P09 - 612-23-005-Specifications - Martinez and Mare Island Generator Fuel Lines.pdf
PDF 7 MB Posted
- Solicitation number
- 36C26126R0048
About this file
This is a Specifications and General Requirements document for a federal construction contract to replace generator fuel line systems at two VA Medical Center locations in Northern California.
The project involves fuel oil piping replacement, system upgrades, and associated work at the Martinez VA Medical Center (Buildings 19 and 20) and the Mare Island VA Clinic (Building 201). Specific work requirements include excavation and backfill for underground piping replacement, installation of replacement fuel oil transfer pumps, seismic restraint of aboveground piping and equipment, replacement of leak detection systems with potential reuse of existing sensors, integration of new fuel management systems with existing building automation systems, replacement of valving and pipe supports, implementation of Infection Control and Risk Assessment (ICRA) requirements, commissioning of new systems, and associated electrical wiring. The project must be executed in three phases per location to maintain 24/7 medical center operations: Phase 1 covers above-grade piping installation with new pumps installed adjacent to existing systems; Phase 2 covers below-grade piping and leak detection equipment; Phase 3 involves system testing, generator connection during off-hours within a single 8-hour shift, and demolition of existing piping. The contractor must provide detailed project schedules using Critical Path Method (CPM), maintain operations during construction with temporary protection and partitioning, comply with security procedures including badge access and document control, coordinate utility interruptions with minimum 7-15 days advance notice, provide photographic documentation with interactive indexing, maintain as-built drawings, develop a comprehensive warranty management plan with extended warranties for roofs, HVAC systems, pumps, motors, and commissioned systems, and obtain access to VA TRIRIGA CPMS project management system.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Correct Martinez and Mare Island Generator Fuel Lines Project Number: 612-23-005 Bid Documents Specifications
Northeast Infrastructure, LLC 34 Brown Street
Honesdale, PA 18431 April 17, 2026
VA Northern California Health Care System
Correct Martinez and Mare Island Generator Fuel Lines Bid Documents Project No. 612-23-005 04-17-2026 VA Northern California Health Care System
00 01 10 - 1
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
SECTION NO DIVISION AND SECTION TITLES DATE
DIVISION 00 - SPECIAL SECTIONS
00 01 15 List of Drawing Sheets 05-20
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 11-21
01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build 01-24
01 33 23 Shop Drawings, Product Data, and Samples 11-23
01 35 26 Safety Requirements for Major Projects 05-24
01 45 00 Quality Control 02-21
01 45 35 Special Inspections 06-21
01 57 19 Temporary Environmental Controls 01-21
01 74 19 Construction Waste Management 04-22
01 91 00 General Commissioning Requirements 04-22
DIVISION 02 – EXISTING CONDITIONS
02 21 13 Site Surveys 12-23
02 41 00 Demolition 08-17
DIVISION 03 – CONCRETE
03 30 00 Cast-in-Place Concrete 01-21
00 01 10 - 2
DIVISION 04 – MASONRY
(NOT USED)
DIVISION 05 – METALS
05 50 00 Metal Fabrications 08-18
DIVISION 06 – WOOD, PLASTICS AND COMPOSITES
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 84 00 Firestopping 01-21
07 92 00 Joint Sealants 04-22
DIVISION 08 - OPENINGS
DIVISION 09 – FINISHES
09 29 00 Gypsum Board 04-20
09 51 00 Acoustical Ceilings 12-18
09 91 00 Painting 01-21
DIVISION 10 – SPECIALTIES
00 01 10 - 3
DIVISION 11 – EQUIPMENT
DIVISION 12 – FURNISHINGS
DIVISION 13 - SPECIAL CONSTRUCTION
13 05 41 Seismic Restraint Requirements for Non-Structural Components 01-21
DIVISION 14– CONVEYING EQUIPEMENT
DIVISION 21- FIRE SUPPRESSION
