36C25622R0094 237300 INDOOR CENTRAL STATION AIR HANDLING UNITS.docx

DOCX document 46 KB Posted

Attached to
Z2DA--Project #502-19-107 - Replace AHU-104 - Construction - 36C25622R0094 Federal contract opportunity
Solicitation number
502-19-107
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 16

About this file

This document contains specifications for replacing an indoor central station air handling unit at a Department of Veterans Affairs health care facility. The specifications require furnishing and installing a new air handling unit to replace an existing unit serving Building 7. Key requirements include an insulated double-wall galvanized steel casing with a stainless steel inner liner; foam insulation with a minimum R-value of 13; multiple direct-drive plenum fans in a pre-engineered frame capable of modulating in unison; premium efficiency motors suitable for variable frequency drive operation; epoxy-coated coils in high humidity areas; factory testing and startup by an authorized representative; and commissioning in accordance with HVAC commissioning specifications. The solicitation number and opportunity type indicate this procurement is open for bids under solicitation number 502-19-107 by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 16.

View the file

Other files for this federal contract opportunity

Other files attached to Z2DA--Project #502-19-107 - Replace AHU-104 - Construction - 36C25622R0094, newest first.
File Type Posted
36C25622R0094 ECS Geotechnical Report.pdf PDF
36C25622R0094 0004.docx DOCX document
36C25622R0094 0001.docx DOCX document
36C25622R0094 Project Risk Assessment .pdf PDF
36C25622R0094 260526 Grounding and Bonding.docx DOCX document
36C25622R0094 260519 Low voltage conductors .docx DOCX document
36C25622R0094 312011 Earthwork .docx DOCX document
36C25622R0094 262416 Panelboards.docx DOCX document
36C25622R0094 281300 Physical Access Control System .doc DOC document
36C25622R0094 EXHIBIT A.docx DOCX document
36C25622R0094 262911 Motor Controllers .docx DOCX document
36C25622R0094 316500 Helical Piles.doc DOC document
36C25622R0094 282300 Video Surveillance .docx DOCX document
36C25622R0094 236400 PACKAGED WATER CHILLERS.docx DOCX document
36C25622R0094 233700 AIR OUTLETS AND INLETS.docx DOCX document
36C25622R0094 260541 UNDERGROUND ELEC CONSTRUCTION .docx DOCX document
36C25622R0094 230541 NOISE AND VIBRATION CONTROL FOR HVAC PIPING AND EQUIPMENT .docx DOCX document
36C25622R0094 230512 GENERAL MOTOR REQUIREMENTS FOR HVAC AND STEAM GENERATION EQUIPMENT.docx DOCX document
36C25622R0094 233100 HVAC DUCTS AND CASINGS.docx DOCX document
36C25622R0094 233600 AIR TERMINAL UNITS .docx DOCX document
36C25622R0094 238216 AIR COILS .doc DOC document
36C25622R0094 230800 COMMISSIONING OF HVAC SYSTEMS.docx DOCX document
36C25622R0094 033000 Cast in Place Concrete.docx DOCX document
36C25622R0094 019100 General Commissioning Requirements .docx DOCX document
36C25622R0094 090600 Schedule for Finishes .docx DOCX document
36C25622R0094 Brand Name JA 502-19-107 Redacted.pdf PDF
36C25622R0094 COVID-19 Safety Protocols for Federal Contractors Rev 2.docx DOCX document
36C25622R0094 280800 Commissioning of Electronic Safety and Security Systems .docx DOCX document
36C25622R0094 000110 VHA Master Specifications Rev 2.docx DOCX document
36C25622R0094 262726 Wiring Devices .docx DOCX document
36C25622R0094 283100 Fire Detection and Alarm .doc DOC document
36C25622R0094 260923 Lighting Controls.docx DOCX document
36C25622R0094 232500 HVAC WATER TREATMENT .docx DOCX document
36C25622R0094 260511 Requirements for ELEC installation.docx DOCX document
36C25622R0094 234000 HVAC AIR CLEANING DEVICES .docx DOCX document
36C25622R0094 238100 DECENTRALIZED UNITARY HVAC EQUIPMENT.docx DOCX document
36C25622R0094 260800 Commissioning of Electrical Systems.docx DOCX document
36C25622R0094 232113 HYDRONIC PIPING .docx DOCX document
36C25622R0094 230923 DIRECT DIGITAL CONTROL SYSTEM FOR HVAC .doc DOC document
36C25622R0094 014500 Quality Control.docx DOCX document
36C25622R0094 013526 Safety Requirements .docx DOCX document
36C25622R0094 099100 Painting .docx DOCX document
36C25622R0094 095100 Acoustical Ceilings .docx DOCX document
36C25622R0094 087100 Door Hardware .docx DOCX document
36C25622R0094 092216 Non-Structural Metal Framing .docx DOCX document
36C25622R0094 096513 Resilient Base and Accessories.docx DOCX document
36C25622R0094 079200 Joint Sealants .docx DOCX document
36C25622R0094 092900 Gypsum Board .docx DOCX document
36C25622R0094 076000 Flashing and Sheet Metal .docx DOCX document
36C25622R0094 015719 Temporary Environmental Controls .doc DOC document
Show all 50

