Attachment 2 OEI VASA Water Softener Commissioning Plan LRL v062624.pdf

PDF 289 KB Posted

Attached to
Z2DA--FY26 - CON Replace Water Softener System - Project 671-18-106 (VA-26-00000201)
Solicitation number
36C25726R0040
Issued by

About this file

This is a Systems Commissioning Plan for a Water Softener Plant replacement project under federal contract VA257-17-C-0110 for San Antonio Water Softeners. The plan, prepared by O'Brien Engineering, Inc., outlines comprehensive procedures for installing, testing, and operationalizing a water softener system comprising multiple ion exchange tanks, brine tanks, brine day tanks, pumps, and associated controls.

The commissioning scope includes verification of equipment installation per specifications; testing of plumbing, electrical, and instrumentation systems; calibration and testing of control systems; functional testing of alarms and interlocks; performance testing for design parameter compliance; and operational staff training. Specific activities encompass pre-commissioning checks with installation verification and documentation compilation; plumbing systems commissioning including pressure and leak tests; electrical systems commissioning with voltage and phase sequence verification; instrumentation and control systems commissioning with sensor and transmitter calibration; chemical handling system setup with brine tank filling and pump operation testing; initial regeneration cycle performance tests; safety and alarm testing including emergency shutdown procedures; staff training with certification; and comprehensive documentation of all tests and inspections. Equipment materials include fiberglass reinforced plastic or stainless steel ion exchange tanks; polyethylene or fiberglass brine tanks; PVC, CPVC, or stainless steel piping; and corrosion-resistant pumps. The control system utilizes PLC-based technology with HMI interface and includes high/low level, pressure, and equipment failure alarms. Timeline start and end dates are to be determined.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Systems

Commissioning Water Softener Plant

Date: 6/28/2024 11:52 AM

San Antonio Water Softeners

VA257-17-C-0110

671-18-106

0497001 VASA Replace Water Softeners Page 1 of 3

1. Objective:

1.1. The objective of this commissioning plan is to ensure the compliant installation, testing, and operational readiness of the water softener plant, comprising multiple ion exchange tanks, a brine tank, brine day tank, and associated pumps and controls. This plan outlines the procedures, responsibilities, and timeline for commissioning activities, coordinated between the commissioning agent and the end user.

2. Scope:

2.1. The scope of commissioning includes but is not limited to:

2.1.1. Verification of equipment installation according to specifications.

2.1.2. Testing of plumbing, electrical, and instrumentation systems.

2.1.3. Calibration and testing of control systems.

2.1.4. Functional testing of alarms, interlocks.

2.1.5. Performance testing to ensure compliance with design parameters.

2.1.6. Training of operational sta2.

3. Commissioning Team:

3.1. Commissioning Agent: O’Brien Engineering, Inc.

3.2. End User Representative: TBD

3.3. Contractor Representative: TBD

3.4. Equipment Supplier Representative: TBD

4. Commissioning Activities:

4.1. Pre-commissioning Checks:

4.1.1. Verify completeness of installation as per drawings and specifications.

4.1.2. Conduct a walkthrough inspection of the plant with the end user to ensure alignment with operational expectations.

4.1.3. Compile all necessary documentation, including operation manuals, as-built drawings, and equipment datasheets.

4.2. Plumbing Systems Commissioning:

4.2.1. Verify alignment, lubrication, and operation of mechanical equipment such as pumps, valves, and ion exchange tanks.

4.2.2. Conduct pressure and leak tests on all piping and connections.

4.2.3. Verify proper installation and functionality of flow meters, pressure gauges, and other mechanical instruments.

4.3. Electrical Systems Commissioning:

Water Softener Plant

Date: 6/28/2024 11:52 AM

San Antonio Water Softeners

0497001 VASA Replace Water Softeners Page 2 of 3

4.3.1. Verify electrical connections and grounding.

4.3.2. Check voltage levels and phase sequence.

4.3.3. Test operation of motors, starters, and motorized valves.

4.4. Instrumentation and Control Systems Commissioning:

4.4.1. Calibrate all instrumentation including level sensors, pressure transmitters, and conductivity meters.

4.4.2. Verify functionality of control panels, PLCs (Programmable Logic Controllers), and SCADA (Supervisory Control and Data Acquisition) systems.

4.4.3. Test control loops and interlocks.

4.5. Chemical Handling System Commissioning:

4.5.1. Fill the brine tank and day tank with the appropriate concentration of salt solution.

4.5.2. Test operation of brine pumps and ensure proper mixing and distribution of brine.

4.6. Performance Testing:

4.6.1. Conduct initial regeneration cycle tests to verify ion exchange resin performance and e2iciency.

4.6.2. Measure water softening capacity and hardness reduction.

4.6.3. Record and analyze operational data to ensure compliance with design parameters.

4.7. Safety and Alarm Testing:

4.7.1. Test emergency shutdown procedures and safety interlocks.

4.7.2. Verify audible and visual alarms for high/low levels, pressure, flow rates, and equipment failures.

4.8. Training:

4.8.1. Provide training sessions for operational sta2 on plant operation, maintenance procedures, and troubleshooting.

4.8.2. Issue training certificates upon completion.

4.9. Documentation:

4.9.1. Compile a comprehensive commissioning report documenting all tests, inspections, and results.

4.9.2. Review the report with the end user and obtain signo2 on the completion of commissioning activities.

4.9.3. Provide operation manuals, maintenance schedules, and record drawings to the end user.

Water Softener Plant

Date: 6/28/2024 11:52 AM

San Antonio Water Softeners

0497001 VASA Replace Water Softeners Page 3 of 3

4.10. Materials of Construction:

4.10.1. Ion Exchange Tanks: Typically constructed from fiberglass reinforced plastic

(FRP) or stainless steel.

4.10.2. Brine Tank and Brine Day Tank: Polyethylene (HDPE) or fiberglass (FRP).

4.10.3. Piping: PVC, CPVC, or stainless steel depending on application and pressure requirements.

4.10.4. Pumps: Stainless steel or corrosion resistant materials suitable for brine handling.

4.11. Controls and Alarms:

4.11.1. Control System: PLC based with HMI (Human Machine Interface) for operator control and monitoring.

4.11.2. Alarms: High/low level alarms for ion exchange tanks, brine tanks, and day tanks. Pressure alarms for pumps and vessels. Failure alarms for critical equipment such as pumps and valves.

5. Timeline:

5.1. Start Date: Date TBD

5.2. End Date: Date TBD

6. Conclusion:

6.1. This commissioning plan aims to ensure that the water softener plant is installed compliance with project requirements, operates e2iciently, and meets the operational requirements of the end user.