36C25520R0072-052.docx
DOCX document Posted
- Solicitation number
- 36C25520R0072
About this file
36C25520R0072 P09 SOW 589A5-19-116 Bldg 6 A_B Wings Construction.docx
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25520R0072-056.pdf | ||
| 36C25520R0072-057.pdf | ||
| 36C25520R0072-053.pdf | ||
| 36C25520R0072-055.pdf | ||
| 36C25520R0072-051.docx | DOCX document | |
| 36C25520R0072-054.pdf | ||
| 36C25520R0072-060.pdf | ||
| 36C25520R0072-058.pdf | ||
| 36C25520R0072-059.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RENOVATION OF A & B – WINGS, BUILDING 6
STATEMENT OF WORK
COLMERY-O’NEIL VA MEDICAL CENTER, TOPEKA, KANSAS
Project 589A5-19-116 December 2019
1. SCOPE:
The Project consists of a major renovation project of Building 6 A & B Wings on the Colmery-O’Neil VA campus in Topeka, KS. The scope includes the remodel of the A & B Wings of Building 6 CLC, approximately 21,500 square feet. The work is to include a complete interior demolition of Wing B of approximately 11,404 square feet as required for new geriatric psychiatric resident rooms and resident/clinical support spaces. A complete demolition of Wing A of approximately 10,120 square feet will be required for a new Geri-PACT clinic and Building 6 offices and support spaces. A summary overview of the project objectives through new renovation includes:
| A. | New Geri-PACT Clinic in A Wing including exam, diagnostic and clinical support |
| spaces; | |
| B. | New offices and support spaces for all CLC services in Building 6; |
| C. | New Physical Therapy/Occupational Therapy and Recreational Therapy facilities in |
| A Wing to support all CLC services in Building 6; | |
| D. | New access to the Building 6 interior courtyard from A Wing; |
| E. | A new 14-bed Geriatric-Psychiatric Unit in Wing B, including Day Room, Resident |
Kitchen, Resident Laundry, Recreational Therapy and associated CLC unit support spaces specific to Wing B Geriatric-Psychiatric services;
F. Improved insulation and HVAC systems that meet the VA’s energy requirements for new construction;
G. A design and layout that supports patient privacy and meets the Safe Patient Handling requirements;
H. A domestic water system that minimizes the risk of Legionella to the greatest extent possible;
| I. | A design that supports the VA’s PACT model; |
| J. | Increase natural light in order to increase staff productivity and enhance the mood |
of CLC Residents;
K. Design the facility to include discrete security and safety features for the patients and staff, paying particular attention to Geriatric-Psychiatric resident requirements;
L. Implement walls and doors with high sound transmission coefficient ratings, and other architectural and engineering controls that contribute to resident & staff comfort.
All areas will be designed under the latest VA design guidelines listed:
| A. | Ambulatory Care (Hospital-Based) (January 2009) |
| B. | Small House Model (January 2017) |
| C. | Polytrauma Rehabilitation Center (December 2014) |
| D. | PACT Space Module (June 2015) (currently in revision) |
| E. | VA Barrier Free Design Guide (Revised June 6, 2017) |
The contractor will be responsible for meeting all contract specifications for the VAMC. The project shall include concrete, electrical, plumbing, steel framing, lighting, telecommunications and finishes work. The renovated wing will consist of 13 resident rooms including 12 standard resident rooms, and 1 bariatric resident room and shall be installed in accordance with all applicable standards available at time of installation to include published commercial specifications as well as standards and preferences expressed in this document. All installation details shall be fully coordinated with VA CO and on-site Contracting Officer’s Representative (COR). Period of Performance for all work 270 days
2. STATEMENT OF WORK:
2.1 SHOP/ DRAWINGS SHALL PROVIDE:
2.1.1 2D as-builts shall be provided to show all work that is installed in this specification.