Z2DA--Project #502-19-107 - Replace AHU-104 - Construction - 36C25622R0094 has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REPLACE AHU #104 AND DUCTWORK BLDG. 7

DEPARTMENT OF VETERANS AFFAIRS HEALTH CARE SYSTEM-ALEXANDRIA, LA

PROJECT NO.: 502-19-107

SECTION 23 73 00

INDOOR CENTRAL-STATION AIR-HANDLING UNITS

PART 1 GENERAL

1.1 DESCRIPTION

A.Air handling units including integral components specified herein.
B.Definitions: Air Handling Unit (AHU): A factory fabricated and tested assembly of modular sections consisting of multiple plenum fans with direct-drive , coils, filters, and other necessary equipment to perform one or more of the following functions of circulating, cleaning, heating, cooling, and dehumidifying of air. Design capacities of units shall be as scheduled on the drawings.

1.2 RELATED WORK

A.Section 01 00 00, GENERAL REQUIREMENTS.
B.Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES,

C. Section 01 91 00, GENERAL COMMISSIONING REQUIREMENTS.

D.Section 09 91 00, PAINTING.
E.Section 23 05 11, COMMON WORK RESULTS FOR HVAC.
F.Section 23 05 12, GENERAL MOTOR REQUIREMENTS FOR HVAC AND STEAM GENERATION EQUIPMENT.
G.Section 23 05 41, NOISE AND VIBRATION CONTROL FOR HVAC PIPING AND EQUIPMENT.
H.Section 23 05 93, TESTING, ADJUSTING, AND BALANCING FOR HVAC.

I. Section 23 07 11, HVAC, AND BOILER PLANT INSULATION.

J.Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.
K.Section 23 09 23, DIRECT-DIGITAL CONTROL SYSTEM FOR HVAC.

L. Section 23 21 13, HYDRONIC PIPING.

M.Section 23 31 00, HVAC DUCTS and CASINGS.
N.Section 23 40 00, HVAC AIR CLEANING DEVICES.
O.Section 26 29 11, LOW-VOLTAGE MOTOR STARTERS.

