This is Amendment 0001 to solicitation 36C25726R0040 issued by the Department of Veterans Affairs Network Contracting Office for a water softener system replacement project (Project 671-18-106) at a VA healthcare facility. The amendment provides Requests for Information responses, updates the Past Performance Relevancy Key, and includes three attachments: a site visit sign-in sheet, the OEI VASA Water Softener Commissioning Plan, and the Appendix D Geotechnical Report. All other terms and conditions of the original solicitation remain unchanged.
The RFI responses clarify critical project requirements including: the project is subject to the Buy-American Act and Texas tax exemptions for VA materials; utility shutdowns affecting patient care must occur during night hours or weekends; the VA will provide commissioning services through A/E O'Brien Engineering, Inc.; temporary equipment storage is limited to the project site with no contractor trailers permitted; ICRA Class 3 infection control requirements apply; lead paint and suspected asbestos materials are present; the system configuration comprises three water softener tanks plus one brine tank (approximately 750 gallons) with N+1 redundancy capability; above-ground interior piping over 3 inches NPS must be stainless steel; Building Automation System integration is required; temporary fencing is mandatory; and all medical gas certifications are required. The Past Performance Relevancy Rating Key establishes evaluation criteria with "Very Relevant" status for similar water softener replacement projects valued at $2 million or greater with the VA on a healthcare campus, and progressively lower ratings for smaller projects or different agencies.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer)
TBD
671-18-106 36C257 Department Of Veterans Affairs Network Contracting Office 17 5441 Babcock Road Ste. 302 San Antonio TX 78240 36C257 Department Of Veterans Affairs Network Contracting Office 17 5441 Babcock Road Ste. 302 San Antonio TX 78240 To all Offerors/Bidders
36C25726R0040 03-03-2026
X X X See CONTINUATION Page X
The purpose of Amendment 0001 is to:
1. Provide the Requests for Information Responses
2. To Update the Past Performance Relevancy Key
3. Provide Attachment 1 the Site Visit Sign In Sheet
4. Provide Attachment 2 OEI VASA Water Softener Commissioning Plan LRL v062624
5. Provide Attachment 3 Appendix D - Geotechnical Report
All other terms and conditions remain unchanged.
Rhonda Richardson Contracting Officer
CONTINUATION PAGE
Amendment 0001 of 36C25726R0040 CON CTX 674-25-007 – Replace Water Softener is to respond to the RFI’s, update the Past Performance Relevancy Key, attach the sign in sheet from the site visit.
36C25726R0040- Replace Water Softener System Requests for Information
1. Is the Buy-American Act included in this contract?
a. Yes
2. Is this project tax exempt?
a. Yes
V.T.C.A. Tax Code §151.311 Offerors are hereby notified that in accordance with V.T.C.A., Tax Code §151.311, the purchase of tangible personal property for use in the performance of a contract for an organization exempted under Section 151.309 or 151.310 of this code is exempt if the tangible personal property is incorporated into realty in the performance of the contract. Additionally, the purchase of tangible personal property, other than machinery or equipment and its accessories and repair and replacement parts, for use in the performance of a contract for an improvement to realty for an organization exempted under Section 151.309 or 151.310 of the code is exempt if the tangible personal property is necessary and essential for the performance of the contract and completely consumed on the job. The VA is an exempt organization.
3. Therefore, the contractor’s purchase of such building and construction materials within the State of Texas to be incorporated into the real property belonging to the U.S. Department of Veterans Affairs (VA) or completely used in the performance of the contract is subject to exemption from Texas Sales and Use taxes under the code. To take advantage of the tax exemption the successful offeror under this solicitation must complete a Texas Sales and Use Tax Exemption Certificate when it purchases construction materials for this contract.
4. Please provide a location for abatement, trash, and connex areas?
a. Only a trash dumpster will be in the loading dock area. Storage containers will not be allowed on site for contractor storage.
