These are mechanical design drawings for a heating water system upgrade at the John L. McClellan Memorial Veterans Hospital in Little Rock, Arkansas. The project involves replacing and upgrading the heating water systems in Building 1, with work spanning multiple phases across the mezzanine and third floor. Key components include installing new heat exchangers (1-HX-1, 1-HX-2, 1-HX-3), hydronic pumps (1-HWP-1, 1-HWP-2, 1-HWP-3), steam pressure reducing valves (1-PRV-1, 1-PRV-2), a flash tank (1-FT-1), expansion tanks (1-ET-1, 1-ET-3), and associated piping and control systems. The project is set for 100% bid documents as of July 9, 2024, with the VA Project Number 598-21-108, and is being managed by Apogee Consulting Group.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
19 20 21 22
E
F
G
2" CR-60
2" HPS
12" CHS
12" CHR
5" CHR
5" CHS
8" HPS
2" CR-60
8" HPS
PRV
5" CR-60
19 20 21 22
E
F
G
2" HPS
12" CHS
12" CHR
5" CHS
5" CHR
2" CR-60
8" HPS
8" HPS
2" CR-60
PRV
5" CR-60
1-FT-1
A. COORDINATE STEAM SHUTDOWN WITH THE
COR. SHUTDOWN TO BE LIMITED TO OFF-PEAK
HOURS.
B. OUTAGE LIMITED TO 8 HOURS. TEMPORARY
PIPING/CONNECTIONS MAY BE REQUIRED.
C. WORK CAN ONLY TAKE PLACE WHEN OUTDOOR
TEMPERATURE IS ABOVE 65 DEGREES F.
Engineers Architects
# KEY NOTES:
# KEY NOTES:
Revisions: Date
Drawing Title
Approved
Project Title
Location
VA PROJECT NUMBER
Building Number
Drawing Number
Dwg of
VA FORM 08-6231
Office of Construction and Facilities Management
CONSULTANTS: PROJECT MANAGER
SHEET NOTES:
WALL RATING LEGEND
1 HR - FIRE SEPARATION
2 HR - FIRE SEPARATION
SMOKE RESISTIVE HAZARDOUS AREA
Date Checked Drawn
FULLY SPRINKLERED
ACG Project Number
Headquarters:
Apogee Consulting Group, P.A.
1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.
S S S S
/8
/2
:4
:3
P
M C
U s e rs \a d e lg a d o \D o c u m e n ts \A
M E
P F
-1
-J L M
U p g ra d e H e a ti n g
W a te r
S y s te m s a d e lg a d o D
Y Q
A
.r v t
M-101
BUILDING 1, MEZZANINE, PHASE 1,
MECHANICAL PLANS
2 18AD
REPLACE/UPGRADE
HEATING WATER SYSTEM
JOHN L. MCCLELLAN MEMORIAL VETERANS HOSPITAL
4300 W 7TH STREET
LITTLE ROCK, AR 72205
JULY 9, 2024
100% BID DOCUMENTS
598-21-10822-100
RHA
Scale: 3/16" = 1'-0"
BUILDING 1, MEZZANINE, PHASE 1, MECHANICAL
DEMOLITION PLAN
Scale: 3/16" = 1'-0"
BUILDING 1, MEZZANINE, PHASE 1, MECHANICAL NEW
WORK PLAN
1 REMOVE FLASH TANK. CAP PIPING AND
PREPARE FOR NEW CONNECTIONS.
2 RELOCATE EXISTING DUCT TEMPORARILY OR
PERMANENTLY IF REQUIRED. COORDINATE
MODIFICATIONS TO THIS DUCTWORK WITH
THE COR.
1 INSTALL NEW FLASH TANK TO
ACCOMMODATE THE MEDIUM PRESSURE
CONDENSATE RETURN BACK TO THE ENERGY
CENTER. CONNECT TO EXISTING PIPING.
REFER TO DETAIL 8 ON SHEET M-501.
2 RELOCATE EXISTING DUCT TEMPORARILY OR
PERMANENTLY IF REQUIRED. COORDINATE
MODIFICATIONS TO THIS DUCTWORK WITH
THE COR.
NORTH
0 4 8 16
NORTH
0 4 8 16
Scale: No Scale
EXISTING MEZZANINE FLASH TANK 2
Scale: No Scale
EXISTING MEZZANINE FLASH TANK 1
N
KEY PLAN
SCALE: NO SCALE
A
D E
C B
7 9
F
DocuSign Envelope ID: 5EB0D510-95A5-4101-AB5F-A83F346704F6
7/8/2024 bmaxwell Cloud bmaxwell Text Box EX. 40x30 EXHAUST DUCT. SERVES TRANSFORMER ROOM. 12,000 CFM bmaxwell Text Box REMOVE SECTION OF DAMAGED 40x30 EXHAUST DUCT SERVING THE TRANSFORMER ROOM THAT AS NEEDED TO REPLACE THE FLASH TANK. COORDINATE WORK WITH THE COR TO LIMIT THE TIME THAT THE DUCT IS OUT OF SERVICE.
bmaxwell Text Box REPLACE SECTION OF 40x30 EXHAUST DUCT SERVING THE TRANSFORMER ROOM WITH NEW 16 GAUGE GALVANIZED DUCT WITH THE NEW DUCT REINFORCED TRAVERSELY PER SMACNA DUCT CONSTRUCTION STANDARDS ON ALL FOUR SIDES AT 16" INTERVALS.
bmaxwell Snapshot bmaxwell Line bmaxwell Snapshot bmaxwell Line bmaxwell Cloud bmaxwell Text Box 40x30 bmaxwell Text Box 40x30 bmaxwell Text Box 40x30 bmaxwell Rectangle bmaxwell Rectangle bmaxwell Line bmaxwell Line bmaxwell Rectangle bmaxwell Rectangle bmaxwell Rectangle bmaxwell Line bmaxwell Line bmaxwell Rectangle bmaxwell Line bmaxwell Text Box 40x30 bmaxwell Line bmaxwell Snapshot bmaxwell Snapshot
16 17 18 19 20 21
E
F
G
H
J
K
L
MECHANICAL
ROOM
3E100
HWP-1
HE-1
HE-2
HWP-2
RF-5
RF-18
EX-25
3" HWR
8" HWR
6" HWS
3" CHR
3" CHS
6" MPS
10" MPS
10" MPS
10" MPS
10" MPS
6" HWS
6" HPS
3" HWR
2 1/2" HWS
2 1/2" HWR
6" MPS
6" HWS
3" HWR
1-PRV-1
1 1/4" HWS
1 1/4" HWR
M-103
HE-3
ET-23
STAIR 4
S14-JLM
AC-28
RF-12
AC-14
AC-6
EX-30
EX-3
RF-6
EX-8
AC-19
AC-15
EX-7
AC-22
AC-5
AC-13
12" CHS
4" CR-30
5" CHR
5" CHS
12" CHS
16 17 18 19 20 21
E
F
G
H
J
K
L
MECHANICAL
ROOM
3E100
RF-5
EX-25
RF-18
8" HWR
6" HWS
6" MPS
3" CHR
3" CHS
3" HWR
2 1/2" HWS
2 1/2" HWR
6" MPS
8" HWR
3" HWR
8" MPS
6" HPS
1-PRV-1
M-103
8" HWR
10" MPS
6" HWS
M-103
HE-3
M-103
1-HX-1
1-HX-21-TCV-2
1-TCV-4
1-TCV-3
1-TCV-1
1-ET-1
1-ST-1
1-AS-1
STAIR 4
S14-JLM
RF-12
AC-28
4" CR-30
12" CHS
12" CHR
5" CHS
5" CHR
4" CR-30
HWP-3
AC-14
AC-6
EX-30
EX-3
RF-6
EX-8
AC-19
AC-15
EX-7
AC-22
AC-5
AC-13
3" HWR
3" HWS
8" HWR
10" MPS
6" HWS
1-FT-1
TCP
3" HWS
1-ST-2
2" HWS
6" HWS
THIRD FLOOR
54' - 0"
FOURTH LEVEL
72' - 8"
4" CR-30
1-HX-2
1-ST-2
1-AS-1
8" HWR
8" HWR
10" MPS
2" HWS TO
EXPANSION TANK
2" D
THIRD FLOOR
54' - 0"
FOURTH LEVEL
72' - 8"
6" HWS
6" HWR
6" HWS
10" MPS
6" HWS
1 1/4" HWS
10" MPS
HE-2
THIRD FLOOR
54' - 0"
FOURTH LEVEL
72' - 8"
1-HX-1
12" MPS
2 1/2" CR-30
" HEAT
EXCHANGER
CLEARANCE
2 1/2" CR-30
4"
1-ST-1
2" HWS TO
EXPANSION TANK
THIRD FLOOR
54' - 0"
FOURTH LEVEL
72' - 8"
1-HX-1
1-HX-2
2" HWS
'0
1-ST-1
1-ST-2
2" HWS
8" HWR
10" MPS
10" MPS
4" CR-30
2 1/2" CR-30
8" HWR8" HWR
A. CONTRACTOR SHALL COORDINATE WORK TO
ENSURE THAT (1) PRIMARY HEATING HOT
WATER HEAT EXCHANGER AND PUMP SET IS
OPERATIONAL AND CONNECTED TO THE END-
USE EQUIPMENT THROUGHOUT THE
CONSTRUCTION PERIOD.