1.3 QUALITY ASSURANCE

A.Refer to Article, Quality Assurance, in Section 23 05 11, COMMON WORK RESULTS FOR.
B.Air Handling Units Certification
1.Air Handling Units with Plenum Fans:
a.Air handling Units with Multiple Fans in an Array shall be tested and rated in accordance with AHRI 430 and AHRI 260.
C.Heating, Cooling, and Air Handling Capacity and Performance Standards: AHRI 430, AHRI 410, ASHRAE 51, and AMCA 210.
D.Performance Criteria:
1.The fan BHPs shall include all system effects for all fans and v-belt drive losses for housed centrifugal fans.
2.The fan motors shall be selected within the rated nameplate capacity, without relying upon NEMA Standard Service Factor.
3.Select the fan operating point as follows:
a.Air Foil, Backward Inclined, or Tubular Fans Including Plenum Fans: At or near the peak static efficiency but at an appropriate distance from the stall line.
4.Operating Limits: AMCA 99 and Manufacturer’s Recommendations.
E.Units shall be factory-fabricated, assembled, and tested by a manufacturer, in business of manufacturing similar air-handling units for at least five (5) years.

1.4. SUBMITTALS:

A.The contractor shall, in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES, furnish a complete submission for all air handling units covered in the project. The submission shall include all information listed below. Partial and incomplete submissions shall be rejected without reviews.
B.Manufacturer's Literature and Data:
1.Submittals for AHUs shall include fans, drives, motors, coils, sections, UV lights, and all other related accessories. The contractor shall provide custom drawings showing total air handling unit assembly including dimensions, operating weight, access sections, flexible connections, door swings, controls penetrations, electrical disconnect, lights, duplex receptacles, switches, wiring, utility connection points, unit support system, vibration isolators, drain pan, pressure drops through each component (filter, coil etc).
2.Submittal drawings of section or component only will not be acceptable. Contractor shall also submit performance data including performance test results, charts, curves or certified computer selection data; data sheets; fabrication and insulation details. It is anticipated that the unit will need to be provided with shipping splits for installation through the existing louver opening. The contractor shall indicate the number of pieces that each unit will have to be broken into to meet installation and/or job site rigging requirements. This data shall be submitted in hard copies and in electronic version compatible to AutoCAD version used by the VA at the time of submission.
3.Submit sound power levels in each octave band for the inlet and discharge of the fan and at entrance and discharge of AHUs at scheduled conditions. In absence of sound power ratings refer to Section 23 05 41, NOISE AND VIBRATION CONTROL FOR HVAC PIPING AND EQUIPMENT.
4.Provide fan curves showing Liters/Second (cubic feet per minute), static pressure, efficiency, and horsepower for design point of operation and at maximum design Liters/Second (cubic feet per minute).
5.Submit total fan static pressure, external static pressure, for AHU including total, inlet and discharge pressures, and itemized specified internal losses and unspecified internal losses. Refer to air handling unit schedule on drawings.
C.Maintenance and operating manuals in accordance with Section 01 00 00, GENERAL REQUIREMENTS. Include instructions for lubrication, filter replacement, motor and drive replacement, spare part lists, and wiring diagrams.
D.Submit written test procedures two weeks prior to factory testing. Submit written results of factory tests for approval prior to shipping.
E.Submit shipping information that clearly indicates how the units will be shipped in compliance with the descriptions below.
1.Units shall be shipped in one (1) piece where possible and in shrink wrapping to protect the unit from dirt, moisture and/or road salt.
2.If not shipped in one (1) piece, provide manufacturer approved shipping splits where required for installation or to meet shipping and/or job site rigging requirements in modular sections. Indicate clearly that the shipping splits shown in the submittals have been verified to accommodate the construction constraints for rigging as required to complete installation and removal of any section for replacement through available access without adversely affecting other sections.
3.If shipping splits are provided, each component shall be individually shrink wrapped to protect the unit and all necessary hardware (e.g. bolts, gaskets etc.) will be included to assemble unit on site (see section 2.1.A4).
4.Lifting lugs will be provided to facilitate rigging on shipping splits and joining of segments. If the unit cannot be shipped in one piece, the contractor shall indicate the number of pieces that each unit will have to be broken into to meet shipping and job site rigging requirements.

