

8 SF

ENGINEERING

CHASE

RCCB38C

12 SF

NUTRITION/FOOD

OFFICE

C011

331 SF

ENGINEERING

ELECTRICAL

STORAGE

C012

180 SF

NUTRITION/FOOD

OFFICE

C012

302 SF

ENVIRONMENTAL MGMT

SOILED LINEN ROOM

C012A

152 SF

ENGINEERING

STORAGE

C012C

73 SF

ENGINEERING

STORAGE

C012D

109 SF ENGINEERING

STORAGE

C012E

45 SF

COMMON SPACE

ELECTRICAL CLOSET

C014

793 SF

NUTRITION/FOOD

TOILET

C015

84 SF

NUTRITION/FOOD

TOILET

C016

82 SF

NUTRITION/FOOD

CHASE

RCCB34C

14 SF

COMMON SPACE

ELECTRICAL CLOSET

C017

1,810 SF

NUTRITION/FOOD

OFFICE

C018

411 SF

NUTRITION/FOOD

CHASE

RCCB35C

13 SF

COMMON SPACE

ELECTRICAL CLOSET

C022

1,623 SF

VERTICAL SPACE

STAIR

RCCB36C

159 SF

VERTICAL

SPACE

CHASE

RCCB37C

25 SF

COMMON SPACE

C020

44 SF

COMMON

SPACE

C020A

10 SF

COMMON SPACE

CORRIDOR

RCCB23R

1,900 SF

NUTRITION/FOOD

H.A.C.

C029

33 SF

NUTRITION/FOOD

TOILET

C025

88 SF

NUTRITION/FOOD

CHASE

RCCB41C

13 SF

VERTICAL SPACE

ELEVATOR

RCCB42C

75 SF

VERTICAL SPACE

ELEVATOR

RCCB43C

149 SF

VERTICAL SPACE

STAIR

RCCB40C

155 SF

NUTRITION/FOOD

ELECTRICAL

CLOSET

C026

99 SF

ENGINEERING

UTILITY

RCCB24R

57 SF

NUTRITION/FOOD

FRIDGE

C024

445 SF

NUTRITION/FOOD

FRIDGE

C025A

316 SF

COMMON SPACE

CORRIDOR

RCCB25R

803 SF

NUTRITION/FOOD

FRIDGE

C025B

365 SF

NUTRITION/FOOD

FREEZER

C031A

713 SF

NUTRITION/FOOD

THAW BOX

C031

326 SF

NUTRITION/FOOD

LOCKER ROOM

C032H

44 SF

NUTRITION/FOOD

H.A.C.

C032G

54 SF

NUTRITION/FOOD

H.A.C.

D011D

47 SF

NUTRITION/FOOD

TOILET

D011E

47 SF

NUTRITION/FOOD

MAIN KITCHEN

C032

8,333 SF

NUTRITION/FOOD

DISH ROOM

C032A

1,243 SF

NUTRITION/FOOD

H.A.C.

C032C

36 SF

NUTRITION/FOOD

DRY FOOD STORAGE

C032D

906 SF

NUTRITION/FOOD

LIQUID STORAGE

C032E

393 SF

NUTRITION/FOOD

FRIDGE

C032F

318 SF

NUTRITION/FOOD

OFFICE

C032K

115 SF

NUTRITION/FOOD

OFFICE

C032L

176 SF

VERTICAL SPACE

CHASE

RCCB44C

74 SF

SPD SERVICE

RCCB26R

26 SF

SPD SERVICE

RCCB27R

28 SF

RADIATION THERAPY

NURSE STATION

D008D

306 SF

NUTRITION/FOOD

TOILET

D001

78 SF

NUTRITION/FOOD

TOILET

D002

73 SF

NUTRITION/FOOD

H.A.C.