B. ALL WORK AFFECTING THE OR SUITE SHALL BE
LIMITED TO 8 HOURS AND SCHEDULED WITH
THE VA COR A MINIMUM OF 45 DAYS IN ADVANCE.
Engineers Architects
# KEY NOTES:
# KEY NOTES:
Revisions: Date
Drawing Title
Approved
Project Title
Location
VA PROJECT NUMBER
Building Number
Drawing Number
Dwg of
VA FORM 08-6231
Office of Construction and Facilities Management
CONSULTANTS: PROJECT MANAGER
SHEET NOTES:
WALL RATING LEGEND
1 HR - FIRE SEPARATION
2 HR - FIRE SEPARATION
SMOKE RESISTIVE HAZARDOUS AREA
Date Checked Drawn
FULLY SPRINKLERED
ACG Project Number
Headquarters:
Apogee Consulting Group, P.A.
1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.
S S S S
/8
/2
:4
:2
P
M C
U s e rs \a d e lg a d o \D o c u m e n ts \A
M E
P F
-1
-J L M
U p g ra d e H e a ti n g
W a te r
S y s te m s a d e lg a d o D
Y Q
A
.r v t
M-103
BUILDING 1, THIRD FLOOR, PHASE 2,
MECHANICAL PLANS
4 18AD
REPLACE/UPGRADE
HEATING WATER SYSTEM
JOHN L. MCCLELLAN MEMORIAL VETERANS HOSPITAL
4300 W 7TH STREET
LITTLE ROCK, AR 72205
JULY 9, 2024
100% BID DOCUMENTS
598-21-10822-100
RHA
Scale: 1/8" = 1'-0"
BUILDING 1, THIRD FLOOR, PHASE 2, MECHANICAL
DEMOLITION PLAN
Scale: 1/8" = 1'-0"
BUILDING 1, THIRD FLOOR, PHASE 2, MECHANICAL NEW
WORK PLAN
NORTH
0 4 8 16
NORTH
0 4 8 16
1 DEMOLISH HEAT EXCHANGER AND ASSOCIATED
PIPING, CONTROLS, AND SUPPORTS COMPLETE
AFTER NEW HEAT EXCHANGER IS
OPERATIONAL. CAP STEAM CONDENSATE 4"
AFF.
2 EXISTING EQUIPMENT PAD TO REMAIN.
3 DEMOLISH ABANDONED EXPANSION TANK AND
ASSOCIATED PIPING. MAKE ROOM FOR NEW
MECHANICAL EQUIPMENT.
4 DEMOLISH ABANDONED DUCT AND EQUIPMENT.
MAKE ROOM FOR NEW MECHANICAL
EQUIPMENT AND PATHWAY.
5 EXISTING PIPING TO REMAIN.
6 DEMOLISH HHWS/R BRANCHES FEEDING
EXISTING HE-1 AND HE-2 TO MAIN AND CAP.
1 INSTALL NEW HEAT EXCHANGERS, STEAM
CONTROL VALVE(S), STEAM TRAP(S), AND
ASSOCIATED EQUIPMENT. INSTALL NEW
EQUIPMENT PER MANUFACTURER'S
RECOMMENDATIONS.
2 POD 7E WILL BE CONNECTED TO THE MAIN HHW
DISTRIBUTION LOOP.
3 KEEP A WALKWAY OF 48" FROM WALL AND 8'
AFF CLEAR OF ALL NEW MECHANICAL
EQUIPMENT AND PIPING.
4 MAINTAIN PIPING AT A HEIGHT OF 8' AFF OR
ABOVE.
5 INSTALL TEMPERATURE CONTROL PANEL.
PROVIDE UNISTRUT STAND FOR TCP.
6 ROUTE CONDENSATE DRAIN LINE ALONG WALL
AND CONNECT TO 4" MPR RISER FROM ENERGY
CENTER BELOW. SLOPE AT 1/8" PER FOOT.
7 ROUTE CONDENSATE LINE FROM 1-HX-1 ALONG
WALL. TIE INTO DRAIN LINE FROM 1-HX-2. SLOPE
AT 1/8" PER FOOT.
8 INSTALL 1-ST-1 AT A HIGHER ELEVATION THAN
1-ST-2 TO ALLOW FOR SLOPE.
9 INSTALL NEW HEAT EXCHANGERS, STEAM
CONTROL VALVE(S), STEAM TRAP(S), AND
ASSOCIATED EQUIPMENT. INSTALL NEW
EQUIPMENT PER MANUFACTURER'S
RECOMMENDATIONS.
10 ROUTE 1 1/2" HWS TO EXPANSION TANK.
11 PROVIDE FLOW TRANSMITTER IN HEATING
WATER PIPING. ALSO SEE 1/M-602.
12 INSTALL NEW 6" PIPE WITH CAPPED VALVE TO
PREPARE FOR CONNECTION TO NEW HEAT
PUMPS IN PHASE 3.