1.5 APPLICABLE PUBLICATIONS

A.The publications listed below form a part of this specification to the extent referenced. The publications are referenced in the text by the basic designation only.
B.AirConditioning, Heating, and Refrigeration Institute (AHRI)/(ARI):
4102001Standard for Forced-Circulation Air-Heating and Air-Cooling Coils
4302014Central Station Air Handling Units
C.Air Movement and Control Association International, Inc. (AMCA):
2102016Laboratory Methods of Testing Fans for Rating
D.American Society of Heating, Refrigerating and Air-conditioning Engineers, Inc. (ASHRAE):
170-2017Ventilation of Health Care Facilities
E.American Society for Testing and Materials (ASTM):
B117-2017Standard Practice for Operating Salt Spray (Fog) Apparatus
D16542016Standard Test Method for Evaluation of Painted or Coated Specimens Subjected to Corrosive Environments
D17352014Standard Practice for Testing Water Resistance of Coatings Using Water Fog Apparatus
D33592017Standard Test Methods for Measuring Adhesion by Tape Test
F.Military Specifications (Mil. Spec.):
P-21035B-2003Paint, High Zinc Dust Content, Galvanizing Repair (Metric)
G.National Fire Protection Association (NFPA):
90A-2018Standard for Installation of Air Conditioning and Ventilating Systems, 2009
H.Energy Policy Act of 2005 (P.L.109-58)

PART 2 - PRODUCTS

2.1 AIR HANDLING UNITS

A.General:
1.AHUs shall be fabricated from insulated, solid double-wall galvanized steel without any perforations in draw-through configuration. Casing shall be fabricated as specified in section 2.1.C.2. Galvanizing shall be hot dipped conforming to ASTM A525 and shall provide a minimum of 0.275 kg of zinc per square meter (0.90 oz. of zinc per square foot) (G90). Aluminum constructed units, subject to VA approval, may be used in place of galvanized steel. The unit manufacturer shall provide published documentation confirming that the structural rigidity of aluminum air-handling units is equal or greater than the specified galvanized steel. The inner liner of the casing shall be 316 stainless steel.
2.The contractor and the AHU manufacturer shall be responsible for ensuring that the unit will not exceed the allocated space shown on the drawings, including required clearances for service and future overhaul or removal of unit components. All structural, piping, wiring, and ductwork alterations of units, which are dimensionally different than those specified, shall be the responsibility of the contractor at no additional cost to the government.
3.AHUs shall be fully assembled by the manufacturer in the factory in accordance with the arrangement shown on the drawings. The unit shall be assembled into the largest sections possible subject to shipping and rigging restrictions and to installation restrictions caused by door sizes and/or louver opening sizes. Contractor shall coordinate with equipment manufacturer for required unit section splits. The correct fit of all components and casing sections shall be verified in the factory for all units prior to shipment. All units shall be fully assembled, tested, and then split to accommodate shipment and job site rigging. On units not shipped fully assembled, the manufacturer shall tag each section and include air flow direction to facilitate assembly at the job site. Lifting lugs or shipping skids shall be provided for each section to allow for field rigging and final placement of unit.
4.The AHU manufacturer shall provide the necessary gasketing, caulking, and all screws, nuts, and bolts required for assembly. The manufacturer shall provide a factory-trained and qualified local representative at the job site to supervise the assembly and to assure that the units are assembled to meet manufacturer's recommendations and requirements noted on the drawings. Provide documentation to the Contracting Officer that the local representative has provided services of similar magnitude and complexity on jobs of comparable size. If a local representative cannot be provided, the manufacturer shall provide a factory representative.
5.Gaskets: All door and casing and panel gaskets and gaskets between air handling unit components, if joined in the field, shall be high quality which seal airtight and retain their structural integrity and sealing capability after repeated assembly and disassembly of bolted panels and opening and closing of hinged components. Bolted sections may use a more permanent gasketing method provided they are not disassembled.
6.Structural Rigidity: Provide structural reinforcement when required by span or loading so that the deflection of the assembled structure shall not exceed 1/200 of the span based on a differential static pressure of 1991 PA (8-inch WG) or higher.
B.Base:
1.Provide a heavy-duty steel base for supporting all major AHU components. Bases shall be constructed of wide-flange steel I-beams, channels, or minimum 150 mm (6 inch) high (minimum) 3.5 mm (10 Gauge) steel base rails. Welded or bolted cross members shall be provided as required for lateral stability. Contractor shall provide supplemental steel supports as required to obtain proper operation heights for cooling coil condensate drain trap and steam coil condensate return trap.
2.AHUs shall be completely self-supporting for installation on concrete housekeeping pad, steel support pedestals, or suspended as shown on drawings.
3.The AHU bases not constructed of galvanized steel shall be cleaned, primed with a rust inhibiting primer, and finished with rust inhibiting exterior enamel.
C.Casing (including wall, floor, and roof):
1.General: AHU casing shall be constructed as solid double wall, galvanized steel insulated outer panels without any perforations and 316 stainless steel inner panels without any perforations, integral of or attached to a structural frame. The thickness of insulation, mode of application and thermal breaks shall be such that there is no visible condensation on the exterior panels of the AHU located in the non-conditioned spaces.
2.Casing Construction:

Table 2.1.C.2

Outer Panel
0.8 mm (22 Gage) Minimum
Inner Panel
0.8 mm (22 Gage) Minimum

Insulation Density Foam

3.0 lb/ft3 Minimum

Total R Value
13.0 ft2.OF.hr/Btu

Minimum

4.Blank-Off: Provide blank-offs as required to prevent air bypass between the AHU sections, around coils, and filters.
5.Casing panels shall be secured to the support structure with stainless steel or zinc-chromate plated screws and gaskets installed around the panel perimeter. Panels shall be completely removable to allow removal of fan, coils, and other internal components for future maintenance, repair, or modifications. Welded exterior panels are not acceptable.
6.Access Doors: Provide in each access section and where shown on drawings. Show single-sided and double-sided access doors with door swings on the floor plans. Doors shall be a minimum of 50 mm (2 inch) thick with same double wall construction as the unit casing. Doors shall be a minimum of 600 mm (24 inches) wide, unless shown of different size on drawings, and shall be the full casing height up to a maximum of 1850 mm (6 feet). Doors shall be gasketed, hinged, and latched to provide an airtight seal and shall swing such that they open against pressure. The access doors for fan sections and coil sections shall include a minimum 150 mm x 150 mm (6-inch x 6 inch) double thickness, with air space between the glass panes tightly sealed, reinforced glass or Plexiglas window in a gasketed frame.
a.Hinges: Manufacturers standard, designed for door size, weight and pressure classifications. Hinges shall hold door completely rigid with minimum 45 kg (100 lb.) weight hung on latch side of door.
b.Latches: Non-corrosive alloy construction, with operating levers for positive cam action, operable from either inside or outside. Doors that do not open against unit operating pressure shall allow the door to ajar and then require approximately 0.785 radian (45 degrees) further movement of the handle for complete opening. Latch shall be capable of restraining explosive opening of door with a force not less than 1991 Pa (8-inch WG).
c.Gaskets: Neoprene, continuous around door, positioned for direct compression with no sliding action between the door and gasket. Secure with high quality mastic to eliminate possibility of gasket slipping or coming loose.
7.Provide sealed sleeves, metal or plastic escutcheons or grommets for penetrations through casing for power and temperature control wiring and pneumatic tubing. Coordinate with electrical and temperature control subcontractors for number and location of penetrations. Coordinate lights, switches, and duplex receptacles and disconnect switch location and mounting. All penetrations and equipment mounting may be provided in the factory or in the field. All field penetrations shall be performed neatly by drilling or saw cutting. No cutting by torches will be allowed. Neatly seal all openings airtight.
D.Painted Exterior Finish: Galvanized steel (G90) exterior shall be mill prepared for painting by bonderizing and factory prepared for prime coat of paint by acid etch cleaning, as required, to assure paint adhesion. Provide factory applied prime coat and enamel finish coat of paint of color selected by owner. Paint corrosion resistance and adhesion shall have satisfactorily passed ASTM B117, D1654, D1735, D3359 and G23 for a minimum of 500 hours. Rating of failure at the scribe mark shall not be less than 6, average creepage not greater than 3 mm (1/8 inch). Rating of the inscribed area shall not be less than 10, no failure. Refer to Section 09 91 00, PAINTING.
E.Floor:
1.Unit floor shall be level without offset space or gap and designed to support a minimum of 488 kg/square meter (100 lbs. per square foot) distributed load without permanent deformation or crushing of internal insulation. Provide adequate structural base members beneath floor in service access sections to support typical service foot traffic and to prevent damage to unit floor or internal insulation. Unit floors in casing sections, which may contain water or condensate, shall be watertight with drain pan.