D004

36 SF

NUTRITION/FOOD

STORAGE

D005

125 SF

RADIATION THERAPY

STORAGE

D006

166 SF

RADIATION THERAPY

SUPPLY STORAGE

D006A

131 SF

RADIATION THERAPY

STORAGE

D006B

133 SF

SURGICAL

RCCB28R

72 SF

VERTICAL SPACE

ELEVATOR

RCCB45C

74 SF

VERTICAL SPACE

ELEVATOR

RCCB46C

75 SF

VERTICAL SPACE

ELEVATOR

RCCB47C

74 SF

VERTICAL SPACE

ELEVATOR

RCCB48C

74 SF

VERTICAL SPACE

ELEVATOR

RCCB49C

74 SF

VERTICAL SPACE

ELEVATOR

RCCB50C

86 SF

VERTICAL SPACE

ELEVATOR

RCCB51C

87 SF

VERTICAL SPACE

ELEVATOR

RCCB52C

86 SF

COMMON SPACE

CORRIDOR

RCCB29R

1,595 SF

NUTRITION/FOOD

CHASE

RCCB53C

11 SF

VERTICAL SPACE

STAIR

RCCB54C

196 SF

NUTRITION/FOOD

CHASE

RCCB55C

14 SF

RADIATION THERAPY

STORAGE

D007

431 SF

RADIATION THERAPY

DARK ROOM

D007B

71 SF

RADIATION THERAPY

RADIATION THERAPY

D007C

429 SF

RADIATION THERAPY

RECEPTION

D008

156 SF

RADIATION

THERAPY

WASH ROOM

D008A

59 SF

RADIATION

THERAPY

MEDS

D008B

58 SF

RADIATION THERAPY

OFFICE

D008C

122 SF

COMMON SPACE

CORRIDOR

RCCB30R

964 SF

COMMON

SPACE

RCCB31R

18 SF

COMMON SPACE

RCCB32R

24 SF

RADIATION THERAPY

OFFICE

D008M

328 SF

RADIATION THERAPY

EXAM

D008K

118 SF

RADIATION THERAPY

EXAM

D008J

144 SF

RADIATION THERAPY

COBALT THERAPY

D008I

477 SF

RADIATION THERAPY

CONSULT

RCCB33R

108 SF

RADIATION

THERAPY

TOILET

D008E

80 SF

RADIATION

THERAPY

TOILET

D008F

75 SF

RADIATION THERAPY

RADIATION THERAPY

D008H

574 SF

RADIATION THERAPY

CHASE

RCCB56C

23 SF

COMMON SPACE

CHASE

RCCB58C

68 SF

VERTICAL SPACE

ELEVATOR

RCCB57C

75 SF

COMMON SPACE

CORRIDOR

RCCB34R

1,731 SF

VERTICAL

SPACE

ELEVATOR

RCCB60C

59 SF

VERTICAL

SPACE

ELEVATOR

RCCB59C

59 SF

VERTICAL SPACE

STAIR

RCCB61C

38 SF

EDUCATION

TRAINING ROOM

D009

1,626 SF

NUTRITION/FOOD

PATIENT DINING

D009A

333 SF

NUTRITION/FOOD

CORRIDOR

RCCB36R

64 SF

NUTRITION/FOOD

CHASE

RCCB62C

65 SF

EDUCATION

ENTRY

RCCB35R

110 SF

NUTRITION/FOOD

STORAGE

D009F

122 SF

NUTRITION/FOOD

CHASE

RCCB64C

10 SF

NUTRITION/FOOD

CHASE

RCCB63C

21 SF

COMMON

SPACE

RCCB37R

3 SF

NUTRITION/FOOD

H.A.C.

D009E

32 SFNUTRITION/FOOD

FRIDGE

D009G

159 SF

NUTRITION/FOOD

CHASE

RCCB65C

16 SF

NUTRITION/FOOD

DEEP FREEZE

D009H

106 SF

NUTRITION/FOOD

DESSERT REFRIG

D009I

106 SF

RADIATION THERAPY

WAITING ROOM

D010

289 SF

RADIATION THERAPY

CHASE

RCCB66C

7 SF

RADIATION THERAPY

OFFICE

D010A

86 SF

RADIATION

THERAPY

EXAM

D010B

87 SF

RADIATION THERAPY

EXAM

D010C

99 SF

RADIATION THERAPY

EXAM

D010D

98 SF

RADIATION THERAPY

OFFICE

D010E

476 SF

RADIATION

THERAPY

DRESSING

ROOM

D010F

128 SF

RADIATION

THERAPY

SUPPLY

STORAGE

D010G

41 SF

RADIATION

THERAPY

STORAGE

CLOSET

D010I

41 SF

RADIATION THERAPY

RADIATION THERAPY

D010J

879 SF

RADIATION THERAPY

ELECTRICAL CLOSET

D010K

135 SF

RADIATION THERAPY

ELECTRICAL CLOSET

D010N

24 SF

RADIATION

THERAPY

LINEN

D010Q

40 SF

COMMON SPACE

CORRIDOR

RCCB38R

1,607 SF

RADIATION THERAPY

CHASE

RCCB67C

4 SF

RADIATION THERAPY

CHASE

RCCB69C

54 SF

RADIATION THERAPY

RECEPTION

RCCB39R

49 SF

RADIATION THERAPY

CHASE

RCCB68C

24 SF

RADIATION THERAPY

OFFICE

D011A

297 SF

RADIATION THERAPY

OFFICE

D011B

257 SF

NUTRITION/FOOD

LOUNGE

D011F

124 SF

RADIATION THERAPY

STORAGE

D011G

443 SF

RADIATION

THERAPY

RCCB40R

29 SF

COMMON SPACE

CORRIDOR

RCCB41R

205 SF

PATHOLOGY

WORK ROOM

D012

172 SF

PATHOLOGY

FRIDGE

D013

192 SF

PATHOLOGY

AUTOPSY SUITE

D014

616 SF

PATHOLOGY

TOILET

D015

111 SF

PATHOLOGY

H.A.C.

D016

42 SF

PATHOLOGY

TOILET

D017

77 SF

PATHOLOGY

CHASE

RCCB70C

9 SF

PATHOLOGY

CHASE

RCCB71C

7 SF

COMMON SPACE

CORRIDOR

RCCB42R

180 SF

COMMON SPACE

CORRIDOR

RCCB43R

55 SF

COMMON

SPACE

ELEVATOR

MACHINE

ROOM

D021

108 SF

COMMON SPACE

MECHANICAL ROOM

D018

746 SFCOMMON

SPACE

COMM CLOSET

D018A

14 SF

COMMON SPACE

ELECTRICAL CLOSET

D018B

29 SF

VERTICAL SPACE

STAIR

RCCB72C

154 SF

COMMON

SPACE

F/E CLOSET

D021A

3 SF

COMMON SPACE

CORRIDOR

RCCB44R

570 SF

VERTICAL

SPACE

ELEVATOR

RCCB73C

85 SF

NUTRITION/FOOD

GREASE ROOM

D022

343 SF

NUTRITION/FOOD

SUPPLY ROOM

D023

940 SF

NUTRITION/FOOD

CHASE

RCCB74C

38 SF

COMMON

SPACE

RCCB45R

3 SF

VERTICAL SPACE

STAIR

RCCB75R

70 SF

UNASSIGNED VACANT SPACE

CORRIDOR

RCCB76R

1,341 SF

CONTRACTING FIRM: CLIENT &

PROJECT

NAME:

DRAWING SCALE:

DRAWING TITLE:

APPROVED BY:

BLDG NUMBER:

PROJECT NUMBER:

ISSUE DATE:

NORTH ARROW

1/

/2

2:

:5

P

M

3/64" = 1'-0"CAI DEPARTMENT FLOOR PLAN - BASEMENT

EDWARD HINES, JR. VA HOSPITAL

RFP: UPDATE HINES CAPITAL ASSETS INVENTORY RECORDS

01/20/2016

578-14-012

ERIC J. KUTCHE

CAI DEPARTMENT AREA

ACS SPECIALTY CARE 1,277 SF

COMMON SPACE 23,964 SF

EDUCATION 1,736 SF

ENGINEERING 3,767 SF

ENVIRONMENTAL MGMT 718 SF

LINEN SERVICE 144 SF

NURSING SVC ADMIN 2,144 SF

NUTRITION/FOOD 18,623 SF

PATHOLOGY 1,225 SF

RADIATION THERAPY 7,580 SF

REHAB MEDICINE 132 SF

SPD SERVICE 7,086 SF

SURGICAL 17,089 SF

UNASSIGNED VACANT SPACE 3,558 SF

VERTICAL SPACE 2,522 SF

LEVEL NET GROSS TOTAL 91,564 SF

7,613.9 sf

SPS staff admin spaces identifi ed during site investigation.

