Attachment 2 - 18708 Asbestos Re-inspection Final Report Bldg 12.pdf
PDF 6 MB Posted
- Attached to
- Y1AZ--674A4-21-703 EHRM Training and Admin Support Space Construction Waco Texas (VA-22-00050768)
- Solicitation number
- 36C77622B0045
About this file
This document contains an asbestos reinspection report for Building 12 at the Waco VA Medical Center. The report details asbestos-containing materials found in the basement, first floor, and second floor of the building including 12x12 floor tile and mastic. It provides condition assessments and removal priority recommendations. The report also includes standard management plan recommendations such as staff training requirements, record keeping, and notification procedures.
The related federal contract opportunity is a solicitation from the Department of Veterans Affairs for construction services to support EHRM training and administrative space at the Waco VA Medical Center campus. The solicitation includes standard contract clauses but no further requirement details. The response deadline and award date are not specified.
View the file
Other files
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
2012 Asbestos Reinspection
INTRODUCTION
2012 ASBESTOS REINSPECTION REPORT
CENTRAL TEXAS VETERANS HEALTH CARE SYSTEM
WACO VA MEDICAL CENTER
SCOPE OF WORK
1. This asbestos reinspection complies with the requirements of Asbestos Hazard
Emergency Response Act (AHERA).
2. Each facility inspection was performed by an accredited inspector.
3. For each facility, the inspector performed the following tasks:
a. Visually inspected all accessible areas for suspect asbestos-containing material
(ACM).
b. Asbestos bulk samples were collected of all suspected materials and the samples were analyzed by EMSL Laboratories which is an NVLAP-accredited laboratory authorized to analyze asbestos bulk samples.
c. If any of the asbestos bulk samples contained asbestos from 1% to 5% in asbestos content, then the laboratory was requested to perform a Polarized Light
Microscopy (PLM) point count of that material for a more accurate analysis.
d. After reviewing the results from the asbestos bulk samples and subsequent point counting, homogeneous areas were determined for the various asbestos-containing materials.
e. Homogeneous area tables were prepared and condition summaries were completed.
f. A report was then completed that is outlined in the report section that follows this scope of work.
g. A management planner reviewed all work provided above and verified that the plan met all AHERA requirements. The appropriate response actions were recommended and the reinspection signed and dated. This report included the accreditation number of inspectors and planners. A copy of the 2012 Asbestos
Reinspection Report was submitted to the owner.
MANAGEMENT PLAN RECOMMENDATIONS
The following general notes are for all facilities inspected during the Asbestos Reinspection:
1. Removal Priorities were developed for each homogeneous area. The Removal Priorities are an indicator of priorities for future repair work or abatement work to be scheduled as financial budgets allow. Please see the 2012 Reinspection Condition and Removal
Priority Table for further details.
2. The current condition of material was listed for each homogeneous area. The condition, location, and potential for disturbance factors are used for the hazard ranking. Please see the 2012 Reinspection Condition and Removal Priority Table for the condition summaries.
3. Records for custodial, janitorial, and maintenance staff who have received two-hour awareness training should be filed in the Management Plan.
4. Any new custodial, janitorial, or maintenance staff that have the potential to come in contact with asbestos-containing materials (ACM) are required to attend a two-hour awareness training class. Records of training for new employees should be filed in the
Management Plan.
5. The Designated Person is required to inform workers and building occupants at least once a year about the Management Plan. This includes information about inspections, response actions, and post-response action activities that are planned or in progress.
6. Maintenance areas (boiler rooms, janitor closets, etc.) are required to have warning labels where ACM is located. Install warning labels in these areas as needed. Some older labels may have come loose and are no longer visible. Post the labels in a prominent location.
7. Review the enclosed 2012 Reinspection Condition and Removal Priority Table for maintenance actions that may be required and to establish priorities and budgets for future repair and abatement work.
8. Periodic “Surveillance Inspections” are required every six (6) months. This inspection should indicate the condition of the material and provide recommendations for repair or potential removal. Consistency of inspections is desired and, therefore, should be performed by the same individual(s) for all facilities. An accredited inspector is not required, but is recommended. Records of Surveillance Inspections should be filed in both the administrative and facility Management Plans.
9. “Reinspections” are required every three (3) years. Updated information should be added to the Management Plan.
10. An accredited “Supervisor” should be on staff or available on a contract basis per
AHERA guidelines. Certification paperwork should be filed in the training section of the
Management Plan.
