About this file

This document contains a technical specification for a construction project to replace an air handling unit and ductwork at a Department of Veterans Affairs health care facility. The specification outlines requirements for temporary environmental controls to be implemented during construction, including plans for protecting air and water quality, disposing of waste, controlling noise, and restoring damaged property. The solicitation number for the project is 502-19-107, with the name "Replace AHU-104 - Construction - 36C25622R0094." The opportunity is open for bidding and the contracting agency is the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 16. Offerors should follow all environmental protection guidelines detailed in the specification when submitting bids for the project.

View the file

Other files for this federal contract opportunity

Other files attached to Z2DA--Project #502-19-107 - Replace AHU-104 - Construction - 36C25622R0094, newest first.
File Type Posted
36C25622R0094 ECS Geotechnical Report.pdf PDF
36C25622R0094 0004.docx DOCX document
36C25622R0094 0002.docx DOCX document
36C25622R0094 0001.docx DOCX document
36C25622R0094 Brand Name JA 502-19-107 Redacted.pdf PDF
36C25622R0094 COVID-19 Safety Protocols for Federal Contractors Rev 2.docx DOCX document
36C25622R0094 280800 Commissioning of Electronic Safety and Security Systems .docx DOCX document
36C25622R0094 000110 VHA Master Specifications Rev 2.docx DOCX document
36C25622R0094 262726 Wiring Devices .docx DOCX document
36C25622R0094 283100 Fire Detection and Alarm .doc DOC document
36C25622R0094 260923 Lighting Controls.docx DOCX document
36C25622R0094 232500 HVAC WATER TREATMENT .docx DOCX document
36C25622R0094 260511 Requirements for ELEC installation.docx DOCX document
36C25622R0094 234000 HVAC AIR CLEANING DEVICES .docx DOCX document
36C25622R0094 238100 DECENTRALIZED UNITARY HVAC EQUIPMENT.docx DOCX document
36C25622R0094 260800 Commissioning of Electrical Systems.docx DOCX document
36C25622R0094 232113 HYDRONIC PIPING .docx DOCX document
36C25622R0094 230923 DIRECT DIGITAL CONTROL SYSTEM FOR HVAC .doc DOC document
36C25622R0094 014500 Quality Control.docx DOCX document
36C25622R0094 013526 Safety Requirements .docx DOCX document
36C25622R0094 099100 Painting .docx DOCX document
36C25622R0094 095100 Acoustical Ceilings .docx DOCX document
36C25622R0094 087100 Door Hardware .docx DOCX document
36C25622R0094 092216 Non-Structural Metal Framing .docx DOCX document
36C25622R0094 096513 Resilient Base and Accessories.docx DOCX document
36C25622R0094 079200 Joint Sealants .docx DOCX document
36C25622R0094 092900 Gypsum Board .docx DOCX document
36C25622R0094 076000 Flashing and Sheet Metal .docx DOCX document
36C25622R0094 Project Risk Assessment .pdf PDF
36C25622R0094 260526 Grounding and Bonding.docx DOCX document
36C25622R0094 260519 Low voltage conductors .docx DOCX document
36C25622R0094 312011 Earthwork .docx DOCX document
36C25622R0094 262416 Panelboards.docx DOCX document
36C25622R0094 281300 Physical Access Control System .doc DOC document
36C25622R0094 EXHIBIT A.docx DOCX document
36C25622R0094 262911 Motor Controllers .docx DOCX document
36C25622R0094 316500 Helical Piles.doc DOC document
36C25622R0094 282300 Video Surveillance .docx DOCX document
36C25622R0094 236400 PACKAGED WATER CHILLERS.docx DOCX document
36C25622R0094 233700 AIR OUTLETS AND INLETS.docx DOCX document
36C25622R0094 260541 UNDERGROUND ELEC CONSTRUCTION .docx DOCX document
36C25622R0094 230541 NOISE AND VIBRATION CONTROL FOR HVAC PIPING AND EQUIPMENT .docx DOCX document
36C25622R0094 230512 GENERAL MOTOR REQUIREMENTS FOR HVAC AND STEAM GENERATION EQUIPMENT.docx DOCX document
36C25622R0094 233100 HVAC DUCTS AND CASINGS.docx DOCX document
36C25622R0094 233600 AIR TERMINAL UNITS .docx DOCX document
36C25622R0094 238216 AIR COILS .doc DOC document
36C25622R0094 230800 COMMISSIONING OF HVAC SYSTEMS.docx DOCX document
36C25622R0094 033000 Cast in Place Concrete.docx DOCX document
36C25622R0094 019100 General Commissioning Requirements .docx DOCX document
36C25622R0094 090600 Schedule for Finishes .docx DOCX document
Show all 50

