36C26122R0010--RFI Reposnes--12.21.2021.pdf

PDF 125 KB Posted

Attached to
Z2GZ--Replace Building 32 Elevator for Safety | 570-21-800 Total SB Set-Aside
Solicitation number
36C26122R0010
Issued by

About this file

This document contains a request for information and responses regarding a federal construction contract opportunity to replace elevators at a Veterans Affairs medical center facility. The contract opportunity involves replacing four story freight elevators, including new mechanical and electrical components, doors, cab, and shaft work. The solicitation is anticipated to be issued on November 23, 2021 for a small business set-aside contract between $1-2 million requiring 329 calendar days to complete. Interested parties must register in the System for Award Management to download solicitation documents from the Governmentwide Point of Entry website, where amendments will also be posted.

View the file

Other files

Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

2615 E. Clinton Ave, Fresno CA 93703

REQUEST FOR INFORMATION

FROM: Department of Veterans Affair.

SUBJECT: PRE-PROPOSAL RFI

SOLICITATION: 36C26122R0010

RFI #1 – Must the rooftop walking platform be ADA compliant, or will OSHA compliance be sufficient?- RESPONSE: Rooftop walking platform will be OSHA compliant.

RFI #2 – FS100 / 2 “Temporary Shaft Wall Detail”. Is this detail intended as a temporary infill for each elevator hoist way door opening as the old doors are replaced?.

RESPONSE: The temporary shaft wall is intended to temporarily close the hoistway while the hoistway doors are replaced.

RFI #3 - Will a 6 MM fire resistant temporary plastic barrier be sufficient during the detail work around each hoist way door? (i.e. door is in place and able to be sealed with tape and plastic)- RESPONSE: 6mm fire resistant temporary plastic barriers meet the intended purpose for dust control.

RFI#4 – Is a fire rated air damper required at the temporary shaft wall for the negative pressure fan?

RESPONSE: A fire rated air damper is not required in the temporary shaft wall.

RFI#5 – May the Superintendent also fulfill the requirement of QA/QC?

RESPONSE: The superintendent may fill secondary roles so long as the individual meets all requirements for both roles per the contract documents. Please see specification 01 45 00 for further details.

RFI# 6 – Has the facility been tested for lead and asbestos?

RESPONSE: Please see attachment 570-21-800 Good Faith Study for further hazardous material information.