2.Where indicated, furnish, and install floor drains, flush with the floor, with nonferrous grate cover and stub through floor for external connection.
F.Condensate Drain Pan: Drain pan shall be designed to extend entire length of cooling coils including headers and return bends. Depth of drain pan shall be at least 43 mm (1.7 inches) and shall handle all condensate without overflowing. Drain pan shall be double-wall, double sloping type, and fabricated from stainless (304) with at least 50 mm (2 inch) thick insulation sandwiched between the inner and outer surfaces. Drain pan shall be continuous metal or welded watertight. No mastic sealing of joints exposed to water will be permitted. Drain pan shall be placed on top of casing floor or integrated into casing floor assembly. Drain pan shall be pitched in all directions to drain line.
1.An intermediate, stainless-steel (304) condensate drip pan with copper downspouts shall be provided on stacked cooling coils. Use of intermediate condensate drain channel on upper casing of lower coil is permissible provided it is readily cleanable. Design of intermediate condensate drain shall prevent upper coil condensate from flowing across face of lower coil.
2.Drain pan shall be piped to the exterior of the unit. Drain pan shall be readily cleanable.
3.Installation, including frame, shall be designed, and sealed to prevent blow-by.
G.Plenum Fans –Multiple Fans in an Array:
1.General: Fans shall be Class II (minimum) construction with single inlet, aluminum wheel and stamped air-foil aluminum bladed. The fan wheel shall be mounted on the directly driven motor shaft in AMCA Arrangement 4. Fans shall be dynamically balanced and internally isolated to minimize the vibrations. Provide a steel inlet cone for each wheel to match with the fan inlet. Locate fan in the air stream to assure proper flow. The fan performance shall be rated in accordance with AMCA 210 or ASHRAE 51.
2.Allowable vibration tolerances for fan shall not exceed a self-excited vibration maximum velocity of 0.005 m/s (0.20 inch per second) RMS, filter in, when measured with a vibration meter on bearing caps of machine in vertical, horizontal, and axial directions or measured at equipment mounting feet if bearings are concealed. After field installation, compliance to this requirement shall be demonstrated with field test in accordance with Section 23 05 41, NOISE AND VIBRATION CONTROL FOR HVAC PIPING AND EQUIPMENT and Section 23 05 93, TESTING, ADJUSTING, AND BALANCING FOR HVAC. Following fan assembly, the complete fan assembly balance shall be tested using an electronic balance analyzer with a tunable filter and stroboscope. Vibration measurements shall be taken on each motor bearing housing in the vertical, horizontal, and axial planes (5 total measurements, 2 each motor bearing and 1 axial).
3.Each plenum fan array shall be driven by a single variable speed drive with one back-up drive. Use of a drive with bypass is not permitted. The AHU unit shall be completely factory-wired, requiring only one field wiring connection of main power for both the power supply with disconnect switch for receptacles and light fixtures as well as the required line side of the main power disconnect switch of each multiple fan array. Motors shall be mounted on an adjustable steel base. All motors shall be tested to IEEE standard 112 test method B and rated per NEMA MG1, Part 31 "Inverter Fed Motors". All motors shall be specifically designed to meet or exceed all (EPAct) requirements for energy efficiency and include Class 'F' insulation. All wiring shall be (75°C) Insulated