SPS new lockers under construction during site investigation.

Vacated ASC space and location of foundation water fi ltration issue.

Area is secured and no access permitted at time of investigation.

SPS

NUTRITION

ASC

NUCLEAR MEDICINE

VA Space Allocation Plan -Basement Floor

The basement fl oor off ers opportunity to expand the existing SPS in its current location. The Ambulatory Surgery Center (ASC) is only utilizing half of the ORs provided in the surgery core. There is an existing foundation water infi ltration issue that has caused an infection control issue for the department, and the department has consolidated their suite to only one corridor of ORs. If the foundation wall is repaired, the ASC could shift to the south, gain an additional two ORs, with two

ORs reconfi gured and modernized with new technology from their current state. This reconfi guration would free up space to expand SPS to the east, into the vacated ASC area. The amount of space available for expansion allows for the construction to be phased to maintain SPS and ASC surgery operations.

There is an existing vacated shaft that is proposed for new equipment to transport carts through the building. Dirty carts are proposed for this shaft in this study. This vertical transport of materials would be applicable to all presented options and concepts in this report. The shaft location is coordinated with the facilities EHRM design and construction project currently in design and will require additional coordination as both this study and that project move forward.

VA Space Allocation Plan Basement Floor Plan Analysis

ACS SPECIALTY CARE

COMMON SPACE

EDUCATION

ENGINEERING

ENVIRONMENTAL MGMT

LINEN SERVICE

NURSING SVC ADMIN

NUTRITION/FOOD

PATHOLOGY

RADIATION THERAPY

REHAB MEDICINE

SPD SERVICE

SURGICAL

UNASSIGNED VACANT SPACE

VERTICAL SPACE

TO BLDG.

OPEN TO

BELOW

TO BLDG.

OPEN

OPEN

SURGICAL

RECOVERY

A001

1,919 SF

SURGICAL

SUPPLY

STORAGE

A001F

111 SF

SURGICAL

STORAGE

A001E

108 SF

SURGICAL

LOUNGE

A001C

161 SF

SURGICAL

SPECIMEN

ROOM

A001D

157 SF

SURGICAL

OFFICE

A002

192 SF

SURGICAL

OPERATING ROOM

A003

380 SF

UNASSIGNED VACANT SPACE

OPERATING ROOM

A004

368 SF

SURGICAL

OPERATING ROOM

A005

528 SF

UNASSIGNED VACANT SPACE

OPERATING ROOM

A006

361 SF

UNASSIGNED

VACANT SPACE

STORAGE

A007

101 SF

SURGICAL

SUPPLY STORAGE

A009

429 SF

UNASSIGNED VACANT SPACE

OPERATING ROOM

A010

387 SF

SURGICAL

OPERATING ROOM

A011

561 SF UNASSIGNED VACANT SPACE

STORAGE

A012

374 SF

UNASSIGNED

VACANT SPACE

STORAGE

A013

108 SF

UNASSIGNED VACANT SPACE

OPERATING ROOM

A015

386 SF

SURGICAL

EQUIPMENT

STORAGE

A017

97 SF

SURGICAL

OPERATING ROOM

A018

364 SF

UNASSIGNED

VACANT SPACE

H.A.C.

A020

46 SF

UNASSIGNED VACANT SPACE

OXYGEN TANK STORAGE

A029

64 SF

SURGICAL

CHASE

RCCB03C

7 SF

UNASSIGNED

VACANT SPACE

CHASE

RCCB04C

8 SF

SURGICAL

CHASE

RCCB05C

17 SF

UNASSIGNED

VACANT SPACE

CHASE

RCCB06C

7 SF

SURGICAL

CHASE

RCCB08C

8 SF

SURGICAL

CHASE

RCCB07C

9 SF

SURGICAL

CHASE

RCCB10C

8 SF

UNASSIGNED

VACANT SPACE

CHASE

RCCB09C

7 SF

SURGICAL

CHASE

RCCB11C

15 SF

COMMON

SPACE

RCCB01R

7 SF

SURGICAL

CHASE

RCCB01C

93 SF

SURGICAL

CHASE

RCCB02C

12 SF

COMMON SPACE

CORRIDOR

RCCB02R

1,685 SF

COMMON SPACE

CORRIDOR

RCCB03R

1,319 SF

SPD SERVICE

PUMP ROOM STORAGE

A021

236 SF

SPD SERVICE

GAS CONTAINER STORAGE

A022B

45 SF

SPD SERVICE

EQUIPMENT STORAGE

A023C

1,529 SF

SPD SERVICE

LINEN

A023D

280 SF

SPD SERVICE

H.A.C.

A023E

40 SF

SPD SERVICE

CART WASH

A025C

112 SF

SPD SERVICE

LINEN

A023F

348 SF

ENVIRONMENTAL

MGMT

H.A.C.

A025B

29 SF

ENVIRONMENTAL

MGMT

H.A.C.