11. ACM should only be removed by contractors licensed and accredited in the State of
Texas. Response actions related to abatement activity should be filed in the Management
Plan. Removal of limited amounts of asbestos by the accredited Supervisor and trained individuals is within the scope of the Management Plan.
12. Notification should be provided to “outside contractors” about ACM within the facility.
This should include such trades or services as telephone, electrical, plumbing, air conditioning, and other construction work. A form should be created for this purpose and placed in the Management Plan.
13. New building construction and portable buildings added to a facility are required to be inspected and sampled for ACM. In lieu of this, a letter from the architect, engineer, or manufacturer can be obtained that states “no ACM were specified or used in the facility.”
A copy of this letter is to be filed with the Management Plan at the facility. This letter will cancel the requirement for sampling.
14. Abatement Costs were developed for each homogeneous area and per facility. The estimated abatement cost is for budget purposes only. The cost is based on the area of material and estimated abatement costs for this material. The cost is for abatement only and does not include abatement design, air monitoring, or project observation costs.
REPORT SECTION
2012 ASBESTOS REINSPECTION REPORT
This report will include a combination of the following sections:
ACM Homogeneous Areas Summary Table and Drawings
This section provides a quick table reference to all asbestos-containing homogeneous areas found during the reinspection, and to drawings with the asbestos-containing homogeneous areas found during the 2012 asbestos reinspection.
This section will not be included in the building reports that did not require any sampling due to no suspected ACM being present. The section will also not be included if asbestos bulk samples were collected and the results indicated no asbestos-containing materials were found in that building.
Condition and Removal Priority Table
This section provides a table with the current condition, potential for disturbance, and removal priority for each homogeneous area.
Master Summary Table – Asbestos Bulk Samples
This table provides a listing of all asbestos bulk samples taken to date.
no suspected ACM being present.
Asbestos-Containing Bulk Samples
This table provides a listing of all asbestos-containing bulk samples.
2012 Reinspection – Inspection Logs
This section provides the field inspection logs for samples taken during the 2012 asbestos reinspection.
Bulk Sample Location Drawings
This section provides drawings with sample locations for all asbestos bulk samples.
Site and sample location drawings will be included in the building reports that did not require any sampling due to no suspected ACM being present.
2012 Reinspection – Photographs
This section provides photographs of all asbestos bulk samples taken during the 2012 asbestos reinspection.
2012 Reinspection – Laboratory Reports
This section provides all laboratory analytical results.
Certifications
This section provides certifications for all Inspectors, the Management Planner who reviewed this Management Plan, and the laboratory that performed the bulk sample analysis.
Periodic Surveillance Forms
This section includes the forms to be completed during the periodic surveillance inspections required every six (6) months.
This section will not be required for building reports that did not require any sampling due to no suspected ACM being present. This section will also not be required if asbestos bulk samples
Management Plan Updates
This section includes the records of any asbestos abatement activities that are completed at the subject site. Notifications, daily notes, drawings, etc., should be placed in this section. This would also include air-monitoring data from asbestos abatement projects.
Response Actions
This section includes the records of any internal asbestos abatement or operation and maintenance activities that may be completed by VA employees. This would include any drawings, field notes, and air monitoring that was completed.
Training Documents
This section includes the records of training for the Designated Person and accredited
Supervisor, as well as the two-hour awareness training for the custodial, janitorial, and maintenance staff.
CONTRACTOR
2012 ASBESTOS REINSPECTION REPORT
OLIN E. TEAGUE VA MEDICAL CENTER
This 2012 Asbestos Reinspection was provided by:
Contractor:
ALTEC Environmental Consulting, LLC
10100 Woolworth Road
Keithville, LA 71047
(318) 687-3771 (Office)
(318) 687-9923 (Fax)
INSPECTORS:
Jerry Heidecker David Hopper
LA Certificate No. 3I166471 LA Certificate No. 3I134762
Donald R. Joiner Bradley Kennon
LA Certificate No. 3I112937 LA Certificate No. 3I182667
Rodney Lewis
LA Certificate No. 3I169456
MANAGEMENT PLANNER:
Robert B. Raines III, P.E.