Scale: No Scale
CONVERTOR AND PUMP 2, PHASE 2 SECTION
Scale: No Scale
CONVERTOR AND PUMP 1, PHASE 2, DEMO SECTION
Scale: No Scale
CONVERTOR 1, PHASE 2, SECTION
Scale: No Scale
CONVERTOR AND PUMP SET, PHASE 2, SECTION
N
AREA OF WORK
KEY PLAN
SCALE: NO SCALE
A
D E
C B
DocuSign Envelope ID: 5EB0D510-95A5-4101-AB5F-A83F346704F6
7/8/2024
*13
*13 bmaxwell Text Box
13 PROVIDE END OF MAIN TRAP ASESEMBLY IN
BOTTOM OF STEAM PIPING AND EXTEND THE
3/4" CR-30 TO THE CR-30 CONDENSATE DRAIN
INDICATED IN NOTE 6. SEE M-501, DETAIL 6.
bmaxwell Text Box
1-1/2" TO
bmaxwell Text Box
1-1/2" TO
bmaxwell Cloud bmaxwell Cloud bmaxwell Text Box 1-1/2" bmaxwell Text Box 8" bmaxwell Text Box 8" bmaxwell Text Box 6" bmaxwell Text Box 6" bmaxwell Text Box 6" bmaxwell Text Box 6" bmaxwell Text Box 6" bmaxwell Text Box 6" bmaxwell Text Box bmaxwell Cloud bmaxwell Text Box 8" bmaxwell Cloud bmaxwell Text Box 1 1/2" bmaxwell Text Box 6" bmaxwell Cloud bmaxwell Callout
REDUCE THE 6" CR-30 TO THE EXISTING 4" CR-30 IN VERTICAL.
bmaxwell Line bmaxwell Line bmaxwell Text Box 8" bmaxwell Text Box 6" bmaxwell Text Box 8" bmaxwell Text Box 8" bmaxwell Text Box 8" bmaxwell Text Box 6" bmaxwell Text Box 8" bmaxwell Text Box 8" bmaxwell Text Box 8" bmaxwell Text Box 8" bmaxwell Line bmaxwell Line bmaxwell Text Box 6" bmaxwell Text Box
8" HWS
bmaxwell Text Box
8" HWS
bmaxwell Text Box
8" HWS
bmaxwell Line bmaxwell Line bmaxwell Callout
PROVIDE A STEAM PIPE ANCHOR TO RESIST 6,300 LBS FORCE.
NOTE:
ALL DRIP POINTS ON STEAM MAINS SHALL BE PROVIDED WITH A 12" MINIMUM HIGH DRIP LEG FROM BOTTOM OF STEAM MAIN TO TRAP INLET. DRIP LEG SHALL HAVE 6" SCALE POCKET BELOW TRAP INLET.
DIELECTRIC FITTING WHERE
RETURN IS COPPER PIPE
TO RETURN MAIN
FLOAT AND THERMOSTATIC TRAP.
SEE PLANS, AND SCHEDULES
1" GATE
VALVE
SCHEDULE 80 STEEL PIPE
PIPE SIZE SHALL BE
SAME SIZE AS TRAP
BYPASS - INSTALL IN HORIZONTAL
PLANE LEVEL WITH TRAP OR IN
VERTICAL PLANE & BELOW TRAP
DRIP LEG OR EQUIPMENT CONNECTION.
MAKE THE SAME SIZE AS THE SUPPLY
MAIN OR EQUIPMENT CONNECTION. SEE
NOTE 1
M
IN
M
IN
FLOW
SEE DRAWINGS
FOR PIPE SIZES
SCALE
POCKET/ DRIP
LEG
SCHEDULE
80 STEEL
PIPE
NOM. SIZE (IN.)
PIPE (FT.)
TUBING (FT.)
5 FT
THRU 3/4
1 1 1/4
1 1/2
HANGER ROD
INSULATION (VAPOR
BARRIER TYPE IS
REQUIRED FOR
LOW TEMPERATURE
PIPE)
PROVIDE HIGH
COMPRESSIVE
STRENGHT
INSULATION (9 PSF
MIN. DENSITY) UNDER
INSULATION SHIELD
INSULATION SHIELD AT
HANGER
WELD
SADDLE
ADJUSTABLE CLEVIS HANGER TYPE 1 - SEE
SPECIFICATIONS
ADJUSTABLE CLEVIS HANGER TYPE 43 - SEE
SPECIFICATIONS
1/2" DIA. HANGER RODS
WITH 36" MAX. SPACING
ON EACH CHANNEL
BAND
1-5/8" 12 GAUGE CHANNEL
OR 2" x 2" x 1/4" ANGLE
NOTES:
SEE SPECIFICATIONS FOR DETAILED
HANGER REQUIREMENTS.
SIDE VIEW TRAPEZE HANGER
FOR UP TO 1000 LB. UNIFORM
LOAD
1" MAX.
PROVIDE INSULATION SHIELD &
INSERT FOR ALL PIPING (8" MIN.)
2 2 1/2 3 4 5 6 8 10 12
11 12 14 16 17 19 22 23
9 10 12 13 14 16 - -
NOTE: FOR TRAPEZE HANGER TAKE SPACING OF SMALLEST SIZE ON TRAPEZE
MAXIMUM PIPE/TUBING SUPPORT SPACING
VENT PIPE THROUGH
ROOF SUPPORT AS
INDICATED ON DWGS.
(NOTES 1,2)
PIPE THREADED
INTO ELBOW (SAME
AIZE AS ELBOW)
DRIP PAN ELBOW
(SECTIONAL VIEW)
FLEXIBLE
CONNECTOR
CONNECTION TO
PRESSURE
VESSEL OR PIPE
OPEN DRAIN
(NOTE 3)
SAFETY
VALVE
PROVIDE UNION
UNLESS SAFETY VALVE
HAS FLANGED OUTLET
3/4" [20mm] DRAIN
TO FLOOR DRAIN
OR OPEN SIGHT
DRAIN (NOTE 4)
M
IN
[2 m m
3"
[76mm]
24" MAX.
[610mm]
ELEVATION
NOTES:
1. UNLESS OTHERWISE SHOWN ON THE DRAWINGS, SIZE THE VENT PIPE SO THAT
STEAM IS NOT BLOWN OUT AT THE VENT PIPE ENTRANCE. UTILIZE THE CALCULATION
METHOD CONTAINED IN ANSI B31.1. POWER PIPING CODE, APPENDIX 11.
2. VENT PIPE SHALL TERMINATE 6' [1829mm] MIN. ABOVE FINISHED ROOF.
3. DISCHARGE OF DRAIN MUST BE DIRECTED AWAY FROM PLATFORMS OR OTHER
AREAS WHICH PERSONNEL MAY OCCUPY.
4. DO NOT CONNECT ANY OTHER DRAIN TO THE DRIP PAN ELBOW DRAIN PIPE.
D
ABOVE 2" [50mm] DIA. PIPE 2" [50mm] DIA. & SMALLER
VERTICAL
2 1/2" [65mm] DIA.
ABOVE 2" [50mm] DIA. PIPE 2" [50mm] DIA. & SMALLER
HORIZONTAL
2 1/2" [65mm] DIA.
LONG RADIUS WELDED
ELBOW
PIPE GUIDES (TYP)
3" THICK EXPANSION ABSORBING
CUSHION. USE MINERAL WOOL
INORGANIC GLASS AND CERAMIC
FIBER BONDED WITH THERMOSETTING
RESINS, 3-5 LB/CU FT DENSITY WITH
CONTINUOUS LIMIT USE ABOVE 450 °F
NOTE:
ANCHORS SHALL BE PROVIDED PER SPECIFICATIONS AND IN ACCORDANCE WITH STRUCTURAL REQUIREMENTS. SUBMIT
ANCHORING DATA FOR APPROVAL BY A/E.
PIPE DRAIN INDIRECT TO FLOOR DRAIN.