A025D

48 SF

SPD SERVICE

SUPPLY STORAGE

A024C

85 SF

ENVIRONMENTAL

MGMT

LOCKER ROOM

A024A

144 SF

SPD SERVICE

STERILE

PROCESSING

A023I

244 SF

SPD SERVICE

STORAGE

RCCB04R

37 SF

SPD SERVICE

PREPERATION &

STERILIZATION

A025

3,808 SF

ENVIRONMENTAL MGMT

LOCKER ROOM

A024B

125 SF

SPD SERVICE

OFFICE

A023G

155 SF

COMMON SPACE

MECHANICAL ROOM

A023J

70 SF

ENVIRONMENTAL

MGMT

CHASE

RCCB12C

7 SF

ENVIRONMENTAL

MGMT

CHASE

RCCB13C

7 SF

COMMON

SPACE

RCCB05R

3 SF

SPD SERVICE

CHASE

RCCB14C

9 SF

SPD SERVICE

STORAGE

RCCB06R

37 SF

COMMON SPACE

CORRIDOR

RCCB07R

60 SF

SURGICAL

ANESTHESIA WORK ROOM

B003

478 SF

SURGICAL

H.A.C.

B006

62 SF

LINEN SERVICE

LINEN

B006B

144 SF

SURGICAL

BLOOD GAS ANALYSIS

B008A

117 SF

COMMON

SPACE

RCCB08R

19 SF

SURGICAL

OFFICE

B009

174 SF

SURGICAL

LOCKER ROOM

B010

322 SF

SURGICAL

TOILET

B010A

143 SF

SURGICAL

LOUNGE

B011

291 SF

SURGICAL

COPY ROOM

B012

259 SF

SURGICAL

LOCKER ROOM

B014

385 SF

SURGICAL

TOILET

B014A

139 SF

SURGICAL

CHASE

RCCB15C

45 SF

COMMON

SPACE

RCCB09R

4 SF

COMMON SPACE

CORRIDOR

RCCB10R

363 SF

COMMON SPACE

CORRIDOR

RCCB11R

471 SF

COMMON SPACE

CORRIDOR

RCCB12R

268 SF

VERTICAL

SPACE

STAIR

RCCB13R

141 SF

SURGICAL

PATIENT HOLDING

B016

583 SF

SURGICAL

SOILED UTILITY

B017

81 SF

SURGICAL

TOILET

B016B

36 SF

SURGICAL

CHASE

RCCB16C

12 SF

SURGICAL

CONFERENCE ROOM

B018

265 SF

SURGICAL

CHASE

RCCB17C

10 SF

COMMON SPACE

CORRIDOR

RCCB14R

1,423 SF

SURGICAL

OFFICE

B019

836 SF

SURGICAL

OFFICE

B019B

88 SF

SURGICAL

OFFICE

B019C

93 SF

SURGICAL

TOILET

B020B

46 SF

COMMON SPACE

CORRIDOR

RCCB15R

174 SF

SURGICAL

TOILET

B020A

38 SF

SURGICAL

RECEPTION

B020

715 SF

SURGICAL

EXAM

B022A

99 SF

SURGICAL

EXAM

B022B

84 SF

SURGICAL

EXAM

B022C

83 SF

SURGICAL

EXAM

B022D

82 SF

SURGICAL

EXAM

B022E

76 SF

SURGICAL

EXAM

B022F

77 SF

SURGICAL

EXAM

B022G

131 SF

SURGICAL

URODYNAMIC

LAB

B022H

192 SF

SURGICAL

TOILET

B022I

37 SF

SURGICAL

UTILITY

B023D

48 SF

COMMON SPACE

CORRIDOR

RCCB16R

520 SF

SURGICAL

CHASE

RCCB19C

7 SF

SURGICAL

TOILET

B024A

30 SF

SURGICAL

TOILET

B023C

30 SF

SURGICAL

TOILET

B023B

33 SF

SURGICAL

STORAGE

B026

133 SF

SURGICAL

PROCEDURE

ROOM

B027

260 SF

SURGICAL

LOCKER ROOM

B024

163 SF

SURGICAL

RECOVERY

B023

1,353 SF

SURGICAL

DRESSING

ROOM

B024B

34 SF

SURGICAL

DRESSING

ROOM

B024C

34 SF

SURGICAL

H.A.C.

B024F

26 SF

SURGICAL

CHASE

RCCB20C

13 SF

SURGICAL

CHASE

RCCB21C

12 SF

SURGICAL

LOCKER ROOM

B024D

57 SF

SURGICAL

LOCKER ROOM

B024E

47 SF

SURGICAL

DECONTAMINATION

ROOM

B025A

48 SF

SURGICAL

SOILED UTILITY

B025B

48 SF

SURGICAL

CLEAN ROOM

B029B

95 SF

SURGICAL

PROCEDURE ROOM

B028

350 SF

SURGICAL

PROCEDURE ROOM

B029

346 SF

COMMON SPACE

CORRIDOR

RCCB17R

470 SF

SURGICAL

CHASE

RCCB22C

8 SF

SURGICAL

CHASE

RCCB24C

20 SF

SURGICAL

CHASE

RCCB23C

14 SF

SURGICAL

CHASE

RCCB25C

7 SF

SURGICAL

CHASE

RCCB27C

7 SF

SURGICAL

CHASE

RCCB26C

18 SF

SURGICAL

ANESTHESIA STORAGE

B036

717 SF

SURGICAL

OFFICE

B036A

96 SF

ENVIRONMENTAL

MGMT

H.A.C.