copper wires. Conduit shall consist of a combination of EMT, or flexible metal conduit as required. Liquidtite flexible metal conduit may be used outside the air tunnel for wet locations. Each air handling unit shall contain one or more electrical control panels consisting of a surface mounted, NEMA rated, UL listed enclosure for the application that shall include all supply fan motor disconnects and overload protection, one for each fan motor in the multiple fan arrays, or alternate means for providing motor disconnecting capability along with overload protection as well as a single point electrical connection for the power wiring for the multiple fan array.
4.Multiple fans shall be installed in a pre-engineered structural frame to facilitate fan stacking. All fans shall modulate in unison, above or below the synchronous speed within the limits specified by the manufacturer, by a common control sequence. Staging of the fans is not permitted. Redundancy requirement shall be met by all operating fans in an array and without the provision of an idle standby fan.
5.Fan Accessories
a.Fan Isolation: Provide an automatic back draft damper to isolate the fan not in operation due to failure. The unit total static pressure shall account for the additional pressure drop through the backdraft dampers. If required electrical service is larger than scheduled, contractor shall provide all required electrical upgrades (at no additional cost) to support equipment electrical service requirements.
b.Fan Airflow Measurement: Provide an airflow measuring device integral to each fan in the array to measure air volume within +/- 5 percent accuracy. The probing device shall not be placed in the airflow path to stay clear of turbulence and avoid loss of performance. The airflow measuring stations shall be integrated into the facility DDC system for indication of airflow and alarms.
H.Fan Motor, Drive, and Mounting Assembly (Plenum Fans):
Fan Motor and Drive: Motors shall be premium energy efficient type, as mandated by the Energy Policy Act of 2005, with efficiencies as shown in the Specifications Section 23 05 12, GENERAL MOTOR REQUIREMENTS FOR HVAC AND STEAM GENERATION EQUIPMENT, on drawings and suitable for use in variable frequency drive applications. Refer to Section 23 05 11, COMMON WORK RESULTS FOR HVAC, for additional motor and drive specifications. Refer to Specification Section 26 29 11, LOW-VOLTAGE MOTOR STARTERS
I.Filter Section: Refer to Section 23 40 00, HVAC AIR CLEANING DEVICES, for filter requirements.
1.Filters including one complete set for temporary use at site shall be provided independent of the AHU. The AHU manufacturer shall install filter housings and racks in filter section compatible with filters furnished. The AHU manufacturer shall be responsible for furnishing temporary filters (pre-filters and after-filters, as shown on drawings) required for AHU testing.
2.Factory-fabricated filter section shall be of the same construction and finish as the AHU casing including filter racks and hinged double wall access doors. Filter housings shall be constructed in accordance with side service or holding frame housing requirements in Section 23 40 00, HVAC AIR CLEANING DEVICES.
J.Coils: Coils shall be mounted on hot dipped galvanized steel supports to assure proper anchoring of coil and future maintenance. Coils shall be face or side removable for future replacement thru the access doors or removable panels. Each coil shall be removable without disturbing adjacent coil. Cooling coils shall be designed and installed to ensure no condensate carry over. Provide factory installed extended supply, return, drain, and vent piping connections. All coils in the high humidity areas, shall be epoxy-coated as shown below. Refer to Drawings and Section 23 82 16, AIR COILS for additional coil requirements.