HOUSEKEEPING PAD
RELIEF PLUG
PRE-CHARGING
AIR CONNECTION
PRESSURE GAUGE
AUTOMATIC AIR VENT
SAFETY RELIEF
VALVE (TYP)
FROM SYSTEM
AIR VENT (HIGH CAPACITY
FLOAT TYPE)
DOMESTIC COLD
WATER MAKE-UP WITH
RPBP AND PRV, SEE
PLUMBING PLANSAIR SEPARATOR
(WITHOUT STRAINER)
ROUTE FULL SIZE DRAIN LINE TO
NEAREST FLOOR DRAIN. REFER
TO PLUMBING DRAWINGS FOR
FLOOR DRAIN LOCATION.
TO PUMP SUCTION
FLOOR
PRESSURIZED EXPANSION TANK. INSTALL PER
MANUFACTURERS RECOMMENDATIONS.
CONNECT TO SIDE OF PIPE MAIN.
AVOID TOP OR BOTTOM CONNECTIONS
TO PREVENT AIR OR DEBRIS FROM
ENTERING PIPE TO THE TANK.
LOCK-SHIELD TYPE SHUTOFF VALVE
SHUTOFF VALVE (TYP)
STEAM PIPE RISER
INVERTED BUCKET
TRAP ASSEMBLY
MV
MANUAL AIR VENT
TO BUILDING
LOAD
GATE VALVE
CONDENSATE
UNION
STRAINER
SCHEDULE 80
STEEL PIPE
TO BUILDING LOAD
1" GATE VALVE
DRIP LEG
6" MIN. (TYP.)
12" MIN. (TYP.)
FLASH STEAM SUPPLY
CONNECTED TO 30 PSI STEAM
MAIN NEAR PRV STATION
HPR (90 PSI) CONDENSATE
FROM PRV STATION TRAPS
3" HPR4" LPS
HORIZONTAL FLASH TANK
24" HIGH, 2" ANGLE IRON
SUPPORT LEGS WITH
CROSS BRACING.
SIMILAR TO DETAIL 4/M-502
DRIP LEG
4" LPRLPR (30 PSI)
CONDENSATE
FROM TRAPS
CAP ALL
OPENINGS THAT
ARE NOT USED
3" LPR
LPR (30 PSI)
CONDENSATE
TO CONDENSATE
PUMPS
TT
-- TT
HW
R
HW
S
D
CONTROL V
ALVES IN
2/3 & 1/3
SIZE A
RRANGEMENT, T
YP.
DDC
TEMPERATURE
SENSORS
THERMOMETER (TYP.)
RUN DRAIN LINE FROM
RELIEF VALVE TO NEAREST
FLOOR DRAIN. (TYP.)
SEE SCHEDULES
FOR RELIEF
VALVE SETTING
HEAT
EXCHANGER
(TYP.)
TEST
PLUG
(TYP.)
1/2" [15mm]
CHECK VALVE
VACUUM
BREAKER (TYP.)
MPS
STEAM
SUPPLY
NOTE:
1. THE ABOVE DETAIL SHOWS REQUIRED PIPING FOR TWO HEAT EXCHANGERS IN PARALLEL.
2. PROVIDE SADDLE SUPPORTS AND LEGS OR HANGERS FOR HEAT EXCHANGER. MOUNTING HEIGHT SHALL
BE ADJUSTED TO FACILITATE GRAVITY RETURN OF STEAM CONDENSATE.
3. MAKE THE BYPASS THE SAME SIZE AS THE CONNECTIONS TO THE CONTROL VALVES.
4. CONTROL VALVES SHALL BE IN A 1/3 AND 2/3 SIZE ARRANGEMENT.
1/3 VALVE SIZED FOR
APPROX. 7,000 LBS/HR
STEAM (TYP.)
2/3 VALVE SIZED
FOR APPROX.
14,000 LBS/HR
STEAM (TYP.)
PIPING SHALL BE EASILY
REMOVABLE FOR HEAT
EXCHNAGER TUBE CLEANING
6" MIN. (TYP.)
12" MIN. (TYP.)
THERMOSTATIS
AIR VENT (TYP.)
SCALE
POCKET (TYP.)
MPR TO FLASH
TANK (TYP.)
BYPASS
PI
PI
VIBRATION ISOLATORS
WHERE REQUIRED
LOAD BEARING CALCIUM
SILICATE INSULATION AT
ALL HANGER POINTS
PIPE
CARBON STEEL
INSULATION WITH
PROTECTIVE
SHEETMETAL
SHIELD
NOTES:
UNIT MOUNTED THERMOSTAT SHALL MAINTAIN SPACE TEMPERATURE BY CYCLING
THE FAN. THE CONTROL VALVE SHALL BE INTERLOCKED WITH THE FAN.
PIPING CONNECTIONS TO HORIZONTAL TYPE STEAM UNIT HEATER
STEAM CONTROL
VALVE, 2 POSITION
UNIT HEATER
SCALE POCKET
STEAM SUPPLY
STEAM CONDENSATE RETURN
M
IN
M
IN
THERMOMETER
SHUT OFF VALVE
WITH MEMORY
STOP
NON-SLAM CHECK
VALVE
FLEXIBLE
CONNECTOR
BUTTERFLY VALVE
STRAINER WITH
BLOWDOWN VALVE
BALL VALVE
FLEXIBLE
CONNECTOR
PRESSURE
GAUGE
GALVANIZED
STEEL DRIP PAN
UNDER CHILLED
WATER PUMPS 3/4"
DRAIN PIPED TO
FLOOR DRAIN
4" HIGH
CONCRETE PAD
CONCENTRIC
INCREASER
CONCENTRIC
REDUCER
NOTES:
1. Y TYPE STRAINER BLOWDOWN HEIGHT SHALL ACCOMMODATE 55 GALLON DRUM.
2. PUMP INSTALLATION IS DIAGRAMMATIC AND INTENDED TO SHOW THE MAJOR COMPONENTS REQUIRED FOR INSTALLATION. THE INSTALLED PIPING CONFIGURATION SHALL BE BASED ON THE ACTUAL PUMP PROVIDED.
THE CONTRACTOR SHALL SUBMIT FOR APPROVAL A COORDINATION DRAWING SHOWING PUMP, PIPING, AND
ACCESSORIES AS REQUIRED BY THIS INSTALLATION DETAIL.
3. ALL PAD, PUMP, AND PIPING DRAINS SHALL BE HARD PIPED TO NEAREST FLOOR DRAIN, TYPICAL.
4. FIRST 3 HANGERS FOR EACH PIPE AND BRANCH SHALL BE SPRING & NEOPRENE TYPE. TYPE "H" FOR 4" [100mm] DIA. PIPE AND SMALLER. TYPE "H-P" FOR 5" [125mm] DIA. PIPE AND LARGER.
AV AV
NOTE 4
PUMP
HOSE CONNECTION
THERMOMETER
INERTIA BASE
WITH ISOLATORS
Engineers Architects
Revisions: Date
Drawing Title
Approved
Project Title
Location
VA PROJECT NUMBER
Building Number
Drawing Number
Dwg of
VA FORM 08-6231
Office of Construction and Facilities Management
CONSULTANTS: PROJECT MANAGER
Date Checked Drawn
ACG Project Number
Headquarters:
Apogee Consulting Group, P.A.