B030

50 SF

NURSING SVC ADMIN

WHEEL CHAIR STORAGE

B031

2,144 SF

ENVIRONMENTAL

MGMT

TOILET

B032

57 SF

ENGINEERING

ELEVATOR MACHINE ROOM

B033

114 SF

SURGICAL

ELECTRICAL CLOSET

B037A

50 SF

COMMON SPACE

CORRIDOR

RCCB18R

1,147 SF

COMMON

SPACE

RCCB19R

23 SF

COMMON SPACE

CORRIDOR

RCCB21R

1,004 SF

COMMON

SPACE

RCCB20R

25 SF

SURGICAL

C005A

3 SF

ENVIRONMENTAL

MGMT

CHASE

RCCB28C

12 SF

VERTICAL SPACE

ELEVATOR

RCCB29C

81 SF

ENGINEERING

COMMUNICATIONS

B040

1,114 SF

ENGINEERING

BED REPAIR

B039

1,338 SF

SURGICAL

ANESTHESIA STORAGE

B037

1,061 SF

SURGICAL

TELEPHONE CLOSET

B037C

12 SF

SURGICAL

COMPUTER

ROOM

B037B

14 SF

SURGICAL

ELECTRICAL CLOSET

B037D

23 SF

COMMON

SPACE

RCCB22R

2 SF

ACS-SPECIALTY CARE

WAITING ROOM

B038

527 SF

ACS-SPECIALTY CARE

EXAM

B038C

127 SF

ACS-SPECIALTY CARE

EXAM

B038D

143 SF

ACS-SPECIALTY CARE

EXAM

B038E

143 SF

ACS-SPECIALTY

CARE

EXAM

B038F

92 SF

ACS-SPECIALTY CARE

EXAM

B038G

92 SF

ACS-SPECIALTY CARE

OFFICE

B038H

154 SF

ENVIRONMENTAL MGMT

TOILET

B038I

38 SF

VERTICAL SPACE

STAIR

RCCB30C

156 SF

ENGINEERING

COMMUNICATIONS

B040A

69 SF

SPD SERVICE

OXYGEN TANK

STORAGE

C003

67 SF

NUTRITION/FOOD

ELECTRICAL CLOSET

C003A

229 SF

ENGINEERING

STORAGE

C004

140 SF

VERTICAL SPACE

CHASE

C004a

49 SF

VERTICAL

SPACE

CHASE

RCCB31C

25 SF

VERTICAL SPACE

CHASE

C099

68 SF

SURGICAL

OFFICE

C005

124 SF

SURGICAL

OFFICE

C006

144 SF

REHAB MEDICINE

OFFICE

C007

132 SF

ENVIRONMENTAL

MGMT

TOILET

C008

40 SF

SURGICAL

OFFICE

C009

261 SF

NUTRITION/FOOD

OFFICE

C010

230 SF

SURGICAL

CHASE

RCCB32C

12 SF

ENVIRONMENTAL

MGMT

CHASE

RCCB33C

9 SF

ENGINEERING

TOILET

C021

508 SF

ENGINEERING

CHASE

RCCB39C

8 SF

ENGINEERING

CHASE

RCCB38C

12 SF

NUTRITION/FOOD

OFFICE

C011

331 SF

ENGINEERING

ELECTRICAL

STORAGE

C012

180 SF

NUTRITION/FOOD

OFFICE

C012

302 SF

ENVIRONMENTAL MGMT

SOILED LINEN ROOM

C012A

152 SF

ENGINEERING

STORAGE

C012C

73 SF

ENGINEERING

STORAGE

C012D

109 SF ENGINEERING

STORAGE

C012E

45 SF

COMMON SPACE

ELECTRICAL CLOSET

C014

793 SF

NUTRITION/FOOD

TOILET

C015

84 SF

NUTRITION/FOOD

TOILET

C016

82 SF

NUTRITION/FOOD

CHASE

RCCB34C

14 SF

COMMON SPACE

ELECTRICAL CLOSET

C017

1,810 SF

NUTRITION/FOOD

OFFICE

C018

411 SF

NUTRITION/FOOD

CHASE

RCCB35C

13 SF

COMMON SPACE

ELECTRICAL CLOSET

C022

1,623 SF

VERTICAL SPACE

STAIR

RCCB36C

159 SF

VERTICAL

SPACE

CHASE

RCCB37C

25 SF

COMMON SPACE

C020

44 SF

COMMON

SPACE

C020A

10 SF

COMMON SPACE

CORRIDOR

RCCB23R

1,900 SF

NUTRITION/FOOD

H.A.C.

C029

33 SF

NUTRITION/FOOD

TOILET

C025

88 SF

NUTRITION/FOOD

CHASE

RCCB41C

13 SF

VERTICAL SPACE

ELEVATOR

RCCB42C

75 SF

VERTICAL SPACE

ELEVATOR

RCCB43C

149 SF

VERTICAL SPACE

STAIR

RCCB40C

155 SF

NUTRITION/FOOD

ELECTRICAL

CLOSET

C026

99 SF

ENGINEERING

UTILITY

RCCB24R

57 SF

NUTRITION/FOOD

FRIDGE

C024

445 SF

NUTRITION/FOOD

FRIDGE

C025A

316 SF

COMMON SPACE

CORRIDOR

RCCB25R

803 SF

NUTRITION/FOOD

FRIDGE

C025B

365 SF

NUTRITION/FOOD

FREEZER

C031A

713 SF

NUTRITION/FOOD

THAW BOX

C031

326 SF

NUTRITION/FOOD

LOCKER ROOM

C032H

44 SF

NUTRITION/FOOD

H.A.C.

C032G

54 SF

NUTRITION/FOOD

H.A.C.

D011D

47 SF

NUTRITION/FOOD

TOILET

D011E

47 SF

NUTRITION/FOOD

MAIN KITCHEN

C032

8,333 SF

NUTRITION/FOOD

DISH ROOM

C032A

1,243 SF

NUTRITION/FOOD

H.A.C.

C032C

36 SF

NUTRITION/FOOD

DRY FOOD STORAGE

C032D

906 SF

NUTRITION/FOOD

LIQUID STORAGE

C032E

393 SF

NUTRITION/FOOD

FRIDGE

C032F

318 SF

NUTRITION/FOOD

OFFICE

C032K

115 SF

NUTRITION/FOOD

OFFICE

C032L

176 SF

VERTICAL SPACE

CHASE

RCCB44C

74 SF

SPD SERVICE

RCCB26R

26 SF

SPD SERVICE

RCCB27R

28 SF

RADIATION THERAPY

NURSE STATION

D008D

306 SF

NUTRITION/FOOD

TOILET

D001

78 SF

NUTRITION/FOOD

TOILET

D002

73 SF

NUTRITION/FOOD

H.A.C.

