36C25622R0094 265100 Interior Lighting .docx
DOCX document 36 KB Posted
- Attached to
- Z2DA--Project #502-19-107 - Replace AHU-104 - Construction - 36C25622R0094 Federal contract opportunity
- Solicitation number
- 502-19-107
About this file
This document contains a specification section for an interior lighting project and details of a related federal contract opportunity. The specification covers requirements for LED exit signs, downlights, troffers, and other interior fixtures. Product standards, testing procedures, submittal requirements, and installation instructions are provided.
The related federal contract opportunity is for project number 502-19-107 to replace an air handling unit and ductwork at a Department of Veterans Affairs health care facility. The specification and opportunity are associated with renovations requiring new interior lighting fixtures that meet the standards detailed in the specification section. Product submittals and certifications are required to be provided, along with installation and testing of the new lighting systems.
View the file
Other files for this federal contract opportunity
Show all 50
Z2DA--Project #502-19-107 - Replace AHU-104 - Construction - 36C25622R0094 has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REPLACE AHU #104 AND DUCTWORK BLDG. 7
DEPARTMENT OF VETERANS AFFAIRS HEALTH CARE SYSTEM-ALEXANDRIA, LA
PROJECT NO.: 502-19-107
SECTION 26 51 00
INTERIOR LIGHTING
PART 1 GENERAL
1.1 DESCRIPTION:
A. This section specifies the furnishing, installation, and connection of the interior lighting systems. The terms “lighting fixture,” “fixture,” and “luminaire” are used interchangeably.
1.2 RELATED WORK
| A. | Section 01 74 19, CONSTRUCTION WASTE MANAGEMENT: Disposal of lamps. |
| B. | Section 02 41 00, DEMOLITION: Removal and disposal of lamps and ballasts. |
| C. | Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS: Requirements that apply to all sections of Division 26. |
| D. | Section 26 05 19, LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES: Low-voltage conductors. |
| E. | Section 26 05 26, GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS: Requirements for personnel safety and to provide a low impedance path to ground for possible ground fault currents. |
F. Section 26 09 23, LIGHTING CONTROLS: Low Voltage lighting controls used for control of the lighting systems.
G. Section 26 27 26, WIRING DEVICES: Line Voltage Wiring devices used for control of the lighting systems.
1.3 qualITY ASSURANCE A. Refer to Paragraph, QUALIFICATIONS (PRODUCTS AND SERVICES), in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS.
1.4 SUBMITTALS
| A. | Submit six copies of the following in accordance with Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS. |
| 1. | Shop Drawings: |
| a. | Submit the following information for each type of lighting fixture designated on the LIGHTING FIXTURE SCHEDULE, arranged in order of lighting fixture designation. |
| b. | Material and construction details, include information on housing and optics system. |
| c. | Physical dimensions and description. |
| d. | Wiring schematic and connection diagram. |
| e. | Installation details. |
| f. | Energy efficiency data. |
| g. | Photometric data based on laboratory tests complying with IES Lighting Measurements testing and calculation guides. |
| h. | lumen output (initial and mean), color rendition index (CRI), rated life (hours), and color temperature (degrees Kelvin). |
| i. | For LED lighting fixtures, submit US DOE LED Lighting Facts label, and IES L70 rated life. |
| 2. | Manuals: |
| a. | Submit, simultaneously with the shop drawings, complete maintenance and operating manuals, including technical data sheets, wiring diagrams, and information for ordering replacement parts. |
| b. | If changes have been made to the maintenance and operating manuals originally submitted, submit updated maintenance and operating manuals two weeks prior to the final inspection. |
| 3. | Certifications: Two weeks prior to final inspection, submit the following. |
| a. | Certification by the Contractor that the interior lighting systems have been properly installed and tested. |
1.5 APPLICABLE PUBLICATIONS
| A. | Publications listed below (including amendments, addenda, revisions, supplements, and errata) form a part of this specification to the extent referenced. Publications are referenced in the text by designation only. |
| B. | American National Standards Institute (ANSI): |
| C78.1-91 | Fluorescent Lamps - Rapid-Start Types - Dimensional and Electrical Characteristics |
| C78.376-01 | Chromaticity of Fluorescent Lamps |
| C. | American Society for Testing and Materials (ASTM): |
| C635-07 | Manufacture, Performance, and Testing of Metal Suspension Systems for Acoustical Tile and Lay-in Panel Ceilings |
| D. | Environmental Protection Agency (EPA): |
| 40 CFR 261 | Identification and Listing of Hazardous Waste |
| E. | Federal Communications Commission (FCC): |
| CFR Title 47, Part 15 | Radio Frequency Devices |
| CFR Title 47, Part 18 | Industrial, Scientific, and Medical Equipment |
| F. | Illuminating Engineering Society (IES): |
| LM-79-08 | Electrical and Photometric Measurements of Solid-State Lighting Products |
| LM-80-08 | Measuring Lumen Maintenance of LED Light Sources |
| LM-82-12 | Characterization of LED Light Engines and LED Lamps for Electrical and Photometric Properties as a Function of Temperature |