Z2DA--Project #502-19-107 - Replace AHU-104 - Construction - 36C25622R0094 has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REPLACE AHU #104 AND DUCTWORK BLDG. 7

DEPARTMENT OF VETERANS AFFAIRS HEALTH CARE SYSTEM-ALEXANDRIA, LA

PROJECT NO.: 502-19-107

SECTION 01 57 19

TEMPORARY ENVIRONMENTAL CONTROLS.

PART 1 - GENERAL

1.1 DESCRIPTION

A.

This section specifies the control of environmental pollution and damage that the Contractor must consider for air, water, and land resources. It includes management of visual aesthetics, noise, solid waste, radiant energy, and radioactive materials, as well as other pollutants and resources encountered or generated by the Contractor. The Contractor is obligated to consider specified control measures with the costs included within the various contract items of work.

B.

Environmental pollution and damage is defined as the presence of chemical, physical, or biological elements or agents which:

1.

Adversely effect human health or welfare, 2.

Unfavorably alter ecological balances of importance to human life, 3.

Effect other species of importance to humankind, or;

4.

Degrade the utility of the environment for aesthetic, cultural, and historical purposes.

C.

Definitions of Pollutants:

1.

Chemical Waste: Petroleum products, bituminous materials, salts, acids, alkalis, herbicides, pesticides, organic chemicals, and inorganic wastes.

2.

Debris: Combustible and noncombustible wastes, such as leaves, tree trimmings, ashes, and waste materials resulting from construction or maintenance and repair work.

3.

Sediment: Soil and other debris that has been eroded and transported by runoff water.

4.

Solid Waste: Rubbish, debris, garbage, and other discarded solid materials resulting from industrial, commercial, and agricultural operations and from community activities.

5.

Surface Discharge: The term "Surface Discharge" implies that the water is discharged with possible sheeting action and subsequent soil erosion may occur. Waters that are surface discharged may terminate in drainage ditches, storm sewers, creeks, and/or "water of the United States" and would require a permit to discharge water from the governing agency.

6.

Rubbish: Combustible and noncombustible wastes such as paper, boxes, glass and crockery, metal and lumber scrap, tin cans, and bones.

7.

Sanitary Wastes:

a.

Sewage: Domestic sanitary sewage and human and animal waste.

b.

Garbage: Refuse and scraps resulting from preparation, cooking, dispensing, and consumption of food.

1.2 QUALITY CONTROL

A.

Establish and maintain quality control for the environmental protection of all items set forth herein.

B.

Record on daily reports any problems in complying with laws, regulations, and ordinances. Note any corrective action taken.

1.3 references

A.

The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.

B.

U.S. National Archives and Records Administration (NARA):

33 CFR 328

Definitions

1.4 SUBMITTALS

A.

In accordance with Section, 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES, furnish the following:

1.

Environmental Protection Plan: After the contract is awarded and prior to the commencement of the work, the Contractor shall meet with the Resident Engineer to discuss the proposed Environmental Protection Plan and to develop mutual understanding relative to details of environmental protection. Not more than 20 days after the meeting, the Contractor shall prepare and submit to the Resident Engineer for approval, a written and/or graphic Environmental Protection Plan including, but not limited to, the following:

a.

