RFI Q-A Response 7-17-2025.pdf
PDF 833 KB Posted
- Solicitation number
- 36C26125R0044
About this file
This document is a Request for Information (RFI) Questions and Answers for a roof replacement project at the VA Medical Center in Las Vegas, Nevada. The solicitation (No. 36C26125R0044) covers replacing the roof of Building 1, with a project duration of 182 calendar days. Key technical details include applying a polyurethane coating system with a minimum of 65 wet mils for the base coat, using Tremco AlphaGuard BIO products as the basis of design, and addressing potential challenges such as temperature restrictions during installation (not recommended when surface temperatures exceed 120°F). The project involves exterior roof work with potential impacts to hospital operations, requiring careful coordination to minimize disruption to patient care areas.
The RFI responses provide extensive clarification on project requirements, including specific instructions for roofing materials, installation methods, safety protocols, and site access. Notable requirements include daily debris removal, potential weekend or after-hours work, limited interior access, and strict infection control measures. The contractor will need to submit detailed plans for crane operations, access strategies, and work schedules. Additional specifications cover lightning protection system installation, electrical and mechanical penetrations, and maintaining existing drainage systems. The proposal submission deadline is set for 7-24-2025 at 14:00 PDT, with the VA's Contracting Officer Representative (COR) providing oversight throughout the project.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C26125R0044 0004.docx | DOCX document | |
| 36C26125R0044 0003.docx | DOCX document | |
| 36C26125R0044 0002.docx | DOCX document | |
| 36C26125R0044 0001.docx | DOCX document | |
| Site Visit Sign-in Form 06-24-2025.pdf | ||
| Attachment SOW 03-14-2025.pdf | ||
| 36C26125R0044_1.docx | DOCX document | |
| Attachment Price Breakdown.xlsx | XLSX spreadsheet | |
| Attachment Drawings.pdf | ||
| Attachment REQUEST FOR INFORMATION FORM.pdf | ||
| Attachment Wage Determination NV20250038 05-02-2025.pdf | ||
| Attachment Pre-solicitation Site Visit Presentation.pptx | PPTX presentation | |
| Attachment Specifications.pdf |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFI Questions & Answers for Solicitation No. 36C26125R0044 Project No. 593-24-302
Replace Roof Bldg. 1 (VAMC) Las Vegas, NV
VA Responses
Q1:
How many total mils are required (DFT) for the polyurethane coating system?
Q1 VA Answer:
64 wet mils (minimum) for the base coat. Additional mils for top coat, dependent upon product selected. For non-slip applications (i.e. walk pads) another additional layer is applied over the base coat (containing sand), further increasing the mils.
Q2:
Is closing down building operations in sections an option during application?
Q2 VA Answer:
It may be requested by the contractor; however, sufficient notice must be provided to allow the COR to coordinate based on the impacted areas of operation. Weekend work or after-hours may also be considered as alternatives if necessary.
Q3:
Are the building cranes operational and in use currently? This will be important to know for how roof application will need to be done in those areas.
Q3 VA Answer:
The contractor may consider using the existing roof hoist/lift equipment as an alternative method for transporting materials to the roof, provided that the equipment is tested and certified for its lifting capacity at the contractor’s own expense. However, the contractor is responsible for providing their own lifting equipment unless otherwise approved.
Any use of hoisting/lifting equipment must comply with all applicable safety standards, and the contractor will be held liable for any damage caused to roof anchors, the roof membrane, building structure, overhangs, or surrounding areas during the lifting operations.
Q4:
Confirm that all single ply membrane @ parapet walls & top of mechanical platform are not in the scope of work
Q4 VA Answer:
Confirmed. Polyurethane coating system terminates at the counterflashing as shown on details in 100% CD set, sheet AE560.
Q5:
Remove & replace sheet metal counter flashing only as needed to install patch work section 07 01 50.91 & installation of roof coating.
Q5 VA Answer:
Confirmed.
Q6:
Section 07 60 00 is for replacing missing coping & counter flashing only & removal & replacement as needed only. Same as 07 01 50.91 as needed.
