This document outlines specifications for resilient base and accessories required as part of a project to replace an air handling unit and ductwork at a Department of Veterans Affairs health care facility. The project solicitation requires furnishing and installing rubber or vinyl resilient base of 3mm thickness and 100mm height in carpeted areas and cove base in other locations, using manufacturer-recommended adhesives. Installation must comply with specifications, extending base into closets and around columns as indicated. The related federal contract opportunity is solicitation number 502-19-107 issued by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 16 to replace air handling unit 104 at the construction site.

View the file

Other files for this federal contract opportunity

Other files attached to Z2DA--Project #502-19-107 - Replace AHU-104 - Construction - 36C25622R0094, newest first.
File Type Posted
36C25622R0094 0003.docx DOCX document
36C25622R0094 0002.docx DOCX document
Site Visit Sign in Sheet 50219107.pdf PDF
36C25622R0094 Brand Name JA 502-19-107 Redacted.pdf PDF
36C25622R0094 COVID-19 Safety Protocols for Federal Contractors Rev 2.docx DOCX document
36C25622R0094 280800 Commissioning of Electronic Safety and Security Systems .docx DOCX document
36C25622R0094 000110 VHA Master Specifications Rev 2.docx DOCX document
36C25622R0094 262726 Wiring Devices .docx DOCX document
36C25622R0094 283100 Fire Detection and Alarm .doc DOC document
36C25622R0094 260923 Lighting Controls.docx DOCX document
36C25622R0094 232500 HVAC WATER TREATMENT .docx DOCX document
36C25622R0094 260511 Requirements for ELEC installation.docx DOCX document
36C25622R0094 234000 HVAC AIR CLEANING DEVICES .docx DOCX document
36C25622R0094 238100 DECENTRALIZED UNITARY HVAC EQUIPMENT.docx DOCX document
36C25622R0094 260800 Commissioning of Electrical Systems.docx DOCX document
36C25622R0094 232113 HYDRONIC PIPING .docx DOCX document
36C25622R0094 230923 DIRECT DIGITAL CONTROL SYSTEM FOR HVAC .doc DOC document
36C25622R0094 014500 Quality Control.docx DOCX document
36C25622R0094 013526 Safety Requirements .docx DOCX document
36C25622R0094 099100 Painting .docx DOCX document
36C25622R0094 095100 Acoustical Ceilings .docx DOCX document
36C25622R0094 087100 Door Hardware .docx DOCX document
36C25622R0094 092216 Non-Structural Metal Framing .docx DOCX document
36C25622R0094 079200 Joint Sealants .docx DOCX document
36C25622R0094 092900 Gypsum Board .docx DOCX document
36C25622R0094 076000 Flashing and Sheet Metal .docx DOCX document
36C25622R0094 015719 Temporary Environmental Controls .doc DOC document
36C25622R0094 IFC Drawings Part 3 .pdf PDF
36C25622R0094 271000 Control Communication and Signal Wiring.docx DOCX document
36C25622R0094 EXHIBIT F.docx DOCX document
36C25622R0094 000115 List of Drawing Sheets .docx DOCX document
36C25622R0094 WD LA20220051 Mod 3 06242022.docx DOCX document
36C25622R0094 EXHIBIT D.docx DOCX document
36C25622R0094 EXHIBIT C.docx DOCX document
36C25622R0094 280500 Common Work Results for Electronic Safety and Security .docx DOCX document
36C25622R0094 230711 HVAC AND BOILER PLANT INSULATION .docx DOCX document
36C25622R0094 081113 Hollow Metal Doors and Frames.docx DOCX document
36C25622R0094 092400 Portland Cement Plastering .docx DOCX document
36C25622R0094 061663 Cementitious Sheathing .docx DOCX document
36C25622R0094 054000 Cold Formed Metal Framing .docx DOCX document
36C25622R0094 089000 Louvers and Vents .docx DOCX document
36C25622R0094 017419 Construction Waste Management .doc DOC document
36C25622R0094 013216.15 Project Schedules (Small Projects-Design-Bid-Build).docx DOCX document
36C25622R0094 018113 Sustainable Construction Requirements.docx DOCX document
36C25622R0094 IFC Drawings Part 4 .pdf PDF
36C25622R0094 Revised SOW 05202022 .docx DOCX document
36C25622R0094 RFP.docx DOCX document
36C25622R0094 IFC Drawings Part 1 .pdf PDF
36C25622R0094 IFC Drawings Part 2.pdf PDF
36C25622R0094 230593 TESTING ADJUSTING AND BALANCING FOR HVAC.docx DOCX document
Show all 50