D004

36 SF

NUTRITION/FOOD

STORAGE

D005

125 SF

RADIATION THERAPY

STORAGE

D006

166 SF

RADIATION THERAPY

SUPPLY STORAGE

D006A

131 SF

RADIATION THERAPY

STORAGE

D006B

133 SF

SURGICAL

RCCB28R

72 SF

VERTICAL SPACE

ELEVATOR

RCCB45C

74 SF

VERTICAL SPACE

ELEVATOR

RCCB46C

75 SF

VERTICAL SPACE

ELEVATOR

RCCB47C

74 SF

VERTICAL SPACE

ELEVATOR

RCCB48C

74 SF

VERTICAL SPACE

ELEVATOR

RCCB49C

74 SF

VERTICAL SPACE

ELEVATOR

RCCB50C

86 SF

VERTICAL SPACE

ELEVATOR

RCCB51C

87 SF

VERTICAL SPACE

ELEVATOR

RCCB52C

86 SF

COMMON SPACE

CORRIDOR

RCCB29R

1,595 SF

NUTRITION/FOOD

CHASE

RCCB53C

11 SF

VERTICAL SPACE

STAIR

RCCB54C

196 SF

NUTRITION/FOOD

CHASE

RCCB55C

14 SF

RADIATION THERAPY

STORAGE

D007

431 SF

RADIATION THERAPY

DARK ROOM

D007B

71 SF

RADIATION THERAPY

RADIATION THERAPY

D007C

429 SF

RADIATION THERAPY

RECEPTION

D008

156 SF

RADIATION

THERAPY

WASH ROOM

D008A

59 SF

RADIATION

THERAPY

MEDS

D008B

58 SF

RADIATION THERAPY

OFFICE

D008C

122 SF

COMMON SPACE

CORRIDOR

RCCB30R

964 SF

COMMON

SPACE

RCCB31R

18 SF

COMMON SPACE

RCCB32R

24 SF

RADIATION THERAPY

OFFICE

D008M

328 SF

RADIATION THERAPY

EXAM

D008K

118 SF

RADIATION THERAPY

EXAM

D008J

144 SF

RADIATION THERAPY

COBALT THERAPY

D008I

477 SF

RADIATION THERAPY

CONSULT

RCCB33R

108 SF

RADIATION

THERAPY

TOILET

D008E

80 SF

RADIATION

THERAPY

TOILET

D008F

75 SF

RADIATION THERAPY

RADIATION THERAPY

D008H

574 SF

RADIATION THERAPY

CHASE

RCCB56C

23 SF

COMMON SPACE

CHASE

RCCB58C

68 SF

VERTICAL SPACE

ELEVATOR

RCCB57C

75 SF

COMMON SPACE

CORRIDOR

RCCB34R

1,731 SF

VERTICAL

SPACE

ELEVATOR

RCCB60C

59 SF

VERTICAL

SPACE

ELEVATOR

RCCB59C

59 SF

VERTICAL SPACE

STAIR

RCCB61C

38 SF

EDUCATION

TRAINING ROOM

D009

1,626 SF

NUTRITION/FOOD

PATIENT DINING

D009A

333 SF

NUTRITION/FOOD

CORRIDOR

RCCB36R

64 SF

NUTRITION/FOOD

CHASE

RCCB62C

65 SF

EDUCATION

ENTRY

RCCB35R

110 SF

NUTRITION/FOOD

STORAGE

D009F

122 SF

NUTRITION/FOOD

CHASE

RCCB64C

10 SF

NUTRITION/FOOD

CHASE

RCCB63C

21 SF

COMMON

SPACE

RCCB37R

3 SF

NUTRITION/FOOD

H.A.C.

D009E

32 SFNUTRITION/FOOD

FRIDGE

D009G

159 SF

NUTRITION/FOOD

CHASE

RCCB65C

16 SF

NUTRITION/FOOD

DEEP FREEZE

D009H

106 SF

NUTRITION/FOOD

DESSERT REFRIG

D009I

106 SF

RADIATION THERAPY

WAITING ROOM

D010

289 SF

RADIATION THERAPY

CHASE

RCCB66C

7 SF

RADIATION THERAPY

OFFICE

D010A

86 SF

RADIATION

THERAPY

EXAM

D010B

87 SF

RADIATION THERAPY

EXAM

D010C

99 SF

RADIATION THERAPY

EXAM

D010D

98 SF

RADIATION THERAPY

OFFICE

D010E

476 SF

RADIATION

THERAPY

DRESSING

ROOM

D010F

128 SF

RADIATION

THERAPY

SUPPLY

STORAGE

D010G

41 SF

RADIATION

THERAPY

STORAGE

CLOSET

D010I

41 SF

RADIATION THERAPY

RADIATION THERAPY

D010J

879 SF

RADIATION THERAPY

ELECTRICAL CLOSET

D010K

135 SF

RADIATION THERAPY

ELECTRICAL CLOSET

D010N

24 SF

RADIATION

THERAPY

LINEN

D010Q

40 SF

COMMON SPACE

CORRIDOR

RCCB38R

1,607 SF

RADIATION THERAPY

CHASE

RCCB67C

4 SF

RADIATION THERAPY

CHASE

RCCB69C

54 SF

RADIATION THERAPY

RECEPTION

RCCB39R

49 SF

RADIATION THERAPY

CHASE

RCCB68C

24 SF

RADIATION THERAPY

OFFICE

D011A

297 SF

RADIATION THERAPY

OFFICE

D011B

257 SF

NUTRITION/FOOD

LOUNGE

D011F

124 SF

RADIATION THERAPY

STORAGE

D011G

443 SF

RADIATION

THERAPY

RCCB40R

29 SF

COMMON SPACE

CORRIDOR

RCCB41R

205 SF

PATHOLOGY

WORK ROOM

D012

172 SF

PATHOLOGY

FRIDGE

D013

192 SF

PATHOLOGY

AUTOPSY SUITE

D014

616 SF

PATHOLOGY

TOILET

D015

111 SF

PATHOLOGY

H.A.C.