Q6 VA Answer:
Q7:
Section 07 92 00 joint sealants as needed only during roofing repairs & roof restoration only as needed during the same as 07 01 50.91 & 07 60 00
Q7 VA Answer:
(Repeated question from Q4) Q8:
Confirm that all single ply membrane @ parapet walls and top of mechanical platform are not in the scope of work.
Q8 VA Answer:
Q9:
Confirm remove and replace sheet metal counter flashing only as needed to install patch work section 07 01 50.91 and installation of roof coating.
Q9 VA Answer:
(Repeated question from Q6) Q10:
Confirm Spec Section 07 60 00 is for replacing missing coping and counter flashing only and removal and replacement as needed only. Same as Section 07 01 50.91 as needed.
Q10 VA Answer:
Q11:
Confirm Spec Section 07 92 00 joint sealants as needed only during roofing repairs and roof restoration only as needed during the same as sections 07 01 50.91 and 07 60 00 as needed only.
Q11 VA Answer:
Q12:
Please identify all air handler intakes.
Q12 VA Answer:
Contractor to request mechanical as-built drawings from VA for air handler intake locations.
Please note that none of the AHUs / RTUs located on the roof will be relocated during this reroofing project.
Q13:
Do all air handlers need to have HEPA filters on them when work on specific roofs is taking place to prevent debris, chemical and other material from entering in the hospital spaces?
Q13 VA Answer:
From a Mechanical perspective, additional filtration at the outside air intakes (such as charcoal or HEPA filters) probably isn’t necessary. The main concern with adding extra filters is the increased pressure drop, which could affect overall system airflow. Since the hospital is designed with precise pressure relationships between various rooms, introducing additional resistance in the intake path could unintentionally disrupt that balance and lead to downstream issues. The TREMCO AlphaGuard BIO Base Coat, BIO Top Coat, and FC LO – Field are all virtually odorless and low in VOCs, so I believe the existing AHU filters should be sufficient. See screenshots below:
It should be noted that feedback/response is based on the Basis of Design (BOD) Tremco products. If alternate products are considered, specifications should match from a performance standpoint.
Q14:
Are any air intake handlers able to be shut down during construction to allow for the reduction in HEPA filter placement? If so, which ones and for how long?
Q14 VA Answer:
The intent is to not relocate any AHUs / RTUs on the roof during this reroofing project. Apart from any shutdowns required regarding any new duct / duct insulation associated with RTUs AMB-3A and AMB-3B (see sheets MP124C & MP124F) no AHU / RTU shutdowns are necessary.
Q15:
Are the various roofs able to be turned back over to the VA after they have been verified by the manufacturer and a warrant has been issued for those roofs or are all roofs going to remain under the care custody and control of the contractor till the final roof is completed?
Q15 VA Answer:
Due to the multiple floor levels within Building 1, it is reasonable to turn the space back over to the VA only after it has been verified by the manufacturer, a warranty has been issued, and the VA has had the opportunity to conduct a final walk-through with all punch list items completed and verified. The contractor will be required to submit a phasing plan that outlines this process.
The plan will be subject to review and approval by both the Contracting Officer and the Contracting Officer Representative.
Q16:
Will the telecommunication work be an afterhours or weekend scope of work to limit the impact to the facility?
Q16 VA Answer:
At this time, we do not anticipate any service impacts, so work during normal business hours is acceptable. However, when the contractor submits a detailed schedule, we will need to review it with our Technology Coordinator to assess any potential service disruptions. If it is determined that the work will impact operations, we may require the work to be performed after hours or on weekends to avoid interference with ongoing services.
Q17:
Will trash and debris need to be removed daily from the roof or can it be removed a few times per week, as long as the safety is maintained.
Q17 VA Answer:
General rule of thumb is to maintain “good housekeeping” for any worksite by keeping the area clean as possible and removing any trash on a daily basis. We have critical infrastructure on the roof e.g., air handlers, cooling equipment, elevator rooms etc. We would want to minimize the impact of a potential fire or other unseen events to the equipment or roof. Therefore, all debris must be removed from the roof at the end of each workday.
Q18:
Is there any engineered tie off points on the penthouses or will those require the installation of parapet wall guardrail system? If so, please identify them on the plans.