DIVISION 22 – PLUMBING
DIVISION 23 – HEATING, VENTILATING, AND AIR
CONDITIONING (HVAC)
23 05 11 Common Work Results for HVAC 03-23
00 01 10 - 4
23 05 12 General Motor Requirements for HVAC and Steam Generation
Equipment
03-23
23 05 41 Noise and Vibration Control for HVAC Piping and Equipment 03-23
23 08 00 Commissioning of HVAC Systems 03-23
23 09 23 Direct-Digital Control System for HVAC 03-23
23 10 00 Facility Fuel Systems 04-20
DIVISION 25 – INTEGRATED AUTOMATION
DIVISION 26 – ELECTRICAL
26 05 11 Requirements for Electrical Installations 11-22
26 05 19 Low-Voltage Electrical Power Conductors and Cables 11-22
26 05 26 Grounding and Bonding for Electrical Systems 11-22
26 05 33 Raceway and Boxes for Electrical Systems 11-22
26 05 41 Underground Electrical Construction 11-22
26 05 73 Overcurrent Protective Device Coordination Study 11-22
26 08 00 Commissioning of Electrical Systems 11-22
26 24 16 Panelboards 11-22
26 43 13 Surge Protective Devices 11-22
DIVISION 27 – COMMUNICATIONS
27 05 11 Requirements for Communications Installations 09-19
27 05 26 Grounding and Bonding for Communications Systems 06-15
27 05 33 Raceways and Boxes for Communications Systems 10-18
27 08 00 Commissioning of Communications Systems 11-16
27 10 00 Control, Communication and Signal Wiring 06-15
00 01 10 - 5
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
DIVISION 31 – EARTHWORK
31 20 11 Earthwork (Short Form) 10-12
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 05 23 Cement and Concrete for Exterior Improvements 08-16
32 12 16 Asphalt Paving 09-15
DIVISION 33 – UTILITIES
DIVISION 34 – TRANSPORTATION
DIVISION 48 – ELECTRICAL POWER GENERATION
00 01 15 - 1
SECTION 00 01 15
LIST OF DRAWINGS
The drawings listed below accompanying this specification form a part of the contract.
Drawing No. Title
GENERAL:
GI-001 COVER SHEET
CIVIL:
CS-001 MARTINEZ CAMPUS - OVERALL SITE PLAN
CS-002 MARTINEZ CAMPUS - SITE PLAN ENLARGEMENT
CS-003 MARE ISLAND CAMPUS - SITE PLAN
CD-001 MARTINEZ CAMPUS - DEMO PLAN
CD-002 MARE ISLAND CAMPUS - DEMO PLAN
CU-001 MARTINEZ CAMPUS - UTILITY PLAN
CU-002 MARE ISLAND CAMPUS - UTILITY PLAN
ICRA:
ICRA-00 ICRA GENERAL REQUIREMENTS
ICRA-01 PCRA GENERAL REQUIREMENTS
ICRA-02 ICRA NOTES & DETAILS
ICRA-100 MARTINEZ BUILDING 19 & 20 ICRA CLASSIFICATION
PLANS
ICRA-101 MARTINEZ BUILDING 20 PENTHOUSE ICRA
CLASSIFICATION PLAN
00 01 15 - 2
PHASING:
GC-100 MARTINEZ BUILDING 19 PHASING PLAN
GC-101 MARTINEZ BUILDING 20 PHASING PLAN 1
GC-102 MARTINEZ BUILDING 20 PHASING PLANS 2
GC-103 MARTINEZ BUILDING 20 PENTHOUSE PHASING PLAN
GC-104 MARE ISLAND PHASING PLAN
MECHANICAL:
M-001 MECHANICAL SYMBOLS & NOTES
MP-100 MARTINEZ BUILDING 19 MECHANICAL PLANS
MP-101 MARTINEZ BUILDING 19 MECHANICAL SCHEMATICS
MP-102 MARTINEZ BUILDING 20 MECHANICAL DEMOLITION
PLAN 1
MP-103 MARTINEZ BUILDING 20 MECHANICAL DEMOLITION
PLANS 2
MP-104 MARTINEZ BUILDING 20 MECHANICAL NEW WORK
PLAN 1
MP-105 MARTINEZ BUILDING 20 MECHANICAL NEW WORK
PLANS 2
MP-106 MARTINEZ BUILDING 20 PENTHOUSE MECHANICAL
PLANS
MP-107 MARTINEZ BUILDING 20 MECHANICAL SCHEMATICS
MP-108 MARE ISLAND MECHANICAL PLANS
MP-109 MARE ISLAND MECHANICAL SCHEMATICS
MI-100 MARTINEZ BUILDING 19 CONTROLS NEW WORK PLAN
00 01 15 - 3
MECHANICAL CONTINUED:
MI-101 MARTINEZ BUILDING 20 CONTROLS NEW WORK PLAN
MI-102 MARTINEZ BUILDING 20 CONTROLS NEW WORK
PLANS 2
MI-103 MARTINEZ BUILDING 20 PENTHOUSE CONTROLS NEW
WORK PLAN
MI-104 MARE ISLAND CONTROLS NEW WORK PLAN
MI-105 MARE ISLAND CONTROLS POINTS LIST
MI-400 MARTINEZ MECHANICAL CONTROLS DIAGRAMS
MI-401 MARE ISLAND MECHANICAL CONTROLS DIAGRAMS
MI-402 CONTROLS SUMMARY
M-500 MECHANICAL DETAILS 1
M-501 MECHANICAL DETAILS 2
M-600 MECHANICAL SCHEDULES
ELECTRICAL:
E-001 GENERAL ELECTRICAL SYMBOLS, NOTES &
ABBREVIATIONS
EP-100 MARTINEZ BUILDING 19 ELECTRICAL PLANS
EP-101 MARTINEZ BUILDING 20 ELECTRICAL DEMOLITION
PLAN
EP-102 MARTINEZ BUILDING 20 ELECTRICAL NEW WORK PLAN
EP-103 MARE ISLAND ELECTRICAL PLANS
E-500 ELECTRICAL DETAILS
E-600 MARTINEZ ELECTRICAL SCHEDULES
