Attachment 1 653-21-104 SOW Replace Doors 3 Revision 1.pdf

PDF 106 KB Posted

Attached to
Y1DA--653-21-104 Replace Doors 3 Federal contract opportunity
Solicitation number
36C26023R0017
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 20

About this file

This statement of work outlines requirements for a construction project to replace doors at a Department of Veterans Affairs medical center. The project involves demolishing and installing eight doors across various locations, installing door actuators and automatic openers, and repairing adjacent structures and finishes. The contractor will manage the project, conduct weekly meetings, and implement quality controls. An initial 30-day period allows for material submittals and ordering, followed by a 90-day construction phase. The contractor must comply with numerous VA design standards and codes, as well as cultural resource and seismic requirements. This project aligns with solicitation 36C26023R0017 from the VA Veterans Health Administration Network 20 for replacement of doors 3 under opportunity Y1DA--653-21-104.

View the file

Other files for this federal contract opportunity

Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK Revision 1

Replace Doors 3 -

Project Number 653-21-104

1.0 DESCRIPTION OF WORK

BACKGROUND: This project includes general construction, alterations, demolition, exterior and interior improvements necessary for the Replace Doors 3, and other items necessary to complete the project.

Contractor will completely prepare the site for construction operations, including demolition and removal of existing structures, furnish labor and materials, perform work for the Installation and

Repair of Electronic doors.

The project is located on the VA Roseburg Healthcare System main campus at 913 NW Garden

Valley Blvd, Roseburg, OR 97471. The site and campus buildings are listed as eligible for the

National Historic Register.

All work on the contract shall be performed between 8:00 a.m. and 4:30 p.m., Monday through

Friday, excluding National Holidays, unless approved by the Contracting Officer (CO).

Contractors may request, in writing, approval to work other hours or weekends or may be directed to work other hours. Except for emergencies, the COR should receive such requests two weeks before the scheduled work. When possible, Contractors will submit emergency requests at least two business days before the scheduled work.

1.0.1 General - Project includes the following:

• Install new doors per plan, verify and coordinate prior to ordering.

• Install wall mounted or remote door actuators as needed.

• Provide power to the wall or remote mounted actuators and Automatic Door

Opener (ADO) system as needed

• Repair ceiling, floor systems and base molding to match existing as needed.

• Perform all work in accordance with specs and drawings.

Door Number Door Location Identifier

1 E101A-71

2 C115-1

3 E105-81

4 E100-57

5 E100-1AC

6 E148D-1AC OUTER

7 E148D-1AC INNER

8 E101-1AC DOCK

1.1 Construction Period of Performance: Contractor will be provided a 30 day limited notice to proceed after pre-construction kick-off meeting for material submittals and ordering period. The Notice to Proceed will be issued after all materials have been delivered for build out. Build out time is expected to last 90 consecutive days.

1.1.1 Project Management: This project will require a high level of coordination with VA staff and regularly scheduled project meetings will be required to facilitate communications for this project.

1.1.2 Construction Inspection: The Contractor will develop and implement a Quality

Assurance/Quality Control Plan that includes project inspection for the duration of the construction period of the project in accordance with specifications.

1.1.3 Construction: The Contractor will provide all labor, materials and equipment for demolition and installation in construction project areas.

1.2 Life Safety: The Contractor will design interim life safety measures as part of the construction documents.

1.3 Contractor shall develop a “Submittal Register” based on the included specification sections. After submittals are reviewed for compliance, the Contractor shall log them in the submittal register. A copy of the submittal register will be returned with the submittals.

1.4 Project Management

1.4.1 Project meetings will be held on a weekly basis or more frequently as needed.

1.4.2 The contractor will plan, coordinate the project meetings, and take notes of the meeting to distribute to all stakeholders after the meeting.

1.4.3 VA meeting room facilities may be utilized for project meetings. The Contractor will coordinate with Facilities Management Service (Building 10) for use of VA facilities.

1.4.4 The Contractor will have an authorized representative on the project site at all times during construction. The authorized representative will have the authority to receive instruction from the Government and direct the actions of Contractor employees and all subcontractors.

1.4.5 The Contracting Officer Representative (COR) shall monitor technical aspects as outlined in the COR Delegation issued by the contracting officer (CO). The COR shall not change any terms and conditions of the contract. Any changes to work or additional work shall be made in writing by a Network Contracting Office 20 (NCO

20) CO

1.4.6 The COR Delegation shall be provided by the CO at or shortly after contract award.

1.5 References

The following criteria shall be used to develop the design (including but not limited to):

Technical Information Library http://www.cfm.va.gov/TIL/

Physical Security Design Manual for VA Mission

Critical Facilities PG-18-10

Master Construction Specifications PG-18-1

Design & Construction Procedures PG-18-3

CAD: National CAD Standard, VHA Application http://www.cfm.va.gov/TIL/

Guide and Standard Details PG-18-4

Equipment Guide List PG-18-5

Space Planning Criteria, and VA SEPS PG-18-9

Design Manuals PG-18-10

Design Guides PG-18-12

Accessibility and Barrier Free Design Guide PG-18-13

Room Finishes, Door, and Hardware Schedules PG-18-14

AE Design Submission Instructions PG-18-15, Volume B

Environmental compliance Manual PG-18-17

Hardware (Equipment) Symbols H-08-6

VAMC Approved Hardware Locking Standards H-08-6

Seismic Design Handbook H-18-8

Cultural Resource Management Procedures H-7545

Space Planning Criteria H-7610

(All related Chapters) http://www.cfm.va.gov/TIL/planning.asp

VA HVAC Design Criteria

VA Signage Standards M-00-2

VA Interior Finish Standards Mem. 138.13

Joint Commission Criteria

Applicable NFPA Codes, and VA Fire Safety Criteria

Sustainable Design & Energy Reduction Manual Latest Edition.

AFGE Master Agreement Latest Publication

International Electrical Testing Association Latest Edition

VA Handbook 0730/5 Security and Law Enforcement Latest Edition http://www.cfm.va.gov/TIL/planning.asp