1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs#
/1
/2
:2
:0
P
M C
U s e rs \a d e lg a d o \D o c u m e n ts \A
M E
P F
-1
-J L M
U p g ra d e H e a ti n g
W a te r
S y s te m s a d e lg a d o D
Y Q
A
.r v t
M-501
MECHANICAL DETAILS
10 17AD
REPLACE/UPGRADE
HEATING WATER SYSTEM
JOHN L. MCCLELLAN MEMORIAL VETERANS HOSPITAL
4300 W 7TH STREET
LITTLE ROCK, AR 72205
MARCH 19, 2024
100% BID DOCUMENTS
598-21-10822-100
RHA
Scale: No Scale
FLOAT AND THERMOSTATIC STEAM TRAP ASSEMBLY
DETAIL
Scale: No Scale
PIPE HANGER DETAIL
Scale: No Scale
STEAM SAFETY VALVE DETAIL
Scale: No Scale
THERMOMETER WELL INSTALLATION DETAIL
Scale: No Scale
EXPANSION LOOP DETAIL
Scale: No Scale
AIR SEPARATOR AND EXPANSION TANK PIPING DETAIL
Scale: No Scale
END OF STEAM LINE DRIP TRAP DETAIL
Scale: No Scale
FLASH TANK DETAIL
Scale: No Scale
HEAT EXCHANGER - STEAM TO HOT WATER DETAIL
Scale: No Scale
CLEVIS HANGER DETAIL
Scale: No Scale
PIPING CONNECTIONS TO HORIZONTAL TYPE STEAM UNIT
HEATER
Scale: No Scale
VERTICAL SPLIT CASE PUMP DETAIL
DocuSign Envelope ID: F9FD3E58-8A33-4126-A35C-3A458E784347
3/19/2024 bmaxwell Line bmaxwell Snapshot bmaxwell Arrow bmaxwell Arrow bmaxwell Snapshot bmaxwell Snapshot bmaxwell Arrow bmaxwell Arrow bmaxwell Arrow bmaxwell Callout
CONNECT NEW FLASH TANK TO EXISTING PIPING (TYPICAL)
bmaxwell Cloud bmaxwell Cloud bmaxwell Cloud bmaxwell Text Box 6" bmaxwell Text Box 8" bmaxwell Text Box 8" bmaxwell Text Box 8" bmaxwell Text Box 10" bmaxwell Text Box 8" bmaxwell Text Box 8" bmaxwell Text Box 6" bmaxwell Text Box 8" bmaxwell Text Box 6" bmaxwell Text Box 6" bmaxwell Text Box 8" bmaxwell Text Box 8" bmaxwell Text Box 8" bmaxwell Text Box 8" bmaxwell Text Box 8" bmaxwell Text Box 8" bmaxwell Text Box 10" bmaxwell Text Box 8" bmaxwell Text Box 8" bmaxwell Text Box 8" bmaxwell Text Box 8" bmaxwell Text Box 8"
1" GATE VALVE
DRIP LEG OR EQUIPMENT CONNECTION.
MAKE THE SAME SIZE AS THE SUPPLY MAIN
OR EQUIPMENT CONNECTION. SEE NOTE 1
BYPASS-INSTALL IN HORIZONTAL
PLANE LEVEL WITH TRAP OR IN
VERTICAL PLANE & BELOW TRAP
PIPE SIZE SHALL BE THE
SAME SIZE AS TRAP
TO RETURN MAIN
SEE DRAWINGS FOR PIPE SIZES
DIELECTRIC
FITTING WHERE
RETURN IS
COPPER PIPE
INVERTED BUCKET
TRAP. SEE PLANS
AND SCHEDULES
M
IN
M
IN
FLOW
NOTES:
1. ALL DRIP POINTS ON STEAM MAINS SHALL BE PROVIDED
WITH A 10" MINIMUM HIGH DRIP LEG FROM THE BOTTOM OF
STEAM MAIN TO TRAP INLET. DRIP LEG SHALL HAVE 6" SCALE
POCKET BELOW TRAP INLET.
2. PROVIDE BYPASS PIPING.
TYPICAL STRUCTURAL
STEEL MEMBER FOR
EQUIPMENT
NUMBER OF
ISOLATION UNITS AS
REQUIRED
DR
IV
EN
EQ
UI
PM
EN
T
M O
TO
R
SHAFT
TYPE "B"
WELDED STEEL BASE
SECTION A-A
TYPE "1"
CONCRETE INERTIA BASE
NUMBER OF
ISOLATION UNITS AS
REQUIRED
TYPICAL STRUCTURAL
STEEL MEMBER FOR
EQUIPMENT
ALL WELDED STEEL
FRAMEWORK
STRUCTURAL
STEEL FRAME
SPRING ISOLATOR
ANCHOR BOLT
REINFORCING BARS
SLEEVE
DR
IV
EN
EQ
UI
PM
EN
T
M O
TO
R
SHAFT
A
A
ANCHOR BOLT
PIPE SLEEVE
(5D, 3" MIN.)
WELD HEAD TO PLATE OR
BEND OVER END 5D
FLOOR
CONCRETE BASE
A
2D
5D
D
SECTION B-BPLAN
A
B B
L
W
D
EQUIPMENT BASE PLATETYPICAL ANCHOR BOLT
AND NUT & WASHER
PROVIDE DOUBLE SLAB
REINFORCING IN BASE AREA
SECTION A-A (BASE POURED WITH FLOOR SLAB)
L /1
M
IN
SECTION A-A (BASE NOT POURED WITH FLOOR SLAB)
EQUIPMENT BASE PLATE
L /1
M
IN
TYPICAL ANCHOR BOLT
AND NUT & WASHER
PROVIDE #3 BARS 12" O.C.
EACH WAY IN THE BASE &
DOWEL BASE FLOOR
NOTE:
L & W DIMENSIONS SHALL BE 6" GREATER
THAN THE EQUIPMENT BASE PLATE
16"
RISER THROUGH ROOF
45°
PAINT ENTIRE ASSEMBLY OFF-WHITE WITH
RUSTPROOF HIGH TEMPERATURE EXTERIOR
PAINT. SUBMIT COLOR TO ENGINEER FOR
APPROVAL
8" MINIMUM. TALLER
AS REQUIRED FOR
ROOFING WARRANTY
FINISHED ROOF LINE
WELDED <4"x4"x5/16" ANCHORS FROM OPENING
FRAME TO THE PIPE HORIZONTALLY AND
DOWN
AT A 45° ANGLE IN TWO LOCATIONS 90° APART.
STEAM RELIEF VENT
INSULATION BELOW
ROOF LINE ONLY
FLEXIBLE SEALANT RATED FOR 400°F
STEEL SLEEVE
MINIMUM 3" CLEAR FROM
PIPE TO METAL LINER
TACKWELD BIRDSCREEN
1" SQUARE STAINLESS
HARDWARE CLOTH
PAINT INSIDE PIPE TO
3" BELOW BOTTOM
OF ANGLED CUT
CONTINUOUS WELD
STAINLESS STEEL HOOD
18" GUAGE IN
16" TALL SQUARE CURB
WITH METAL LINER
SEE ROOF CURB DETAIL
ROOF CONSTRUCTION
PACKED INSULATION
METAL ESCUTCHEON
FORCE FIT TO PIPE
STRUCTURAL FRAME AROUND
OPENING. SEE STRUCTURAL
DRAWINGS OR PROVIDE <4"x4"x5/16"
APPROXIMATELY X'-X" ABOVE ROOF
DECK (6" BELOW TOP OF SCREEN
WALL). VERIFY SCREEN WALL
HEIGHT PRIOR TO FABRICATION TO
MAINTAIN 6" DIMENSION.
