This document contains responses to questions regarding Solicitation Number 36C25723B0057 for the upgrade of the medical gas system at buildings 1, 28, and 29 of the Amarillo VA Medical Center. The solicitation is for a design-bid-build project where the government's architect engineer is responsible for the design and specifications, and offerors are responsible for bidding and construction based on the provided design documents. Work is to be performed during normal business hours of 8:00 to 16:30 Monday through Friday, unless approved otherwise. The project areas are classified as Infection Control Risk Assessment Level IV unless noted otherwise. There are no required subcontractors specified. The document did not contain information on pricing terms, award dates, set asides, or incumbent contractors.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
IFB 36C 25723B0057 – PROJECT # 504-22-108 – AMARILLO VAMC – UPGRADE MEDICAL GAS
RFI’S
1. Are we to dispose/abate of any asbestos, lead, mold, or other hazardous material as part of this project? If so, provide appropriate hazardous material site survey report.
1. What will the ICRA level be for this project? Refer to GC sheet series and specification section 01 35 26 1.12 B Infection Control. Areas are classified as CLASS IV unless otherwise specifically noted.
1. Are there any required/proprietary subcontractors the general contractor is to hire associated with this project? No.
1. Will all work associated with this project able to be performed during regular working hours? Refer to GC sheet series and specifications. The normal hours of work are 08:00 to 16:30 (4:30) Monday through Friday. Work shall be performed during normal work hours. Work to be performed in other than normal hours shall be approved by the Contracting Officer’s Representative.
1. It is our understanding that the Solicitation is a negotiated Bid (RFP) design-bid-build project with the Government's AE being responsible for the design portion (providing a full and complete set of Specifications and Plans) and the successful offeror being responsible for bidding and building the project based on the Specifications and Plans provided by the Government's AE. Put another way, the successful offeror will not be required to perform any design-build services as part of the contract - correct? Refer to plans and specifications for designation of delegated design items, if any.
1. Will all work need to be performed after normal working hours? Refer to GC sheet series and specifications. The normal hours of work are 08:00 to 16:30 (4:30) Monday through Friday. Work shall be performed during normal work hours. Work to be performed in other than normal hours shall be approved by the Contracting Officer’s Representative.