36C25520R0072-053.pdf
PDF Posted
- Solicitation number
- 36C25520R0072
About this file
36C25520R0072 SPECIFICATION VOL 1 (664 pages).pdf
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25520R0072-056.pdf | ||
| 36C25520R0072-057.pdf | ||
| 36C25520R0072-055.pdf | ||
| 36C25520R0072-051.docx | DOCX document | |
| 36C25520R0072-054.pdf | ||
| 36C25520R0072-060.pdf | ||
| 36C25520R0072-058.pdf | ||
| 36C25520R0072-052.docx | DOCX document | |
| 36C25520R0072-059.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Renovate A & B Wing Building 6 | Topeka VAMC Project Number: 589A5-18-116
Bid Documents | Specifications - Volume I of III
July 10, 2019
405.842.6100
312 SW 25th Street
Oklahoma City, OK 73109
816.214.8730
11020 King Street
Overland Park, KS 66210
A Service-Disabled Veteran-Owned Small Business spur-design.com
VA 589-A5-19-116 Building 6 Renovate A & B Wing Bid Documents
07-19
MECHANICAL ENGINEER SEAL PAGE
DESIGN PROFESSIONAL OF RECORD SEALS PAGE
MECHANICAL ENGINEER:
1. Name: John Sommers, PE
2. Kansas Professional Engineer (Mechanical)
3. License No.: 22162
4. Responsible for the following Specification Divisions:
22 (All Sections) 23 (All Sections)
7/10/2019
ARCHITECT
1. Name: Seth A. Cavin, AIA
2. Kansas Professional Architect
3. License No.: 6728
4. Responsible for the following Specification Divisions
00 (All Sections) 01 (All Sections except 'General Commissioning Requirements' 02-14 (All Sections)
07-19
MECHANICAL ENGINEER SEAL PAGE
DESIGN PROFESSIONAL OF RECORD SEALS PAGE
MECHANICAL ENGINEER:
1. Name: John Sommers, PE
2. Kansas Professional Engineer (Mechanical)
3. License No.: 22162
4. Responsible for the following Specification Divisions:
22 (All Sections) 23 (All Sections)
7/10/2019
07-19
ELECTRICAL ENGINEER SEAL PAGE
DESIGN PROFESSIONAL OF RECORD SEALS PAGE
ELECTRICAL ENGINEER:
1. Name: Jeffrey G. Wheeler, PE
2. Kansas Professional Engineer (Electrical)
3. License No.: 16527
4. Responsible for the following Specification Divisions:
• 26 (All Sections)
• 27 (All Sections)
• 28 (All Sections, except 28 31 00)
Building 6 Renovate A & B Wing
VA 589-A5-19-116
Colmery-O’Neil VAMC - Topeka, KS
Addendum 02
03-29-19
00 01 10-1
TABLE OF CONTENTS
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
Section 00 01 10
DIVISION 00 - SPECIAL SECTIONS DATE
00 01 15 List of Drawing Sheets 07-15
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 12-18
01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build 04-13
01 33 23 Shop Drawings, Product Data, and Samples 05-17
01 35 26 Safety Requirements 02-17
01 42 19 Reference Standards 09-19
01 45 29 Testing Laboratory Services 11-18
01 45 35 Special Inspections 03-19
01 91 00 General Commissioning Requirements 10-15
DIVISION 02 – EXISTING CONDITIONS
02 41 00 Demolition 08-17
02 82 11 Traditional Asbestos Abatement 04-19
02 82 13.19 Asbestos Floor Tile and Mastic Abatement 09-15
02 82 13.31 Asbestos Transite Abatement 09-15
02 83 33.13 Lead-Based Paint Removal and Disposal 08-16
DIVISION 03 – CONCRETE
Not Used
DIVISION 04 – MASONRY
04 01 00 Maintenance of Masonry 02-16
04 20 00 Unit Masonry 08-17
DIVISION 05 – METALS
DIVISION 06 – WOOD,PLASTICS AND COMPOSITES
06 10 00 Rough Carpentry 10-17
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 21 13 Thermal Insulation 10-17
07 24 00 Exterior Insulation and Finish Systems 02-16
07 27 26 Fluid-Applied Membrane Air Barrier, Vapor Permeable 02-16
07 51 00 Built-Up Bituminous Roofing 08-18
07 84 00 Firestopping 02-16
07 92 00 Joint Sealants 10-17
07 95 13 Expansion Joint Cover Assemblies 02-16
Colmery-O’Neil VAMC - Topeka, KS
00 01 10-2
DIVISION 08 - OPENINGS
08 11 13 Hollow Metal Doors and Frames 08-16
08 14 00 Interior Wood Doors 02-16
08 31 13 Access Doors and Frames 02-16
08 41 13 Aluminum-Framed Entrances and Storefronts 08-16
08 71 00 Door Hardware 11-19
08 80 00 Glazing 10-15
08 90 00 Louvers and Vents 05-15
DIVISION 09 – FINISHES
09 05 16 Subsurface Preparation for Floor Finishes 02-15
09 06 00 Schedule for Finishes 04-15
09 22 16 Non-Structural Metal Framing 06-18
09 29 00 Gypsum Board 09-18
09 30 13 Ceramic/Porcelain Tiling 09-15
09 51 00 Acoustical Ceilings 12-18
09 65 13 Resilient Base and Accessories 02-16
09 65 16 Resilient Sheet Flooring 05-18
09 65 19 Resilient Tile Flooring 05-18
09 68 00 Carpeting 10-15
09 72 16 Vinyl-Coated Fabric Wall Covering 10-15
09 91 00 Painting 01-16
DIVISION 10 – SPECIALTIES
10 11 13 Chalkboards and Markerboards 10-15
10 14 00 Signage 10-15