LA Certificate No. 3P103065 – Management Planner
Accreditation Agency: Louisiana Department of Environmental Quality which is a recognized EPA accreditation agency
ACM HOMOGENEOUS AREAS
SUMMARY TABLE AND DRAWINGS
WACO V. A. MEDICAL CENTER
2012 THREE-YEAR ASBESTOS REINSPECTION
ACM HOMOGENEOUS AREAS SUMMARY TABLE
Floor Flooring Materials Ceiling Materials TSI Materials Miscellaneous Materials
B HMA-01 12x12 Floor Tile & Mastic
HMA-02 Flooring Mastic No ACM No ACM HMA-03 Fire Doors
Floor Flooring Materials Ceiling Materials TSI Materials Miscellaneous Materials
First HMA-01 12x12 Floor Tile & Mastic
HMA-02 Flooring Mastic No ACM No ACM HMA-03 Fire Doors
Floor Flooring Materials Ceiling Materials TSI Materials Miscellaneous Materials
Second HMA-01 12x12 Floor Tile & Mastic
HMA-02 Flooring Mastic No ACM No ACM HMA-03 Fire Doors
Floor Flooring Materials Ceiling Materials TSI Materials Miscellaneous Materials
Attic No ACM No ACM No ACM No ACM
Building 12 Basement
Building 12 - First Floor
Building 12 - Second Floor
Building 12 - Attic
Basement
First Floor
Second Floor
CONDITION AND REMOVAL PRIORITY TABLE
Qualitative Ranking Numerical Rating
Good 8, 9, 10
Fair 4, 5, 6, 7
Poor 1, 2, 3
Physical Disturbance Environmental Disturbance
Low 1, 2, 3
Medium 4, 5, 6, 7
High 8, 9, 10
Qualitative Ranking Numerical Rating
High 1, 2, 3
Medium 4, 5, 6, 7
Low 8, 9, 10
Address with on-going maintenance procedures
Maintain in good condition
Surfacing material has moderate but not extensive amounts of visible damage; covering on thermal system insulation is cut or torn, exposing moderate but not extensive amounts of insulation; moderate but not extensive damage to miscellaneous materials such as floor tile; moderate but not extensive amounts of visible dust and debris..
Qualitative Rankings and Quantitative (Numerical) Ratings for Removal Priority
Description of Current Condition
Address short-term
Extensive damage to surfacing material; covering on thermal system insulation is cut or torn extensively and insulation itself is damage; miscellaneous materials such as floor tile extensively damaged and underlying mastic exposed; extensive amounts of dust and debris.
Accessibility: accessibility during normal operations
Activities: activities that people do and how often they do them
Vibration: vibration from operating machinery, HVAC equipment, and so forth
Air/Dust: air currents strong enough to dislodge loose
ACM; airborne dust that can erode material
Corrosive: corrosive atmosphere or liquids that can erode the covering or matrix
Water Damage: water damage from leaking roof, pipe or other source
Qualitative Rankings and Quantitative (Numerical) Ratings for Current Condition
Qualitative Rankings and Quantitative (Numerical) Ratings for Potential for Disturbance
Assessment Factors Qualitative Ranking Numerical Rating
Description of Current Condition
Surfacing material has no visible damage or small amounts of damage; covering on thermal system insulation is intact or has small amounts of damage; miscellaneous materials intact; no visible debris or small amounts of debris.
CONDITION AND REMOVAL PRIORITY TABLE
Rating Based On Rating Based On
HMA-01 12 Basement 12"x12" Floor Tile and Mastic No No 10 Intact 2 Floor
Maintenance
HMA-02 12 Basement Flooring Mastic No No 10 Intact 1 Access 10
HMA-03 12 Basement Fire Doors No No 10 Intact 1 Maintenance 10
HMA-01 12 1 12"x12" Floor Tile and Mastic No No 10 Intact 2 Floor
Maintenance
HMA-02 12 1 Flooring Mastic No No 10 Intact 1 Access 10
HMA-03 12 1 Fire Doors No No 10 Intact 1 Maintenance 10
HMA-01 12 2 12"x12" Floor Tile and Mastic No No 10 Intact 2 Floor
Maintenance
HMA-02 12 2 Flooring Mastic No No 10 Intact 1 Access 10
HMA-03 12 2 Fire Doors No No 10 Intact 1 Maintenance 10
Building 12 - Basement
Building Friable
Yes/No
Accessibility
Yes/No Restricted
Potential for
Disturbance
Homogeneous
Area No.