00 01 15 - 4
- - - E N D - - -
01 00 00 - 1
SECTION 01 00 00
GENERAL REQUIREMENTS
GENERAL
1.1 SAFETY REQUIREMENTS
A. Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.
1.2 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for the replacement of fuel oil piping at both the Martinez and Mare Island VA Medical center campuses as required by drawings and specifications. The Martinez campus fuel oil piping replacement shall occur for fuel oil piping at buildings 19 and 20. Work located at building 19 of the Martinez campus shall include but is not limited to fuel oil piping replacement (including excavation, backfill and site restoration for existing underground piping replacement), seismic restraint of aboveground piping and equipment, traffic control during trenching operations near parking lot at Building 19, fuel oil transfer pump replacement, replacement of the leak detection system (including re-use of existing leak detection as noted), integration of new fuel management system with existing facility building automation system, implementation of ICRA requirements, replacement of valving, pipe supports controls, and associated electrical wiring, and commissioning of new systems as required by drawings and specifications, . Work located at building 20 of the Martinez campus shall include but is not limited to fuel oil piping replacement
(including excavation, backfill and site restoration for underground piping replacement) incidental architectural work involving removal and replacement of existing indoor ceilings for piping replacement), seismic restraint of aboveground piping and equipment, pump replacement, replacement of the leak detection system (including re-use of existing leak detection sensors and wiring as noted), integration of new fuel management system with existing facility building automation system, implementation of
ICRA requirements, the addition of a fuel polisher into the fuel oil system, commissioning of new systems, and replacement of valving, pipe supports, controls, commissioning of new systems, and associated electrical wiring as required by drawings and specifications. Work located at building 201 on the Mare Island campus shall include but
01 00 00 - 2 is not limited to replacement of fuel oil piping, fuel oil transfer pumps, seismic restraint of aboveground piping and equipment, replacement of the leak detection systems
(including re-use of existing leak detection sensors and wiring as noted), integration of new fuel management system with existing facility building automation system, valving, pipe supports, controls, commissioning of new systems and associated electrical wiring as required by drawings and specifications.
B. Visits to the site by Bidders may be made only by appointment with the COR.
C. Offices of Northeast Infrastructure, LLC, as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by COR.
D. Before placement and installation of work subject to tests by testing laboratory retained by Department of Veterans Affairs, the Contractor shall notify the COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three workdays unless otherwise designated by the COR.
E. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.
1.3 STATEMENT OF BID ITEM(S)
A. ITEM I, GENERAL CONSTRUCTION: Work includes general construction, alterations, roads, walks, grading, drainage, necessary removal of existing structures and construction and certain other items.
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.
1.5 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
01 00 00 - 3
B. Security Procedures:
1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. Before starting work the General Contractor shall give one week’s notice to the COR so that security escort arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.
3. No photography of VA premises is allowed without written permission of the COR.
Patients and staff are not to be photographed at any time.