10 21 23 Cubicle Curtain Tracks 05-15
10 22 26.13 Accordion Folding Partitions 04-19
10 26 00 Wall and Door Protection 10-15
10 28 00 Toilet, Bath, and Laundry Accessories 02-16
10 44 13 Fire Extinguisher Cabinets 08-18
DIVISION 11 – EQUIPMENT
11 73 00 Ceiling Mounted Patient Lift System 01-17
DIVISION 12 – FURNISHINGS
12 24 00 Window Shades 08-17
12 32 00 Manufactured Wood Casework 09-15
12 36 00 Countertops 12-18
DIVISION 13 - SPECIAL CONSTRUCTION – NOT USED
DIVISION 14– CONVEYING EQUIPEMENT – NOT USED
DIVISION 21- FIRE SUPPRESSION
21 13 13 Wet-Pipe Sprinkler Systems 06-15
DIVISION 22 – PLUMBING
22 05 11 Common Work Results for Plumbing 07-16
22 05 12 General Motor Requirements for Plumbing Equipment 09-15
22 05 19 Meters and Gages for Plumbing Piping 09-15
Colmery-O’Neil VAMC - Topeka, KS
00 01 10-3
22 05 23 General-Duty Valves for Plumbing Piping 09-15
22 07 11 Plumbing Insulation 09-15
22 11 00 Facility Water Distribution 11-19
22 11 23 Domestic Water Pumps 09-15
22 13 00 Facility Sanitary and Vent Piping 09-15
22 14 00 Facility Storm Drainage 09-15
22 35 00 Domestic Water Heat Exchangers 12-16
22 40 00 Plumbing Fixtures 09-15
22 63 00 Gas Systems for Laboratory and Healthcare Facilities 09-15
DIVISION 23 – HEATING, VENTILATING, AND AIR
CONDITIONING (HVAC)
23 05 11 Common Work Results for HVAC 08-17
23 05 12 General Motor Requirements for HVAC and Steam
Generation Equipment
08-17
23 05 41 Noise and Vibration Control for HVAC Piping and
Equipment
02-15
23 05 93 Testing, Adjusting, and Balancing for HVAC 02-15
23 07 11 HVAC and Boiler Plant Insulation 02-15
23 08 00 Commissioning of HVAC Systems 11-16
23 09 23 Direct-Digital Control System for HVAC 09-11
23 21 13 Hydronic Piping 08-17 23 21 23 Hydronic Pumps 08-17 23 22 13 Steam and Condensate Heating Piping 08-17 23 23 00 Refrigerant Piping 02-15
23 25 00 HVAC Water Treatment 02-15
23 31 00 HVAC Ducts and Casings 03-13
23 34 00 HVAC Fans 02-15
23 36 00 Air Terminal Units 02-15
23 37 00 Air Outlets and Inlets 02-15
23 38 13 Commercial-Kitchen Hoods 01-11
23 40 00 HVAC Air Cleaning Devices 02-12
23 52 28 Low Pressure Steam Boilers 08-17 23 74 13 Packaged, Outdoor, Central-Station Air-Handling Units 04-11
23 81 00 Decentralized Unitary HVAC Equipment 02-11
23 82 00 Convection Heating and Cooling Units 04-11
23 82 16 Air Coils 04-11
Colmery-O’Neil VAMC - Topeka, KS
00 01 10-4
DIVISION 26 – ELECTRICAL
26 05 11 Requirements for Electrical Installations 01-16
26 05 19 Low-Voltage Electrical Power Conductors and Cables 01-17
26 05 26 Grounding and Bonding for Electrical Systems 01-17
26 05 33 Raceway and Boxes for Electrical Systems 01-18
26 05 41 Underground Electrical Construction 01-17
26 05 73 Overcurrent Protective Device Coordination Study 01-18
26 09 23 Lighting Controls 01-18
26 24 13 Distribution Switchboards 01-18
26 24 16 Panelboards 01-18
26 27 26 Wiring Devices 01-18
26 29 11 Motor Controllers 01-18
26 29 21 Enclosed Switches and Circuit Breakers 01-17
26 36 23 Automatic Transfer Switches 01-17
26 41 00 Facility Lightning Protection 01-17
26 43 13 Surge Protective Devices 01-17
26 51 00 Interior Lighting 01-18
DIVISION 27 – COMMUNICATIONS
27 05 11 Requirements for Communications Installations 06-15
27 05 26 Grounding and Bonding for Communications Systems 06-15
27 05 33 Raceways and Boxes for Communications Systems 10-18
27 10 00 Control, Communication and Signal Wiring 06-15
27 11 00 Communications Equipment Room Fittings 06-15
27 15 00 Communications Structured Cabling 01-16
27 41 31 Master Antenna Television Equipment and Systems 06-15
27 51 16 Public Address and Mass Notification Systems 10-18
27 52 23 Nurse Call and Code Blue Systems 10-18
Colmery-O’Neil VAMC - Topeka, KS
00 01 10-5
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
28 05 00 Common Work Results for Electronic Safety and Security 04-18
28 05 13 Conductors and Cables for Electronic Safety and
Security
10-18
28 05 26 Grounding and Bonding for Electronic Safety and
Security
09-11
28 05 28.33 Conduits and Backboxes for Electronic Safety and
Security
09-11
28 13 00 Physical Access Control System 10-11
28 23 00 Video Surveillance 09-11
28 26 00 Electronic Personal Protection System 09-11
28 31 00 Fire Detection and Alarm 10-11
DIVISION 31 – EARTHWORK
Colmery-O’Neil VAMC - Topeka, KS Bid Documents
07-01-15
00 01 15 - 1
LIST OF DRAWING SHEETS
SECTION 00 01 15
LIST OF DRAWING SHEETS
The drawings listed below accompanying this specifi cation form a part of the contract.