| G. | Institute of Electrical and Electronic Engineers (IEEE): |
| C62.41-91 | Surge Voltages in Low Voltage AC Power Circuits |
| H. | International Code Council (ICC): |
| IBC-12 | International Building Code |
| I. | National Fire Protection Association (NFPA): |
| 70-17 | National Electrical Code (NEC) |
| 101-12 | Life Safety Code |
| J. | National Electrical Manufacturer's Association (NEMA): |
| C82.1-04 | Lamp Ballasts – Line Frequency Fluorescent Lamp Ballasts |
| C82.2-02 | Method of Measurement of Fluorescent Lamp Ballasts |
| C82.4-02 | Lamp Ballasts - Ballasts for High-Intensity Discharge and Low-Pressure Sodium (LPS) Lamps (Multiple-Supply Type) |
| C82.11-11 | Lamp Ballasts - High Frequency Fluorescent Lamp Ballasts |
| LL-9-09 | Dimming of T8 Fluorescent Lighting Systems |
| SSL-1-10 | Electronic Drivers for LED Devices, Arrays, or Systems |
| K. | Underwriters Laboratories, Inc. (UL): |
| 496-08 | Lampholders |
| 542-0599 | Fluorescent Lamp Starters |
| 924-12 | Emergency Lighting and Power Equipment |
| 935-01 | Fluorescent-Lamp Ballasts |
| 1598-08 | Luminaires |
8750-09.................Light Emitting Diode (LED) Light Sources for Use in Lighting Products
PART 2 PRODUCTS
2.1 LIGHTING FIXTURES
| A. | Shall be in accordance with NFPA, UL, as shown on drawings, and as specified. | |
| B. | Sheet Metal: | |
| 1. | Shall be formed to prevent warping and sagging. Housing, trim and lens frame shall be true, straight (unless intentionally curved), and parallel to each other as designed. | |
| 2. | Wireways and fittings shall be free of burrs and sharp edges, and shall accommodate internal and branch circuit wiring without damage to the wiring. | |
| 3. | When installed, any exposed fixture housing surface, trim frame, door frame, and lens frame shall be free of light leaks. | |
| 4. | Hinged door frames shall operate smoothly without binding. Latches shall function easily by finger action without the use of tools. | |
| C. | Drivers and LED modules shall be serviceable while the fixture is in its normally installed position. Drivers shall not be mounted to removable reflectors or wireway covers unless so specified. | |
| D. | Recessed fixtures mounted in an insulated ceiling shall be listed for use in insulated ceilings. D. | Mechanical Safety: Lighting fixture closures (lens doors, trim frame, hinged housings, etc.) shall be retained in a secure manner by captive screws, chains, aircraft cable, captive hinges, or fasteners such that they cannot be accidentally dislodged during normal operation or routine maintenance. |
| E. | Metal Finishes: | |
| 1. | The manufacturer shall apply standard finish (unless otherwise specified) over a corrosion-resistant primer, after cleaning to free the metal surfaces of rust, grease, dirt, and other deposits. Edges of pre-finished sheet metal exposed during forming, stamping, or shearing processes shall be finished in a similar corrosion resistant manner to match the adjacent surface(s). Fixture finish shall be free of stains or evidence of rusting, blistering, or flaking, and shall be applied after fabrication. | |
| 2. | Interior light reflecting finishes shall be white with not less than 85 percent reflectance, except where otherwise shown on the drawing. | |
| F. | Lighting fixtures shall have a specific means for grounding metallic wireways and housings to an equipment grounding conductor. | |
| G. | Lighting fixtures in SPD areas shall be certified by NSF P442 as a cleanroom light fixture. These fixtures shall also be listed as suitable for splash zone / washdown locations. |
2.2 LED exit light fixtures
| A. | Exit light fixtures shall meet applicable requirements of NFPA and UL. |
| B. | Housing and door shall be die-cast aluminum. |
| C. | For general purpose exit light fixtures, door frame shall be hinged, with latch. For vandal-resistant exit light fixtures, door frame shall be secured with tamper-resistant screws. |
| D. | Finish shall be satin or fine-grain brushed aluminum. |
| E. | There shall be no radioactive material used in the fixtures. |
| F. | Fixtures: |
| 1. | Inscription panels shall be cast or stamped aluminum a minimum of 2.25 mm (0.090 inch) thick, stenciled with 150 mm (6 inch) high letters, baked with red color stable plastic or fiberglass. Lamps shall be luminous Light Emitting Diodes (LED) mounted in center of letters on red color stable plastic or fiberglass. |
| 2. | Double-Faced Fixtures: Provide double-faced fixtures where required or as shown on drawings. |
| 3. | Directional Arrows: Provide directional arrows as part of the inscription panel where required or as shown on drawings. Directional arrows shall be the "chevron-type" of similar size and width as the letters and meet the requirements of NFPA 101. |
| G. | Voltage: Multi-voltage (120 – 277V). |
2.3 led light fixtures
| A. | General: |
| 1. | LED light fixtures shall be in accordance with IES, NFPA, UL, as shown on the drawings, and as specified. |
| 2. | LED light fixtures shall be Reduction of Hazardous Substances (RoHS)-compliant. |
| 3. | LED drivers shall include the following features unless otherwise indicated: |
| a. | Minimum efficiency: 85% at full load. |
| b. | Minimum Operating Ambient Temperature: -20˚ C. (-4˚ F.) |
| c. | Input Voltage: 120 - 277V (±10%) at 60 Hz. |
d. Capable of dimming down to 1% of rated output using 0-10V dimming.