BOLT SADDLE
TO FRAME
PROVIDE A SUPPORT AT EACH END
OF THE HEAT EXCHANGER
2x HEAT EXCHANGER DIAMETER
NOTE: ALL WELDED CONSTRUCTION
HEAT EXCHANGER
SADDLE
2" x 2" x 1/4"
ANGLES
PRESSURE GAUGE
IN-LINE PUMP AND MOTOR. PUMP
MOTOR SHAFT SHALL BE
MOUNTED IN THE VERTICAL
POSITION
UNION (TYP.)
ISOLATION VALVE (TYP.)
SYSTEM
FLOW
STRAINER WITH
BLOW-DOWN VALVE,
HOSE END AND CAP
ECCENTRIC REDUCER
TO PUMP INLET
ECCENTRIC INCREASER
TO PUMP OUTLET
SHUT-OFF
COCK (TYP.)
CHECK VALVE
SPRING VIBRATION ISOLATION
HANGERS.
FROM PUMP DISCHARGE
TO PUMP SUCTION
3/4" HOSE BIBB
PRESSURE RATED
GALVANIZED IRON
POT FEEDER SEE
SPECIFICATION FOR
SIZE
1" FILL
FUNNEL
LOCATED AT 4'-0"
AFF
SIGHT GLASS OR
FLOW INDICATOR
AIR VENT
GLOBE VALVE (TYP.)
NOTE:
SUPPORT POT FEEDER PER MANUFACTURER'S GUIDELINES. LOCATE
IN CLOSE PROXIMITY TO SYSTEM PUMPS.
HOT
WATER
SUPPLY
HOT
WATER
RETURN
RETURN
SUPPLY
COIL
3/4" DRAIN WITH
HOSE END AND CAP
DRAIN VALVE AT
LOW POINT
STRAINER WITH BLOW-DOWN
VALVE, HOSE END AND CAP
ISOLATION
VALVE (TYP.)
UNION (TYP.)
MANUAL AIR VENT
AT HIGH POINT
BALANCING VALVE
TEMPERATURE CONTROL VALVE
PRESSURE AND TEMPERATURE PLUG (TYP.)
NOTES:
1. PIPE COILS TO ALLOW COIL PULL BY REMOVING UNIONS ADJACENT TO COIL.
2. THIS DETAIL APPLIES TO ALL EQUIPMENT COIL CONNECTIONS, EXCEPT AIR HANDLING UNITS, INCLUDING FAN COIL
UNITS, TERMINAL UNITS, ETC. THAT ARE DESIGNATED FOR TWO-WAY CONTROL.
3. SEE DRAWINGS FOR SUPPLY AND RETURN PIPE SIZES.
4. REFER TO SPECIFICATIONS FOR OPTIONS INVOLVING ACCESSORY COMBINATION.
PIPE
GROUND PIPE TO
BUILDING GROUND
PIPE SLEEVE. EXTEND 1"
BEYOND PENETRATION
PIPE INSULATION AS
REQUIRED
POURED CONCRETE
OR C.M.U. WALL.
APPROVED
FIRESTOPPING SEALANT
NOTES:
1. DRAIN ALL LOW POINTS AS INDICATED ABOVE.
2. WHERE SCALE POCKETS ARE SHOWN ON PIPE RISER DIAGRAMS
AND/OR PLANS, LOCATE DRAIN AT BOTTOM OF SCALE POCKET.
ELEVATION:
THREADED PIPING
ELEVATION:
WELDED PIPING
TYPICAL WATER PIPING
REDUCER, IF REQUIRED
3/4" BALL VALVE
ADAPTER TO 3/4" HOSE
THREAD. PROVIDE HOSE
CAP NUT
NOTES:
1. VENT ALL HIGH POINTS INDICATED ABOVE.
2. IF AUTOMATIC AIR VENTS ARE USED, PIPE DISCHARGE TO DRAIN.
ELEVATION
MV
OR
AV
1/4" COPPER TUBING
1/2" X 4" NIPPLE
1/2" BALL VALVE
AIR VENT
CIRCULATING WATER
PIPING
1-ST-4
10"
VENT TO ATMOSPHERE
PILOT
CONTROL
LINE
SIPHON (TYP.)
INVERTED
BUCKET TRAP
ASSEMBLY SEE
NOTE 3. (TYP.)
8"
N.C.
6"
6"
10 x D1 MIN. 20 x D2 MIN.
4 x D2 MIN.
NOTES:
1. STEAM VALVES AND ACCESSORIES ON HPS SHALL BE 300 PSI
RATED.
2. PROVIDE A LINE-SIZED STEAM SEPERATOR IN SUPPLY PIPING TO
EACH PRV.
3. SEE INVERTED BUCKET TRAP ASSEMBLY DETAIL FOR ACCESSORIES
REQUIRED AT TRAP ASSEMBLIES.
4. STRAINERS SHOWN ON THIS DETAIL SHALL BE INSTALLED ON THEIR
SIDE TO AVOID TRAPPING CONDENSATE.
STEAM
CONDENSATE
RETURN TO
FLASH TANK
(TYPICAL FOR
ALL ON THIS
DETAIL.)
REDUCER (TYP.) IF
REQUIRED
PRESSURE
GAUGE (TYP.)
8"
1-ST-5
3"
6" 1-ST-7
1-ST-8
1-ST-6
NOTE 2
NOTE 2
STEAM FROM
FLASH TANK
STEAM FLOW
METER
10"
SUPPLY
TO 1-HX-1
AND 2
Engineers Architects
Revisions: Date
Drawing Title
Approved
Project Title
Location
VA PROJECT NUMBER
Building Number
Drawing Number
Dwg of
VA FORM 08-6231
Office of Construction and Facilities Management
CONSULTANTS: PROJECT MANAGER
Date Checked Drawn
FULLY SPRINKLERED
ACG Project Number
Headquarters:
Apogee Consulting Group, P.A.
1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.
/1
/2
:2
:0
P
M C
U s e rs \a d e lg a d o \D o c u m e n ts \A
M E
P F
-1
-J L M
U p g ra d e H e a ti n g
W a te r
S y s te m s a d e lg a d o D
Y Q
A
.r v t
M-502
MECHANICAL DETAILS
11 17JT
REPLACE/UPGRADE
HEATING WATER SYSTEM
JOHN L. MCCLELLAN MEMORIAL VETERANS HOSPITAL
4300 W 7TH STREET
LITTLE ROCK, AR 72205
MARCH 19, 2024
100% BID DOCUMENTS
598-21-10822-100
RHA
Scale: No Scale
INVERTED BUCKET STEAM TRAP ASSEMBLY DETAIL
Scale: No Scale
VIBRATION ISOLATION BASES DETAIL
Scale: No Scale
CONCRETE EQUIPMENT BASES DETAIL
Scale: No Scale
STEAM VENT (CONTINUOUS, WET) DETAIL
Scale: No Scale
HEAT EXCHANGER SUPPORT DETAIL
Scale: No Scale
IN-LINE PUMP PIPING DETAIL
Scale: No Scale
CHEMICAL POT FEEDER DETAIL
Scale: No Scale
THREE-WAY COIL PIPING DETAIL
Scale: No Scale
TYPICAL PIPE PENETRATION THROUGH SECURE AREA
WALL DETAIL
Scale: No Scale
TYPICAL CHILLED WATER AND HOT WATER PIPING DRAIN
VALVE CONNECTIONS
Scale: No Scale
TYPICAL MANUAL AIR VENT
Scale: No Scale
STEAM PRESSURE REDUCING STATION (1/3 AND 2/3
ARRANGMENT)
DocuSign Envelope ID: F9FD3E58-8A33-4126-A35C-3A458E784347
3/19/2024 bmaxwell Text Box
1-PRV-1
bmaxwell
1-PRV-2
Engineers Architects
Revisions: Date
Drawing Title
Approved
Project Title
Location
VA PROJECT NUMBER
Building Number
Drawing Number
Dwg of
VA FORM 08-6231
Office of Construction and Facilities Management
CONSULTANTS: PROJECT MANAGER
Date Checked Drawn
ACG Project Number
Headquarters:
Apogee Consulting Group, P.A.
