36C25618R0764-0002000.docx
DOCX document 25 KB Posted
- Solicitation number
- 36C25618R0764
About this file
36C25618R0764 0002 36C25618R0764 0002.docx
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25618C0183-000.docx | DOCX document | |
| 36C25618R0764-0001000.docx | DOCX document | |
| 36C25618R0764-0001002.pdf | ||
| 36C25618R0764-0001001.docx | DOCX document | |
| 36C25618R0764-002.pdf | ||
| 36C25618R0764-004.pdf | ||
| 36C25618R0764-003.pdf | ||
| 36C25618R0764-005.pdf | ||
| 36C25618R0764-000.docx | DOCX document | |
| 36C25618R0764-001.doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2.
AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE
OF PAGES
10A. MODIFICATION OF
CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV.
11/2016) is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO:
Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITE M 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES
SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR
43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes r eference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS
ENTERED INTO
PURSUANT TO AUTHORITY OF:
D. OTHER
BY
Contractor
16C. DATE SIGNED
14.
DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME
AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS
OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) 08-30-2018 629-18-3-6151-0105 629-16-105 Department of Veterans Affairs Gulf Coast Veterans Health Care System Network Contracting Office 16 400 Veterans Avenue Biloxi MS 39531 Department of Veterans Affairs Gulf Coast Veterans Health Care System Network Contracting Office 16 400 Veterans Avenue Biloxi MS 39531 To all Offerors/Bidders
36C25618R0764 08-30-2018
X X The purpose of this Amendment is to:
A. Provide clarification, and add to , the existing information already provided on this project.
B. All other terms and conditions remain unchanged.
Beth A. Cook Contracting Officer A. The purpose of this Amendment is to clarify, and add to, the existing information already provided on the project.
B. The following information is provided to clarify, and add to, the existing information already provided on the project:
1. The plans identify on certain areas that have siding replacement, while during the site visit it was made clear we were to replace the siding on the entire building. We are replacing the siding on the entire building, correct?
A: Yes, siding shall be replaced on entire building.
2. There is wooden framing for the bottom of the siding around the perimeter of the building, the part covering the crawlspace. Due to the moisture content beneath the building, are we to replace this our use existing?
A: Any item that is rotted needs to be replaced. If any item is deemed reusable, it can be used.
3. Using the 4 x 8 sheets of hardie siding as per spec, we are going to have seams running down the side of the building even after they are caulked and painted. Does the VA want the seams to show or do they want to cover them with trim boards?
A: The specs call for 4 x 10 sheets. There shall be no trim for the vertical seams.
4. Most important one. Electrical sub says if we want to move the mounted boxes and electrical gear (not the solar panel system) away from the walls to replace behind them, this will cost thousands of dollars extra, require heavy equipment and shut down the facility for about a week. Are we allowed to butt up to the existing siding with new or does the VA want those items removed and reset? Also, the Electricians stated they cannot warranty equipment if it is removed and reset, it will be hooked up correctly but still may not work due to the nature of that kind of move on that kind of equipment.
A: The existing siding must be removed as leaks are occurring in this area. Siding should be able to be removed by breaking around the electrical panels without having to remove. You may splice two pieces together to replace but it must be sealed well.