This solicitation is for a chiller plant upgrade project at the John L. McClellan VA Medical Center in Little Rock, Arkansas. The contractor shall provide all materials, equipment, labor, demolition, supervision and expertise necessary to perform general construction, fire protection, structural, architectural, mechanical and electrical work, as well as selective removal of existing construction and other items. The project value is estimated between $1,000,000 to $2,500,000. NAICS code 236220 for commercial and institutional building construction applies with a size standard of $36.5 million. This acquisition is 100% set aside for service-disabled veteran owned small businesses. Interested vendors must register at VETBIZ and under NAICS 236220 to be eligible for award. The anticipated solicitation issue date is March 18, 2021, with responses due as specified once released. The point of contact for questions is Bradley Martin at the VA.

View the file

Other files

File Type Posted
36C25621R0076 0007.docx DOCX document
236400 Packaged Water Chillers.doc DOC document
36C25621R0076 0006.docx DOCX document
Updated RFI questions.docx DOCX document
36C25621R0076 0005.docx DOCX document
REV RFI questions_JDa Response_2021.06.24 (002).docx DOCX document
36C25621R0076 0004.docx DOCX document
RFI questions_JDa Response_2021.06.24 (002).docx DOCX document
36C25621R0076 0003.docx DOCX document
261316 - Medium-Voltage Fusible Interrupter Switches.pdf PDF
262416 - Panelboards.pdf PDF
Site Visit Sign In_Chiller Upgrade.pdf PDF
260519 - Low-Voltage Electrical Power Conductors and Cables.pdf PDF
265100 - Interior Lighting.pdf PDF
262921 - Enclosed Switches and Circuit Breakers.pdf PDF
260573 - Overcurrent Protective Device Coordination Study.pdf PDF
260800.pdf PDF
264313 - Surge Protective Devices.pdf PDF
260533 - Raceway and Boxes for Electrical Systems.pdf PDF
260526 - Grounding and Bonding for Electrical Systems.pdf PDF
262726 - Wiring Devices.pdf PDF
262419 - Motor Control Centers.pdf PDF
261313 - Metal Clad breakers 02.pdf PDF
261116 - Secondary Unit Substation.pdf PDF
260513 - Medium-Voltage Cables.pdf PDF
262413 - Distribution Switchboards.pdf PDF
36C25621R0076 0002.docx DOCX document
260533 - Raceway and Boxes for Electrical Systems 02.pdf PDF
260511 - Requirements for Electrical Installation.pdf PDF
261313 - Metal Clad breakers.pdf PDF
Division Cost Page (002).docx DOCX document
36C25621R0076 0001.docx DOCX document
36C25621R0076_2.docx DOCX document
PAST PERFORMANCE SURVEY SPS.pdf PDF
598-19-101 CD Submission Specifications.pdf PDF
WAGE DETERMINATION_.docx DOCX document
598-19-101 CD Submission Drawings.pdf PDF
Show all 37

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Upgrade Chiller Plant @JLM: Project 1 JLM Memorial Veterans Hospital

598-19-101 01-01-18

Construction Documents 2020.12.30

26 22 00 - 1

SECTION 26 22 00

LOW-VOLTAGE TRANSFORMERS

PART 1 – GENERAL

1.1 DESCRIPTION

A. This section specifies the furnishing, installation, connection, and testing of low-voltage dry-type general-purpose transformers, indicated as transformers in this section.

1.2 RELATED WORK

A. Section 03 30 00, CAST-IN-PLACE CONCRETE: Requirements for concrete equipment pads.

B. Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS:

Requirements that apply to all sections of Division 26.

C. Section 26 05 19, LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES:

Low-voltage conductors.

D. Section 26 05 26, GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS:

Requirements for personnel safety and to provide a low impedance path for possible ground fault currents.

E. Section 26 05 33, RACEWAY AND BOXES FOR ELECTRICAL SYSTEMS: Conduit.

1.3 QUALITY ASSURANCE

A. Quality Assurance shall be in accordance with Paragraph, QUALIFICATIONS (PRODUCTS AND SERVICES) in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS.

1.4 SUBMITTALS

A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements:

1. Shop Drawings:

a. Submit sufficient information to demonstrate compliance with drawings and specifications.

b. Include electrical ratings, dimensions, mounting details, materials, required clearances, terminations, weight, temperature rise, wiring and connection diagrams, plan, front, side, and rear elevations, accessories, and device nameplate data.

26 22 00 - 2

2. Manuals:

a. Submit, simultaneously with the shop drawings, companion copies of complete maintenance and operating manuals including technical data sheets and wiring diagrams.

1) Schematic signal and control diagrams, with all terminals identified, matching terminal identification in the transformers.

2) Include information for testing, repair, troubleshooting, assembly, disassembly, and factory recommended/required periodic maintenance procedures and frequency.

b. If changes have been made to the maintenance and operating manuals originally submitted, submit updated maintenance and operating manuals two weeks prior to the final inspection.

3. Certifications: Two weeks prior to final inspection, submit the following.

a. Certification by the manufacturer that the transformers conform to the requirements of the drawings and specifications.

b. Certification by the Contractor that the transformers have been properly installed, adjusted, and tested.