Floor
Building 12 - Attic
No ACM
Material Description
Building 12 - Second Floor
Removal
Priority
Building 12 - First Floor
Current
Condition
MASTER SUMMARY TABLE
ASBESTOS BULK SAMPLES
SUMMARY OF BULK SAMPLES TAKEN TO DATE
(determined by Point Count Analysis)
Building Floor Room Sample ID Material Description
12 Basement 102A WA-09-292-1049 Layer 1 - tan 12x12 floor tile
12 Basement 102A WA-09-292-1049 Layer 2 - black mastic
12 Basement 102A WA-09-292-1050 Layer 1 - tan 12x12 floor tile
12 Basement 102A WA-09-292-1050 Layer 2 - black mastic
12 Basement 102 WA-09-292-1151 4" vertical pipe - yellow insulation, white wrap
12 Basement 101 WA-09-292-1152 White 2x4 ceiling tile
12 Basement 103 WA-09-292-1153 3" horizontal pipe - yellow insulation, white wrap
12 Basement 103 WA-09-292-1154 White caulk
12 Basement 100A WA-09-292-1155 White 2x4 ceiling tile
12 Basement 100A WA-09-292-1156 White caulk
12 Basement CB-1 WA-09-292-1157 Brown plaster
12 Basement CB-1 WA-09-292-1158 Layer 1 - light brown 12x12 floor tile
12 Basement CB-1 WA-09-292-1158 Layer 2 - black mastic
12 Basement CB-2 WA-09-292-1159 4" horizontal pipe - yellow insulation, white wrap
12 Basement 103 WA-09-292-1160 White plaster
12 Basement 103 WA-09-292-1161 Layer 1 - tan 12x12 floor tile
12 Basement 103 WA-09-292-1161 Layer 2 - black mastic
12 Basement 103 WA-09-292-1162 Layer 1 - brown 12x12 floor tile
12 Basement 103 WA-09-292-1162 Layer 2 - black mastic
12 Basement 101 WA-09-292-1163 5" horizontal pipe - yellow insulation, white wrap
12 Basement 101 WA-09-292-1164 3" T - yellow insulation, white wrap
12 Basement 107 WA-09-292-1165 Gray spray-on
12 Basement 106 WA-09-292-1166 5" horizontal pipe - yellow insulation, white wrap
12 Basement 106 WA-09-292-1167 5" valve - yellow insulation, white wrap, white mud
12 Basement 104A WA-09-292-1168 Layer 1 - tan 12x12 floor tile
12 Basement 104A WA-09-292-1168 Layer 2 - black mastic
12 Basement 104A WA-09-292-1169 Layer 1 - brown 12x12 floor tile
12 Basement 104A WA-09-292-1169 Layer 2 - black mastic
12 1 C1-1 WA-09-292-1170 Gray spray-on
12 1 C1-1 WA-09-292-1171 White 2x4 ceiling tile
12 1 C1-1 WA-09-292-1172 Layer 1 - light brown 12x12 floor tile
12 1 C1-1 WA-09-292-1172 Layer 2 - black mastic
12 1 C1-1 WA-09-292-1173 Layer 1 - blue 12x12 floor tile
12 1 C1-1 WA-09-292-1173 Layer 2 - black mastic
12 1 106 WA-09-292-1174 Gray spray-on
12 1 106 WA-09-292-1175 White caulk
12 1 1B-100 WA-09-292-1176 White 2x4 ceiling tile
12 1 1B-103 WA-09-292-1177 White 2x4 ceiling tile
12 1 1B-102B WA-09-292-1178 White 12x12 floor tile, yellow mastic
12 1 1B-102A WA-09-292-1179 White 12x12 floor tile, yellow mastic
12 1 1A-101 WA-09-292-1180 White caulk
12 1 1A-104B WA-09-292-1181 Sheetrock, white tape, white mud
12 2 C2-1 WA-09-292-1182 Light brown 12x12 floor tile, yellow mastic
12 2 C2-1 WA-09-292-1183 Blue 12x12 floor tile, yellow mastic
12 2 C2-1 WA-09-292-1184 Gray spray-on
12 2 2B-101 WA-09-292-1185 White 2x4 ceiling tile
Red = Asbestos-Containing Material (ACM) Blue = Non ACM Green = Non Asbestos-Containing Material
Purple = Abated
SUMMARY OF BULK SAMPLES TAKEN TO DATE
(determined by Point Count Analysis)