Z2DA--Project #502-19-107 - Replace AHU-104 - Construction - 36C25622R0094 has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REPLACE AHU #104 AND DUCTWORK BLDG. 7

DEPARTMENT OF VETERANS AFFAIRS HEALTH CARE SYSTEM-ALEXANDRIA, LA

PROJECT NO.: 502-19-107

SECTION 09 65 13

RESILIENT BASE AND ACCESSORIES

GENERAL

SUMMARY

Section Includes:

Resilient base (RB) adhered to interior walls and partitions.

APPLICABLE PUBLICATIONS

Comply with references to extent specified in this section.

ASTM International (ASTM):

F186116 Resilient Wall Base.

SUBMITTALS

Submittal Procedures: Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.

Manufacturer's Literature and Data:

Description of each product.

Adhesives and primers indicating manufacturer's recommendation for each application.

Installation instructions.

Samples:

Resilient Base: 150 mm (6 inches) long, each type and color.

Operation and Maintenance Data:

Care instructions for each exposed finish product.

DELIVERY

Deliver products in manufacturer's original sealed packaging.

Mark packaging, legibly. Indicate manufacturer's name or brand, type, color, production run number, and manufacture date.

Before installation, return or dispose of products within distorted, damaged, or opened packaging.

STORAGE AND HANDLING

Store products indoors in dry, weathertight facility.

Protect products from damage when handling and during construction operations.

FIELD CONDITIONS

Environment:

Product Temperature: Minimum 21 degrees C (70 degrees F) for minimum 48 hours before installation.

Work Area Ambient Temperature Range: 21 to 27 degrees C (70 to 80 degrees F) continuously, beginning 48 hours before installation.

Install products when building is permanently enclosed and when wet construction is completed, dried, and cured.

WARRANTY

Construction Warranty: FAR clause 52.24621, "Warranty of Construction."

PRODUCTS

PRODUCTS

Basis of Design: Match adjacent base finish Provide each product from one manufacturer and from one production run.

RESILIENT BASE

Resilient Base: 3 mm (1/8 inch) thick, 100 mm (4 inches) high.

Type: Rubber or vinyl; use one type throughout.

ASTM F1861, Type TP thermoplastic rubber or Type TV thermoplastic vinyl, Group 2 - layered.

Applications:

Carpet Flooring Locations: Style A - Straight.

Other Locations: Style B - Cove.

ADHESIVES

Adhesives: Low pollutantemitting, water-based type recommended by adhered product manufacturer for each application.

EXECUTION

PREPARATION

Examine and verify substrate suitability for product installation.

Protect existing construction and completed work from damage.

Remove existing base to permit new installation.

Dispose of removed materials.

INSTALLATION GENERAL

Install products according to manufacturer's instructions.

When instructions deviate from specifications, submit proposed resolution for Contracting Officer consideration.

RESILIENT BASE INSTALLATION

Applications:

Install resilient base in rooms scheduled on Drawings.

Extend resilient base into closets, alcoves, and cabinet knee spaces, and around columns within scheduled room.

Lay out resilient base with minimum number of joints.

Length: 600 mm (24 inches) minimum, each piece.

Locate joints 150 mm (6 inches) minimum from corners and intersection of adjacent materials.

Installation:

Apply adhesive uniformly for full contact between resilient base and substrate.

Set resilient base with hairline butted joints aligned along top edge.

Factory form corners and end stops.

Vgroove back of outside corner.

Vgroove face of inside corner and notch cove for miter joint.

Roll resilient base ensuring complete adhesion.

CLEANING

Remove excess adhesive before adhesive sets.

Clean exposed resilient base surfaces. Remove contaminants and stains.

Clean with mild detergent. Leave surfaces free of detergent residue.

Polish exposed resilient base to gloss sheen.

PROTECTION

Replace damaged products and reclean.

Damaged Products include cut, gouged, scraped, torn, and unbonded products.

- E N D - 09 65 13 - 1