GENERAL INFORMATION
Drawing No. Title
GI-000 COVER
Gi-001 GENERAL INFORMATION
GI-010 PARTITION TYPES
GI-102 ICRA PLAN / ICRA DETAILS / PHASING PLAN
Gi-103 LIFE SAFETY FLOOR PLAN
GI-104 LIFE SAFETY OCCUPANCY CLASSIFICATION FLOO R PLAN
GI-105 DEDUCT ALTERNATE PLAN
HAZARDOUS MATERIALS
HA-001 WING A ENVIRONMENTAL REMEDIATION
HA-002 WING B ENVIRONMENTAL REMEDIATION
HA-003 CRAWLSPACE REMEDIATION
ARCHITECTURAL
AD-100A WING A - DEMO FLOOR PLAN
AD-100B WING B - DEMO FLOOR PLAN
AS-100A WING A - FLOOR PLAN
AS-100B WING B - FLOOR PLAN
AS-101A WING A - FF&E FLOOR PLAN
AS-101B WING B - FF&E FLOOR PLAN
AS-110A WING A - ROOF PLAN
AS-110B WING B - ROOF PLAN
AS-200A WING A - REFLECTED CEILING PLAN
AS-200B WING B - REFLECTED CEILING PLAN
AS-400 WING A – FF&E – ENLARGED PLANS & ELEVATIO NS
AS-401 WING A – FF&E – ENLARGED PLANS & ELEVATIO NS
AS-402 WING A – FF&E – ENLARGED PLANS & ELEVATIO NS
Colmery-O’Neil VAMC - Topeka, KS Bid Documents
07-01-15
00 01 15 - 2
LIST OF DRAWING SHEETS
AS-403 WING B – FF&E - ENLARGED PLANS & ELEVATIO NS
AS-404 WING B – FF&E – ENLARGED PLANS & ELEVATIO NS
AS-405 WING B – FF&E – ENLARGED PLANS & ELEVATIO NS
AS-500 DOOR, FRAME & WINDOW SCHEDULES & ELEVATIO NS
AS-600 INTERIOR FINISH SCHEDULES AND DETAILS
AS-601A WING A – FINISH PLAN
AS-601B WING B – FINISH PLAN
AS-602A WING A - SIGNAGE PLAN
AS-602B WING B - SIGNAGE PLAN
AS-700 PLAN & SECTION DETAILS
AS-800 ARCHITECTURAL CASEWORK LEGEND
AS-802 ARCHITECTURAL CASEWORK LEGEND
AS-803 CASEWORK – ENLARGED PLANS & ELEVATIONS
AS-804 CASEWORK – ENLARGED PLANS & ELEVATIONS
AS-805 CASEWORK – ENLARGED PLANS & ELEVATIONS
AS-806 CASEWORK – ENLARGED PLANS & ELEVATIONS
AS-807 MILLWORK DETAILS
AS-808 MILLWORK DETAILS
STRUCTURAL
SS-001 STRUCTURAL GENERAL NOTES
SS-101A STRUCTURAL ROOF PLAN - WING A
SS-101B STRUCTURAL ROOF PLAN - WING B
SS-200 STRUCTURAL DETAILS
FIRE PROTECTION
F-001 LIFE SAFETY CODE REVIEW
F-002 LIFE SAFETY CODE REVIEW
F-101 LIFE SAFETY OCCUPANCY CLASSIFICATION FLOO R PLAN
F-102 LIFE SAFETY FLOOR PLAN
FA-001 FIRE ALARM GENERAL NOTES, LEGEND AND MATR IX
FA-101 FIRE ALARM FLOOR PLAN - WING A
FA-102 FIRE ALARM FLOOR PLAN - WING B
FX-001 FIRE SUPPRESSION GENERAL NOTES
Colmery-O’Neil VAMC - Topeka, KS Bid Documents
07-01-15
00 01 15 - 3
LIST OF DRAWING SHEETS
FX-101 FIRE SUPPRESSION HAZARD CLASSIFICATION FLOO R PLAN - WING A
FX-102 FIRE SUPPRESSION HAZARD CLASSIFICATION FLOO R PLAN - WING B
PLUMBING
P-000 PLUMBING LEGEND
PLD-100A PLUMBING WASTE DEMO PLAN - BASEMENT WING A FLOOR PLAN
PLD-100B PLUMBING WASTE DEMO PLAN - BASEMENT WING B FLOOR PLAN 54
PLD-101A PLUMBING WASTE DEMO PLAN - LEVEL 1 WING A FLOOR PLAN
PLD-101B PLUMBING WASTE DEMO PLAN - LEVEL 1 WING B FLOOR PLAN
PPD-100A PLUMBING SUPPLY DEMO PLAN - BASEMENT WIN G A FLOOR PLAN
PPD-100B PLUMBING SUPPLY DEMO PLAN - BASEMENT WIN G B FLOOR PLAN
PPD-101A PLUMBING SUPPLY DEMO PLAN - LEVEL 1 WING A FLOOR PLAN
PPD-101B PLUMBING SUPPLY DEMO PLAN - LEVEL 1 WING B FLOOR PLAN
PJD-100A MEDICAL GAS DEMO PLAN - BASEMENT WING A FLOOR PLAN
PJD-100B MEDICAL GAS DEMO PLAN - BASEMENT WING B FLOOR PLAN
PJD-101B MEDICAL GAS DEMO PLAN - LEVEL 1 WING B F LOOR PLAN
PL-100A PLUMBING WASTE PLAN - BASEMENT WING A FLO OR PLAN
PL-100B PLUMBING WASTE PLAN - BASEMENT WING B FLO OR PLAN
PL-101A PLUMBING WASTE PLAN - LEVEL 1 WING A FLOO R PLAN
