Triennial Electrical Testing - Questions and Answers.docx

DOCX document 19 KB Posted

Attached to
H261--Triennial Electrical Testing Federal contract opportunity
Solicitation number
36C25926Q0605
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 19

About this file

This file is a Questions and Answers document providing clarifications to offerors regarding the Triennial Electrical Testing solicitation for the Rocky Mountain Regional VA Medical Center.

The Q&A document serves to address inquiries submitted by potential offerors prior to the revised quote submission deadline of 10:00 AM MT on July 24, 2026. This RFQ (solicitation number 36C25926Q0605) is issued by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 19 and seeks firm-fixed price quotes for triennial electrical testing services. The procurement is classified under NAICS code 541350 (Building Inspection Services) with an $11.5 million business size standard and is 100% set-aside for small businesses. Quotes must be submitted via email only to Noaa.Lanotte@va.gov with a 10MB file size limit. The original question submission deadline was 10:00 AM MT on July 13, 2026, with all official answers provided through solicitation amendments. The Government reserves the right to award based solely on initial quotes received and requires all RFQ sections to be completed, signed, and dated for consideration. The solicitation incorporates provisions and clauses effective through Federal Acquisition Circular 2026-01.

View the file

Other files for this federal contract opportunity

Other files attached to H261--Triennial Electrical Testing, newest first.
File Type Posted
36C25926Q0605 0002.docx DOCX document
Triennial Electrical Testing - Additional Questions and Answers 7-23-26.pdf.docx DOCX document
36C25926Q0605 0001.docx DOCX document
480V Cutoff.pdf PDF
Elect One Line 11x17_2024-04-29.pdf PDF
Statement of Work - Electrical Testing - 07-01-2026.docx DOCX document
Conduct Campuswide Electrical Coordination Study.pdf PDF
Department of Labor Wage Determination - 2015-5419 Rev 32 - 05-13-2026.pdf PDF
36C25926Q0605.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers

1. Voltage Level Can you confirm the voltage level for line item #0001, #0002, #0003, #0005, and #0006 in the pricing table?

Answer:

#0001 13,200V #0002 277/480V #0003 13,200V Line side to 277/480V load side #0005 13,200V to 277/480V #0006 13,200V to 277/480V X2 13,200V to 120/208V

2. Period of Performance Please confirm the required period of performance.

Answer:

The quoter should detail the anticipated timeline to perform the required services in their submission.

3. Applicable Testing Standards Please confirm whether all testing and services are to be performed in accordance with ANSI/NETA MTS and VHA Directive 1028.

Answer:

Yes ANSI/NETA MTS and VHA Directive 1028 are the minimum standard we are requesting.

4. Utility Coordination Please clarify whether utility coordination (including any required utility personnel or outage scheduling) is to be included in our scope, or if it will be handled by the facility/owner.

Answer:

Contractor is responsible for the coordination of utility outage

5. Thermographic Scanning Please confirm whether infrared (IR) thermographic scanning is required as part of this solicitation.

Answer:

All the electrical vaults and the 2 utility connections are required to be IR scanned

6. ATS/MTS Testing Requirement (SOW pg. 2/11) Please clarify whether the required LOAD TEST of the transfer switch (ATS/MTS) is intended to be: A real load transfer test using facility load, or a load bank test requiring supplemental equipment.

Answer:

A real load transfer test using facility load.

7. Low Voltage Circuit Breaker Testing (SOW pg. 4/11) Per VHA Directive 1028, low-voltage circuit breakers rated 225A and above typically require primary current injection testing. Please confirm whether primary current injection testing is required, or secondary injection testing is acceptable for this project scope.

Answer:

Primary current injection testing is required on All 480V breakers.

8. Previous Bid Information Could you please provide the name, year, awarded value, and awarded contractor for the most recent bid performed at this site? Additionally, please confirm whether the scope of work for that contract is identical to the scope for the current 2026 bid.

Answer:

Prior contract #36C25920P1001. Requested information can be found on SAM.gov. The scope of this requirement is similar in nature.

9. Protective Relay Calibration Study (PRCS) Can DVA confirm whether the Protective Relay Calibration Study (PRCS) refers to a coordination study?

Answer:

Do not need a Protective Relay Calibration Study. We need a review of calibration study’s recommended relay settings and current relay settings and have them changed if different, with approval.

10. Line Item 0010 – Metering and Instrumentation:

The line item lists a total of 107 devices comprising meters, current transformers (CTs), and potential transformers (PTs); please specify the quantity of each device type.

Answer:

Meters31 in substations, 67 in ATS
PT10 in PSG/ATO, 31 Substations
CTs67 sets from ATS, 31 sets from Substations

11. Electrical Vault:

In the Statement of Work, section 3.5.1 - Inspection of electrical vaults requires the inspection of electrical vaults. Please specify the quantity.

Answer:

40 different vaults.

12. Protective Relay Calibration Study Can the VA confirm what do you mean by Protective Relay Calibration Study? Do you refer to Arc Flash Study and Coordination study or else? If so, do they have a previous SKM model available or a PDF of the actual report?

Answer:

Do not need a Protective Relay Calibration Study. We want a review of our current relay setting compared to our last Protective Relay Calibration recommended settings. If there is a difference change them to the last Protective Relay Calibration recommended settings with VA approval.

13. BOM clarification In case the provided equipment quantity in pricing table do not match the SLD and 480V Cut off document. What should the contractor prioritize?

Answer:

The contractor should prioritize the provided equipment quantity pricing table.

14. Relay quantity Can the VA provide a list of the relay types and quantities that are required to be tested?

Answer:

MV relays

GE G60 Relays5 in ATO
GE Multilin 350 relay81 throughout the campus
GE Multilin 750 relay2 in ATO
GE Multilin MIB relay42 in PSG & 2 in ATO
Eaton Digitrip 3000 relays4 in Building A (CBS)

15. Dry Transformer Are all the dry type substation transformers rate 1500kVA? Could you provide nameplate ratings for the oil-filled type transformers?

Answer:

Dry Type:

Range is 1500VA to 2500VA

Olid filled:

2X 300VA 13.2 KV to 480Y/277V 150VA 13.8 KV to 12/208V