Building Floor Room Sample ID Material Description
Red = Asbestos-Containing Material (ACM) Blue = Non ACM Green = Non Asbestos-Containing Material
Purple = Abated
12 2 Hall WA-09-292-1186 White 2x4 ceiling tile
12 2 2A-108 WA-09-292-1187 White 2x4 ceiling tile
12 2 South Deck WA-09-292-1188 Black roofing tar
12 1 1A-103 WA-09-292-1189 3" vertical pipe - black insulation, black mastic
12 2 2A-103 WA-09-292-1190 3" horizontal pipe - yellow insulation, white wrap
12 2 North Deck WA-09-292-1299 Black roofing felt, black tar
12 2 North Deck WA-09-292-1300 Black roofing felt, black tar
ASBESTOS-CONTAINING BULK SAMPLES
LIST OF ASBESTOS-CONTAINING SAMPLES
Building Floor Room Sample ID Material Description
12 Basement 102A WA-09-292-1049 Layer 1 - tan 12x12 floor tile
12 Basement 102A WA-09-292-1049 Layer 2 - black mastic
12 Basement 102A WA-09-292-1050 Layer 1 - tan 12x12 floor tile
12 Basement 102A WA-09-292-1050 Layer 2 - black mastic
12 Basement CB-1 WA-09-292-1158 Layer 2 - black mastic
12 Basement 103 WA-09-292-1161 Layer 2 - black mastic
12 Basement 103 WA-09-292-1162 Layer 2 - black mastic
12 Basement 104A WA-09-292-1168 Layer 2 - black mastic
12 1 C1-1 WA-09-292-1172 Layer 2 - black mastic
12 1 C1-1 WA-09-292-1173 Layer 2 - black mastic
Red = Asbestos-Containing Material (ACM)
BULK SAMPLE LOCATION DRAWINGS
Basement
First Floor
Second Floor
Attic
CERTIFICATIONS
z— r C
I
C pc)
C l)
‘-4 0.)
4-4
I
•—•—E•—re-i
Z r:—
L c t c c o
I c r
CC
C
4-4 0)0)Cz
0.)
C l)
CQ00)
Jerald Heidecker
3I166471
9/12/2012
166471
9/25/2013
ASBESTOS INSPECTOR
CB
C I
0 CD
Z
J
Z —
CD
‘e
CD
P w
— o O
C cm C CD
C
C L i fl o
CD 0
David Hopper
3I134762
2/3/2012
134762
2/14/2013
SG
Donald R Joiner
3I112937
9/12/2012
112937
9/29/2013
Professional Environmental Training
Occupational and Environmental Training Program
Awards this Certificate to
BRADLEY W. KENNON
Certificate No. TL-0993
For completion of the
3-HOUR COURSE
TEXAS ASBESTOS HEALTH PROTECTION ACT
November 3, 2012 9001 Airport Blvd., Suite 510
Houston, Texas 77061
713-921-8921
P sident, Fredy Polanco, M.S.
Instructor, Philip
Date of Course www.proenvtraining.com
Bradley Kennon
3I182667
8/16/2012
182667
8/1/2013
0 cm 0 c l Ct
C C
C t
O o S C
Lte •
C
0 I
. S — v s L
D
Rodney Lewis
3I169456
2/3/2012
169456
3/3/2013
SG
Robert B Raines III
3P103065
8/21/2012
103065
8/5/2013
ASBESTOS MANAGEMENT PLANNER
6-MONTH ASBESTOS SURVEILLANCE
BUILDING 12
HMA Material Description Location Friable
Yes/No
Conditions at Last
Inspection1
Damage
Severity2
Conditions at Current
Inspection1
Comments
HMA-01
12x12 Floor Tile &
Mastic Basement
HMA-02 Flooring Mastic Basement
HMA-03 Fire Doors Basement
HMA-01
12x12 Floor Tile &
Mastic First Floor
HMA-02 Flooring Mastic First Floor
HMA-03 Fire Doors First Floor
HMA-01
12x12 Floor Tile &
Mastic Second Floor
HMA-02 Flooring Mastic Second Floor
HMA-03 Fire Doors Second Floor
Conditions: G=Good R=Repaired D=Damaged SD= Significantly Damaged
Damage Severity: M=Minor O=Occasional X-Extensive P=Punctures N=None
Printed Competent Person’s Name
Asbestos Inspector Certification Number and Expiration Date
Signature
Surveillance Inspection Date
File details come from the government source that posted it. Updated .