1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.
/1
/2
:2
:1
P
M C
U s e rs \a d e lg a d o \D o c u m e n ts \A
M E
P F
-1
-J L M
U p g ra d e H e a ti n g
W a te r
S y s te m s a d e lg a d o D
Y Q
A
.r v t
M-601
MECHANICAL SCHEDULES
12 17AD
REPLACE/UPGRADE
HEATING WATER SYSTEM
JOHN L. MCCLELLAN MEMORIAL VETERANS HOSPITAL
4300 W 7TH STREET
LITTLE ROCK, AR 72205
MARCH 19, 2024
100% BID DOCUMENTS
598-21-10822-100
RHA
STEAM TO WATER HEAT EXCHANGER SCHEDULE
MARK LOCATION
AREA AND/OR BLDG
SERVED SYSTEM
WATER CONDITIONS STEAM PRESSURE
CONTROL
VALVE
SHELL
DIAMETER TUBE LENGTH TRAP
REMARKSTYPE FLOW EWT LWT WPD
ENT CONTROL
VALVE
ENT HEAT
EXCHANGER LBS/HR IN FT
TRAP CAPACITY
# LBS/HR
1-HX-1 3E100 BUILDING 1 MAIN HEATING WATER SHELL & TUBE 1200 GPM 160 °F 180 °F 2.3 FT 30 psig 20 psig 20000 24" 4 1-ST-1 5042 1,2
1-HX-2 3E100 BUILDING 1 MAIN HEATING WATER SHELL & TUBE 1200 GPM 160 °F 180 °F 2.3 FT 30 psig 20 psig 20000 24" 4 1-ST-2 5042 1,2
1-HX-3 3E100 BUILDING 1 OR HEATING WATER SHELL & TUBE 140 GPM 160 °F 180 °F 2.3 FT 30 psig 20 psig 1500 12 1/2" 3 1-ST-3 3971 1
HYDRONIC PUMP SCHEDULE
MARK LOCATION
AREA AND/OR
BLDG
SERVED
SYSTEM
AND/OR
SERVICE TYPE
CIRCULATING FLUID
MIN % EFF
ELECTRICAL MOTOR
SPEED
CONTROL REMARKSFLUID
FLOW HEAD
NPSH
REQUIRED
SP GR
NOMINAL
POWER
PHASE VOLT R.P.M.GPM FT FT HP
1-HWP-1 3E-100 BUILDING 1
MAIN
HEATING
WATER
VERTICAL
SPLIT CASE
PUMP
Water 1200 GPM 100 12 1 80 40 3 460 1800 VARIABLE 1,2,3
1-HWP-2 3E-100 BUILDING 1
MAIN
HEATING
WATER
VERTICAL
SPLIT CASE
PUMP
Water 1200 GPM 100 12 1 80 40 3 460 1800 VARIABLE 1,2,3
1-HWP-3 3E-100 BUILDING 1
OR
HEATING
WATER
VERTICAL
IN-LINE PUMP
Water 140 GPM 100 18 1 73.36 5 3 460 3800 VARIABLE 1,2
AIR SEPARATOR SCHEDULE
MARK LOCATION
SYSTEM
AND/OR
SERVICE TYPE
AIR SEPARATOR
BASIS OF DESIGN REMARKS
SIZE
(IN)
FLOW
GPM
MAX WPD
FT
BUILT-IN
STRAINER
REQ'D
1-AS-1 MECH 004 HEATING
WATER
FULL FLOW
TANGENTIAL
8 1200 2 NO BELL & GOSSETT RL-8F 1, 2
1-AS-3 MECH 004 HEATING
WATER
FULL FLOW
TANGENTIAL
4 140 2 NO BELL & GOSSETT RL-4F 1, 2
NOTES:
1. INSTALL PER MANUFACTURER'S RECOMMENDATIONS.
2. PROVIDE INVERTER DUTY PREMIUM EFFICIENCY MOTOR, PROVIDE A VARIABLE FREQUENCY DRIVE WITH BYPASS.
3. 100% REDUNDANT PUMP.
NOTES:
1. INSTALL PER MANUFACTURER'S RECOMMENDATIONS.
2. 100% REDUNDANT HEAT EXCHANGER.
STEAM PRESSURE REDUCING VALVE SCHEDULE
Mark LOCATION
SYSTEM
AND/OR
SERVICE
REQUIRED
CAPACITY
(LBS/HR)
MAX FLOW WIDE
OPEN VALVE
(LBS/HR)
VALVE SIZE
(IN)
PRESSURE
BASIS OF
DESIGN REMARKS
IN OUT
PSIG PSIG
1-PRV-1 3E100 PRV STATION 20000 24000 2 1/2 90 30 SPIRAX
SARCO 25P
1,2,3
1-PRV-2 3E100 PRV STATION 20000 24000 4 90 30 SPIRAX
SARCO 25P
1,2,3
FLASH TANK SCHEDULE
MARK LOCATION SYSTEM
EST FLASH
STEAM
(LBS/HR)
DIMENSIONS (IN)
BASIS OF
DESIGN REMARKSDIAMETER LENGTH
1-FT-1 MEZZ BUILDING 1 2100 24 72 ARMSTRONG
HAFT-2472
1, 2,3,4
EXPANSION TANK SCHEDULE
MARK LOCATION
SYSTEM AND/OR
SERVICE TYPE
SYSTEM TEMPERATURE (°F) INITIAL
PRESSURE IN
TANK (PSIG)
MAX
OPERATING
PRESSURE
(PSIG)
FILL PRESSURE AT TANK
(PSIG)
MIN VOLUME
TANK (GAL)
MIN BLADDER
VOLUME
(GAL)
PIPE SIZE TO
TANK (IN)
COLD WATER
FILL SIZE (IN) BASIS OF DESIGN REMARKSMIN TEMP MAX TEMP RELIEF VALVE AT TANK
1-ET-1 3E100 HEATING WATER,
PRIMARY
BLADDER 50 190 15 60 65 60 370 370 1 0.75 BELL & GOSSETT
B-1400
1,2,3,4
1-ET-3 3E100 HEATING WATER, ORs BLADDER 50 190 15 60 65 60 80 80 1 0.75 BELL & GOSSETT B-200
1,2,3,4
STEAM TRAP SCHEDULE
MARK LOCATION
SYSTEM
AND/OR
SERVICE
TRAP CAPACITY
(LBS/HR) SIZING (▲P)
MAX INLET
PRESSURE
(PSI) TRAP TYPE TRAP SIZE
BASIS OF DESIGN
MANUF.
