About this file

This document outlines a federal contract opportunity for upgrading the chiller plant at the John L. McClellan VA Medical Center in Little Rock, Arkansas. The contractor shall provide all materials, equipment, labor, demolition, supervision and expertise necessary to perform work including general construction, fire protection, structural, architectural, mechanical and electrical work, and selective removal of existing construction in accordance with project plans and specifications. The dollar value of the contract is estimated between $1,000,000 to $2,500,000. The acquisition is set aside 100% for Service-Disabled Veteran Owned Small Businesses. Offerors must be registered in VETBIZ under NAICS code 236220 and on the contract opportunities website to receive solicitation documents and amendments. The anticipated solicitation issue date is March 18, 2021, with Brad Martin serving as the contracting officer and point of contact.

View the file

Other files

File Type Posted
36C25621R0076 0007.docx DOCX document
236400 Packaged Water Chillers.doc DOC document
36C25621R0076 0006.docx DOCX document
Updated RFI questions.docx DOCX document
36C25621R0076 0005.docx DOCX document
REV RFI questions_JDa Response_2021.06.24 (002).docx DOCX document
36C25621R0076 0004.docx DOCX document
RFI questions_JDa Response_2021.06.24 (002).docx DOCX document
36C25621R0076 0003.docx DOCX document
261316 - Medium-Voltage Fusible Interrupter Switches.pdf PDF
262416 - Panelboards.pdf PDF
Site Visit Sign In_Chiller Upgrade.pdf PDF
260519 - Low-Voltage Electrical Power Conductors and Cables.pdf PDF
265100 - Interior Lighting.pdf PDF
262921 - Enclosed Switches and Circuit Breakers.pdf PDF
260573 - Overcurrent Protective Device Coordination Study.pdf PDF
264313 - Surge Protective Devices.pdf PDF
260533 - Raceway and Boxes for Electrical Systems.pdf PDF
260526 - Grounding and Bonding for Electrical Systems.pdf PDF
262726 - Wiring Devices.pdf PDF
262419 - Motor Control Centers.pdf PDF
261313 - Metal Clad breakers 02.pdf PDF
261116 - Secondary Unit Substation.pdf PDF
262200 Low-Voltage Transformers.pdf PDF
260513 - Medium-Voltage Cables.pdf PDF
262413 - Distribution Switchboards.pdf PDF
36C25621R0076 0002.docx DOCX document
260533 - Raceway and Boxes for Electrical Systems 02.pdf PDF
260511 - Requirements for Electrical Installation.pdf PDF
261313 - Metal Clad breakers.pdf PDF
Division Cost Page (002).docx DOCX document
36C25621R0076 0001.docx DOCX document
36C25621R0076_2.docx DOCX document
PAST PERFORMANCE SURVEY SPS.pdf PDF
598-19-101 CD Submission Specifications.pdf PDF
WAGE DETERMINATION_.docx DOCX document
598-19-101 CD Submission Drawings.pdf PDF
Show all 37

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Upgrade Chiller Plant @JLM: Project 1 JLM Memorial Veterans Hospital 598-19-101 11-01-16 Construction Documents 2020.12.30

26 08 00 - 1

SECTION 26 08 00

COMMISSIONING OF ELECTRICAL SYSTEMS

PART 1 - GENERAL

1.1 DESCRIPTION

A. The requirements of this Section apply to all sections of Division 26.

B. This project will have selected building systems commissioned. The complete list of equipment and systems to be commissioned is specified in Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS. The commissioning process, which the Contractor is responsible to execute, is defined in Section 01 91 00 GENERAL COMMISSIONING REQUIRMENTS. A

Commissioning Agent (CxA) appointed by the VA will manage the commissioning process.

1.2 RELATED WORK

A. Section 01 00 00 GENERAL REQUIREMENTS.

B. Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS.

C. Section 01 33 23 SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.

1.3 SUMMARY

A. This Section includes requirements for commissioning the Facility electrical systems, related subsystems and related equipment. This

Section supplements the general requirements specified in Section 01 91

00 General Commissioning Requirements.

B. Refer to Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS for more details regarding processes and procedures as well as roles and responsibilities for all Commissioning Team members.

