36C25919R0113-0006001.pdf

PDF 18 KB Posted

Attached to
Demolish and remodel hazardous drug compounding area (VA-19-00046876)
Solicitation number
36C25919R0113
Issued by

About this file

36C25919R0113 0006 000110 TOC 201810.pdf

View the file

Other files

File Type Posted
36C25919R0113-0006002.pdf PDF
36C25919R0113-0006003.pdf PDF
36C25919R0113-0006004.pdf PDF
36C25919R0113-0006000.docx DOCX document
36C25919R0113-0005000.docx DOCX document
36C25919R0113-0004000.docx DOCX document
36C25919R0113-0003000.docx DOCX document
36C25919R0113-0002001.pdf PDF
36C25919R0113-0002000.docx DOCX document
36C25919R0113-0001002.pdf PDF
36C25919R0113-0001000.docx DOCX document
36C25919R0113-0001001.pdf PDF
36C25919R0113-002.pdf PDF
36C25919R0113-003.pdf PDF
36C25919R0113-004.docx DOCX document
36C25919R0113-001.docx DOCX document
36C25919R0113-005.docx DOCX document
36C25919R0113-000.docx DOCX document
Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Grand Junction VAMC May 30, 2019 Upgrade Hazardous Drug Workspace Addendum 1 Grand Junction, CO Project No. 575-18-110

00 01 10-1

DEPARTMENT OF VETERANS AFFAIRS

GRAND JUNCTION VA PHARMACY UPGRADES

TABLE OF CONTENTS

Section 00 01 10

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 General Requirements 10-17 01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build 04-13 01 33 23 Shop Drawings, Product Data, and Samples 05-17 01 35 26 Safety Requirements 02-17 01 42 19 Reference Standards 05-16 01 45 00 Quality Control 01-18 01 45 35 Special Inspections 04-18 01 81 13 Sustainable Construction Requirements 10-17

DIVISION 02 – EXISTING CONDITIONS

02 41 00 Demolition 08-17

DIVISION 05 – METALS

05 50 00 Metal Fabrications 08-18

DIVISION 06 – WOOD,PLASTICS AND COMPOSITES

06 20 00 Finish Carpentry 08-16

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 84 00 Firestopping 02-16 07 92 00 Joint Sealants 10-17

DIVISION 08 - OPENINGS

08 31 13 Access Doors and Frames 08 42 29 Sliding Cleanroom Doors 08 80 00 Glazing 10-15 08 90 00 Louvers and Vents 05-15

DIVISION 09 – FINISHES

09 05 16 Subsurface Preparation for Floor Finishes 02-15 09 06 00 Schedule for Finishes 04-15 09 22 16 Non-Structural Metal Framing 06-18 09 29 00 Gypsum Board 06-18 09 51 00 Acoustical Ceilings 12-16 09 65 13 Resilient Base and Accessories 02-16 09 65 16 Resilient Sheet Flooring 05-18

00 01 10-2

09 91 00 Painting 01-16 09 96 59 High-Build Glazed Coatings 07-14

DIVISION 11 – EQUIPMENT

11 40 12 Custom Fabricated Stainless Steel Cleanroom Counters 11 53 54 HEPA Filtered Interlock Doors Pass-Throughs

DIVISION 12 – FURNISHINGS

12 36 00 Countertops 12-15

DIVISION 21 – FIRE PROTECTION

21 13 13 Wet-Pipe Sprinkler Systems 06-15

DIVISION 22 – PLUMBING

22 05 11 Common Work Results for Plumbing 07-16 22 07 11 Plumbing Insulation 09-15 22 11 00 Facility Water Distribution 09-15 22 13 00 Facility Sanitary and Vent Piping 09-15 22 40 00 Plumbing Fixtures 09-15

DIVISION 23 – HEATING, VENTILATING, AND AIR

CONDITIONING (HVAC)

23 05 11 Common Work Results for HVAC 08-17 23 05 41 Noise and Vibration Control for HVAC Piping and

Equipment 02-15

23 05 93 Testing, Adjusting, and Balancing for HVAC 02-15 23 07 11 HVAC and Boiler Plant Insulation 23 09 23 Direct-Digital Control System for HVAC 09-11 23 21 13 Hydronic Piping 08-17 23 31 00 HVAC Ducts and Casings 03-13 23 36 00 Air Terminal Units 02-15 23 37 00 Air Outlets and Inlets 02-15 23 40 00 HVAC Air Cleaning Devices 02-12 23 82 16 Air Coils 04-11

DIVISION 26 – ELECTRICAL

26 05 11 Requirements for Electrical Installations 01-16 26 05 19 Low-Voltage Electrical Power Conductors and Cables 01-17 26 05 26 Grounding and Bonding for Electrical Systems 01-17 26 05 33 Raceway and Boxes for Electrical Systems 01-18 26 05 73 Overcurrent Protective Device Coordination Study 01-18 26 09 23 Lighting Controls 01-18 26 24 16 Panelboards 01-18 26 27 26 Wiring Devices 01-18

00 01 10-3

26 29 21 Enclosed Switches and Circuit Breakers 01-17 26 51 00 Interior Lighting 01-18

DIVISION 27 – COMMUNICATIONS

27 15 00 Communications Structured Cabling 01-16

File details come from the government source that posted it.