Q18 VA Answer:
Unknown. If tie off points exist on these roof overrun areas, they are not present in the as-builts and would have to be verified in field.
(Repeated question from Q4) Q19:
Confirm that all single ply membrane @ parapet walls and top of mechanical platform are not in the scope of work
Q19 VA Answer:
Confirmed.
Q20:
Is it the intension to terminate the coating below counterflashing in all areas?
Q20 VA Answer:
No, the intention is to apply the coating at counterflashing per detail B3/AE560.
Q21:
Are exposed single ply parapet sections also to be restored?
Q21 VA Answer:
No, roofing restoration terminates at the counterflashing per detail B3/AE560.
Q22:
Per site plan that's labeled in alphabetical roof sections , are any of these service elevators accessible for contractor use?
Q22 VA Answer:
To avoid disruption to patient care and occupied work areas, this project should prioritize exterior access over interior access whenever possible. We understand that some areas may have limitations that require interior entry therefore it is critical that all contracted personnel, including subcontractors whose employees require routine physical access, must request Non-Personal Identity Verification (PIV) access.
As part of the comprehensive work plan, contractors must provide an access strategy for each building level, detailing how access will be achieved from the exterior or, if necessary, through the interior when no other alternative is feasible.
Q23:
Can a lightning protection plan be supplied?
Q23 VA Answer:
If as-built lightning protection system plans are being requested, please request from the VA.
New lightning protection plans are to be provided by the LPS installer.
Q24:
Lightning protection was not visible on all roofing sections. Are the areas that currently do not have protection in the SOW?
Q24 VA Answer:
The intent of the installation is to provide a complete, fully functional lightning protection system in accordance with the relevant codes. The new system must be able to be certified. All areas that are required to be protected by a lightning protection system are considered in scope.
Q25:
Per schedule 182 calendar days is the requested duration of the project. How many weather related days will be grated?
Q25 VA Answer:
This is sufficient time for construction, and with keeping with the full duration of 182 days to account for any delays. The 182 calendar period of performance accounts for any potential delays for weather.
For our climate in Las Vegas, we see in manufacturers recommendations that this product should not be installed when surface temperatures exceed ~120°F (49°C), or when air temperature above 95°F (35°C). The ideal substrate application temperature is 50°F to 90°F (10°C to 32°C). In Las Vegas, this usually means that installation should NOT occur from late morning through early evening (10 AM – 6 PM), from June to early September. And in general the best application time is early morning (sunrise to ~9:30 AM) during spring, fall, or early summer.
Q26:
Do all coating alternatives meaning base and top-coat need to meet all requires per 07 01 50.91 if it meets warranty duration?
Q26 VA Answer:
Yes. Alternatives should meet warranty and performance criteria of specification.
Q27:
The proposed coating system has installed temperature restrictions. Are hot weather delays from the coating manufacture considered or is the 182 day projected time frame include all variables?
Q27 VA Answer:
See answer on Q25
Q28:
Is all internal plumbing accessible with drop ceiling or is there drywalled areas?
Q28 VA Answer:
Conditions may vary, drywalled in some areas and drop ceiling in others.
Q29:
Per drawings on a previous project at the facility, drawings called out for areas that lightweight concrete. Can a map of decking areas be supplied?
Q29 VA Answer:
VA can provide as-builts showing areas of lightweight concrete. The design team can provide a graphical map showing these areas if necessary.
Q30:
If lightweight concrete is under the wet areas to be removed, there is a chance that lightweight may need to be repaired. This may cause an open roof situation due to a 24 hr dry time before it can be covered up. Can the government confirm yes or no if lightweight is under the areas of roof removal?
Q30 VA Answer:
Design team can verify based on response to Q29 above.
Q31:
Are there any visible areas of rusted metal B decking in the areas to be removed?
Q31 VA Answer:
No.
Q32:
The loading dock is to be used as a temporary laydown area per plan. What duration will this area be granted to the contractor chosen?
Q32 VA Answer:
The loading dock may be used as a temporary laydown area for unloading or delivering materials. An enclosed waste dumpster is also permitted for use at the loading dock. The dumpster may remain at the loading dock for the duration of the project, provided there is adequate space and prior approval is obtained from the Facilities team.