PL-101B PLUMBING WASTE PLAN - LEVEL 1 WING B FLOO R PLAN
PP-100A PLUMBING SUPPLY PLAN - BASEMENT WING A FL OOR PLAN
PP-100B PLUMBING SUPPLY PLAN - BASEMENT WING B FL OOR PLAN
PP-101A PLUMBING SUPPLY PLAN - LEVEL 1 WING A FLO OR PLAN
PP-101B PLUMBING SUPPLY PLAN - LEVEL 1 WING B FLO OR PLAN
PJ-100A MEDICAL GAS PLAN - BASEMENT WING A FLOOR PLAN
PJ-100B MEDICAL GAS PLAN - BASEMENT WING B FLOOR PLAN
PJ-101B MEDICAL GAS PLAN - LEVEL 1 WING B FLOOR P LAN
P-102A PLUMBING PLAN - WING A ROOF PLAN
P-102B PLUMBING PLAN - WING B ROOF PLAN
P-301 PLUMBING RISER DIAGRAMS
P-302 PLUMBING RISER DIAGRAMS
P-303 PLUMBING RISER DIAGRAMS
P-304 PLUMBING RISER DIAGRAMS
P-401 PLUMBING PARTIAL PLANS
P-402 PLUMBING PARTIAL PLANS
Colmery-O’Neil VAMC - Topeka, KS Bid Documents
07-01-15
00 01 15 - 4
LIST OF DRAWING SHEETS
P-501 PLUMBING DETAILS I
P-502 PLUMBING DETAILS II
P-601 PLUMBING SCHEDULES I
MECHANICAL
M-000 MECHANICAL LEGEND AND ABBREVIATIONS
MD-100A MECHANICAL DEMOLITION PLAN - WING A BASEM ENT FLOOR PLAN
MD-100B MECHANICAL DEMOLITION PLAN - WING B BASEM ENT FLOOR PLAN
MHD-101A MECHANICAL HVAC DEMOLITION PLAN - WING A LEVEL 1 FLOOR PLAN
MHD-101B MECHANICAL HVAC DEMOLITION PLAN - WING B LEVEL 1 FLOOR PLAN
MPD-101A MECHANICAL PIPING DEMOLITION PLAN - LEVE L 1 WING A FLOOR PLAN
MPD-101B MECHANICAL PIPING DEMOLITION PLAN - LEVE L 1 WING B FLOOR PLAN
MD-102A MECHANICAL DEMOLITION PLAN - WING A ROOF PLAN
MD-102B MECHANICAL DEMOLITION PLAN - WING B ROOF PLAN
MH-101A MECHANICAL HVAC DESIGN PLAN - WING A LEVE L 1 FLOOR PLAN
MH-101B MECHANICAL HVAC DESIGN PLAN - WING B LEVE L 1 FLOOR PLAN
MP-100A MECHANICAL PIPING DESIGN PLAN - BASEMENT FLOOR PLAN
MP-100B MECHANICAL PIPING DESIGN PLAN - BASEMENT FLOOR PLAN
MP-101A MECHANICAL PIPING DESIGN PLAN - WING A LE VEL 1 FLOOR PLAN
MP-101B MECHANICAL PIPING DESIGN PLAN - WING B LE VEL 1 FLOOR PLAN
M-102A MECHANICAL DESIGN PLAN - WING A ROOF PLAN
M-102B MECHANICAL DESIGN PLAN - WING B ROOF PLAN
MH-103A MECHANICAL HVAC DEDUCT ALTERNATE PLAN – WI NG A LEVEL 1
M-201 MECHANICAL FLOW DIAGRAMS
M-401 MECHANICAL ENLARGED PLANS I
M-501 MECHANICAL DETAILS I
M-502 MECHANICAL DETAILS II
M-601 MECHANICAL SCHEDULES I
M-602 MECHANICAL SCHEDULES II
M-701 MECHANICAL CONTROLS I
M-702 MECHANICAL CONTROLS II
M-703 MECHANICAL CONTROLS III
M-704 MECHANICAL CONTROLS IV
M-705 MECHANICAL CONTROLS V
M-706 MECHANICAL CONTROLS VI
Colmery-O’Neil VAMC - Topeka, KS Bid Documents
07-01-15
00 01 15 - 5
LIST OF DRAWING SHEETS
ELECTRICAL
E-000 ELECTRICAL LEGEND
ELD-101A ELECTRICAL LIGHTING DEMOLITION PLAN - A WING
ELD-101B ELECTRICAL LIGHTING DEMOLITION PLAN - B WING
EPD-101A ELECTRICAL POWER DEMOLITION PLAN - A WING
EPD-101B ELECTRICAL POWER DEMOLITION PLAN - B WING
EPD-102A ELECTRICAL POWER DEMOLITION ROOF PLAN - A WING
EPD-102B ELECTRICAL POWER DEMOLITION ROOF PLAN - B WING
EL-101A ELECTRICAL LIGHTING PLAN - A WING
EL-101B ELECTRICAL LIGHTING PLAN - B WING
EP-101A ELECTRICAL POWER PLAN - A WING
EP-101B ELECTRICAL POWER PLAN - B WING
EQ-101A ELECTRICAL MECHANICAL PLAN - A WING
EQ-101B ELECTRICAL MECHANICAL PLAN - B WING
EQ-102A ELECTRICAL ROOF PLAN - A WING
EQ-102B ELECTRICAL ROOF PLAN - B WING
E-401 ELECTRICAL ENLARGED FLOOR PLANS
E-501 ELECTRICAL DETAILS
E-502 ELECTRICAL DETAILS
E-601 ELECTRICAL ONE-LINE DIAGRAM
E-602 ELECTRICAL SCHEDULES
