This is a Standard Form 30 Amendment to Solicitation and accompanying contractor Q&As for a federal construction project. The amendment extends the proposal due date from January 21, 2026 to January 29, 2026 at 12:00 AM CST and posts critical project documentation including geotechnical investigation data, detailed construction drawings, site visit records, ICRA (Infection Control Risk Assessment) requirements, and general requirements specifications. Proposals must be submitted via email to contract specialist Jesus A. Villegas at jesus.villegas@va.gov. The solicitation number is 36C25925R0112, issued by the Department of Veterans Affairs Network Contracting Office 19 (Rocky Mountain Acquisition Center) in Greenwood Village, Colorado, for the VAMC Muskogee Replace Exterior Utility Lines Project (623-24-101).

The project requires full construction services for replacement of exterior utility lines at the Jack C. Montgomery Veterans Affairs Medical Center in Muskogee, Oklahoma, with a base period of performance from March 2, 2026 to September 27, 2028 (940 days from Notice to Proceed). The principal NAICS code is 237110 (Water and Sewer Line and Related Structures Construction). The work includes removing and replacing all exterior site water lines, creating separate fire protection and domestic water loops to prevent Legionella contamination, installing new fire hydrants, removing/decommissioning replaced lines with abatement as necessary, and phasing installation to maintain operational water service. Contractors must be properly licensed and bonded for general contracting work in Oklahoma. The Q&As address critical technical issues including rock excavation methods (blasting prohibited; sawing and hammering with dust control allowed), steel casing specifications, utility conflict resolution procedures, asbestos handling protocols, confined space permits, fire watch requirements, badging timelines (supervisors approximately 3 months, workers approximately 1.5 months), and pressure/bacteria testing parameters, with contractors responsible for third-party ground-penetrating radar utility location services, all permits, and fire watch personnel.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

36C25925R0112 0004

5. PROJECT NUMBER (if applicable)

CODE

7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer) 623-24-101 36C259 Department of Veterans Affairs Network Contracting Office

NCO 19

6162 South Willow Drive, Suite 300 Greenwood Village CO 80111 36C259 Department of Veterans Affairs Network Contracting Office

NCO 19

6162 South Willow Drive, Suite 300 Greenwood Village CO 80111 To all Offerors/Bidders

36C25925R0112 10-31-2025

X X X ** HOUR & DATE for Receipt of Offers is EXTENDED to: 01-29-2026 12:00AM CST See CONTINUATION Page VAMC Muskogee Replace Exterior Utility Lines Project 623-24-101

Block 14 continuation on page 2.

CONTINUATION PAGE

AN AMENDMENT TO SOLICITATION 36C25925R0112 POSTED ON January 21, 2026.

The purpose of this amendment is as follows:

A) Post the RFI questions and answers.

B) Post Att 5 12424 Details-REV12.18.2025.

C) Post Att 6 Site Visit and Att 7 Site Visit Attendance document.

D) Post Att 8 Geotechnical Subsurface Investigation E) Post Att 9 EOVAHCS ICRA Utility Line replacement F) Post Att 10 DIVISION 01 – GENERAL REQUIREMENTS G) Extend the proposal due date from 01-21-2026 to 01-29-2026 at 12:00AM CST.

H) Proposals need to be submitted via email to contract specialist, Jesus A. Villegas at jesus.villegas@va.gov.

All other Terms and Conditions remain the same.

DEPARTMENT OF VETERANS AFFAIRS

VHA Network Contracting Office 19 Rocky Mountain Acquisition Center 6162 South Willow Drive, Suite 300 Greenwood Village, CO 80111

CONTRACTOR Q&As

VAMC Muskogee Replace Exterior Utility Lines Project 623-24-101

Question No.1: Are there any geotechnical borings for this project, or any historical data that the government can provide to help determine underground conditions, specifically potential rock formations?

Answer No. 1: Yes, See Attachment 8 Geotechnical Subsurface Investigation.

Question No. 2: Did the Government estimate contemplate or include any rock excavation or removal?

Answer No. 2: No

Question No. 3: If rock is encountered, what would be the acceptable method of removal given the close proximity to the hospital? Will blasting be allowed?

Answer No. 3: Blasting will not be allowed. Sawing, hammering will be allowed as long as dust is controlled.

Question No. 4: If blasting is not allowed, will hammering and drilling be the acceptable method?

Answer No. 4: See response to question 3.

Question No. 5: Existing utility and structural conflicts: Are there any additional existing utility or structural as-built plans available that the government can provide?

Answer No. 5: Yes, see Attachment 8 Geotechnical Subsurface Investigation

Question No. 6: With the inevitable utility and structural conflicts, in line and grade, would the contractor be allowed to change the alignment of the proposed lines as-needed and submit final as-builts based on those adjustments?

Answer No. 6: Within reason and if the engineer on file approves, this would be seen as unforeseen conditions and will be answered as necessary.

Question No 7: As it relates to the existing retaining walls and the need to install steel casing underneath, are there any as built or structural drawings that the government can provide to help the contractor to determine depths and thickness of existing footers?

Answer No. 7: Provided, see Attachment 8 Geotechnical Subsurface Investigation

Question No. 8: For the connections at approximately 15+10, 15+25, and 16+10 shown on pages CU009 and CU010, will the government provide a profile detail and restraint details for these connections? The contractor is concerned about the pipe routing and restraint requirements. For instance, at 15+10 there is roughly 20’ of space from the existing retaining wall to the hydrant connection. The steel casing detail states that the casing must extend 7.5’ minimum past the retaining wall – leaving only 13 LF to come from a depth of +/- 30’ to the depth of the hydrant connection at +/- 6’.

Answer No. 8: In this unique scenario, an alternative could be at 15+10 to use a combination of a hydrant riser with 90° vertical bends to ensure the vertical distance is met. At 16+10, use 90° bends. The restraint table indications for 90° bends will need to be used.

Question No. 9: On sheet CU011 near the existing meter station, there is an indication that another steel casing should be installed on the new proposed 8” DIP waterline, heading North-West away from the meter station. There is a second retaining wall roughly 8’ to the South of the retaining wall we are being directed to install a casing under, with only 3’ of space available from the proposed 45 Bend to the North retaining wall. There does not appear to be enough space to install a steel casing as shown in detail 7 of CU018, especially without being given retaining wall and footer depths. How should the contractor price this work?

Answer No. 9: As an alternative, contractor may provide a minimum of 36" of clearance under these shallow walls. This alternative does not apply to the larger retaining walls on the west.

Question No. 10: Is there a required steel casing size for use on this project? The detail provided on Sheet CU018, Detail 8, does not indicate spacing between carrier pipe and the casing.

Answer No. 10: After coordination with the manufacturer, they no longer supply this product. See updated plans on Att 5 12424 Details-REV12.18.2025, which indicate casing size and skid height based on carrier size.

Question No. 11: On sheet CU011 There are notes pointing to “Bid Alternative #1 Replace Meter Station”. There is only one bid item for this solicitation. Please confirm whether this work should be priced as part of this solicitation.

Answer No. 11: Please include the Replace Meter Station in the base line item pricing. No alternate pricing is called for in this solicitation.

Question No. 12: The Solicitation mentions possible abatement. Is there any record of potential asbestos or other contaminants that the government can provide?

Answer No. 12: We are not aware of known areas that require abatement. However, if encountered the awardee will need to include plan for safe containment in the safety plan. Any potential hazardous materials will need to be tested and then a modification for required containment, remediation or abatement will be issued.

Question No. 13: There is no ductile iron pipe thickness class called out in the specifications. Please indicate which class of DIP is required.

Answer No. 13: See specs: 22 11 00 - 7

Question No.14: Are there any details for proposed thrust blocking required on the newly installed lines, including size and concrete PSI?

Answer No. 14: Thrust blocks are not permitted unless COR approves. The VA has migrated to pipe restraints. Refer to detail 13 on CU019 on Att 5 12424 Details-REV12.18.2025 provided.

Question No. 15: The Improved Areas or Lawns detail on CU018 shows a 6” thick topsoil requirement to the side but also seems to indicate a 12” typical thickness on the same detail. Please confirm which is correct.

Answer No. 15: See updated detail with distance corrected. The answer is 6". The 12" distance refers to the depth of the identification tape on Att 5 12424 Details-REV12.18.2025.

Question No. 16: Please provide a seeding specification for restoration in greenspace areas.

Answer No. 16: Match existing or submit local seed mix for COR approval

Question No. 17: Will the government provide the required pressure testing and bacteria testing parameters for both the domestic and firewater lines?

Answer No. 17: Please see Attachment 8 Geotechnical Subsurface Investigation, specs, section 22 11 00 page 12.

Question No. 18: Is the contractor responsible to perform 3rd party ground penetrating radar utility location services?

Answer No. 18: Yes and maintain the markings.

Question No. 19: For the 4” and 6” Fire service lines crossing Honor Heights Drive, is the intent for these lines to be open-cut or directionally drilled?

Answer No. 19: We had planned on open cut but a city ROW permit may require otherwise. Coordinate with City to ensure their requirements are met within city ROW. Contractor is responsible for all permits. This will be determined by the contractor.

Question No. 20: For sheets CU105 and CU021, on Sheet CU021 it is indicated that the existing valve vault at the water tower is 26’ deep. The profile view on CU105 indicates that the “tank” is 8’ deep from existing topography. Which is correct?

Answer No. 20: See updated Att 5 12424 Details-REV12.18.2025. The vault is roughly 6' deep. Contractor to verify. The 26' dimension has been removed as the "2" was never removed.

Question No. 21: On Sheet CU105, for the profile of the new 16” connection at the water tower, the profile shows us connecting to the outside of the “tank”. Please clarify that we are connecting to an existing 10” pipe with a 16” x 10” reducer, and no work is to be done within the holding tank.

Answer No. 21: Confirmed no work is done with the tank itself. Exact demarcation (limit of work) is shown on the connection to tank detail on CU015 with solid lines for all new work and existing is dashed to remain.

Question No. 22: Has the internal government estimate been updated recently, or does the government have additional funds for this project? Preliminarily, we do not see any way that this project can be built for under $6,000,000.

Answer No. 22: Contractors are encouraged to propose best price. Pricing will be evaluated after the solicitation closes according to the instructions to offerors. At this time our construction magnitude remains unchanged.

Question No. 23: Would the government consider abandoning the existing waterline pipe with flow fill instead of removing the pipe completely? This would allow for the entire system to be kept active while installing the new pipe but would also lower demo and restoration costs of removing that pipe.

Answer No. 23: VA standards require that abandoned utilities be removed; however, the COR may allow an exception if an acceptable justification is provided. If this is accepted, the contractor would be responsible for completely removing the defunct existing pipeline facilities where conflicts arise.

Question No. 24: On CI101 – Suggested Phasing – Line 1.3 The contractor is instructed to verify that the pumps can operate as a pressure sustaining system and be throttled up or down as necessary. What are the desired pressures that the contractor should adhere to?

Answer No. 24: Maintain operating pressures on the campus. Contractor to use existing pressure reading locations to ensure continuity. Refer to Att 5 12424 Details-REV12.18.2025.

Question No. 25: Can the VA provide an asbestos report for this project and the existing waterlines?

Answer No. 25: No asbestos report is available according to our records. Reference response to question 12.

Question No. 26: Should we assume all abandoned pipes contain asbestos?

Answer No. 26: No, asbestos is not expected in the abandoned pipes; however, its presence cannot be completely ruled out. Appropriate precautions should be taken if handling or disturbing the pipes. Reference response to question 12.

Question No. 27: Will space be available on campus for a job trailer and material storage?

Answer No. 27: No, there will not be available space.

Question No. 28: May the Superintendent also serve as the Quality Control Manager (QCM)?

Answer No. 28: As long as the Super meets the QCM requirements as well.

Question No. 29: May the Superintendent serve simultaneously as the SSHO and the QCM?

Answer No. 29: As long as the Super meets the QCM and SSHO requirements as well.

Question No. 30: Is this project tax-exempt?

Answer No. 30: Federal agencies are tax exempt; however, Oklahoma does not allow the transfer of the exempt status to contractors at this time.

Question No. 31: Is this project currently funded?

Answer No. 31: Yes, the project is funded.

Question No. 32: How long may the fire line remain out of service before a fire watch is required?

Answer No. 32: An ILSM is required for the line to be out service, 8 hours is its limit.

Question No. 33: If the fire line outage affects multiple floors, is more than one person required for fire watch duties?

Answer No. 33: Yes.

Question No. 34: Can the VA provide fire watch personnel, or is this the responsibility of the general contractor?

Answer No. 34: No, this will be the responsibility of the contractor.

Question No. 35: Can the VA provide more detail on the one-year maintenance and inspection requirements? How frequently are inspections required, and what specific items must be inspected each time?

Answer No. 35: Please see Att 10 DIVISION 01 – GENERAL REQUIREMENTS.

Question No. 36: Will any areas of the project require confined space permits?

Answer No. 36: There is one known area that will require a confined space permit.

Question No. 37: Can the VA provide ICRA requirements for the rooms we must access to complete water tie-ins?

Answer No. 37: Provided. Refer to Att 9 EOVAHCS ICRA Utility Line replacement.

Question No. 38: How long should we anticipate the badging process to take, and what documentation is required?

Answer No. 38: Supervisors have been taking about 3 months; workers have been taking about 1.5 months once all paperwork was filled out and submitted. That is assuming that the workers have submitted everything needed the first time. We have only been able to find success on fingerprints when taken at a VA. These times were before the shutdown; I have yet to send someone though after it.

Question No. 39: Will any fire alarm system work be required when tying into the fire lines?

Answer No. 39: No, not currently envisioned.

Question No. 40: Are geotechnical borings available for this project, or can the government provide historical data regarding underground conditions—specifically potential rock formations?

Answer No. 40: Please see Attachment 8 Geotechnical Subsurface Investigation.

Question No. 41: Did the Government’s estimate include allowances for rock excavation or removal?

Answer No. 41: No rock excavation or removal is anticipated for this project.

Question No. 42: If rock is encountered, what removal methods will be permitted given the proximity to the hospital? Will blasting be allowed?

Answer No. 42: Refer to response for question 3.

Question No. 43: If blasting is prohibited, will hammering or drilling be acceptable alternatives?

Answer No. 43: Refer to response for question 3.

Question No. 44: Are additional existing utility or structural as-built drawings available that the Government can provide?

Answer No. 44: Provided, see Att 8 Geotechnical Subsurface Investigation.

Question No. 45: If unforeseen utility or structural conflicts occur, will the contractor be permitted to adjust the proposed utility alignment as needed and submit final as-builts reflecting the modifications?

Answer No. 45: Within reason and if the engineer on file approves.

Question No. 46: Regarding the existing retaining walls and the need to install steel casing beneath them, can the Government provide as built or structural drawings to determine footer depths and thickness?

Answer No. 46: No as built or structural drawings of the retaining walls are available according to our knowledge.

Question No. 47: For the connections at approximately stations 15+10, 15+25, and 16+10 (Sheets CU009 and CU010), will the Government provide a profile and restraint details? The contractor is concerned about line routing and restraint requirements—for example, at 15+10 there is roughly 20 feet between the retaining wall and the hydrant, but the casing must extend 7.5 feet beyond the wall, leaving only 13 feet to transition from approximately 30 feet deep to about 6 feet at the hydrant.

Answer No. 47: See response to question 8.

Question No. 48: Is there a specified steel casing size for this project? Detail 8 on Sheet CU018 does not indicate required spacing between the carrier pipe and the casing.

Answer No. 48: See Attachment 8 Geotechnical Subsurface Investigation. See specs: 22 11 00 – 7.

Question No. 49: On Sheet CU011, notes reference “Bid Alternative #1 Replace Meter Station,” but only one bid item exists in the solicitation. Please confirm whether this work is included in the base solicitation.

Answer No. 49: Yes, it is included. Reference response to question 11.

Question No. 50: The solicitation mentions possible abatement. Is there any documentation on potential asbestos or other contaminants that the Government can provide?

Answer No. 50: No documentation is available according to our records. Reference response to question 12.

Question No. 51: The specifications do not identify the required ductile iron pipe thickness class. Please clarify which DIP class is required.

Answer No. 51: Specs: 22 11 00 – 7

Question No. 52: Are there details for required thrust blocking on the new lines, including block size and concrete PSI?

Answer No. 52: See specs, section 33 10 00 page 19

Question No. 53: The “Improved Areas or Lawns” detail on CU018 indicates 6 inches of topsoil on the side but also shows a typical 12-inch thickness. Please confirm the correct requirement.

Answer No. 53: See response to question 15.

Question No. 54: Please provide seeding specifications for green-space restoration.

Answer No. 54: See response to question 16.

Question No. 55: Will the Government provide pressure-testing and bacteria-testing parameters for both domestic water and firewater lines?

Answer No. 55: See Attachment 8 Geotechnical Subsurface Investigation Specs: 22 11 00.

Question No. 56: Is the contractor responsible for hiring third-party ground-penetrating radar services for utility locating?

Answer No. 56: Yes, the contractor is required.

Question No. 57: For the 4-inch and 6-inch fire service lines crossing Honor Heights Drive, is the intent to open-cut or directionally drill these crossings?

Answer No. 57: We had planned on open cut but a city ROW permit may require otherwise. Coordinate with City to ensure their requirements are met within city ROW. Contractor is responsible for all permits. This will be determined by the contractor.

Question No. 58: Sheets CU105 and CU021 show conflicting depths for the existing valve vault at the water tower. CU021 indicates a 26-foot depth, while CU105 shows approximately 8 feet. Which is correct?

Answer No. 58: See response to question 20.

Question No. 59: On CU105, the profile for the new 16-inch connection at the water tower shows a connection to the exterior of the “tank.” Please confirm that we are connecting to an existing 10-inch pipe using a 16"×10" reducer, with no work occurring inside the holding tank.

Answer No. 59: See response to question 21.

Question No. 60: Are cathodic protection measures required for this project?

Answer No. 60: Specs 01 91 00 – 19 Please see Attachment 8 Geotechnical Subsurface Investigation.

Question No. 61: Near the VA entrance, what excavation safety measures does the VA require? Is orange safety fencing acceptable? Will the VA provide signage to inform staff and patients about entrance closures and detours during construction?

Answer No. 61: Refer to Spec 01 35 26 on Att 5.

Question No. 62: Can the VA provide contact information for submitting the SWPPP permit for Muskogee?

Answer No. 62: It can be submitted through the provided link. https://www.muskogeeok.gov/departments/public_works/stormwater_management.php

Question No. 63: What type of soil conditions are expected on-site?

Answer No. 63: Type B and Type C

Question No. 64: Are there significant amounts of rock, sandstone, or other hard material to excavate?

Answer No. 64: Provided site survey. Please see Attachment 8 Geotechnical Subsurface Investigation.

Question No. 65: Are there existing utility lines within the proposed work area, and if so, approximately how many?

Answer No. 65: 6, Steam, City water, Site Water, sewer X 4, internet X 2, diesel. 14.4KV electric

Question No. 66: Is the project area generally flat or does it include hilly or uneven terrain?

Answer No. 66: This VA is on top of a hill.

Question No. 67: Is the work area open, or are there trees, structures, or other obstacles that will require removal prior to excavation?

Answer No. 67: There are obstacles everywhere that will have to be worked around.

Question No. 68: What are the required trench dimensions (length, width, and depth)?

Answer No. 68: See Specs: 31 20 00

Question No. 69: Are there any specific digging or shoring requirements we should anticipate?

Answer No. 69: See Attachment 8 Geotechnical Subsurface Investigation. Specs: 31 20 00

A.1 PRICE/COST SCHEDULE

ITEM INFORMATION

ITEM NUMBER
DESCRIPTION OF SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
1.00
JB
__________________
__________________

Full construction services for the replacement of the exterior utility line under Project: 623-24-101

Contract Period: Base POP Begin: 03-02-2026 POP End: 09-27-2028 PRINCIPAL NAICS CODE: 237110 - Water and Sewer Line and Related Structures Construction PRODUCT/SERVICE CODE: Z1DA - Maintenance of Hospitals and Infirmaries PoP is 940 days from the NTP.

All dates are estimated dates. Actual performance dates are based on NTP.

GRAND TOTAL
__________________

A.2 List of Attachments See attached document: Att 5 12424 Details-REV12.18.2025.

See attached document: Att 6 Site Visit Meeting Doc Muskogee.

See attached document: Att 7 PreBid Construction Sign In Sheet.

See attached document: Att 8 Geotechnical Subsurface Investigation.

See attached document: Att 9 EOVAHCS ICRA Utility Line replacement.

See attached document: Att 10 DIVISION 01 _ GENERAL REQUIREMENTS.