Y1DA--671-18-118 Install Electrical Generator at the PTRP (VA-22-00011728)
Solicitation number
36C25722B0032
Issued by

About this file

This solicitation is for the installation of an electric generator at the Polytrauma Transitional Rehabilitation Program facility operated by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 17. The solicitation number is 36C25722B0032 and seeks to award a contract under project number 671-18-118 to install the generator. Responses are due by the date specified in the solicitation document 36C25722B0032 0002.docx. The work involves installing the generator at the PTRP to provide backup power. The Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 17 is the contracting agency seeking this installation work.

View the file

Other files

File Type Posted
36C25722B0032 0005.docx DOCX document
36C25722B0032 0004.docx DOCX document
PTRP Irrigation Drawings.pdf PDF
Clarification Response RFIs 2 16 and 22.pdf PDF
ICRA-2.0-ICRA.Permit.pdf PDF
36C25722B0032 0003.docx DOCX document
ICRA 2.0 ICRA. Permit.pdf PDF
PTRP Irrigation Drawing.pdf PDF
S04 Sign in Sheet PreBid Site Visit Conference AUG 16 2022.pdf PDF
36C25722B0032 0001.docx DOCX document
671-18-118 Install Generator at PTRP-Bid Drawings.pdf PDF
671-18-118 Install Generator at PTRP-Bid Specifications.pdf PDF
36C25722B0032_1.docx DOCX document
Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE

7.

ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF

PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE

OF YOUR

ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERE

D CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES

SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendmen t, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED

STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF

CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF

SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer) 671-18-118 Department of Veterans Affairs Network Contracting Office, NCO17 1901 Veterans Memorial Dr. Building #171 Temple TX 76504 Department of Veterans Affairs Network Contracting Office, NCO17 1901 Veterans Memorial Dr. Building 171 Temple TX 76504 To all Offerors/Bidders

36C25722B0032

X X X September 13, 2022 @ 10AM CST

A. Amendment 0002 is issued to provide the consolidated RFIs with responses.

B. The Bid Closing is changed to September 13, 2022, at 10 AM CST.

C. Number of days to complete the project is changed to 540 days from receipt of the NTP.

Joyce M. Mills Contracting Officer Consolidated RFIs with Responses: 36C25722C0032:

1. Are we to dispose/abate of any asbestos, lead, mold or other hazardous material as part of this project? If so, provide appropriate hazardous material site survey report.

A: No ACM identified.

1. What will the ICRA level be for this project?

A: This project will fall as Type C, Level III Medium, Risk under the new ICRA requirement.

1. Are there any required/proprietary subcontractors the general contractor is to hire associated with this project?

A: Reference Statement of Work (SOW)

1. Will all work associated with this project able to be performed during regular working hours?

A: Reference sheet MEP100, “Construction Noise and Traffic Requirements” and “Project Phasing Plan”. The contractor is responsible for developing a construction plan that will minimize disruption to site activities and limit construction noise to the hours indicated.

1. It is our understanding that the Solicitation is a negotiated Bid (RFP) design-bid-build project with the Government's AE being responsible for the design portion (providing a full and complete set of Specifications and Plans) and the successful offeror being responsible for bidding and building the project based on the Specifications and Plans provided by the Government's AE. Put another way, the successful offeror will not be required to perform any design-build services as part of the contract - correct?

A: Yes…correct.

1. Could we please be provided with the Geo-Tech report due to structural upgrade needed to for soils.

A: Reference specification section 01 00 00.01 Geotechnical Engineering Report.

7. Period of Performance: There is no way that this project can be completed in 180 days if the NTP is issued prior to knowing when long-lead equipment will arrive. Current generator lead times are running 40-60 weeks, depending on the manufacturer and actual release date. It would be best if the CO, COR, & contractor coordinate a construction start time based on when the equipment is scheduled to arrive. That date can be tracked via the supplier once submittals have been approved and equipment is released for production. Please consider this approach.

A: Adjusted completion day will be adjusted to 540 days.

8. Section 014500-6: Normally on VA projects, a superintendent can perform SSHO duties in addition to Quality Control duties. Due to the relatively small size of this project would that be acceptable? This will save the VA a considerable amount of money.