E-603 ELECTRICAL SCHEDULES
E-604 ELECTRICAL SCHEDULES
E-701 LIGHTING CONTROLS
E-702 LIGHTING CONTROL DIAGRAMS
TELECOMMUNICATIONS
T-000 TECHNOLOGY LEGEND
TD-101A TECHNOLOGY DEMOLITION PLAN - A WING
TD-101B TECHNOLOGY DEMOLITION PLAN - B WING
TI-101A INTERCOM AND PUBLIC ADDRESS PLAN - A W ING
TI-101B INTERCOM AND PUBLIC ADDRESS PLAN - B W ING
TM-101A NURSE CALL AND MONITORING SYSTEMS PLAN - A WING
Colmery-O’Neil VAMC - Topeka, KS Bid Documents
07-01-15
00 01 15 - 6
LIST OF DRAWING SHEETS
TM-101B NURSE CALL AND MONITORING SYSTEMS PLAN - B WING
TN-101A COMMUNICATIONS PLAN - A WING
TN-101B COMMUNICATIONS PLAN - B WING
TY-101A SECURITY PLAN - A WING
TY-101B SECURITY PLAN - B WING
T-401 TECHNOLOGY ENLARGED FLOOR PLANS
T-501 TECHNOLOGY DETAILS
T-601 TECHNOLOGY RISER DIAGRAMS
T-602 TECHNOLOGY SCHEDULES
TOTAL SHEETS: 160
- - - END - - -
Colmery-O’Neil VAMC - Topeka, KS
ADDENDUM 02
i
GENERAL REQUIREMENTS
SECTION 01 00 00
GENERAL REQUIREMENTS
TABLE OF CONTENTS
1.1 SAFETY REQUIREMENTS
1.2 GENERAL INTENTION
1.3 STATEMENT OF BID ITEM(S)
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
1.5 CONSTRUCTION SECURITY REQUIREMENTS
1.6 OPERATIONS AND STORAGE AREAS
1.7 ALTERATIONS
1.8 DISPOSAL AND RETENTION
1.9 RESTORATION
1.10 AS-BUILT DRAWINGS
1.11 WARRANTY MANAGEMENT
1.12 USE OF ROADWAYS
1.13 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT
1.14 TEMPORARY TOILETS
1.15 NEW TELEPHONE EQUIPMENT
1.16 TESTS
1.17 INSTRUCTIONS
1.18 GOVERNMENT-FURNISHED PROPERTY
1.19 RELOCATED EQUIPMENT & ITEMS
1.20 CONSTRUCTION SIGN
1.21 SAFETY SIGN
1.22 BIDDER EVALUATION
NOTE: TEXT HIGHLIGHTED BLUE ADDED PER ADDENDUM 01, 11/26/2019
NOTE: TEXT HIGHLIGHTED RED ADDED PER ADDENDUM 02, 01/24/2020
NOTE: TEXT HIGHLIGHTED PURPLE ADDED PER VA DIRECTION 03/20/20
VA 589A5-18-116
Colmery-O’Neil VAMC - Topeka, KS
ADDENDUM 01
12-01-18
01 00 00 -1
GENERAL REQUIREMENTS
SECTION 01 00 00
GENERAL REQUIREMENTS
1.1 SAFETY REQUIREMENTS
Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.
1.2 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for the Renovation of A & B Wings in Building 6 at the Colmery-O’Neil VAMC as required by drawings and specifications.
B. Only one organized site visit will be scheduled prior to the bid date.
Attendance is highly recommended.
C. Offices of Spur Design, as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer or his duly authorized representative.
D. Before placement and installation of work subject to tests by testing laboratory retained by Department of Veterans Affairs, the Contractor shall notify the COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three work days unless otherwise designated by the COR.
E. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.
1.3 STATEMENT OF BID ITEM(S)
A. ITEM I, GENERAL CONSTRUCTION: Work includes general construction, supervision, labor, material, alterations, mechanical and electrical
Colmery-O’Neil VAMC - Topeka, KS
ADDENDUM 01
12-01-18
01 00 00 -2
GENERAL REQUIREMENTS
construction equipment and certain other items to perform the required work on the project.
B. ITEM II, ALTERNATE NO.1: All items in Bid Item I, including Wing A
PT/OT Room A110 and corridor alcoves to be renovated; except the following: remaining Wing A renovation to be removed from scope of work in its entirety.