1. Epoxy Immersion Coating – Electrically Deposited: The multi-stage corrosion-resistant coating application comprises of cleaning (heated alkaline immersion bath) and reverse-osmosis immersion rinse prior to the start of the coating process. The coating thickness shall be maintained between 0.6-mil and 1.2-mil. Before the coils are subjected to high-temperature oven cure, they are treated to permeate immersion rinse and spray. Where the coils are subject to UV exposure, UV protection spray treatment comprising of UV-resistant urethane mastic topcoat shall be applied. Provide complete coating process traceability for each coil and minimum five years of limited warranty.

2. The coating process shall such that uniform coating thickness is maintained at the fin edges. The quality control shall be maintained by ensuring compliance to the applicable ASTM Standards for the following:

a. Salt Spray Resistance (Minimum 6,000 Hours)

b. Humidity Resistance (Minimum 1,000 Hours)

c. Water Immersion (Minimum 260 Hours)

d. Crosshatch Adhesion (Minimum 4B-5B Rating)

e. Impact Resistance (Up to 160 Inch/Pound)

3. Water Coils, Including Glycol-Water.

K.Discharge Section:
Provide aerodynamically designed framed discharge openings or spun bellmouth fittings to minimize pressure loss.
L.Electrical and Lighting: Wiring and equipment specifications shall conform to Division 26, ELECTRICAL.
1.Vapor-proof lights using cast aluminum base style with glass globe and cast aluminum guard shall be installed in access sections for fans and any section over 300 mm (12 inch) wide. A switch shall control the lights in each compartment with pilot light mounted outside the respective compartment access door. Wiring between switches and lights shall be factory installed. All wiring shall run in neatly installed electrical conduits and terminate in a junction box for field connection to the building system. Provide single point 115 volt - one phase connection at junction box.
2.Install compatible 100-watt bulb in each light fixture.
3.Provide a convenience duplex receptacle next to the light switch.
4.Disconnect switch and power wiring: Provide factory or field mounted disconnect switch. Coordinate with Division 26, ELECTRICAL.

PART 3 – EXECUTION

3.1 INSTALLATION

A.Install air handling unit in conformance with ARI 435.
B.Assemble air handling unit components following manufacturer's instructions for handling, testing, and operation. Repair damaged galvanized areas with paint in accordance with Military Spec. DOD-P-21035. Repair painted units by touch up of all scratches with finish paint material. Vacuum the interior of air handling units clean prior to operation.
C.Leakage and test requirements for air handling units shall be the same as specified for ductwork in Specification Section 23 31 00, HVAC DUCTS AND CASINGS except leakage shall not exceed Leakage Class (CL) 12 listed in SMACNA HVAC Air Duct Leakage Test Manual when tested at 1.5 times the design static pressure. Repair casing air leaks that can be heard or felt during normal operation and to meet test requirements.
D.Perform field mechanical (vibration) balancing in accordance with Section 23 05 41, NOISE AND VIBRATION CONTROL FOR HVAC PIPING AND EQUIPMENT.
E.Seal and/or fill all openings between the casing and AHU components and utility connections to prevent air leakage or bypass.

3.2 startup services

A.The air handling unit shall not be operated for any purpose, temporary or permanent, until ductwork is clean, filters are in place, bearings are lubricated, and fan has been test run under observation.
B.After the air handling unit is installed and tested, provide startup and operating instructions to VA personnel.
C.An authorized factory representative should start up, test, and certify the final installation and application specific calibration of control components. Items to be verified include fan performance over entire operating range, noise and vibration testing, verification of proper alignment, overall inspection of the installation, Owner/Operator training, etc.

3.3 COMMISSIONING

A.Provide commissioning documentation in accordance with the requirements of Section 23 08 00 – COMMISSIONING OF HVAC SYSTEMS for all inspection, start up, and contractor testing required above and required by the System Readiness Checklist provided by the Commissioning Agent.
B.Components provided under this section of the specification will be tested as part of a larger system. Refer to Section 23 08 00 – COMMISSIONING OF HVAC SYSTEMS and related sections for contractor responsibilities for system commissioning.

- - - E N D - - -

23 73 00 - 1