BASIS OF
DESIGN
MODEL NO. REMARKS
1-ST-1 BUILDING 1
MER
1-HX-1 4760 30 20.00 psi FLOAT AND
THERMOSTATIC
2" SPIRAX SARCO FT-15 1
1-ST-2 BUILDING 1
MER
1-HX-2 4760 30 20.00 psi FLOAT AND
THERMOSTATIC
2" SPIRAX SARCO FT-15 1
1-ST-3 BUILDING 1
MER
1-HX-3 4580 30 20.00 psi FLOAT AND
THERMOSTATIC
2" SPIRAX SARCO FT-15 1
1-ST-4 PRV STATION LPR DRIP 800 30 30.00 psi INVERTED BUCKET 1/2" SPIRAX SARCO 211/12 1, 2
1-ST-5 PRV STATION LPR DRIP 800 30 30.00 psi INVERTED BUCKET 1/2" SPIRAX SARCO 211/12 1, 2
1-ST-6 PRV STATION HPR DRIP 1200 60 90.00 psi INVERTED BUCKET 3/4" SPIRAX SARCO 212/12 1, 2
1-ST-7 PRV STATION 1/3 SEPARATOR 800 60 90.00 psi INVERTED BUCKET 1/2" SPIRAX SARCO 211/12 1, 2
1-ST-8 PRV STATION 2/3 SEPARATOR 800 60 90.00 psi INVERTED BUCKET 1/2" SPIRAX SARCO 211/12 1, 2
BYPASS CHEMICAL FEEDER SCHEDULE
MARK LOCATION
SYSTEM AND/OR
SERVICE TYPE
CAPACITY
GALLONS
MAX
PRESSURE
PSIG
BASIS OF
DESIGN REMARKS
1-CF-3 BUILDING 1
MER
HEATING WATER CARTRIDGE FILTER
FEEDER
5 300 NEPTUNE
VTFC-5-1
1,2,3
1-CF-1 BUILDING 1
MER
HEATING WATER CARTRIDGE FILTER
FEEDER
5 300 NEPTUNE
VTFC-5-1
1,2,3
TEMPERATURE CONTROL VALVE
Mark LOCATION
SYSTEM
AND/OR
SERVICE
FLOW RATE SIZE
BODY
MATERIAL RATED Cv MODEL TRIM
PRESSURE
BASIS OF DESIGN REMARKSLBS/HR IN
IN OUT
PSIG PSIG
1-TCV-1 3E100 1-HX-1 (2/3) 4133 3 CAST IRON 42 LEA31PTSUSS.2 PRV STATION 30 20 SPIRAX SARCO SPIRA-TROL 1,2,3
1-TCV-2 3E100 1-HX-1 (1/3) 8266 3 CAST IRON 116 LEA31PTSUSS.2 PRV STATION 30 20 SPIRAX SARCO SPIRA-TROL 1,2,3
1-TCV-3 3E100 1-HX-2 (1/3) 4133 3 CAST IRON 42 LEA31PTSUSS.2 PRV STATION 30 20 SPIRAX SARCO SPIRA-TROL 1,2,3
1-TCV-4 3E100 1-HX-2 (2/3) 8266 3 CAST IRON 116 LEA31PTSUSS.2 PRV STATION 30 20 SPIRAX SARCO SPIRA-TROL 1,2,3
1-TCV-5 3E100 1-HX-3 1447 3 CAST IRON 29 LEA31PTSUSS.2 PRV STATION 30 20 SPIRAX SARCO SPIRA-TROL 1,2,3
NOTES:
1. INSTALL PER MANUFACTURER'S RECOMMENDATIONS.
2. TANK SHALL BE ASME STAMPED TO 150 PSIG.
3. TANK SHALL HAVE REPLACEABLE HEAVY DUTY BUTYL RUBBER BLADDER.
4. VERTICAL WITH FLOOR STAND.
NOTES:
1. INSTALL PER MANUFACTURER'S RECOMMENDATIONS.
2. PROVIDE INVERTED BUCKET TRAP WITH INTEGRAL CHECK VALVE AND LARGE VENT. SIMILAR TO SPIRAX-SARCO 200 SERIES.
NOTES:
1. INSTALL PER MANUFACTURER'S RECOMMENDATIONS.
2. PROVIDE WITH ELECTRIC MODULATING ACTUATOR, 24 VAC ACTUATOR.
3. VALVE SHALL HAVE HAND WHEEL MANUAL OVERRIDE.
NOTES:
1. INSTALL PER MANUFACTURER'S RECOMMENDATIONS.
2. TANK SHALL BE ASME STAMPED TO 150 PSIG. PROVIDE WITH GAUGE CLASS AND INSULATION COVER BY MANUFACTURER.
3. PROVIDE WITH GAUGE GLASS AND INSULATION COVER BY MANUFACTURER.
4. PROVIDE WITH TOP CONNECTIONS ONE 2" NPT, ONE 4" FLANGED, ONE 6" FLANGED, TWO SAME SIDE 4" FLANGED INLETS, TWO BOTTOM 3" NPT AND ONE BOTTOM 1" NPT DRAIN.
NOTES:
1. INSTALL PER MANUFACTURER'S RECOMMENDATIONS.
2. MAXIMUM WORKING PRESSURE IS AT 200 DEGREES F. PROVIDE FEEDER WITH LEGS.
3. INITIAL FILTER USED FOR CLEANING SYSTEM SHALL BE A 20 MICRON PLEATED FILTER. AFTER SYSTEM IS CLEANED, INSTALL A
5 MICRON PLEATED FILTER FOR USE DURING SYSTEM OPERATION. PROVIDE ONE SPARE 5 MICRON PLEATED FILTER TO VA.
NOTES:
1. INSTALL PER MANUFACTURER'S RECOMMENDATIONS.
2. TANK SHALL BE ASME STAMPED TO 125 PSIG.
NOTES:
1. INSTALL PER MANUFACTURER'S RECOMMENDATIONS.
2. VALVE SHALL BE PILOT OPERATED WITH AN ELECTRIC PILOT OVERRIDE. POWER CONNECTION SHALL BE 115VAC.
3. PRV SHALL BE RATED AT 300 PSI WORKING PRESSURE AND HAVE 300 POUND FLANGES.
DocuSign Envelope ID: F9FD3E58-8A33-4126-A35C-3A458E784347
3/19/2024 bmaxwell Rectangle bmaxwell Text Box
FT-46
bmaxwell Text Box
FT-46
bmaxwell Text Box
FT-46
bmaxwell Text Box
HM-34
bmaxwell Text Box
HM-34
bmaxwell Text Box
HM-34
bmaxwell Text Box
HM-34
bmaxwell Text Box
HM-34
bmaxwell Snapshot bmaxwell Rectangle bmaxwell Rectangle bmaxwell Text Box
MPR DRIP
bmaxwell Text Box
MPR DRIP
bmaxwell Snapshot bmaxwell Rectangle bmaxwell Text Box
1-ST-9
bmaxwell Text Box bmaxwell Text Box 12000 bmaxwell Text Box 14000 bmaxwell Text Box 16000 bmaxwell Rectangle bmaxwell Cloud bmaxwell Snapshot bmaxwell Text Box
1-ST-10
bmaxwell Text Box
1-HX-1 MPS
bmaxwell
1-HX-2 MPS
| m-502 FROM 20240327 MECH_100_% |
| Pages from 20240327 MECH_100_% |
| Pages from 22-100 100% BD MECH |
| 22-100 Flash tank plan |
File details come from the government source that posted it. Updated .