C. CONSTRUCTION DURATION: The expected duration of the project including pre-phase PT/OT renovation work is 500 calendar days.
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.
1.5 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
B. Security Procedures:
1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. Before starting work the General Contractor shall give one week’s notice to the Contracting Officer so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.
3. No photography of VA premises is allowed without written permission of the Contracting Officer.
Colmery-O’Neil VAMC - Topeka, KS
ADDENDUM 01
12-01-18
01 00 00 -3
GENERAL REQUIREMENTS
4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.
D. Key Control:
1. The General Contractor shall provide duplicate keys and lock combinations to the Contracting officers representative (COR) for the purpose of security inspections of every area of project including tool boxes and parked machines and take any emergency action.
2. The General Contractor shall turn over all permanent lock cylinders to the VA locksmith for permanent installation. See Section 08 71
00, DOOR HARDWARE and coordinate.
E. Document Control:
1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of
“sensitive information”.
2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.
3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”.
Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.
4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting
Officer.
5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.
Colmery-O’Neil VAMC - Topeka, KS
ADDENDUM 01
12-01-18
01 00 00 -4
GENERAL REQUIREMENTS
6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.
7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document
Management Software (EDMS).
a. Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the
EDMS system.
b. “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.
F. Motor Vehicle Restrictions
1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.
2. A limited number of (2 to 5) permits shall be issued for General
Contractor and its employees for parking in designated areas only.
1.6 OPERATIONS AND STORAGE AREAS
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the
Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the
Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the
Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the Contracting
Colmery-O’Neil VAMC - Topeka, KS
ADDENDUM 01
12-01-18
01 00 00 -5
GENERAL REQUIREMENTS
Officer, the buildings and utilities may be abandoned and need not be removed.
C. The Contractor shall, under regulations prescribed by the Contracting
Officer, use only established roadways. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
(FAR 52.236-10)
D. Working space and space available for storing materials shall be as determined by the COR.
E. Workers are subject to rules of the Medical Center applicable to their conduct.
F. Execute work in such a manner as to interfere as little as possible with work being done by others. Keep roads clear of construction materials, debris, standing construction equipment and vehicles at all times.
G. Execute work so as to interfere as little as possible with normal functioning of the Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by the COR.
1. Do not store materials and equipment in other than assigned areas.
2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of
Veterans Affairs in quantities sufficient for not more than two work
Colmery-O’Neil VAMC - Topeka, KS
ADDENDUM 01
12-01-18
01 00 00 -6
GENERAL REQUIREMENTS
days. Provide unobstructed access to Medical Center areas required to remain in operation.
3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.
H. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by the COR. All such actions shall be coordinated with the COR or Utility Company involved:
I. Phasing:
The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur.
It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks. The work to be outlined shall include, but not be limited to:
To ensure such executions, Contractor shall furnish the COR with a schedule of approximate dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such dates to ensure accomplishment of this work in successive phases mutually agreeable to
COR and Contractor, as follows:
Pre-Phase: New Access to Existing Wing B PT/OT & ICRA Barriers, continuous HVAC Service to Existing Wing B PT/OT. Note that Wing B PT/OT must be fully operational prior to the activation of Wing C (currently in construction).
Colmery-O’Neil VAMC - Topeka, KS
ADDENDUM 01
12-01-18
01 00 00 -7
GENERAL REQUIREMENTS
Phase I: Wing A & B Demolition, Wing A North & East Construction, Wing A
PT/OT Construction
Phase II: Wing A South Construction, Wing B Construction
Phase III: Wing B PT/OT Construction
J. Part of Bldg. 6 will be vacated by Government in accordance with above phasing beginning immediately after date of receipt of Notice to
Proceed and turned over to Contractor.
1. Certain areas of Building No. 6 will be occupied by Medical Center personnel for various periods as listed below:
AREA PERIOD
Wing D Duration of Project
Wing C Duration of Project
Wing B PT/OT Relocated to Wing A upon completion of
Wing A PT/OT & Wing A North & East
Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical Centers operations will not be hindered. Contractor shall permit access to Department of
Veterans Affairs personnel and patients through other construction areas which serve as routes of access to such affected areas and equipment. These routes whether access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces, lighting etc to facilitate patient and staff access.
Coordinate alteration work in areas occupied by Department of
Veterans Affairs so that Medical Center operations will continue during the construction period.
2. Immediate areas of alterations not mentioned in preceding
Subparagraph 1 will be temporarily vacated while alterations are performed.
Colmery-O’Neil VAMC - Topeka, KS
ADDENDUM 01
12-01-18
01 00 00 -8
GENERAL REQUIREMENTS
K. When a building and/or construction site is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:
1. Contractor shall maintain a minimum temperature of 4 degrees C (40 degrees F) at all times, except as otherwise specified.
2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company (Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from
Contractor's employee or watchman.
L. Utilities Services: Maintain existing utility services for Medical
Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services.
Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR. Electrical work shall be accomplished with all affected circuits or equipment de-energized.
When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the Medical Center Director’s prior knowledge and written approval. Refer to specification Sections 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, 27 05 11 REQUIREMENTS FOR
COMMUNICATIONS INSTALLATIONS and 28 05 00, COMMON WORK RESULTS FOR
ELECTRONIC SAFETY AND SECURITY for additional requirements.
2. Contractor shall submit a request to interrupt any such services to
COR, in writing, 7 days n advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.