5. Can the contractor have a job trailer onsite?
a. No. Contractors or their sub will not be allowed to have a job trailer onsite
6. Is the VA providing the Commissioning Agent?
a. The VA is providing commissioning via the A/E O’Brien Engineering, Inc.
7. Does the contractor need to account for after-hour work? If so, please provide applicable working hours.
a. Yes. Utility shutdowns and work that can interrupt patient care services are required to be done at night. Ex building water shutdowns for water softener isolation and/or tie in; Medical gas isolation and/or tie in.
8. Are there any parking restrictions for contractor personnel on the medical center campus?
a. Contractors will not be given any contractor specific parking.
9. What level of Infection Control Risk Assessment (ICRA) requirements will apply to this project?
a. ICRA Class 3
10. Are there any hazardous materials?
a. Lead paint is possible in the water softener equipment room.
11. How many gallons is the existing tank to be filled with?
a. The below grade basin contains a 6 inch bottom layer of gravel and approximately 130 cubic yards of wet salt. The two storage sections are approximately 10 feet deep. The existing Brine tank is 750gal.
12. Does the temporary equipment require controls?
a. Yes. Provide temporary controls based on the new controls provided.
13. All VA-stored material around the exterior site - is this to be moved by the VA or the contractor?
a. The VA will remove item in the canopy area. Provide a 20 ft shipping container to be placed near the loading dock for the VA to store items.
14. MCC: Are we to use existing buckets for the temporary setup?
a. Yes
15. Phasing clarification:
Phase 1 – Install temporary Water Softener Phase 2 – Install new medical vacuum system Phase 3 – Install new water softener
16. Are pumps to be stored onsite or offsite?
a. The new pumps to be installed can be stored onsite or offsite. Please follow manufacturer's long-term storage instructions.
17. Will a laydown yard be provided?
a. The only laydown area will be limited to the project site area.
18. Specification 22 11 00 Facility Water Distribution section 2.2 Above Ground (interior) Water Piping states that piping above 3" NPS needs to be stainless steel. Would the VA accept alternative piping materials?
a. No.
19. Will MED Gas certifications be required?
a. Yes
20. Will the contractor or VA provide the commissioning agent?
a. The VA will provide the commissioning agent via the A/E O’Brien Engineering, Inc.
21. Will 3rd party testing be required for concrete or rebar placement? Will slump tests be required?
a. No. Rebar placement will be inspected by the A/E/ COR. Provide the concrete at a slump of 5
22. Will there be any 3rd party testing on the mortar compound?
a. No.
23. Will the VA coordinate the shutdowns with the city for the existing water supply?
a. Shutdowns coordination with the City will not be required. There is a bypass available
24. Please provide the model and serial number of the existing exhaust fan on M-101.
a. The serial number and model are unknown
25. Please provide the model and serial number of the existing unit heater on M-101
a. The serial number and model are unknown
26. Do the water softeners and pumps need to be tied into the Building Automation System on the MCC panel of the boilers?
a. The new system will need to be tied to the Building Automation System
27. Will temporary fencing be required around the project workspace?
a. Yes
28. Section 01 00 00 appears to reference a geotechnical report. Please provide the report and confirm whether it is part of the bidding documents.
a. Attached is the geotechnical report titled “Appendix D – Geotechnical Report” the report is part of the project.
29. The specifications appear to reference a draft systems commissioning plan. Please provide that document and confirm whether it is part of the bidding package.
a. Please see the attached commissioning plan “OEI VASA Water Softener Commissioning Plan LRL v062624”
30. Please confirm whether any bid alternates are active in this solicitation and identify any base bid versus alternate scope tied to medical vacuum equipment or related commissioning language.
a. The work required in this solicitation is all part of the base bid. There are no bid alternatives
31. Please confirm the full design basis and required criteria for delegated fire alarm and sprinkler modifications and identify any additional existing-system information that will be provided to bidders.
a. The existing Fire alarm and sprinkler shall remain.