D016

42 SF

PATHOLOGY

TOILET

D017

77 SF

PATHOLOGY

CHASE

RCCB70C

9 SF

PATHOLOGY

CHASE

RCCB71C

7 SF

COMMON SPACE

CORRIDOR

RCCB42R

180 SF

COMMON SPACE

CORRIDOR

RCCB43R

55 SF

COMMON

SPACE

ELEVATOR

MACHINE

ROOM

D021

108 SF

COMMON SPACE

MECHANICAL ROOM

D018

746 SFCOMMON

SPACE

COMM CLOSET

D018A

14 SF

COMMON SPACE

ELECTRICAL CLOSET

D018B

29 SF

VERTICAL SPACE

STAIR

RCCB72C

154 SF

COMMON

SPACE

F/E CLOSET

D021A

3 SF

COMMON SPACE

CORRIDOR

RCCB44R

570 SF

VERTICAL

SPACE

ELEVATOR

RCCB73C

85 SF

NUTRITION/FOOD

GREASE ROOM

D022

343 SF

NUTRITION/FOOD

SUPPLY ROOM

D023

940 SF

NUTRITION/FOOD

CHASE

RCCB74C

38 SF

COMMON

SPACE

RCCB45R

3 SF

VERTICAL SPACE

STAIR

RCCB75R

70 SF

UNASSIGNED VACANT SPACE

CORRIDOR

RCCB76R

1,341 SF

CONTRACTING FIRM: CLIENT &

PROJECT

NAME:

DRAWING SCALE:

DRAWING TITLE:

APPROVED BY:

BLDG NUMBER:

PROJECT NUMBER:

ISSUE DATE:

NORTH ARROW

1/

/2

2:

:5

P

M

3/64" = 1'-0"CAI DEPARTMENT FLOOR PLAN - BASEMENT

EDWARD HINES, JR. VA HOSPITAL

RFP: UPDATE HINES CAPITAL ASSETS INVENTORY RECORDS

01/20/2016

578-14-012

ERIC J. KUTCHE

CAI DEPARTMENT AREA

ACS SPECIALTY CARE 1,277 SF

COMMON SPACE 23,964 SF

EDUCATION 1,736 SF

ENGINEERING 3,767 SF

ENVIRONMENTAL MGMT 718 SF

LINEN SERVICE 144 SF

NURSING SVC ADMIN 2,144 SF

NUTRITION/FOOD 18,623 SF

PATHOLOGY 1,225 SF

RADIATION THERAPY 7,580 SF

REHAB MEDICINE 132 SF

SPD SERVICE 7,086 SF

SURGICAL 17,089 SF

UNASSIGNED VACANT SPACE 3,558 SF

VERTICAL SPACE 2,522 SF

LEVEL NET GROSS TOTAL 91,564 SF

7,613.9 sf

Existing elevator shaft through all fl oors of

Building 200. Option to use 1 shaft for new cart elevator conveyor system to transport dirty materials between fl oors. Access would need to be provided at fl oors b, 1, 2, 12, 13 and

14. The EHRM project for new telecom rooms utilizes these vertical chases.

VACANT

Edward Hines, Jr. VA Medical Center | 18

VA Space Allocation Plan First Floor Plan Analysis

ACS URGENT CARE

CANTEEN SERVICE

CARDIOLOGY

CHAPLAIN

COMMON SPACE

ENVIRONMENTAL MGMT

EYE CLINIC

MEDICAL ADMIN

PATHOLOGY

PHARMACY

POLICE/SECURITY

RADIOLOGY

UNASSIGNED VACANT SPACE

VERTICAL SPACE

MEDICAL ADMIN

PATIENT ID

A126

50 SF

ACS-URGENT CARE

OFFICE

A123G

66 SF

COMMON SPACE

VESTIBULE

A100A

188 SF

COMMON SPACE

VESTIBULE

A100B

387 SF

MEDICAL ADMIN

INFO DESK

A101B

445 SF

MEDICAL ADMIN

ADMISSIONS DESK

A102A

416 SF

MEDICAL ADMIN

ADMISSIONS OFFICE

A102B

391 SF

COMMON SPACE

FIRE ALARM PANEL ROOM

A102C

56 SF

MEDICAL ADMIN

INTERVIEW

A102D

164 SF

MEDICAL ADMIN

TOILET

A102E

353 SF

MEDICAL ADMIN

TOILET

A102F

344 SF

MEDICAL ADMIN

CHASE

RCC101C

19 SF

MEDICAL ADMIN

TOILET

A102G

80 SF

COMMON SPACE

TELEPHONE CLOSET

A102I

37 SF

COMMON SPACE

ELECTRICAL CLOSET

A102J

68 SF

COMMON SPACE

CORRIDOR

A103A

4,432 SF

CANTEEN SERVICE

CAFÉ

A103B

1,063 SF

CANTEEN SERVICE

CAFÉ WORK RM.