A: If the proposed superintendent can demonstrate the qualifications to perform as both the SSHO and perform the QC duties, it is acceptable that the superintendent performs both duties.

9. Energized Electrical Work: In past projects for the VA, we have had to work on panels that were energized due to being critical/life safety panels. Will that be the case on this project? Are there panels that cannot be shut down that we will be doing work on?

A: Reference sheet MEP100, “Construction Noise and Traffic Requirements” and “Project Phasing Plan”. Reference sheet ES300. It is the contractor’s responsibility to determine the means and methods of implementing the installation of the equipment indicated. Planning and coordination should allow the installation of the new electrical service/gear within the indicated time constraints.

10. Lightning Protection Counterpoise: Does the lightning protection system require a grounding counterpoise?

A: Reference sheet ES301 “Lightning Protection Plan”. The generator lightning protection system shall be designed, installed and certified by a licensed lightning Protection contractor. Coordinate requirements with approved shop drawings and installed field conditions.

11. Grounding Rods: Typically, lightning protection grounding rods are located within 5’ of vertical riser to air terminal. This would place said rods in the footprint of the new concrete pavement.

Please clarify if ground rod testing wells are required and/ or if ground rods shall be accessible below concrete.

A: Reference sheet ES301 “Lightning Protection Plan”. The generator lightning protection system shall be designed, installed and certified by a licensed lightning Protection contractor. Coordinate requirements with approved shop drawings and installed field conditions. It is preferable to locate ground rod(s) as indicated on Lightning Protection Plan.

12. Building Conduit Penetrations: During the site visit, it was observed that the underground conduit entry point at the building electrical room would be obstructed by switchgear inside the room. Contractor proposes to route said conduits exposed on perimeter of building and enter the electrical room at approximately 6-7’. This would put the conduit entry above the main electrical switchboard and unobstructed. Will the VA allow this?

A: Reference sheet ES300, Detail 2. Route conduit under existing sidewalk. Rise up at building wall and penetrate building wall. Adjust height of wall penetration per existing conditions. Minimize obstruction to egress along existing sidewalk.

13. Sheet ES300, Detail#2: New racking calls for “PVC Coated Galvanized Steel Channel”.

Existing channel is not PVC Coated. Shall we replace existing and/ or leave as is and only install any new pieces to comply with the “PVC Coated Galvanized Steel Channel” requirement?

A: Replace/extend posts as indicated/required. Existing serviceable channel to remain.

14. Generator House Panel: Please confirm ATE 100A/1P shall feed the generator house panel that subsequently serves the generators ancillary loads. Typically, battery chargers and/ or block heaters require 208V.

A: The specified generator is provided with the features listed on sheet ES200. Coordinate electrical requirements with proposed generator prior to construction.

15. CPS Fee: In order to re-build the electrical service entrance, CPS will charge utility outage fees.

Please confirm if contractor is responsible or if Govt will pick up said fees.

A: Contractor responsibility.

16. Temporary Generator: Re-building the electrical service will require an extensive outage. Please confirm if a temporary generator will be required during the service installation of the new service entrance for the ATS. This will be a lengthy outage.

A: Refer to Question #9.

17. Alternate Temporary Power: Are there any additional electrical panels or feeds that will need temporary power installed during construction that is not explicitly shown on the design documents?

A: Refer to Question #9.

18. Duct-Bank Backfill: Please confirm whether electrical duct-bank backfill is select fill, flowable fill or concrete. Select compacted backfill.

19. Sheet ES200, KN#14: Instead of boring under the roadway, would it be ok to sawcut and excavate if road plates are provided for vehicle traffic as necessary? This may be more cost effective while still allowing driveway use. Work could also be scheduled to be done during off-peak hours.

A: Reference sheet MEP100, “Construction Noise and Traffic Requirements” and “Project Phasing Plan”. The contractor is responsible for developing a construction plan that will minimize disruption to site activities and limit construction noise to the hours indicated.

20. Permits: What permits, if any, are required for this project?

A: Refer to Question #3.

21. Sheet MEP100, Detail 1: The site plan shows that the generator shall sit a minimum of 25’ from the property line and the driveway. It appears that the relationship between the back fence-line and generator cannot achieve this spacing. Please clarify for contractors.