4. VA reserves the right to close down or shut down the project site and order General
Contractor’s employees off the premises in the event of a national emergency. The
General Contractor may return to the site only with the written approval of the COR.
C. Key Control:
1. The General Contractor shall provide duplicate keys and lock combinations to the
COR for the purpose of security inspections of every area of project including tool boxes and parked machines and take any emergency action.
D. Document Control:
1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of “sensitive information”.
2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.
3. Certain documents, sketches, videos or photographs and drawings may be marked
“Law Enforcement Sensitive” or “Sensitive Unclassified”. Secure such information in separate containers and limit the access to only those who will need it for the project.
Return the information to the COR upon request.
4. These security documents shall not be removed or transmitted from the project site without the written approval of COR.
5. All paper waste or electronic media such as CD’s shall be shredded and destroyed in a manner acceptable to the VA.
01 00 00 - 4
6. Notify COR and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.
7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document Management Software (EDMS).
Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the EDMS system.
“Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.
E. Motor Vehicle Restrictions
1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.
2. A limited number of permits shall be issued for General Contractor and its employees for parking in designated areas only. Contractor to coordinate with VA Medical Center
Facility Manager.
1.6 OPERATIONS AND STORAGE AREAS (FAR 52.236-10 (DEVIATION AUG 2025))
A. The Contractor shall confine all operations (including storage of materials) on
Government premises to areas authorized or approved by the COR. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the COR and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the COR, the buildings and utilities may be abandoned and need not be removed.
C. The Contractor shall, under regulations prescribed by the COR, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the COR. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect
01 00 00 - 5 them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
D. Working space and space available for storing materials shall be as shown on the drawings and must be coordinated with the COR.
E. Workers are subject to rules of Medical Center applicable to their conduct.
F. Execute work in such a manner as to interfere as little as possible with work being done by others. Keep roads clear of construction materials, debris, standing construction equipment and vehicles at all times.
G. Execute work so as to interfere as little as possible with normal functioning of Medical
Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space.
1. Do not store materials and equipment in other than assigned areas.
2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of Veterans Affairs in quantities sufficient for not more than two work days. Provide unobstructed access to Medical Center areas required to remain in operation.
3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.
H. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems
(except telephone), they shall be cut and capped at suitable places where shown on drawings; or, in absence of such indication, where directed by COR. All such actions shall be coordinated with the COR or Utility Company involved:
1. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the
Government and not the Contractor.
01 00 00 - 6
I. Phasing:
1. The Medical Center must maintain its operation 24 hours a day 7 days a week.
Therefore, any interruption in service must be scheduled and coordinated with the
COR to ensure that no lapses in operation occur. It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks. The work to be outlined shall include, but not be limited to the requirements listed below list item 2:
2. To ensure such executions, Contractor shall furnish the COR with a schedule of approximate dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the
COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such dates to ensure accomplishment of this work in successive phases mutually agreeable to COR and
Contractor, as follows:
MARTINEZ BUILDING 19:
PHASE 1: The Contractor shall install replacement fuel piping in parallel to existing fuel piping in all locations where existing fuel piping traverses above grade. Contractor shall install replacement pumps and associated controls during phase 1. Replacement pumps and associated controls shall be installed adjacent to existing. Replacement pumps shall not be utilized until phase 3.
PHASE 2: Contractor shall install replacement fuel oil piping in parallel to existing fuel oil piping in all locations where existing fuel oil piping traverses below grade. Contractor shall install replacement leak detection equipment in this phase.
PHASE 3: After the replacement fuel oil system is in place and tested, the Contractor shall connect the emergency generator to the installed replacement fuel oil system during the off hours. The system shutdown utilized to switch from the existing fuel piping system to the replacement must be completed within a single 8 hour shift. Upon completion of successful transition to the replacement fuel oil piping system, the contractor shall demolish all remaining existing fuel oil piping.
01 00 00 - 7
MARTINEZ BUILDING 20:
PHASE 1: the Contractor shall install replacement fuel piping in parallel to existing fuel piping in all locations where existing fuel piping traverses above grade. Contractor shall install replacement pumps and associated controls during phase 1. Replacement pumps and associated controls shall be installed adjacent to existing. Replacement pumps shall not be utilized until phase 3.
PHASE 2: Contractor shall install replacement fuel oil piping in parallel to existing fuel oil piping in all locations where existing fuel oil piping traverses below grade. Contractor shall install replacement leak detection equipment in this phase.