2.1.2 The contractor shall provide complete drawings as stated in the specification.
2.2 DEMOLITION:
2.2.1 The contractor shall provide all materials and labor to perform interior demolition of the walls and associated finishes. Demolition in the basement will include, but is not limited to the following: chipping of concrete toping of the concrete pan joist floor, removal of perimeter brick and block wall, removal of flooring materials, removal of walls, including furring, removal of doors and frames, removal of ceilings, removal of lighting, removal of ductwork, removal of a window, removal of wiring and controls and miscellaneous associated items.
2.3 ELECTRICAL:
2.3.1 Recommended System Modifications/Upgrades:
GENERAL
The electrical portion of this project will consist of complete phased replacement of all Division 26 electrical systems, downstream of the existing main electrical service and main emergency distribution panel, for both A Wing and B Wing of Building 6. Because of existing asbestos and lead contaminants, A and B Wings will be fully demolished internally and remodeled to meet the new space programming requirements.
| 2.3.2 | ELECTRICAL CODES AND STANDARDS |
| A. | Americans with Disabilities Act |
| B. | ASHRAE Standard 90.1-2016 – Energy Standard for Buildings |
| C. | Illuminating Engineering Society (IES) Handbook, 10th Edition |
| D. | IBC 2018 – International Building Code |
| E. | IEBC 2018 – International Existing Building Code |
| F. | IECC 2018 – International Energy Conservation Code |
| G. | JCAHO EC 7.40 – Emergency Electrical Power System Inspection, Maintenance, and Testing |
| H. | NFPA 70-2017 - National Electrical Code (NEC) |
| I. | NFPA 99-2018 – Standard for Healthcare Facilities |
| J. | NFPA 101-2018 – Life Safety Code |
| K. | NFPA 110-2019 – Standard for Emergency and Standby Power Systems |
| L. | NFPA 780-2017 – Standard for the Installation of Lightning Protection Systems |
| M. | VA PG-18-10 Electrical Design Manual, December 2015 |
| N. | VA PG-18-10 Lighting Design Manual, December 2015 |
| O. | VA Physical Security Design Manual for VA Life-Safety Protected Facilities, January 2015 |
| 2.3.4 | ELECTRICAL DEMOLITION |
| A. | Demolition of electrical systems in A Wing will include: |
| 1. | Power distribution panelboards, their feeder conductors and conduits, and upstream over-current protection devices back to the main electrical service distribution board. |
| 2. | All branch conductors, conduits (excluding any conduits in existing walls to 12” away from an existing wall), surface raceways, non-recessed electrical boxes and all electrical devices downstream of the panelboards. |
| 3. | The hallway 2x4 direct-indirect troffer light fixtures will be removed, stored and reused. |
| 4. | All other light fixtures with their feeder conductors/conduits and all lighting control devices with their feeder conductors/conduits back to the upstream panelboards. |
| B. | Demolition of electrical systems in B Wing will include: | |
| 1. | All power distribution panelboards, their feeder conductors and conduits, and upstream | overcurrent protection devices back to the main electrical service distribution board. |
| 2. | All branch conductors, conduits, surface raceways, electrical boxes and all electrical devices downstream of the panelboards. | |
| 3. | All light fixtures with their feeder conductors/conduits and all lighting control devices with their feeder conductors/conduits back to the upstream panelboards. |
2.3.5 SITE POWER DISTRIBUTION SYSTEMS
Building 6 is currently provided electrical service by existing transformer 6-T1-A; this transformer is pad mounted, 500KVA, and transitions primary 12,470V campus power down to secondary 208Y/120V building power. The building side of the transformer is equipped with a 1600A circuit breaker which provides protection for the main service feeders supplying the Main Switch Board located in the basement main electrical room of Building 6. The existing transformer, secondary circuit breaker, main building feeders, and main switch board are all to remain.
2.3.6 SITE & BUILDING MOUNTED LIGHTING SYSTEMS
A. Site lighting and controls are not included in this scope of work.
B. Building mounted lighting and controls will be modified as related to the area of work outlined by the scope of work. Emergency egress lighting and controls for A and B Wing exterior exit doors will be provided as new. Any other building mounted lighting and controls will remain; new branch circuits will be provided if the remaining lights/controls are currently fed from a panelboard designated for replacement.