| e. | Integral short circuit, open circuit, and overload protection. | |
| f. | Power Factor: ≥ 0.95. | |
| g. | Total Harmonic Distortion: ≤ 20%. | |
| h. | Comply with FCC 47 CFR Part 15. | |
| 4. | LED modules shall include the following features unless otherwise indicated: | |
| a. | Comply with IES LM-79 and LM-80 requirements. | |
| b. | Minimum CRI 80 and color temperature 3500˚ K unless otherwise specified in LIGHTING FIXTURE SCHEDULE. | |
| c. | Minimum Rated Life: 50,000 hours per IES L70. | |
| d. | Light output lumens as indicated in the LIGHTING FIXTURE SCHEDULE.B. | LED Downlights: |
| e. | Housing, LED driver, and LED module shall be products of the same manufacturer. | |
| B. | LED Troffers: | |
| 1. | LED drivers, modules, and reflector shall be accessible, serviceable, and replaceable from below the ceiling. | |
| 2. | Housing, LED driver, and LED module shall be products of the same manufacturer. |
PART 3 EXECUTION
3.1 INSTALLATION
| A. | Installation shall be in accordance with the NEC, manufacturer's instructions, and as shown on the drawings or specified. |
| B. | Align, mount, and level the lighting fixtures uniformly. |
| C. | Wall-mounted fixtures shall be attached to the studs in the walls, or to a 20 gauge metal backing plate that is attached to the studs in the walls. Lighting fixtures shall not be attached directly to gypsum board. |
| D. | Lighting Fixture Supports: |
| 1. | Shall provide support for all of the fixtures. Supports may be anchored to channels of the ceiling construction, to the structural slab or to structural members within a partition, or above a suspended ceiling. |
| 2. | Shall maintain the fixture positions after cleaning. |
| 3. | Shall support the lighting fixtures without causing the ceiling or partition to deflect. |
| 4. | Outlet boxes for support of lighting fixtures (where permitted) shall be secured directly to the building structure with approved devices or supported vertically in a hung ceiling from the building structure with a nine-gauge wire hanger and be secured by an approved device to a main ceiling runner or cross runner to prevent any horizontal movement relative to the ceiling. |
| E. | Furnish and install the new lamps as specified for all lighting fixtures installed under this project, and for all existing lighting fixtures reused under this project. |
| F. | The electrical and ceiling trades shall coordinate to ascertain that approved lighting fixtures are furnished in the proper sizes and installed with the proper devices (hangers, clips, trim frames, flanges, etc.), to match the ceiling system being installed. |
| G. | Bond lighting fixtures to the grounding system as specified in Section 26 05 26, GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS. |
| H. | At completion of project, replace all defective components of the lighting fixtures at no cost to the Government. |
| I. | Dispose of lamps per requirements of Section 01 74 19, CONSTRUCTION WASTE MANAGEMENT, and Section 02 41 00, DEMOLITION. |
3.2 Acceptance Checks and Tests
| A. | Perform the following: |
| 1. | Visual Inspection: |
| a. | Verify proper operation by operating the lighting controls. |
| b. | Visually inspect for damage to fixtures, lenses, reflectors, diffusers, and louvers. Clean fixtures, lenses, reflectors, diffusers, and louvers that have accumulated dust, dirt, or fingerprints during construction. |
| 2. | Electrical tests: |
| a. | Exercise dimming components of the lighting fixtures over full range of dimming capability by operating the control devices(s) in the presence of the COTR. Observe for visually detectable flicker over full dimming range, and replace defective components at no cost to the Government. |
| b. | Burn-in all lamps that require specific aging period to operate properly, prior to occupancy by Government. Burn-in period to be 40 hours minimum, unless specifically recommended otherwise by the lamp manufacturer. Replace any lamps and ballasts which fail during burn-in. |
3.3 Follow-Up Verification
A. Upon completion of acceptance checks and tests, the Contractor shall show by demonstration in service that the lighting systems are in good operating condition and properly performing the intended function.
---END---
26 51 00 - 18
File details come from the government source that posted it. Updated .