PHASE 3: After the replacement fuel oil system is in place and tested, the Contractor shall connect the emergency generator to the installed replacement fuel oil system during the off hours. The system shutdown utilized to switch from the existing fuel piping system to the replacement must be completed within a single 8 hour shift. Upon completion of successful
MARE ISLAND:
PHASE 1: The Contractor shall install replacement fuel piping in parallel to existing fuel piping in all locations where existing fuel piping traverses above grade. Contractor shall install replacement pumps and associated controls during phase 1. Replacement pumps and associated controls shall be installed adjacent to existing. Replacement pumps shall not be utilized until phase 3.
PHASE 2: Contractor shall install replacement fuel oil piping in parallel to existing fuel oil piping in all locations where existing fuel oil piping traverses below grade. Contractor shall install replacement leak detection equipment in this phase.
PHASE 3: After the replacement fuel oil system is in place and tested, the contractor shall connect the emergency generator to the installed replacement fuel oil system during the off hours. The system shutdown utilized to switch from the existing fuel piping system to the replacement must be completed within a single 8 hour shift. Upon completion of successful
Contractor shall refer to contract drawings for additional phasing information.
01 00 00 - 8
J. Building(s) No.(s) 19 and 20 at the Martinez campus and Building No. 201 at the Mare
Island campus will be occupied during performance of work.
1. Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical Centers operations will not be hindered. Contractor shall permit access to Department of
Veterans Affairs personnel and patients through other construction areas which serve as routes of access to such affected areas and equipment. These routes whether access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces, lighting etc. to facilitate patient and staff access.
Coordinate alteration work in areas occupied by Department of Veterans Affairs so that Medical Center operations will continue during the construction period.
2. Immediate areas of alterations not mentioned in preceding Subparagraph 1 will be temporarily vacated while alterations are performed.
K. Construction Fence: Before construction operations begin, Contractor shall provide a chain link construction fence, 2.1m (seven feet) minimum height, around the construction area indicated on the drawings. Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum 375mm (15 inches). Bottom of fences shall extend to 25mm (one inch) above grade. Remove the fence when directed by COR.
L. When a building and/or construction site is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:
1. Contractor shall maintain a minimum temperature of 4 degrees C (40 degrees F) at all times, except as otherwise specified.
2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company
(Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from Contractor's employee or watchman.
M. Utilities Services: Maintain existing utility services for Medical Center at all times.
Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services. Where necessary to cut existing water, steam, gases, 01 00 00 - 9 sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of
COR . Electrical work shall be accomplished with all affected circuits or equipment de-energized. When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the
Medical Center Director’s prior knowledge and written approval. Refer to specification Sections 26 05 11, REQUIREMENTS FOR ELECTRICAL
INSTALLATIONS and 27 05 11 REQUIREMENTS FOR COMMUNICATIONS
INSTALLATIONS for additional requirements.
2. Contractor shall submit a request to interrupt any such services to COR, in writing, 7 days in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.
3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical
Center. Interruption time approved by Medical Center may occur at other than
Contractor's normal working hours.
4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COR.
5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.
6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the
Government and not the Contractor.
N. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, shall be removed back to their source. Those which are indicated to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or
01 00 00 - 10 plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions;
so that they are completely behind the finished surfaces.
O. To minimize interference of construction activities with flow of Medical Center traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles. Wherever excavation for new utility lines cross existing roads, at least one lane must be open to traffic at all times with approval.
2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.
P. Coordinate the work for this contract with other construction operations as directed by
COR. This includes the scheduling of traffic and the use of roadways, as specified in
Article, USE OF ROADWAYS.
1.7 ALTERATIONS
A. Survey: Before any work is started, the Contractor shall make a thorough survey with the
COR and a representative of VA Supply Service, of buildings and areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by the COR. This report shall list by rooms and spaces:
1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of buildings.
2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.
3. Shall note any discrepancies between drawings and existing conditions at site.
4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by
Contractor and COR.
B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by Contractor with new items in accordance with specifications which will be furnished by Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING SITE
01 00 00 - 11
CONDITIONS" (FAR 52.236-2 (DEVIATION AUG 2025)) and "CHANGES" (FAR 52.243-
4 (DEVIATION JUL 2025)).
C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved.