A: The project documents were developed utilizing survey information obtained during the design process. Please clarify differing site conditions.

22. Sheet MEP100, KN#4: Please provide drawing showing existing irrigation layout and zones, valve locations, etc. This is needed so contractors know how to maintain a temporary system during construction.

A: See attached PTRP Irrigation Drawings.

23. MEP Drawings: Cover sheet GI100 lists MEP101, but that sheet is missing from the plans.

MEP200 was provided, but not shown on the cover sheet. Please confirm that this is correct and we are not missing drawings.

A: Sheet numbers on cover sheet are not correct. Project sheet list should be: MEP100 Site Plan:

General Requirements, Phasing Plan & SW3P Plan. Sheet MEP200 Site Plan: Grading.

24. CAD As-builts: Are CAD as-built drawings required by contractors or will standard redline drawings suffice?

A; Standard Redline Will Suffice.

25. Additional RFIs: Please allow for one additional round of RFIs prior to bidding the project so contractors have more time to review the project specifications and requirements.

A: No.

Install Electrical Generator at the PTRP, Project No. 671-18-118 PTRP Irrigation Drawings.pdf

671-237 19 OF 103.L1.00

671-237 20 OF 103.L1.01

671-237 21 OF 103.L1.02

671-237 22 OF 103.L2.00

671-237 23 OF 103.L2.01

671-237 24 OF 103.L2.02

671-237 25 OF 103.L2.03

671-237 26 OF 103.L2.04

image1.emf

ICRA-2.0-ICRA.Permit.pdf

©2022. American Society for Health Care Engineering of the American Hospital Association

ICRA 2.0 Infection Control Risk Assessment and Permit

Project Name:

ICRA Number: Requested by

Location of Work Activity Project Start Date Estimated Duration Completion Date

Foreman/Supervisor Phone Contractor Performing Work Phone

Approving Authority Phone Please note that the above signature is approval of the work activity as described and assessed documented here.

Should the scope of work change or the discovery of additional toxic or biological substances.

STOP WORK and seek additional approval and guidance before proceeding.

1. Type of Activity Explain this reasoning for this assessment Type A: Non-invasive Type B: Small-scale, short duration Type C: Large-scale, longer duration Type D: Major demolition, construction

2. Patient Risk Area Describe key patient risks Low: Non-patient care areas Medium: Patient care support areas High: Patient care areas Highest: Invasive, sterile or highly compromised care

3. Class of Precautions Type A TYPE B TYPE C TYPE D

Low I II II III Medium I II III IV

High I III IV V Highest III IV V V

4. Surrounding Area

Unit Below: Above: Lateral: Behind: In Front:

Risk group Contact

Phone Controls Noise

Vibration Dust Ventilation Pressurization

Noise

Dust

Dust

Dust

Dust

Systems impacted:

Data Mechanical Med Gas Hot/Cold Water Other

Med Gas

Med Gas

Med Gas

Med Gas

Were there discoveries in surrounding areas that would serve as cause to increase the class of precautions and necessitate additional controls? If so, please summarize.

©2022. American Society for Health Care Engineering of the American Hospital Association

5. Detailed Plan of ICRA Controls for this Work Final Class of Precautions being applied I II III IV V

Controls required for this project Specifications/ Materials Verification method and frequency

Exceptions/Additions to this permit Date and Initials are noted by attached memoranda

Initials Date

Permit Request By Date

Permit Authorized By Date

Approval Signature

©2022 The American Society for Health Care Engineering of the American Hospital Association Disclaimer: This document is provided by ASHE as a service to its members. The information provided may not apply to a reader’s specific situation and is not a substitute for application of the reader’s own independent judgment or the advice of a competent professional. ASHE does not make any guaranty or warranty as to the accuracy or completeness of any information contained in this document. ASHE and the authors disclaim liability for personal injury, property damage, or other damages of any kind, whether special, indirect, consequential, or compensatory, that may result directly or indirectly from use of or reliance on this document.

