S06 Question and Response - Solicitation 36C26326B033.pdf
PDF 88 KB Posted
- Solicitation number
- 36C26326B0033
About this file
This document is a Responses to Questions/RFI/Clarifications file for federal contract solicitation 36C26326B0033, Project Number 568A4-24-202, titled "Update Electrical Equipment on Campus."
The document addresses a single clarification question regarding Building 12's emergency power requirements during generator switchgear replacement work. The questioner inquired about the acceptable duration for Building 12 to operate without emergency backup power while the new generator switchgear is installed in the same location as the old switchboard, noting that relocation of the switchgear might be necessary if extended outages are unacceptable. The government's response confirms that no definite timeframe for the outage has been established, but states that outages will be executed as quickly as possible and will be coordinated with VA staff. The response also definitively clarifies that the generator switchgear will not be relocated. This clarification establishes project parameters for contractors regarding scheduling constraints and facility limitations during the electrical equipment upgrade work.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation Number: 36C26326B0033 Project Number: 568A4-24-202, Update Electrical Equipment on Campus
Responses to Questions/RFI/Clarifications
Q: Building 12 will have a period of time where emergency power isn’t available. How long can building 12 go without emergency backup due to replacement of the generator switchgear going in the same place as the old switchboard. If long periods without emergency power isn’t acceptable it may be required to relocate the generator switchgear.
A: We do not have a definite time period, but it is anticipated that outages will be performed as quickly as possible. Outages to be coordinated with VA staff. Generator switchgear will not be relocated.