They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:
1. Re-survey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of Contractor to restore damage caused by
Contractor's workers in executing work of this contract.
D. Protection: Provide the following protective measures:
1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.
2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.
3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.
1.8 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
1. Reserved items which are to remain property of the Government are noted on drawings or in specifications as items to be stored. Items that remain property of the
Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.
2. Items not reserved shall become property of the Contractor and be removed by
Contractor from Medical Center.
3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government.
When rooms and spaces are vacated by the Department of Veterans Affairs during
01 00 00 - 12 the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.
4. PCB Transformers and Capacitors: The Contractor shall be responsible for disposal of the Polychlorinated Biphenyl (PCB) transformers and capacitors. The transformers and capacitors shall be taken out of service and handled in accordance with the procedures of the Environmental Protection Agency (EPA) and the Department of
Transportation (DOT) as outlined in Code of Federal Regulation (CFR), Titled 40 and
49 respectively. The EPA's Toxic Substance Control Act (TSCA) Compliance
Program Policy Nos. 6-PCB-6 and 6-PCB-7 also apply. Upon removal of PCB transformers and capacitors for disposal, the "originator" copy of the Uniform
Hazardous Waste Manifest (EPA Form 8700-22), along with the Uniform Hazardous
Waste Manifest Continuation Sheet (EPA Form 8700-22A) shall be returned to the
COR who will annotate the contract file and transmit the Manifest to the Medical
Center's Chief.
a) Copies of the following listed CFR titles may be obtained from the Government
Printing Office:
40 CFR 261 .............. Identification and Listing of Hazardous Waste
40 CFR 262 .............. Standards Applicable to Generators of Hazardous Waste
40 CFR 263 .............. Standards Applicable to Transporters of Hazardous Waste
40 CFR 761 .............. PCB Manufacturing, Processing, Distribution in
Commerce, and use Prohibitions
49 CFR 172 .............. Hazardous Material tables and Hazardous Material
Communications Regulations
49 CFR 173 .............. Shippers - General Requirements for Shipments and
Packaging
49 CRR 173 .............. Subpart A General
49 CFR 173 .............. Subpart B Preparation of Hazardous Material for
Transportation
49 CFR 173 .............. Subpart J Other Regulated Material; Definitions and
Preparation
TSCA ........................ Compliance Program Policy Nos. 6-PCB-6 and 6-PCB-7
01 00 00 - 13
1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES,
AND IMPROVEMENTS (FAR 52.236-9 (DEVIATION AUG 2025))
A. The Contractor shall preserve and protect all structures, equipment, and vegetation
(such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workers, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the COR.
B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the COR may have the necessary work performed and charge the cost to the Contractor.
C. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, for additional requirements on protecting vegetation, soils and the environment. Refer to Articles, "Alterations", "Restoration", and "Operations and Storage Areas" for additional instructions concerning repair of damage to structures and site improvements.
D. Refer to FAR clause 52.236-7 (DEVIATION AUG 2025), "Permits and Responsibilities," which is included in General Conditions. A National Pollutant Discharge Elimination
System (NPDES) permit is required for this project. The Contractor is considered an
"operator" under the permit and has extensive responsibility for compliance with permit requirements. VA will make the permit application available at the (appropriate medical center) office. The apparent low bidder, contractor and affected subcontractors shall furnish all information and certifications that are required to comply with the permit process and permit requirements. Many of the permit requirements will be satisfied by completing construction as shown and specified. Some requirements involve the
Contractor's method of operations and operations planning and the Contractor is
01 00 00 - 14 responsible for employing best management practices. The affected activities often include, but are not limited to the following:
1. Designating areas for equipment maintenance and repair;
2. Providing waste receptacles at convenient locations and provide regular collection of wastes;
3. Locating equipment wash down areas on site, and provide appropriate control of wash-waters;
4. Providing protected storage areas for chemicals, paints, solvents, fertilizers, and other potentially toxic materials; and
5. Providing adequately maintained sanitary facilities.
1.10 RESTORATION
A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
B. Upon completion of contract, deliver work complete and undamaged. Existing work
(walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems
(including telephone) which are not scheduled for discontinuance or abandonment.
D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES" (FAR 52.243-4 (DEVIATION JUL 2025)) and "DIFFERING SITE CONDITIONS" (FAR 52.236-2 (DEVIATION AUG 2025)).