1.5 APPLICABLE PUBLICATIONS

A. Publications listed below (including amendments, addenda, revisions, supplements, and errata) form a part of this specification to the extent referenced. Publications are referenced in the text by designation only.

B. International Code Council (ICC):

IBC-15 ................. International Building Code

C. National Fire Protection Association (NFPA):

70-17 .................. National Electrical Code (NEC)

D. National Electrical Manufacturers Association (NEMA):

TR 1-13 ................ Transformers, Step Voltage Regulators and

Reactors

ST 20-14 ............... Dry Type Transformers for General Applications

E. Underwriters Laboratories, Inc. (UL):

UL 506-17 .............. Standard for Specialty Transformers

UL 1561-11 ............. Dry-Type General Purpose and Power

Transformers

F. United States Department of Energy:

26 22 00 - 3

10 CFR Part 431 ........ Energy Efficiency Program for Certain

Commercial and Industrial Equipment

PART 2 - PRODUCTS

2.1 TRANSFORMERS

A. Unless otherwise specified, transformers shall be in accordance with

NEMA, NFPA, UL and as shown on the drawings.

B. Transformers shall have the following features:

1. Self-cooled by natural convection, isolating windings, indoor dry-type. Autotransformers will not be accepted.

2. Rating and winding connections shall be as shown on the drawings.

3. Ratings shown on the drawings are for continuous duty without the use of cooling fans.

4. Copper windings.

5. Insulation systems:

a. Transformers 30 kVA and larger: UL rated 220 °C (428 °F) system with an average maximum rise by resistance of 150 °C (302 °F) in a maximum ambient of 40 °C (104 °F).

b. Transformers below 30 kVA: Same as for 30 kVA and larger or UL rated 185 °C (365 °F) system with an average maximum rise by resistance of 115 °C (239 °F) in a maximum ambient of 40 °C (104

°F).

6. Core and coil assemblies:

a. Rigidly braced to withstand the stresses caused by short-circuit currents and rough handling during shipment.

b. Cores shall be grain-oriented, non-aging, and silicon steel.

c. Coils shall be continuous windings without splices except for taps.

d. Coil loss and core loss shall be minimized for efficient operation.

e. Primary and secondary tap connections shall be brazed or pressure type.

f. Coil windings shall have end filters or tie-downs for maximum strength.

7. Average audible sound levels shall comply with NEMA.

8. If not shown on drawings, nominal impedance shall be as permitted by NEMA.

26 22 00 - 4

9. Single phase transformers rated 15 kVA through 25 kVA shall have two 5% full capacity taps below normal rated primary voltage. All transformers rated 30 kVA and larger shall have two 2.5% full capacity taps above, and four 2.5% full capacity taps below normal rated primary voltage.

10. Core assemblies shall be grounded to their enclosures with adequate flexible ground straps.

11. Enclosures:

a. Comprised of not less than code gauge steel.

b. Outdoor enclosures shall be NEMA 3R.

c. Temperature rise at hottest spot shall conform to NEMA

Standards, and shall not bake and peel off the enclosure paint after the transformer has been placed in service.

d. Ventilation openings shall prevent accidental access to live components.

e. The enclosure at the factory shall be thoroughly cleaned and painted with manufacturer's prime coat and standard finish.

12. Standard NEMA features and accessories, including ground pad, lifting provisions, and nameplate with the wiring diagram and sound level indicated.

13. Dimensions and configurations shall conform to the spaces designated for their installations.

14. Transformers shall meet the energy conservation standards for transformers per the United States Department of Energy’s 10 CFR

Part 431.

PART 3 - EXECUTION

3.1 INSTALLATION

A. Installation of transformers shall be in accordance with the NEC, as recommended by the equipment manufacturer and as shown on the drawings.

B. Anchor transformers with rustproof bolts, nuts, and washers, in accordance with manufacturer’s instructions, and as shown on drawings.

C. Install transformers with manufacturer's recommended clearance from wall and adjacent equipment for air circulation. Minimum clearance shall be 150 mm (6 inches).

26 22 00 - 5

D. Install transformers on vibration pads designed to suppress transformer noise and vibrations.

3.2 ACCEPTANCE CHECKS AND TESTS

A. Perform tests in accordance with the manufacturer's recommendations.

In addition, include the following:

1. Visual Inspection and Tests:

a. Compare equipment nameplate data with specifications and approved shop drawings.

b. Inspect physical and mechanical condition.

c. Inspect all field-installed bolted electrical connections, using the calibrated torque-wrench method to verify tightness of accessible bolted electrical connections.

d. Perform specific inspections and mechanical tests as recommended by manufacturer.

e. Verify correct equipment grounding.

f. Verify proper secondary phase-to-phase and phase-to-neutral voltage after energization and prior to connection to loads.

3.3 FOLLOW-UP VERIFICATION

A. Upon completion of acceptance checks, settings, and tests, the contractor shall demonstrate that the transformers are in good operating condition, and properly performing the intended function.

---END---