This is Amendment 0004 to Solicitation 36C25726B0001, issued by the El Paso Contracting Office of the Department of Veterans Affairs for Project 549-23-601: Upgrade Chillers & Cooling Towers at Energy Center. The amendment extends the proposal due date to June 1, 2026, at 10:00 CDT and announces an additional pre-bid site visit scheduled for Wednesday, May 13, 2026, at 10:00 AM CST at Building 9 of the Dallas VA Medical Center (4500 S. Lancaster Rd., Dallas, TX 75216).
The amendment provides clarifications to eight Request for Information (RFI) responses addressing technical requirements for the chiller and cooling tower upgrade work. Key clarifications include: (1) all pneumatic actuators must be replaced with DDC controls, with contractors responsible for assessing valve conditions and replacing valves/actuators if conversion is not feasible; (2) contractors are responsible for means and methods to provide isolation valves and coordinate all shutdowns with the VA; (3) existing VFDs serving current pumps may be reused unless new pumps exceed their horsepower rating; (4) new chillers rated for 4160V service shall include factory-mounted variable speed drives per mechanical specifications; (5) standard schedule notes for 480V chillers are not applicable to this 4160V project; and (6) the project requires replacement of three 350A molded case circuit breakers with 225A breakers inside MCC-CH1 with field retrofit to match existing style and AIC ratings, with no requirement to replace starter buckets or load break switches as Eaton has discontinued legacy equipment lines.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE 7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO. 1. CONTRACT ID CODE
FACILITY CODE CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR
ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES
SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30 PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243
(Type or print) (Type or print)
(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code)
(If other than Item 6)
(Specify type of modification and authority)
(such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) none
549-23-601
36C257
Network Contract Office 17
Department of Veterans Affairs
11495 Turner Road
El Paso TX 79936-4221
36C257
El Paso Contracting Office
Department of Veterans Affairs
11495 Turner Road
El Paso TX 79936-1372
To all Offerors/Bidders
36C25726B0001
X
X X
** HOUR & DATE for Receipt of Offers is EXTENDED to: 06-01-2026 10:00 CDT
Amendment 0004 is issued to extend the proposal due date, provide clarifications to the RFIs, and announce an additional pre-bid site visit.
The additional site visit is scheduled for Wednesday, May 13, 2026, at 10:00 AM CST. Participants will meet at the front desk/waiting area of Building 9 at the Dallas VA Medical Center, located at 4500 S. Lancaster Rd., Dallas, TX 75216.
Rhonda Richardson
Contracting Officer
CONTINUATION PAGE
Project: 549-23-601 Upgrade Chillers & Cooling Towers at Energy Center - Clarifications
1. RFI response question 12- it call for existing valves to remain and be reused, however it later call for pneumatic to be replaced.
Response: Replace any and all pneumatic actuators with DDC. Contractor shall be responsible for assessing the condition of all existing valves being reused. If the pneumatic actuator and valves cannot be converted to DOC, valve and actuator shall be replaced.
2. RFI response question 14- the answer does not match the question given and does not address the situation. There are not additional isolation valve before the pump and there is no way to change the control valve without performing a pipe freeze. Additionally, the bypass piping if after the control valve so it cannot function in per the drawings.
Response: Yes - means and methods are the contractor's responsibility. All shutdowns shall be coordinated with the VA. Provide any additional valves needed for pump/chiller replacement to ensure equipment functions according to the existing sequence of operation.
3. There seems to be some confusion on if the existing vfd's can be reused or replaced.
Response: We see no issue with the reuse of the existing VFD's that serve the existing pumps unless the new pumps have a higher HP rating. For example, if the VF D's are rated for 20 HP but a 25 HP pump is to be installed the VFD will need to be replaced. There is no option to reuse starters associated with the Chillers to be replaced.
4. Can you please provide clarification on the following? There is a discrepancy in the verbiage related to the notes below. I assume we are sticking with the current (remote mounted) configuration
Response: See response to question 6.
5. Note 14 states: 5kv solid state starter soft starter. Chiller 7 has a remote mounted, variable speed drive. Are we to match that style or follow the plans using the soft starter?
Response: Mechanical Specifications and mechanical schedules dictate the requirements for the new chillers. Spec Section 23 64 00, par 2.1.Y calls for a variable speed drive for the chillers integral to Chiller package. Chiller schedule on M-501 calls for the new chillers to be rated for 4160V service.
6. Page m-501 - chiller schedule (ccu) note 2 states: "provide factory mounted starter and disconnect switch" - the current setup has for chiller 3-6 has remote mounted solid state reduced voltage starter.
Response: This std note is applicable for 480V chiller packages, not 4160V. Note 2 is not applicable to this project.
7. Page e-201- electrical keynote: note 14 (truncated) - combination electronic 5kv solid state starter (soft starter) with disconnect for new chillers provided with chiller package.
Response: See response to RFI 5 above.
8. We received notice that eaton (the manufacturer for the fuse buckets for the existing switch gear) is not releasing pricing as they claim what is specified is no longer available. See statement from eaton below:
At the end of 2025, eaton discontinued all classic ampgard full starters and load break switch offerings.
We can provide these in our nextgen ampgard. Eaton does not offer retrofit into existing cells either.
The new switches would be in entirely new structures and to close couple them to existing lineup requires splitting and separating the existing lineup to fit new structures.
Response: This project requires the replacement of (3) 350A existing molded case circuit breakers inside MCC-CH1 with (3) 225A circuit molded case breakers. There are no starters or load break switches as part of this work. This work does not require the replacement of the buckets that hold these breakers.
Provide new breakers to match existing style and AIC rating. Field retrofit to MCC2 to perform this work.