Name(s) of person(s) within the Contractor's organization who is (are) responsible for ensuring adherence to the Environmental Protection Plan.

b.

Name(s) and qualifications of person(s) responsible for manifesting hazardous waste to be removed from the site.

c.

Name(s) and qualifications of person(s) responsible for training the Contractor's environmental protection personnel.

d.

Description of the Contractor's environmental protection personnel training program.

e.

A list of Federal, State, and local laws, regulations, and permits concerning environmental protection, pollution control, noise control and abatement that are applicable to the Contractor's proposed operations and the requirements imposed by those laws, regulations, and permits.

f.

Methods for protection of features to be preserved within authorized work areas including trees, shrubs, vines, grasses, ground cover, landscape features, air and water quality, fish and wildlife, soil, historical, and archeological and cultural resources.

g.

Procedures to provide the environmental protection that comply with the applicable laws and regulations. Describe the procedures to correct pollution of the environment due to accident, natural causes, or failure to follow the procedures as described in the Environmental Protection Plan.

h.

Permits, licenses, and the location of the solid waste disposal area.

i.

Drawings showing locations of any proposed temporary excavations or embankments for haul roads, material storage areas, structures, sanitary facilities, and stockpiles of excess or spoil materials. Include as part of an Erosion Control Plan approved by the District Office of the U.S. Soil Conservation Service and the Department of Veterans Affairs.

j.

Environmental Monitoring Plans for the job site including land, water, air, and noise.

k.

Work Area Plan showing the proposed activity in each portion of the area and identifying the areas of limited use or nonuse. Plan should include measures for marking the limits of use areas. This plan may be incorporated within the Erosion Control Plan.

B.

Approval of the Contractor's Environmental Protection Plan will not relieve the Contractor of responsibility for adequate and continued control of pollutants and other environmental protection measures.

1.5 PROTECTION OF ENVIRONMENTAL RESOURCES

A.

Protect environmental resources within the project boundaries and those affected outside the limits of permanent work during the entire period of this contract. Confine activities to areas defined by the specifications and drawings.

B.

Protection of Land Resources: Prior to construction, identify all land resources to be preserved within the work area. Do not remove, cut, deface, injure, or destroy land resources including trees, shrubs, vines, grasses, topsoil, and land forms without permission from the Resident Engineer. Do not fasten or attach ropes, cables, or guys to trees for anchorage unless specifically authorized, or where special emergency use is permitted.

1.

Work Area Limits: Prior to any construction, mark the areas that require work to be performed under this contract. Mark or fence isolated areas within the general work area that are to be saved and protected. Protect monuments, works of art, and markers before construction operations begin. Convey to all personnel the purpose of marking and protecting all necessary objects.

2.

Protection of Landscape: Protect trees, shrubs, vines, grasses, landforms, and other landscape features shown on the drawings to be preserved by marking, fencing, or using any other approved techniques.

a.

Box and protect from damage existing trees and shrubs to remain on the construction site.

b.

Immediately repair all damage to existing trees and shrubs by trimming, cleaning, and painting with antiseptic tree paint.

c.

Do not store building materials or perform construction activities closer to existing trees or shrubs than the farthest extension of their limbs.

3. Handle and dispose of solid wastes in such a manner that will prevent contamination of the environment. Place solid wastes (excluding clearing debris) in containers that are emptied on a regular schedule. Transport all solid waste off Government property and dispose of waste in compliance with Federal, State, and local requirements.

4.

Store chemical waste away from the work areas in corrosion resistant containers and dispose of waste in accordance with Federal, State, and local regulations.

5.

Handle discarded materials other than those included in the solid waste category as directed by the Resident Engineer.

C.

Protection of Water Resources: Keep construction activities under surveillance, management, and control to avoid pollution of surface and ground waters and sewer systems. Implement management techniques to control water pollution by the listed construction activities that are included in this contract.

1.

Washing and Curing Water: Do not allow wastewater directly derived from construction activities to enter water areas. Collect and place wastewater in retention ponds allowing the suspended material to settle, the pollutants to separate, or the water to evaporate.