A103C

299 SF CANTEEN

SERVICE

CAFÉ

SUPPLIES

A103D

65 SF

PATHOLOGY

BLOOD BANK

A104

1,078 SF

PATHOLOGY

OFFICE

A106

132 SF

PATHOLOGY

OFFICE

A107

113 SF

COMMON

SPACE

RCC101R

9 SF

COMMON SPACE

CHASE

RCC102C

13 SF

VERTICAL

SPACE

ELEVATOR

103C

59 SF

VERTICAL

SPACE

ELEVATOR

104C

59 SF

PATHOLOGY

CHASE

RCC105C

6 SF

PATHOLOGY

CHASE

RCC106C

28 SF

PATHOLOGY

OFFICE

A110

531 SF

RADIOLOGY

X-RAY

A111

390 SF

RADIOLOGY

ELECTRICAL CLOSET

A112

40 SF

ACS-URGENT

CARE

TOILET

A117

38 SFACS-URGENT

CARE

TOILET

A118

58 SF

ACS-URGENT

CARE

TOILET

A119

59 SF

ACS-URGENT

CARE

CHASE

RCC107C

13 SF

ACS-URGENT

CARE

ELECTRICAL

CLOSET

A129B

49 SF

ACS-URGENT

CARE

ELECTRICAL

CLOSET

A121A

44 SF

ACS-URGENT

CARE

ELECTRICAL

CLOSET

A129A

42 SF

ACS-URGENT CARE

OFFICE

A121B

96 SF

ACS-URGENT CARE

OFFICE

A129D

103 SF

ACS-URGENT CARE

OFFICE

A121

1,230 SF

COMMON SPACE

CHASE

68 SF

COMMON

SPACE

CHASE

RCC108C

12 SF

COMMON

SPACE

CHASE

RCC110C

13 SF

ACS-URGENT

CARE

H.A.C.

A105

43 SF

ACS-URGENT CARE

STORAGE

RCC102R

17 SF

ACS-URGENT CARE

WAITING / RECEPTION

A122

1,151 SF

ACS-URGENT CARE

OFFICE

A123A

116 SF

ACS-URGENT CARE

LOUNGE

A123D

159 SF

ACS-URGENT

CARE

BREAK ROOM

A123E

167 SF

ACS-URGENT CARE

LOCKER ROOM

A123F

85 SF

ACS-URGENT

CARE

CHASE

RCC111C

9 SF

COMMON

SPACE

CORRIDOR

RCC103R

131 SF

ACS-URGENT CARE

TREATMENT ROOM

A142S

124 SF

POLICE/SECURITY

SECURITY

A124

149 SF

ACS-URGENT CARE

OFFICE

A127

105 SF

ACS-URGENT CARE

SOILED UTILITY

A128

102 SF

ACS-URGENT CARE

TREATMENT ROOM

A129C

145 SF

ACS-URGENT

CARE

TOILET

A130

40 SF

ACS-URGENT CARE

NURSE STATION

A142A

299 SF

VERTICAL SPACE

STAIR

RCC112C

158 SF

ACS-URGENT CARE

BREAK ROOM

A142B

165 SF

ACS-URGENT CARE

MEDICINE ROOM

A142F

56 SF

ACS-URGENT

CARE

CHASE

RCC113C

32 SF

ACS-URGENT CARE

CHASE

RCC114C

7 SF

ACS-URGENT CARE

STORAGE

A142G

118 SF

ACS-URGENT CARE

TREATMENT ROOM

A142H

104 SF

ACS-URGENT CARE

ANTE ROOM

A142I

101 SF

ACS-URGENT CARE

TREATMENT ROOM

A142J

137 SF

ACS-URGENT CARE

TREATMENT ROOM

A142K

107 SF

ACS-URGENT CARE

TREATMENT ROOM

A142L

120 SF

ACS-URGENT CARE

TREATMENT ROOM

A142M

129 SF

ACS-URGENT CARE

TREATMENT ROOM

A142N

114 SF

ACS-URGENT CARE

EXAM

A142P

120 SF

ACS-URGENT CARE

TRIAGE

A142Q

118 SF

ACS-URGENT CARE

CONSULT

A142R

120 SFACS-URGENT CARE

CHASE

RCC115C

14 SF

ACS-URGENT CARE

TREATMENT ROOM

A142T

120 SF

ACS-URGENT CARE

TREATMENT ROOM

A143

128 SF

ACS-URGENT CARE

TREATMENT ROOM

A144A

238 SF

ACS-URGENT

CARE

EXAM

A146A

96 SF

ACS-URGENT

CARE

EXAM

A146B

81 SF

ACS-URGENT

CARE

EXAM

A146C

100 SF

ACS-URGENT

CARE

EXAM

A146D

91 SF

ACS-URGENT

CARE

WORK STATION

A146E

95 SF

ACS-URGENT CARE

TREATMENT ROOM

A146F

136 SF

ACS-URGENT CARE

TREATMENT ROOM

A146G

139 SF

ACS-URGENT

CARE

H.A.C.

A146H

24 SF

ACS-URGENT CARE

TREATMENT RM

A146J

124 SF

COMMON SPACE

CORRIDOR

RCC104R

355 SF

ACS-URGENT CARE

CHASE

RCC116C

90 SF

COMMON SPACE

CORRIDOR

A125B

422 SF

COMMON SPACE

CORRIDOR

1,098 SF

COMMON SPACE

CORRIDOR

RCC106R

2,490 SF

ACS-URGENT CARE

PATIENT INTERVIEW

RCC107R

200 SF

ACS-URGENT CARE

UTILITY

A147

84 SF

ACS-URGENT CARE

CONFERENCE ROOM

A148

185 SF

ACS-URGENT CARE

OFFICE

A149

124 SF

ACS-URGENT CARE

OFFICE

A150

126 SF

ACS-URGENT CARE

OFFICE

A152

123 SF

EYE CLINIC

WAITING ROOM

A153

793 SF

EYE CLINIC

CHASE

RCC117C

23 SF

EYE CLINIC

PHARMACY

A155

99 SF

EYE CLINIC

EXAM

A156

150 SF

EYE CLINIC

EXAM

A157

92 SF

EYE CLINIC

EXAM

A158

92 SF

EYE CLINIC

EXAM

A159

144 SF

EYE CLINIC

EXAM

A160

109 SF

EYE CLINIC

EXAM

A161

122 SF

EYE CLINIC

EXAM

A162

118 SF

EYE CLINIC

EXAM

A163

128 SF

EYE CLINIC

EXAM