Colmery-O’Neil VAMC - Topeka, KS
ADDENDUM 01
12-01-18
01 00 00 -9
GENERAL REQUIREMENTS
3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.
4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COR.
5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.
M. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, which are to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.
N. To minimize interference of construction activities with flow of
Medical Center traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.
O. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.
1.7 ALTERATIONS
A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR and a representative of VA Supply Service, of areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by all
Colmery-O’Neil VAMC - Topeka, KS
ADDENDUM 01
12-01-18
01 00 00 -10
GENERAL REQUIREMENTS
three, to the Contracting Officer. This report shall list by rooms and spaces:
1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of the building.
2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.
3. Shall note any discrepancies between drawings and existing conditions at site.
4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and COR.
B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR and/or Supply Representative, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by
Contractor with new items in accordance with specifications which will be furnished by Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING SITE
CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR 52.243-4 and VAAR
852.236-88).
C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:
1. Re-survey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of
Colmery-O’Neil VAMC - Topeka, KS
ADDENDUM 01
12-01-18
01 00 00 -11
GENERAL REQUIREMENTS
Contractor to restore damage caused by Contractor's workers in executing work of this contract.
D. Protection: Provide the following protective measures:
1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.
2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.
3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.
1.8 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
1. Reserved items which are to remain property of the Government are identified by attached tags or noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.
2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.
3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to
Colmery-O’Neil VAMC - Topeka, KS
ADDENDUM 01
12-01-18
01 00 00 -12
GENERAL REQUIREMENTS
be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.
1.9 RESTORATION
A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the
COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
B. Upon completion of contract, deliver work complete and undamaged.
Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.
D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES"
(FAR 52.243-4 and VAAR 852.236-88) and "DIFFERING SITE CONDITIONS" (FAR
52.236-2).
1.10 AS-BUILT DRAWINGS
A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.
Colmery-O’Neil VAMC - Topeka, KS
ADDENDUM 01
12-01-18
01 00 00 -13
GENERAL REQUIREMENTS
B. All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built drawings shall be made available for the COR review, as often as requested.
C. Contractor shall deliver two approved completed sets ofas-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.
D. Paragraphs A, B, & C shall also apply to all shop drawings.
1.11 WARRANTY MANAGEMENT
A. Warranty Management Plan: Develop a warranty management plan which contains information relevant to FAR 52.246-21 Warranty of Construction at least 30 days before the planned pre-warranty conference, submit two sets of the warranty management plan. Include within the warranty management plan all required actions and documents to assure that the
Government receives all warranties to which it is entitled. The plan must be in narrative form and contain sufficient detail to render it suitable for use by future maintenance and repair personnel, whether tradesman, or of engineering background, not necessarily familiar with this contract. The term “status” as indicated below must include due date and whether item has been submitted or was approved. Warranty information made available during the construction phase must be submitted to the Contracting Officer for approval prior to each monthly invoice for payment. Assemble approved information in a binder and turn over to the Government upon acceptance of the work. The construction warranty period will begin on the date of the project acceptance and continue for the product warranty period. A joint 4 month and 9 month warranty inspection will be conducted, measured from time of acceptance, by the Contactor and the Contracting Officer. Include in the warranty management plan, but not limited to, the following:
1. Roles and responsibilities of all personnel associated with the warranty process, including points of contact and telephone numbers within the company of the Contractor, subcontractors, manufacturers or suppliers involved.
Colmery-O’Neil VAMC - Topeka, KS
ADDENDUM 01
12-01-18
01 00 00 -14
GENERAL REQUIREMENTS
2. Furnish with each warranty the name, address and telephone number of each of the guarantor’s representatives nearest project location.
3. Listing and status of delivery of all Certificates of Warranty for extended warranty items, to include roofs, HVAC balancing, pumps, motors, transformers and for all commissioned systems such as fire protection and alarm systems, sprinkler systems and lightning protection systems, etc.
4. A list for each warranted equipment item, feature of construction or system indicating:
a. Name of item.
b. Model and serial numbers.
c. Location where installed.
d. Name and phone numbers of manufacturers and suppliers.
e. Name and phone numbers of manufacturers or suppliers.
f. Names, addresses and phone numbers of sources of spare parts.
g. Warranties and terms of warranty. Include one-year overall warranty of construction, including the starting date of warranty of construction. Items which have extended warranties must be indicated with separate warranty expiration dates.
h. Starting point and duration of warranty period.
i. Summary of maintenance procedures required to continue the warranty in force.
j. Cross-reference to specific pertinent Operation and Maintenance manuals.
k. Organizations, names and phone numbers of persons to call for warranty service.
l. Typical response time and repair time expected for various warranted equipment.
Colmery-O’Neil VAMC - Topeka, KS
ADDENDUM 01
12-01-18
01 00 00 -15
GENERAL REQUIREMENTS
5. The plans for attendance at the 4 and 9-month post construction warranty inspections conducted by the government.
6. Procedure and status of tagging of all equipment covered by extended warranties.
7. Copies of instructions to be posted near selected pieces of equipment where operation is critical for warranty and/or safety reasons.
B. Performance Bond: The Performance Bond must remain effective throughout the construction period.
1. In the event the Contractor fails to commence and diligently pursue any construction warranty work required, the Contracting Officer will have the work performed by others, and after completion of the work, will charge the remaining construction warranty funds of expenses incurred by the Government while performing the work, including, but not limited to administrative expenses.