2.

Control movement of materials and equipment at stream crossings during construction to prevent violation of water pollution control standards of the Federal, State, or local government.

SPEC WRITER NOTE: Specify additional operations unique to this contract.

3.

Monitor water areas affected by construction.

D.

Protection of Fish and Wildlife Resources: Keep construction activities under surveillance, management, and control to minimize interference with, disturbance of, or damage to fish and wildlife. Prior to beginning construction operations, list species that require specific attention along with measures for their protection.

E.

Protection of Air Resources: Keep construction activities under surveillance, management, and control to minimize pollution of air resources. Burning is not permitted on the job site. Keep activities, equipment, processes, and work operated or performed, in strict accordance with the State of // insert Name of State and title of State Air Pollution Statue, Rule, or Regulation // and Federal emission and performance laws and standards. Maintain ambient air quality standards set by the Environmental Protection Agency, for those construction operations and activities specified.

1.

Particulates: Control dust particles, aerosols, and gaseous by-products from all construction activities, processing, and preparation of materials (such as from asphaltic batch plants) at all times, including weekends, holidays, and hours when work is not in progress.

2.

Particulates Control: Maintain all excavations, stockpiles, haul roads, permanent and temporary access roads, plant sites, spoil areas, borrow areas, and all other work areas within or outside the project boundaries free from particulates which would cause a hazard or a nuisance. Sprinklering, chemical treatment of an approved type, light bituminous treatment, baghouse, scrubbers, electrostatic precipitators, or other methods are permitted to control particulates in the work area.

3.

Hydrocarbons and Carbon Monoxide: Control monoxide emissions from equipment to Federal and State allowable limits.

4.

Odors: Control odors of construction activities and prevent obnoxious odors from occurring.

F.

Reduction of Noise: Minimize noise using every action possible. Perform noise-producing work in less sensitive hours of the day or week as directed by the Resident Engineer. Maintain noise-produced work at or below the decibel levels and within the time periods specified.

1.

Perform construction activities involving repetitive, high-level impact noise only between 8:00 a.m. and 6:00p.m unless otherwise permitted by local ordinance or the Resident Engineer. Repetitive impact noise on the property shall not exceed the following dB limitations:

Time Duration of Impact Noise
Sound Level in dB
More than 12 minutes in any hour
70
Less than 30 seconds of any hour
85
Less than three minutes of any hour
80
Less than 12 minutes of any hour
75

2.

Provide sound‑deadening devices on equipment and take noise abatement measures that are necessary to comply with the requirements of this contract, consisting of, but not limited to, the following:

a.

Maintain maximum permissible construction equipment noise levels at 15 m (50 feet) (dBA):

MATERIALS HANDLING

CRANES
75
DERRICKS IMPACT
75
SAWS
75

b.

Use shields or other physical barriers to restrict noise transmission.

c.

Provide soundproof housings or enclosures for noise‑producing machinery.

d.

Use efficient silencers on equipment air intakes.

e.

Use efficient intake and exhaust mufflers on internal combustion engines that are maintained so equipment performs below noise levels specified.

f.

Line hoppers and storage bins with sound deadening material.

g.

Conduct truck loading, unloading, and hauling operations so that noise is kept to a minimum.

G.

Restoration of Damaged Property: If any direct or indirect damage is done to public or private property resulting from any act, omission, neglect, or misconduct, the Contractor shall restore the damaged property to a condition equal to that existing before the damage at no additional cost to the Government. Repair, rebuild, or restore property as directed or make good such damage in an acceptable manner.

H.

Final Clean‑up: On completion of project and after removal of all debris, rubbish, and temporary construction, Contractor shall leave the construction area in a clean condition satisfactory to the Resident Engineer. Cleaning shall include off the station disposal of all items and materials not required to be salvaged, as well as all debris and rubbish resulting from demolition and new work operations.

‑ ‑ ‑ E N D ‑ ‑ ‑