01 00 00 - 15
1.11 PROFESSIONAL SURVEYING SERVICES
A. A registered professional land surveyor or registered civil engineer whose services are retained and paid for by the Contractor shall perform services specified herein and in other specification sections. The Contractor shall certify that the land surveyor or civil engineer is not one who is a regular employee of the Contractor, and that the land surveyor or civil engineer has no financial interest in this contract.
1.12 LAYOUT OF WORK
A. The Contractor shall lay out the work from Government established base lines and bench marks, indicated on the drawings, and shall be responsible for all measurements in connection with the layout. The Contractor shall furnish, at Contractor's own expense, all stakes, templates, platforms, equipment, tools, materials, and labor required to lay out any part of the work. The Contractor shall be responsible for executing the work to the lines and grades that may be established or indicated by the COR. The Contractor shall also be responsible for maintaining and preserving all stakes and other marks established by the COR until authorized to remove them. If such marks are destroyed by the Contractor or through Contractor's negligence before their removal is authorized, the
COR may replace them and deduct the expense of the replacement from any amounts due or to become due to the Contractor.
(FAR 52.236-17 (DEVIATION AUG 2025))
B. Establish and plainly mark center lines for each building and corner of column lines and/or addition to each existing building, and such other lines and grades that are reasonably necessary to properly assure that location, orientation, and elevations established for roads and parking lots are in accordance with lines and elevations shown on contract drawings.
C. Following completion of general mass excavation and before any other permanent work is performed, establish and plainly mark (through use of appropriate batter boards or other means) sufficient additional survey control points or system of points as may be necessary to assure proper alignment, orientation, and grade of all major features of work. Survey shall include, but not be limited to, location of lines and grades of footings, exterior walls, center lines of columns in both directions, major utilities and elevations of floor slabs:
1. Such additional survey control points or system of points thus established shall be checked and certified by a registered land surveyor or registered civil engineer.
01 00 00 - 16
Furnish such certification to the COR before any work (such as footings, floor slabs, columns, walls, utilities and other major controlling features) is placed.
D. Whenever changes from contract drawings are made in line or grading requiring certificates, record such changes on a reproducible drawing bearing the registered land surveyor or registered civil engineer seal, and forward these drawings upon completion of work to COR.
E. Upon completion of the work, the Contractor shall furnish the COR one electronic copy and reproducible drawings at the scale of the contract drawings, showing the finished grade on the grid developed for constructing the work, including burial monuments and fifty foot stationing along new road centerlines. These drawings shall bear the seal of the registered land surveyor or registered civil engineer.
F. The Contractor shall perform the surveying and layout work of this and other articles and specifications in accordance with the provisions of Article "Professional Surveying
Services".
1.13 AS-BUILT DRAWINGS
A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.
B. All variations shall be shown in the same general detail as used in the contract drawings.
To ensure compliance, as-built drawings shall be made available for the COR review, as often as requested.
C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.
D. Paragraphs A, B, & C shall also apply to all shop drawings.
1.14 WARRANTY MANAGEMENT
A. Warranty Management Plan: Develop a warranty management plan which contains information relevant to FAR 52.246-21 Warranty of Construction in at least 30 days before the planned pre-warranty conference, submit four sets of the warranty management plan. Include within the warranty management plan all required actions and documents to assure that the Government receives all warranties to which it is entitled. The plan must be in narrative form and contain sufficient detail to render it suitable for use by future maintenance and repair personnel, whether tradesman, or of
01 00 00 - 17 engineering background, not necessarily familiar with this contract. The term “status” as indicated below must include due date and whether item has been submitted or was approved. Warranty information made available during the construction phase must be submitted to the COR for approval prior to each monthly invoice for payment. Assemble approved information in a binder and turn over to the Government upon acceptance of the work. The construction warranty period will begin on the date of the project acceptance and continue for the product warranty period. A joint 4 month and 9 month warranty inspection will be conducted, measured from time of acceptance, by the
Contactor and the COR. Include in the warranty management plan, but not limited to, the following:
1. Roles and responsibilities of all personnel associated with the warranty process, including points of contact and telephone numbers within the company of the
Contractor, subcontractors, manufacturers or suppliers involved.
2. Furnish with each warranty the name, address and telephone number of each of the guarantor’s representatives nearest project location.