To prevent cross-contamination from VA employees or other contractors improperly disposing of waste, we recommend using a top-enclosed dumpster. This issue has occurred in the past, so precautionary measures are highly encouraged.
Q33:
Plans from previous ITB for project VAMC Install Campus Fall Protection at the same facility require roofing scopes. May the awarded contractor of that project be different than this project, the situation of covering up a contractor’s warrantable work is unavoidable. Should it be assumed the coating contractor is also taking liability of the roofing installed for life safety?
Q33 VA Answer:
Based on the BOD product warranty information, the new roofing product warranty will extend to cover work by others as it relates to roofing materials, waterproofing, sealants, and Division 7 specification items. The warranty would cover liability associated with items pertaining to installation and performance of these items, but for items that concern life safety issues (i.e. the installation and fastening of a guardrail or anchor or roof stanchion to roofing structural members below) the roofing warranty would NOT cover. For example, if there is a leak around a point of attachment at an anchor, the warranty would cover this. If the anchor pulls out because it was not installed correctly, the roofing product warranty would not cover.
Q34:
HVAC – Drawings MP124C Sheet Note #1 and MP124F/ Sheet Note #1 - Indicate extent of insulation to be removed/ repaired on ductwork referenced in Detail D/ Dwg MP700
Q34 VA Answer:
Insulation on supply and return ductwork serving existing RTUs AMB-3A and AMB-3B (as shown in roof plans on sheets MP124C & MP124F) shall be removed and replaced. Refer to detail D7 on sheet MP700 for new insulation requirements.
Q35:
Electrical – What LPS certification is required? – Master Label, Letter of Findings or other?
Q35 VA Answer:
Master Label certification will be required.
Q36:
Electrical – Drawings EE121J, EE124C and EE125LP – Please provide specification for GFCI receptacles to be replaced.
Q36 VA Answer:
Weatherproof, GFCI duplex receptacles to be replaced in kind.
Q37:
Plumbing – is the intent to add new tapered insulation from edge of sump to the drains to match Dwg MP700/ Detail F7?
Q37 VA Answer:
To prevent ponding between the sump and the existing roof drains, the sump shall be made to sit flush with roof drain per detail F7 on sheet MP700. Contractor to ensure the proper roof slope towards the existing roof drains are maintained.
Q38:
Can the Govt indicate allowed laydown and staging areas?
Q38 VA Answer:
Drawing GS101, titled “Partial Site Plan”, indicates the staging and laydown area located near the southeast of Parking Lots I and J.
Q39:
Is overhead pedestrian protection from falling objects to be provided? If so, please indicate locations.
Q39 VA Answer:
Yes, overhead pedestrian protection should be provided in alignment with OSHA 29 CFR 1926 and VA Architectural Design Guidelines (which align with OSHA requirements. Protection should be installed as canopies or similar protection when all of these are true:
• Roofing is taking place ≥ 6 feet above a pedestrian area, such as sidewalks, entryways, vehicle or ambulance zones.
• There’s a hazard of falling objects, such as shingles, tools, debris—common in roofing and demolition activity.
• The work area is accessible to staff, veterans, or the public, where foot traffic is likely beneath the work zone.
Q40:
Spec Sections 01 21 00 Allowances & 01 22 00 Unit Prices – Are unit prices required to be submitted with the bid? If so can the Govt provide a bid schedule?
Q40 VA Answer:
The solicitation attachment “Price Breakdown” form should be filled out and included with the proposal submission. Please reference the “Instructions to Offerors” section of the solicitation requirement for guidance.
Q41:
Clarification on Quantity and Specifications of Roof Drains (Section 22 14 00 – Facility Storm Drainage) Question: The specifications outline requirements for storm drainage systems, including roof drains, but do not provide a specific quantity, size, or configuration of roof drains to be replaced. Can the VA provide a plumbing schedule or detailed drawings specifying the number, size, location, and type of roof drains to be replaced? Additionally, are there specific material requirements (e.g., cast iron, PVC) or connection details to existing drainage systems that should be followed?