2.3.7 ELECTRICAL SERVICE AND GENERATOR UPGRADE
The existing building loads have been reviewed for the proposed modifications in A and B Wings, along with the current renovation project in C Wing and the existing loading in D Wing. At this time, we are recommending an electrical service upgrade in order to accommodate all of the building load. As this is a 24/7 patient occupied building, we would recommend adding a second electrical service to segregate the new A and B Wing loads and allow for construction without losing power to the existing building. Preliminary service has been shown in order to plan for a future new service transformer but is not included in the project.
| 2.3.8 | BUILDING POWER DISTRIBUTION SYSTEMS |
| A. | New 208Y/120V, 3-phase, 4-wire power distribution systems will be provided in both A and B Wings. |
| B. | Two new 225A, 2-Section and one new 225A normal power panelboards and upstream |
feeders/breakers originating from/in the existing Main Switchboard MSB.
| C. | Existing Panelboard 6E will be demolished to allow for upgrade of an old panelboard and allow room for the new automatic transfer switch ATS2. Existing panelboards fed from 6E serving A and B wings will be demolished and served by new panelboards on the second electrical service. Existing panelboards fed from 6E serving C and D wings will be fed from new circuit breakers direct from the existing Emergency Distribution Panelboard EMDB. |
| D. | Six new essential power panelboards and feeders, four of these will be downstream of the new secondary essential power distribution panelboard and two downstream of the existing EMDB panelboard (including panelboard separation for life safety and equipment/IT branches). |
| E. | New normal and essential power feeders and branch circuits will be provided to all new receptacles, lighting and related controls. |
| F. | Refer to power plan sheets 6-EP100, 6-EP101A, 6-EP101B and one-line diagram sheet 6-E-601 for additional representation of the power distribution system work. |
| 2.3.9 | BUILDING LIGHTING SYSTEMS |
| A. | All A and B Wing spaces will receive new LED lighting to meet the new space programs and to closely match fixture types installed in the previous D Wing expansion and C Wing renovation. Refer to the submission drawings for the light fixture layouts and schedule of fixtures. Refer to Appendix A of this electrical narrative for a space type lighting guide and cut-sheets of all scheduled light fixtures (after review, please provide any applicable feedback regarding light fixture selections). |
| B. | The basement mechanical and electrical rooms below A Wing will also receive new LED lighting. |
| C. | New lighting controls will be provided in all A and B Wing spaces (including the basement) in |
accordance with the space program requirements, the VA design guides and the International Energy Code.
| 2.3.10 | GENERAL LIGHTING EQUIPMENT |
| A. | Building Lighting |
| 1. | Building lighting will consist of recessed troffer, downlight, and strip light style fixtures with LED light sources with integral lamps and drivers. Drivers will be a minimum of 85% efficient at full load, have a power factor greater than 95%, total harmonic distortion less than 20%, and operate with a universal 120/277V input. All lights will be serviceable from below the ceiling. Emergency lighting fixtures along the path of egress will be circuited to generator backed essential power |
2. Wall-mounted bed light fixtures in single bed patient rooms will consist of an upward and downward lamp with a 2-position on-off pull cord control of the downward portion of the light.
3. Exit light fixtures will be LED type with red lettering and a brushed aluminum finish. Fixtures will be single or double-faced with directional arrows as required. Fixtures will be circuited to generator backed essential power.
| 4. | Exterior building wall mounted lighting will be full cut-off, LED type. Lights in areas of emergency building egress will be circuited to generator backed essential power. |
| B. | Lighting Controls |
| 1. | Indoor wall-mounted occupancy sensors will be dual technology, automatic off/manual on, low voltage type. Wall-mounted sensors will be utilized in enclosed offices and small spaces where ceiling mounted coverage is not required. Sensors will include all required power packs, etc. for a complete control system. |
2. Indoor ceiling-mounted occupancy sensors will be dual technology, automatic off/manual on, low voltage type. Ceiling-mounted sensors will be utilized in open offices and larger spaces where coverage by ceiling is required. Sensors will include all required digital room controller, power packs, etc. for a complete control system. Wall-mounted override switches will be included.