3. Listing and status of delivery of all Certificates of Warranty for extended warranty items, to include roofs, HVAC balancing, pumps, motors, transformers and for all commissioned systems such as fire protection and alarm systems, sprinkler systems and lightning protection systems, etc.
4. A list for each warranted equipment item, feature of construction or system indicating:
a. Name of item.
b. Model and serial numbers.
c. Location where installed.
d. Name and phone numbers of manufacturers and suppliers.
e. Name and phone numbers of manufacturers or suppliers.
f. Names, addresses and phone numbers of sources of spare parts.
g. Warranties and terms of warranty. Include one-year overall warranty of construction, including the starting date of warranty of construction. Items which have extended warranties must be indicated with separate warranty expiration dates.
h. Starting point and duration of warranty period.
i. Summary of maintenance procedures required to continue the warranty in force.
01 00 00 - 18
j. Cross-reference to specific pertinent Operation and Maintenance manuals.
k. Organizations, names and phone numbers of persons to call for warranty service.
l. Typical response time and repair time expected for various warranted equipment.
5. The plans for attendance at the 4 and 9-month post construction warranty inspections conducted by the Government.
6. Procedure and status of tagging of all equipment covered by extended warranties.
7. Copies of instructions to be posted near selected pieces of equipment where operation is critical for warranty and/or safety reasons.
B. Performance & Payment Bonds: The Performance & Payment Bonds must remain effective throughout the construction period.
1. In the event the Contractor fails to commence and diligently pursue any construction warranty work required, the COR will have the work performed by others, and after completion of the work, will charge the remaining construction warranty funds of expenses incurred by the Government while performing the work, including, but not limited to administrative expenses.
2. In the event sufficient funds are not available to cover the construction warranty work performed by the Government at the contractor’s expenses, the CORwill have the right to recoup expenses from the bonding company.
3. Following oral or written notification of required construction warranty repair work, the
Contractor shall respond in a timely manner. Written verification will follow oral instructions. Failure to respond will be cause for the COR to proceed against the
Contractor.
C. Pre-Warranty Conference: Prior to contract completion, and at a time designated by the
COR, the Contractor shall meet with the COR to develop a mutual understanding with respect to the requirements of this section. Communication procedures for Contractor notification of construction warranty defects, priorities with respect to the type of defect, reasonable time required for Contractor response, and other details deemed necessary by the COR for the execution of the construction warranty will be established/ reviewed at this meeting. In connection with these requirements and at the time of the Contractor’s quality control completion inspection, furnish the name, telephone number and address of a licensed and bonded company which is authorized to initiate and pursue construction warranty work action on behalf of the Contractor. This point of contract will
01 00 00 - 19 be located within the local service area of the warranted construction, be continuously available and be responsive to Government inquiry on warranty work action and status.
This requirement does not relieve the Contractor of any of its responsibilities in conjunction with other portions of this provision.
D. Contractor’s Response to Construction Warranty Service Requirements:
E. Following oral or written notification by the COR, the Contractor shall respond to construction warranty service requirements in accordance with the “Construction
Warranty Service Priority List” and the three categories of priorities listed below. Submit a report on any warranty item that has been repaired during the warranty period. Include within the report the cause of the problem, date reported, corrective action taken, and when the repair was completed. If the Contractor does not perform the construction warranty within the timeframe specified, the Government will perform the work and back charge the construction warranty payment item established.
1. First Priority Code 1. Perform onsite inspection to evaluate situation, and determine course of action within 4 hours, initiate work within 6 hours and work continuously to completion or relief.
2. Second Priority Code 2. Perform onsite inspection to evaluate situation, and determine course of action within 8 hours, initiate work within 24 hours and work continuously to completion or relief.
3. Third Priority Code 3. All other work to be initiated within 3 work days and work continuously to completion or relief.
4. The “Construction Warranty Service Priority List” is as follows:
a) Code 1-Life Safety Systems
Fire suppression systems.
Fire alarm system(s).
b) Code 1-Air Conditioning Systems
Air conditioning leak in part of the building, if causing damage.
Air conditioning system not cooling properly.
c) Code 1 Doors
Overhead doors not operational, causing a security, fire or safety problem.
Interior, exterior personnel doors or hardware, not functioning properly, causing security, fire or safety problem.
01 00 00 - 20
d) Code 3-Doors
Overhead doors not operational.
Interior/exterior personnel doors or hardware not functioning…