Q41 VA Answer:
The intent is for the existing roof drains to be reused. Contractor to remove debris / clean sumps around existing roof drains and ensure the proper roof slope towards the existing roof drains are maintained.
Q42:
Details of Existing Roof Drains and Drainage System Integration (Section 22 14 00) Question: The specifications mention compatibility with existing pipe materials (Page 271) but do not provide details about the existing storm drainage system’s configuration, pipe materials, or connection points. Can the VA provide as-built drawings or specifications for the existing roof drains and storm drainage system to ensure proper integration with new drains? Additionally, are there any specific requirements for testing or inspecting the existing drainage system prior to connecting new drains?
Q42 VA Answer:
As-built drawings or specifications for the existing roof drains and storm drainage systems can be provided to the awarded contractor upon request.
Regarding testing or inspection of the existing drainage system prior to connections, any requirements will be addressed during the submittal review process and in coordination with the VA team during construction. The contractor should be prepared to verity compatibility and functionality as part of their scope.
Q43:
Asbestos Abatement Scope and Testing Requirements (Section 02 82 13.21 – Asbestos Roofing Abatement) Question: The specifications detail procedures for asbestos roofing abatement but do not specify the extent of asbestos-containing materials (ACM) present or the total area of roofing to be abated. Additionally, the testing and clearance requirements (e.g., air sampling, visual inspections) are referenced but not quantified. Can the VA provide a survey or report identifying the locations, quantities, and types of ACM in the roofing system?
Furthermore, can the VA clarify the number of air samples required and the specific clearance criteria for abatement completion?
Q43 VA Answer:
Per General Notes on GI003, samples must be tested in the areas of demolition per the abatement schedule. Roof areas are identified in this schedule as well.
The number of air samples required and the specific clearance criteria for asbestos abatement will be provided at the beginning of the project. This information will be coordinated with the VA’s Industrial Hygienist and outline prior to the start of the abatement activities.
Q44:
Roofing Material Quantities and Specifications (Section 07 01 50.91 – Roof Restoration) Question: The roof restoration specifications outline materials and installation methods but do not include quantities (e.g., square footage of roofing material, number of flashings) or specific roof areas to be restored. Can the VA provide detailed roof drawings, including plan views, sections, and a schedule of quantities for roofing materials, flashings, and accessories?
Additionally, are there preferred manufacturers or specific performance criteria (e.g., wind uplift resistance) for the roofing system?
Q44 VA Answer:
Refer to sheet GI003 of the 100% Construction Documents drawing set, and associated plan sheets. The BOD is Tremco (AlphaGuard BIO Base Coat, AlphaGuard BIO Top Coat, and AlphaGuard FC LO products). While Tremco products are referenced as a basis of design, equivalent systems by other manufacturers that meet or exceed the specified performance criteria are acceptable, subject to approval.
Additional performance criteria for wind uplift is below:
Q45:
Coordination of HVAC and Electrical Penetrations (Sections 23 05 11, 26 05 11) Question: The specifications address HVAC and electrical work, including penetrations through the roof, but the drawings do not provide details on the location, number, or size of these penetrations. Can the VA provide detailed mechanical and electrical drawings showing the exact locations and specifications for HVAC and electrical penetrations? Additionally, are there specific flashing or sealing requirements for these penetrations to ensure compatibility with the new roofing system?
Q45 VA Answer:
Specifications covering the penetrations have been provided for information only. It is not expected that any equipment will need to be relocated and require new penetrations. Please provide a unit price for both electrical and mechanical penetrations in the event it is determined during construction that electrical or mechanical equipment will need to be relocated and require new penetrations.
Flashing or sealing at penetrations should follow details on AE560 of the 100% Construction Documents.
Q46:
Safety Requirements for Roofing Work at Heights (Section 01 35 26 – Safety Require- ments) Question: Are there designated anchor points or specific fall protection systems required by the
VA?
Q46 VA Answer:
The contractor will be provided with drawings of the specific fire protection systems if requested at the start of the project by the project architect or by the VA. However, the contractor is still responsible for verifying that existing conditions match the drawings.