Project Name:

Requested by:

Location of Work Activity:

Project Start Date:

Estimated Duration:

Completion Date:

ForemanSupervisor:

Phone:

Contractor Performing Work:

Phone_2:

Approving Authority:

Phone_3:

Explain this reasoning for this assessmentRow1:

Describe key patient risksRow1:

BelowRisk group:

AboveRisk group:

LateralRisk group:

BehindRisk group:

In FrontRisk group:

BelowContact:

AboveContact:

LateralContact:

BehindContact:

In FrontContact:

BelowPhone:

AbovePhone:

LateralPhone:

BehindPhone:

In FrontPhone:

Noise: Off

Vibration: Off

Dust: Off

Ventilation: Off

Pressurization: Off

Noise_2: Off

Vibration_2: Off

Dust_2: Off

Ventilation_2: Off

Pressurization_2: Off

Noise_3: Off

Vibration_3: Off

Dust_3: Off

Ventilation_3: Off

Pressurization_3: Off

Noise_4: Off

Vibration_4: Off

Dust_4: Off

Ventilation_4: Off

Pressurization_4: Off

Noise_5: Off

Vibration_5: Off

Dust_5: Off

Ventilation_5: Off

Pressurization_5: Off

Data: Off

Mechanical: Off

Med Gas: Off

Water Systems: Off

Other: Off

Data_2: Off

Mechanical_2: Off

Med Gas_2: Off

Water Systems_2: Off

Other_2: Off

Data_3: Off

Mechanical_3: Off

Med Gas_3: Off

Water Systems_3: Off

Other_3: Off

Data_4: Off

Mechanical_4: Off

Med Gas_4: Off

Water Systems_4: Off

Other_4: Off

Data_5: Off

Mechanical_5: Off

Med Gas_5: Off

Water Systems_5: Off

Other_5: Off

Were there discoveries in surrounding areas that would serve as cause to increase the class of precautions and necessitate additional controls If so please summarize:

Controls required for this projectRow1:

Specifications MaterialsRow1:

Verification method and frequencyRow1:

Controls required for this projectRow2:

Specifications MaterialsRow2:

Verification method and frequencyRow2:

Controls required for this projectRow3:

Specifications MaterialsRow3:

Verification method and frequencyRow3:

Controls required for this projectRow4:

Specifications MaterialsRow4:

Verification method and frequencyRow4:

Controls required for this projectRow5:

Specifications MaterialsRow5:

Verification method and frequencyRow5:

Controls required for this projectRow6:

Specifications MaterialsRow6:

Verification method and frequencyRow6:

Controls required for this projectRow7:

Specifications MaterialsRow7:

Verification method and frequencyRow7:

Controls required for this projectRow8:

Specifications MaterialsRow8:

Verification method and frequencyRow8:

Controls required for this projectRow9:

Specifications MaterialsRow9:

Verification method and frequencyRow9:

Controls required for this projectRow10:

Specifications MaterialsRow10:

Verification method and frequencyRow10:

Controls required for this projectRow11:

Specifications MaterialsRow11:

Verification method and frequencyRow11:

Controls required for this projectRow12:

Specifications MaterialsRow12:

Verification method and frequencyRow12:

Controls required for this projectRow13:

Specifications MaterialsRow13:

Verification method and frequencyRow13:

Controls required for this projectRow14:

Specifications MaterialsRow14:

Verification method and frequencyRow14:

Controls required for this projectRow15:

Specifications MaterialsRow15:

Verification method and frequencyRow15:

Controls required for this projectRow16:

Specifications MaterialsRow16:

Verification method and frequencyRow16:

Controls required for this projectRow17:

Specifications MaterialsRow17:

Verification method and frequencyRow17:

Controls required for this projectRow18:

Specifications MaterialsRow18:

Verification method and frequencyRow18:

Controls required for this projectRow19:

Specifications MaterialsRow19:

Verification method and frequencyRow19:

Initials:

Date:

Permit Request By:

Date_2:

Permit Authorized By:

Date_3:

Approval Signature:

Final Class of Precautions: [Class I]

Unit Above:

Unit Below:

Unit Lateral:

Unit Behind:

Unit In Front:

Patient Risk: Off

Activity: Off

ICRA Number:

Class: Off image2.emf