1.4 DEFINITIONS

A. Refer to Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS for definitions.

1.5 COMMISSIONED SYSTEMS

A. Commissioning of a system or systems specified in Division 26 is part of the construction process. Documentation and testing of these systems, as well as training of the VA’s Operation and Maintenance personnel in accordance with the requirements of Section 01 91 00 and of Division 26, is required in cooperation with the VA and the

Commissioning Agent.

B. The Facility electrical systems commissioning will include the systems listed in Section 01 91 00 General Commissioning Requirements:

26 08 00 - 2

1.6 SUBMITTALS

A. The commissioning process requires review of selected Submittals that pertain to the systems to be commissioned. The Commissioning Agent will provide a list of submittals that will be reviewed by the

Commissioning Agent. This list will be reviewed and approved by the VA prior to forwarding to the Contractor. Refer to Section 01 33 23 SHOP

DRAWINGS, PRODUCT DATA, and SAMPLES for further details.

B. The commissioning process requires Submittal review simultaneously with engineering review. Specific submittal requirements related to the commissioning process are specified in Section 01 91 00 GENERAL

COMMISSIONING REQUIREMENTS.

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION

3.1 CONSTRUCTION INSPECTIONS

A. Commissioning of Electrical systems will require inspection of individual elements of the electrical systems construction throughout the construction period. The Contractor shall coordinate with the

Commissioning Agent in accordance with Section 01 91 00 and the

Commissioning plan to schedule electrical systems inspections as required to support the Commissioning Process.

3.2 PRE-FUNCTIONAL CHECKLISTS

A. The Contractor shall complete Pre-Functional Checklists to verify systems, subsystems, and equipment installation is complete and systems are ready for Systems Functional Performance Testing. The

Commissioning Agent will prepare Pre-Functional Checklists to be used to document equipment installation. The Contractor shall complete the checklists. Completed checklists shall be submitted to the VA and to the Commissioning Agent for review. The Commissioning Agent may spot check a sample of completed checklists. If the Commissioning Agent determines that the information provided on the checklist is not accurate, the Commissioning Agent will return the marked-up checklist to the Contractor for correction and resubmission. If the Commissioning

Agent determines that a significant number of completed checklists for similar equipment are not accurate, the Commissioning Agent will select a broader sample of checklists for review. If the Commissioning Agent determines that a significant number of the broader sample of checklists is also inaccurate, all the checklists for the type of

26 08 00 - 3 equipment will be returned to the Contractor for correction and resubmission. Refer to SECTION 01 91 00 GENERAL COMMISSIONING

REQUIREMENTS for submittal requirements for Pre-Functional Checklists, Equipment Startup Reports, and other commissioning documents.

3.3 CONTRACTORS TESTS

A. Contractor tests as required by other sections of Division 26 shall be scheduled and documented in accordance with Section 01 00 00 GENERAL

REQUIREMENTS. All testing shall be incorporated into the project schedule. Contractor shall provide no less than 7 calendar days’ notice of testing. The Commissioning Agent will witness selected Contractor tests at the sole discretion of the Commissioning Agent. Contractor tests shall be completed prior to scheduling Systems Functional

Performance Testing.

3.4 SYSTEMS FUNCTIONAL PERFORMANCE TESTING

A. The Commissioning Process includes Systems Functional Performance

Testing that is intended to test systems functional performance under steady state conditions, to test system reaction to changes in operating conditions, and system performance under emergency conditions. The Commissioning Agent will prepare detailed Systems

Functional Performance Test procedures for review and approval by the

Resident Engineer. The Contractor shall review and comment on the tests prior to approval. The Contractor shall provide the required labor, materials, and test equipment identified in the test procedure to perform the tests. The Commissioning Agent will witness and document the testing. The Contractor shall sign the test reports to verify tests were performed. See Section 01 91 00 GENERAL

COMMISSIONING REQUIREMENTS, for additional details.

3.5 TRAINING OF VA PERSONNEL

A. Training of the VA operation and maintenance personnel is required in cooperation with the Resident Engineer and Commissioning Agent.

Provide competent personnel to provide instruction to operation and maintenance personnel concerning the location, operation, and troubleshooting of the installed systems. Contractor shall submit training agendas in accordance with the requirements of Section 01 91

00. The instruction shall be scheduled in coordination with the VA

Resident Engineer after submission and approval of formal training

26 08 00 - 4 plans. Refer to Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS and

Division 26 Sections for additional Contractor training requirements.

----- END -----