2. In the event sufficient funds are not available to cover the construction warranty work performed by the Government at the contractor’s expenses, the Contracting Officer will have the right to recoup expenses from the bonding company.
3. Following oral or written notification of required construction warranty repair work, the Contractor shall respond in a timely manner. Written verification will follow oral instructions. Failure to respond will be cause for the Contracting Officer to proceed against the Contractor.
C. Pre-Warranty Conference: Prior to contract completion, and at a time designated by the Contracting Officer, the Contractor shall meet with the Contracting Officer to develop a mutual understanding with respect to the requirements of this section. Communication procedures for
Contractor notification of construction warranty defects, priorities with respect to the type of defect, reasonable time required for
Contractor response, and other details deemed necessary by the
Contracting Officer for the execution of the construction warranty will be established/ reviewed at this meeting. In connection with these
Colmery-O’Neil VAMC - Topeka, KS
ADDENDUM 01
12-01-18
01 00 00 -16
GENERAL REQUIREMENTS
requirements and at the time of the Contractor’s quality control completion inspection, furnish the name, telephone number and address of a licensed and bonded company which is authorized to initiate and pursue construction warranty work action on behalf of the Contractor.
This point of contract will be located within the local service area of the warranted construction, be continuously available and be responsive to Government inquiry on warranty work action and status. This requirement does not relieve the Contractor of any of its responsibilities in conjunction with other portions of this provision.
D. Contractor’s Response to Construction Warranty Service Requirements:
Following oral or written notification by the Contracting Officer, the
Contractor shall respond to construction warranty service requirements in accordance with the “Construction Warranty Service Priority List” and the three categories of priorities listed below. Submit a report on any warranty item that has been repaired during the warranty period.
Include within the report the cause of the problem, date reported, corrective action taken, and when the repair was completed. If the
Contractor does not perform the construction warranty within the timeframe specified, the Government will perform the work and back charge the construction warranty payment item established.
1. First Priority Code 1. Perform onsite inspection to evaluate situation, and determine course of action within 4 hours, initiate work within 6 hours and work continuously to completion or relief.
2. Second Priority Code 2. Perform onsite inspection to evaluate situation, and determine course of action within 8 hours, initiate work within 24 hours and work continuously to completion or relief.
3. Third Priority Code 3. All other work to be initiated within 3 work days and work continuously to completion or relief.
4. The “Construction Warranty Service Priority List” is as follows:
Code 1-Life Safety Systems
a. Fire suppression systems.
b. Fire alarm system(s).
Colmery-O’Neil VAMC - Topeka, KS
ADDENDUM 01
12-01-18
01 00 00 -17
GENERAL REQUIREMENTS
Code 1-Air Conditioning Systems
a. Air conditioning leak in part of the building, if causing damage.
b. Air conditioning system not cooling properly.
Code 1 Doors
a. Overhead doors not operational, causing a security, fire or safety problem.
b. Interior, exterior personnel doors or hardware, not functioning properly, causing security, fire or safety problem.
Code 3-Doors
a. Interior/exterior personnel doors or hardware not functioning properly.
Code 1-Electrical
a. Power failure (entire area or any building operational after 1600 hours).
b. Security lights.
c. Smoke detectors.
Code 2-Electrical
a. Power failure (no power to a room or part of building).
b. Receptacles and lights not operational (in a room or part of building).
Code 3-Electrical
a. Exterior lights not operational.
Code 1-Gas
a. Leaks and pipeline breaks.
Code 1-Heat
a. Power failure affecting heat.
Colmery-O’Neil VAMC - Topeka, KS
ADDENDUM 01
12-01-18
01 00 00 -18
GENERAL REQUIREMENTS
Code 1-Plumbing
a. Hot water heater failure.
b. Leaking water supply pipes.
Code 2-Plumbing
a. Flush valves not operating properly
b. Fixture drain, supply line or any water pipe leaking.
c. Toilet leaking at base.
Code 3- Plumbing
a. Leaky faucets.
Code 3-Interior
a. Floors damaged.
b. Paint chipping or peeling.
c. Casework damaged.
Code 1-Roof Leaks
a. Damage to property is occurring.
Code 2-Water (Exterior)
a. No water to facility.
Code 2-Water (Hot)
a. No hot water in portion of building listed.
Code 3
a. All work not listed above.
E. Warranty Tags: At the time of installation, tag each warranted item with a durable, oil and water-resistant tag approved by the Contracting
Officer. Attach each tag with a copper wire and spray with a silicone waterproof coating. Also submit two record copies of the warranty tags showing the layout and design. The date of acceptance and the QC
Colmery-O’Neil VAMC - Topeka, KS
ADDENDUM 01
12-01-18
01 00 00 -19
GENERAL REQUIREMENTS
signature must remain blank until the project is accepted for beneficial occupancy. Show the following information on the tag.
1.12 USE OF ROADWAYS
A. For hauling, use only established public roads and roads on Medical
Center property.
1.13 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT
A. Use of new installed mechanical and electrical equipment to provide heat, ventilation, plumbing, light and power will be permitted subject to written approval and compliance with the following provisions:
1. Permission to use each unit or system must be given by COR in writing. If the equipment is not installed and maintained in accordance with the written agreement and following provisions, the
COR will withdraw permission for use of the equipment.
Colmery-O’Neil VAMC - Topeka, KS
ADDENDUM 01
12-01-18
01 00 00 -20
GENERAL REQUIREMENTS
2. Electrical installations used by the equipment shall be completed in accordance with the drawings and…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .