This is a Division 01 General Requirements specification document outlining quality control, inspection, and commissioning procedures for a construction project. The document establishes mandatory inspection protocols across multiple construction phases and systems, including quality control testing, safety requirements, environmental compliance, waste management, and commissioning activities. Key inspection requirements include punch-out inspections with contractor QC and correction verification, pre-final and final acceptance inspections by government representatives, special third-party code-required inspections, and daily egress and fire safety inspections with weekly reporting. Additional requirements mandate monthly crane and lifting equipment inspections with documented submittals, daily environmental compliance inspections with logs and corrective actions, post-storm inspections of sediment basins and erosion controls, daily waste management inspections, periodic sustainability inspections reviewed during job conferences, and installation inspections during the commissioning phase including pre-functional and warranty phase inspections.
The specification also requires commissioning of fire suppression systems with continuous installation inspections, pre-functional checklists, witnessed functional performance testing, and O&M staff training. Site utility work specifications mandate hydrostatic pressure testing prior to concealment, sterilization inspections with post-test disinfection verification, as-built inspection documentation before final acceptance, geotechnical inspections during continuous excavation, subgrade and compaction testing per ASTM standards, concrete curing verification (minimum 7-day), proof-rolling and compaction inspections for asphalt paving with course-by-course approval, post-installation pavement marking inspection with COR approval, water utility inspections including hydrostatic pressure testing at 1.5 working pressure, video inspection of entire pipelines, and disinfection verification through chlorination. All inspections require documentation and Resident Engineer or COR approval as applicable.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Att 9 EOVAHCS ICRA Utility Line replacement.pdf | ||
| 36C25925R0112 0004.docx | DOCX document | |
| Att 7 PreBid Construction Sign In Sheet.pdf | ||
| Att 6 Site Visit Meeting Doc Muskogee.pdf | ||
| Att 5 12424 Details-REV12.18.2025.pdf | ||
| Att 8 Geotechnical Subsurface Investigation.pdf | ||
| 36C25925R0112 0003.docx | DOCX document | |
| 36C25925R0112 0002.docx | DOCX document | |
| 36C25925R0112 0001.docx | DOCX document | |
| Att 3 Past Performance Questionnaire_Blank.docx | DOCX document | |
| Att 1 Drawings CS001 - Replace Exterior Utility Lines.pdf | ||
| 36C25925R0112.docx | DOCX document | |
| Att 4 VAAR 852.219 75 Limitation On Subcontracting Certification.docx | DOCX document | |
| Att 2 Specs 00 01 10 General Requirements Submitted.pdf |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DIVISION 01 – GENERAL REQUIREMENTS
01 45 00 – Quality Control
1. Construction inspections & testing
0. Tests, inspections, operational checks, documentation
0. PART 3 – Tests
1. Punch-out inspection
1. Contractor QC inspection + correction verification
1. PART 3 – Completion Inspection
1. Pre-final inspection
2. Government inspection prior to acceptance
2. PART 3 – Pre-Final Inspection
1. Final acceptance inspection
3. Required for project closeout
3. PART 3 – Final Acceptance Inspection
1. Special inspections
4. Code-required third-party inspections
4. PART 3 – Special Inspections
01 35 26 – Safety Requirements
1. Daily egress inspections
0. Daily inspection, weekly reporting
0. Fire Safety – Egress Routes
1. Weekly fire safety inspections
1. Entire work area
1. Fire Safety – Hazard Prevention
1. Monthly crane / LHE inspections
2. Documented inspections
2. Submittals – LHE Reports
01 57 19 – Temporary Environmental Controls
1. Daily environmental compliance inspections
0. Logs + corrective actions
0. Quality Control
1. Post-storm inspections
1. Sediment basins, erosion controls
1. Protection of Resources
1. Environmental monitoring
2. Air, water, noise per monitoring plan
2. Submittals
01 74 19 – Construction Waste Management
1. Pre-work site assessment
0. Waste stream evaluation
0. Quality Assurance
1. Daily waste management inspections
1. Ongoing monitoring & documentation
1. Quality Assurance
01 81 13 – Sustainable Construction
1. Periodic sustainability inspections
0. Reviewed during job conferences
0. Quality Assurance
01 91 00 – General Commissioning
1. Installation inspections
0. System accessibility & compliance
0. Commissioning Description
1. Site observation visits
1. CxA inspections during construction
1. Definitions
1. Pre-functional inspections
2. Before functional testing
2. Definitions
1. Warranty phase inspections
3. Post-occupancy inspections
3. Definitions
1. Maintenance documentation
4. O&M manuals incl. inspection & PM procedures
4. Training & Documentation
DIVISION 02–33 – SITE & UTILITIES
02 41 00 – Demolition
1. Pre-demolition site survey
0. Inspection of existing conditions
0. Part 1 – Protection
1. Daily safety & protection inspections
1. Barricades, fencing, fire protection
1. Part 1 – Protection
1. Post-demolition cleanup inspection
2. Resident Engineer approval
2. Part 3 – Cleanup
21 08 00 – Commissioning of Fire Suppression Systems
1. Construction inspections
0. Continuous inspection during installation
0. Part 3 – Construction Inspections
1. Pre-functional inspections
1. Checklist-based verification
1. Part 3 – Pre-Functional Checklists
1. Functional performance testing
2. Witnessed testing
2. Part 3 – Systems Functional Performance Testing
1. Maintenance training
3. O&M staff training
3. Part 3 – Training
22 11 00 – Facility Water Distribution
1. Hydrostatic inspections
0. Pressure testing prior to concealment
0. Part 3 – Tests
1. Sterilization inspections
1. Post-test disinfection verification
1. Part 3 – Sterilization
1. As-built inspection documentation
2. Required before final acceptance
2. As-Built Documentation
1. Maintenance documentation
3. O&M manuals with inspection procedures
3. Submittals
31 20 00 – Earthwork
1. Geotechnical inspections
0. Continuous excavation inspections by Geotech
0. Part 3 – Excavation
1. Subgrade inspections
1. Approval before placement of work
1. Part 3 – Excavation Drainage
1. Compaction testing
2. Density testing per ASTM
2. Part 3 – Filling and Backfilling
32 05 23 – Cement & Concrete for Exterior Improvements
1. Pre-installation inspections
0. Subgrade & forms verification
0. Execution – Preparation
1. Field testing
1. Concrete, subbase testing
1. Quality Assurance
1. Curing inspections
2. Minimum 7-day curing verification
2. Concrete Curing
32 12 16 – Asphalt Paving
1. Plant & equipment inspections
0. Resident Engineer access
0. Section 1.3
1. Proof-rolling inspections
1. Subgrade verification
1. Part 3 – Subgrade
1. Rolling & compaction inspections
2. Course-by-course approval
2. Part 3 – Execution
32 17 23 – Pavement Markings
1. Surface inspection prior to marking
0. COR approval required
0. Preparation
1. Post-installation inspection
1. Alignment, thickness, coverage
1. Paint Application
1. Maintenance / repair
2. Replace deficient markings
2. Protection & Cleaning
33 08 00 – Commissioning of Site Utility Systems
1. Construction inspections
0. Continuous site utility inspections
0. Part 3 – Construction Inspections
1. Pre-functional inspections
1. Checklist verification
1. Part 3 – Pre-Functional Checklists
1. Functional testing
2. Witnessed testing
2. Part 3 – Systems Functional Performance Testing
1. Maintenance training
3. Owner O&M staff
3. Part 3 – Training
33 10 00 – Water Utilities
1. Hydrostatic pressure inspections
0. 1.5× working pressure
0. Field Quality Control
1. Video inspection
1. Entire pipeline prior to acceptance
1. Field Quality Control
1. Disinfection inspection
2. Chlorination verification
2. Execution – Disinfection
1. Maintenance access inspections
3. Backflow preventers, valves, hydrants
3. Execution – Backflow Preventers