32. Please confirm the required performance criteria, minimum capacity, tie-in points, controls expectations, and acceptance criteria for the temporary water softener system so all bidders are pricing the same temporary scope.
a. The temporary water softener system shall meet the same requirements are the new permanent replacement water softener system.
33. Please confirm allowed shutdown windows and notice requirements for domestic water, electrical, fire alarm, sprinkler, medical gas, and communications work.
a. Utility shutdowns that will interrupt patient care services must be done at nights or off-peak hours for the utility use (weekends).
34. Please confirm whether the provided asbestos or hazardous-material information is complete for all planned disturbance areas and whether any additional investigation or abatement should be included in the bid.
a. There is known lead paint in the water softener room. ACM is suspected in the insulation covering the pipes.
35. Please confirm that commissioning requirements, warranty-phase commissioning expectations, and any owner-furnished commissioning procedures are fully included in the current package.
a. Please refer to the attached commissioning plan “OEI VASA Water Softener Commissioning Plan LRL v062624”
36. Please confirm whether any equipment under this project is owner-furnished or contractor-furnished.
a. Temporary equipment will be returned to the contractor unless it is to be retained by the VA. The new temporary medical vacuum system will remain in the new location and turn over to the VA after the project is completed.
37. Will the VA remove all of the surrounding materials around the existing brine tanks or will this be the contractor's responsibility?
a. The VA will remove items from the canopy. The Contractor will remove items in the water softener room.
36. The equipment selection and plan sheets indicate a triplex softener configuration with two options. A true (N+1, three 60x 60 tanks) and a (N+2, two Duplex 60x72 design 4 tank). There are multiple conflicting references within the plans that call for three and four tanks. The equipment schedule and notes list 4 tanks, but multiple plan details only show 3 tanks.
Under standard redundancy definitions:
A three‑tank configuration represents N+1 (two duty + one redundant). A true N+2 configuration would require four tanks total (two duty + two redundant). The design notes reference an N+2 configuration while only showing three tanks. (attachment 1 pg-34)
· Is the project intended to be an N+1 system with three total tanks, and the N+2, three vessel label is a documentation error: or
· Is the project intended to be a true N+2 system, requiring four total tanks, specs need to be updated accordingly?
The intent is to have 3 tank configurations for the water softeners and 1 brine tank. The system is intendent to be functional with the single brine tank and one water softener tank. The other two water softener tanks are to be redundant. One water softener tank should be able to enter a regeneration cycle independent of the other two water softener tanks. The brine tank should be sized so all three water softener tanks can regenerate at the same time.
Updated Past Performance Relevancy Rating Key
The Government intends to use the following rating system to guide its evaluation of the relevance of past performance information:
Past Performance Relevancy Rating Key
| Rating |
| Definition |
| Very Relevant |
| Present/Past performance effort involved essentially the same scope and magnitude of effort and complexities this solicitation requires. |
An example would be a replacement of water softener system project of $2M or greater, with the VA in a healthcare campus. *Note, $2M is used as a benchmark based off the project’s magnitude Between $2,000,000 and $5,000,000.
| Relevant |
| Past performance effort involved similar scope and magnitude of effort and complexities this solicitation requires. |
An example would be a replacement of water softener system project of $2M or greater, with other Government agencies on a healthcare campus.
| Somewhat Relevant |
| Past performance effort involved some of the scope and magnitude of effort and complexities this solicitation requires. |
An example would be a replacement of water softener system project worth less than $2M on a healthcare campus.
| Not Relevant |
| Past performance effort involved little or none of the scope and magnitude of effort and complexities this solicitation requires. |
An example would be a replacement of water softener system project worth less than $2M and with a non-government business.
Attachments:
Attachment 1 10_MARCH_2026_REPLACE_WATER_SOFTENER_SITE_VISIT_SIGN-IN _SHEET.
Attachment 2 OEI VASA Water Softener Commissioning Plan LRL v062624.
Attachment 3 Appendix D - Geotechnical Report.