ATTACH 190 - Clarification Log - 36C25821B0007 20210420.docx
DOCX document 70 KB Posted
- Solicitation number
- 36C25821B0007
About this file
This document contains a clarification log and specifications for a federal construction contract opportunity to convert Building 126 at the Long Beach VA Health Care System to single patient rooms. The project will include upgrading all architectural finishes, as well as structural, mechanical, plumbing, material and fixture, medical gas, electrical, and low voltage systems. The clarification log addresses questions from contractors regarding specifications for interior and exterior special functioning glazing. It also revises specification section 01 00 00 to clarify terminology for these elements. The related federal contract opportunity is for the described construction project to convert the 8th floor north of Building 126 to single patient rooms. The solicitation is expected to be posted in February 2021. The construction scope of work includes upgrading all finishes, systems, and incorporating single patient rooms.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Clarification Log Convert Bldg 126 8th North to Private Rooms Project#: 600-17-115 April 20, 2021 Long Beach, California VA Health Care System 600
| Number |
| Clarification |
| Answer |
001.
Referencing Sage Glass
In addendum A, the Specifications included:
1. SPECIFICATION SECTION 08 81 80, Interior Special Function Glazing (new Section)
1. SPECIFICATION SECTION 08 88 00, Exterior Special Function Glazing (revised Section)
The Drawings included:
Sheet AF 601, in which Interior Finish Legend: Finish O-11 is Revised. It addressed the Special Functioning Glazing and states that the Exterior Windows are to receive the Insulating Units (spec section 08 88 00) and at Patient Rooms Laminated Glazing (spec section 08 81 80)
The contractor should look at the floor plans to determine the quantity.
Note: per Specification Section 01 00 00 these items are listed in the bid items as follows:
Base Bid: Added the exterior windows to receive the Special Functioning Glazing (spec section 08 88 00).
Deductive Bid Alternate 1: Delete the change to the exterior windows (the Special Functioning Glazing (spec section 08 88 00)).
Deductive Bid Alternate 2, item 1: Change the Laminated Glass, with Smart Screen Switchable Privacy Glass, identified as O-11 and remove the associated power, provide tempered glass instead. This is for the Interior Special Functioning Glazing (spec section 08 81 80)
Attached is a revised Specification Section 01 00 00 to further clarify the terminology to match the elements as described in Addendum A.
Contractors are not sharing all of the project information with the vendors; hence the discrepancy is based on how the contractor interprets the bid documents.