Q47:
Unit Prices for Additional Work (Section 01 22 00 – Unit Prices) Question: The specifications mention unit prices for roofing assembly removal but do not provide a baseline quantity or scope for additional work. Can the VA clarify the anticipated quantities for roofing removal or other unit price items? Additionally, are there specific conditions (e.g., unforeseen damage, additional asbestos) that would trigger the application of unit prices, and how should contractors document such conditions?
Q47 VA Answer:
VA contracts often include unit price line items for roofing assembly removal, hazardous material abatement (like asbestos), or unforeseen structural repairs. These are typically:
Contingency-based items, only activated by a Contracting Officer’s direction.
Intended to price in-place work not fully defined at bid time.
Q48:
Construction Waste Management Quantities (Section 01 74 19 – Construction Waste Management) Question: The waste management section requires recycling, and disposal plans but does not specify the estimated quantities of roofing materials, asbestos, or other waste to be generated. Can the VA provide an estimate of the total roofing area, volume of asbestos-containing materials, or other waste quantities to assist in developing the waste management plan? Additionally, are there designated disposal facilities or recycling requirements specific to the VA?
Q48 VA Answer:
Total roof area, demolition areas, etc. are defined in the 100% Construction Documents.
VA COR to provide information regarding designated disposal facilities or recycling requirements at the start of the project.
Q49:
ICRA Classification and Specific Requirements for Building 1 Question: Can the VA provide the ICRA risk group classification for this project and any specific infection control measures required based on the location of Building 1 relative to patient care areas?
Q49 VA Answer:
Per the ICRA, the Patient Risk Category is classified as High if the activity occurs within a patient-care area (e.g. inpatient units or patient care rooms).
If it is determined that interior work is required such as ceiling tile removal, drilling, or HVAC modifications then further confirmation will be needed to assess potential impacts to patient-care areas.
For now, preliminary ICRA Level II precautions have been identified to meet design requirements.
Q50:
Is an SSHO required for this project?
Q50 VA Answer:
Yes
Q51:
Is a Quality Control Manager required for this project?
Q51 VA Answer:
Yes
Q52:
Will the VA be providing an ICRA classification or matrix to establish the required level of infection control compliance for this scope of work?
Q52 VA Answer:
Yes, VHA PCRA 1.1 (May 21, 2024) and VHA ICRA 1.3 (December 2024).
Q53:
Will any interior access be required (e.g., for access to stairwells, roof hatches, or mechanical/electrical rooms) that would trigger the need for interior containment, dust control, or negative air pressure zones?
Q53 VA Answer:
Since this project is expected to be entirely exterior work, interior containment, dust control measures, and negative air pressure zones are not anticipated or required. If any interior access becomes necessary such as for stairwells, roof hatches, or mechanical/electrical rooms, it will be coordinated in advance, and appropriate ICRA measures will be implemented based on the activity and location.
Q54:
Is the contractor responsible for implementing physical infection control measures (such as HEPA filtration units, temporary barriers, or particle monitoring) even if the scope remains entirely exterior?
Q54 VA Answer:
If construction activity is entirely exterior, negative pressurization and particulate monitoring are not applicable.
Q55:
Are there any known patient care areas or building zones directly impacted by the roofing scope that would require elevated ICRA mitigation measures?
Q55 VA Answer:
At this point, there are no identified patient care areas directly impacted by the roofing scope of work. We do not foresee any direct impact to patient care areas. However, the contractor should remain mindful of adjacent work zones that could potentially affect these areas. If it is determined during course of work that any activities may impact patient care spaces or pedestrian safety, the contractor must promptly notify the VA so appropriate ICRA mitigation measures can be evaluated and implemented.
Q56:
Will the contractor be responsible for removing loose equipment on the roof prior to installation?
Q56 VA Answer:
Yes, limited to Lightning Protection System and any “loose” blocking for ducts, lines, conduits directly laying upon roof surfaces. Excludes removal of MEP equipment mounted to pads or curbs.
Q57:
What are the hours of operation for crane use?
Q57 VA Answer:
This will depend on your crane pick/lift plan. Once submitted and reviewed, we can determine whether adjustments are needed, either by coordinating the work after hours or, if necessary, during regular hospital hours. If the lift affects any occupied floors within the approved area, we will require adequate time to coordinate and ensure those areas are cleared from employee and patient access during the lift.
Q58:
What are the available locations for the crane to be operated?
Q59 VA Answer:
The contractor must submit a crane pick/lift plan indicating the proposed crane location and the anticipated time impact. This plan is subject to approval by both the VA safety Officer and the COR. The COR will subsequently seek approval from various facility personnel.
Q59:
How many layers of coating is the contractor applying?
Q59 VA Answer:
65 wet mils minimum for base coat (16pprox.. 2 coats), plus additional layers where topcoat and walk pads are located. This is an estimate and the total number of layers depends on the selected product and manufacturers’ recommendations for installation.
Q60:
How far up the parapet walls is the coating going?
Q60 VA Answer:
8” min per detail B3/AE560.
Q61:
How many layers of material are currently on the roof
Q61 VA Answer:
With a reasonable degree of certainty, the roof is comprised of three plys of asphalt sheets with a modified bitumen cap sheet. This is based upon the as-built construction documents as well as the roof cores that Tremco performed as part of the assessment of the existing roof.
Q62:
Is the contractor replacing the drain caps?
Q62 VA Answer:
The intent is for the existing roof drains to be reused. Contractor to remove debris / clean sumps around existing roof drains and ensure the proper roof slope towards the existing roof drains are maintained.
Q63:
Where is the contractor able to store equipment during install and after hours of install?
Q63 VA Answer:
Storage space within the VA Medical Center is limited, and we are unable to provide access or accommodate storage of privately owned equipment. However, contractors may utilize designated areas on the roof to store equipment and materials, provided all items are properly secured and strapped down due to the potential for strong winds. The contractor’s safety representative is responsible for inspecting and ensuring that everything is secure at the end of each shift. Materials must be properly weighted to prevent them from becoming airborne.
Please note that the VA will not be responsible for any equipment or materials left unattended or damaged overnight.
Q64:
Is the contractor replacing current pipe jacks on the roof or just coating over?
Q64 VA Answer:
If using Tremco AlphaGuard BIO products, coating over. However, if alternates are used refer to manufacturer recommendations for installation to meet roofing warranty.
Q65:
What are the hours of operation for the crew in each building?
Q65 VA Answer:
Since most of the work will take place on the exterior roof, the contractor will need to propose the working hours for each building. The key requirement is that construction activities must not interfere with the hospital’s daily operations and services. Note: VA hospital service hours are Monday through Friday, 8:00am to 5:00pm. The facility is closed on Saturday and Sundays.
Q66:
Will the crew be able to use the access door inside the hospital?
Q66 VA Answer:
The crew may use interior hospital access doors if specifically requested and approved by the
COR.
Q67:
Will scaffolding be needed around the whole building?
Q67 VA Answer:
Not likely. Depends on Contractor means and methods.
Q68:
Will tarping or covers be needed for plants or any sidewalk areas?
Q68 VA Answer:
It is the contractor’s responsibility to maintain existing conditions as they were prior to the start of work. If necessary, protective measures such as tarping or covering plants and sidewalk areas should be implemented at the contractor’s discretion to prevent damage. Any damage caused by the contractor must be repaired at the contractor’s expense to match the original condition.
As stated in the scope of work, the contractor shall take photographs of all areas within the scope prior to the commencement of any activities. These photographs must be shared with the
COR for our records prior to the start of work. This documentation will assist in resolving any disputes regarding pre-existing conditions.
Q69:
Is the contractor responsible for resealing around pipe jacks and vents prior to coating?
Q69 VA Answer:
Follow selected product requirements for installation to meet warranty.
Q70:
Will the contractor be required to use intake filters on all vents?
Q70 VA Answer:
See answer on Q13
Q71:
Where are contractor vehicles able to park on site?
Q71 VA Answer:
Parking lot J
Q72:
Does the equipment need to be taken off the roof after each day or can it stay on each section until the roof is done?
Q72 VA Answer:
See answer on Q63
(END OF RFI Q&A RESPONSES)
| RFI Questions & Answers for Solicitation No. 36C26125R0044 |
| Project No. 593-24-302 |
| Replace Roof Bldg. 1 (VAMC) Las Vegas, NV |