3. Daylighting sensors will be automatic dimming, digital style photo-sensors compatible with the digital room controllers to interconnect with occupancy sensors and lights. Sensor will allow for foot-candle set points from 20-60 fc. Sensors will be set at 5 fc greater than the required average maintained illumination in the space.
4. Standard manual light switches will be quiet toggle type or paddle/slide 0-10V wall dimming type, specification grade and ivory in color as required by the VA design guide. Manual light switches will be utilized in spaces where automatic control of lights is detrimental to the occupant, such as in electrical and mechanical rooms.
2.4 HVAC system:
The system will be designed to meet the air-change and pressure relationship requirements for the different space types, with ducted supply, return and exhaust air systems. All ducted perimeter rooms with windows will be provided with linear diffusers. Interior ducted spaces will be served by square supply air diffusers. associated materials as specified on the drawings and in specifications.
| 2.4.1 | GENERAL |
| A. | Project Objectives |
1. Renovate and reconfigure existing spaces in Wings A and B of Building 6 and support areas of the Topeka VA to provide HVAC systems to better serve the new layouts to provide a fully functional space to meet all standards and requirements. Conversion of Building 6 A and B wing into a Geriatric Community Living Center that fully meets current VA standards.
2. The specific features inside the CLC include:
a) Standard and Bariatric patient rooms including the required mechanical patient lifts;
b) Physical therapy and occupational therapy rooms;
c) Bariatric bathrooms;
d) Dining areas;
| 3. | Med rooms will have individual room temperature, humidity, and pressure requirements. |
| 4. | Design the MEP systems based on new design standards and using existing utility systems in place. |
| 5. | Use indoor central air handling units for new construction in lieu of fan coils units in occupied space in compliance with the VA HVAC Design Manual. |
| B. | Building Description |
| 1. | Building 6 of the VA Medical complex is made up of 4 wings. Wings A and B are the wings being renovated for this project. |
| 2. | See architectural descriptions and drawings for additional information regarding structure type and envelope characteristics. |
| C. | Existing Site Utilities |
| 1. | Steam – piping entry to basement mechanical room is existing. |
| 2. | Chilled Water - piping entry to basement mechanical room is existing. |
| 3. | Natural gas is present in Wing C but will not be used or extended to Wings A or B currently. |
| 4. | Domestic Water utility entry is existing to basement mechanical room. |
| 5. | See Division 21 descriptions for fire utility extensions and related coordination. |
D. Phasing
| 1. | Site utility extensions for steam and chilled water will need to be coordinated with the footing and foundation work. Refer Architecture for general phasing of construction. |
| E. | Commissioning |
| 1. | The system will be commissioned subject to the requirement of Section 01 91 00 General Commissioning Requirements and related specification divisions. |
| F. | Testing, Adjusting, and Balancing for HVAC |
| 1. | Final testing of systems will be performed and reviewed during the commissioning functional performance testing of the systems. |
| G. | Freeze Protection |
| 1. | Provide freeze protection methods as appropriate in climates with ASHRAE 99% Winter Design Condition is below 32°F. Project condition for location is 3.5°F. Therefore, freeze protection measures will be included where appropriate. |
| H. | Noise and Vibration Control |
| 1. | Noise and vibration control will be provided in compliance with the specifications and seismic control requirements. |
| 2. | Sound attenuation will be provided where necessary to maintain the sound level requirements based on the new HVAC equipment sound power ratings. |
| I. | Seismic Requirements |
| 1. | Seismic controls, when required shall comply with VA Publication H-18-8 Seismic Design Requirements. |
| 2. | Structures assigned to Seismic Design Category C, D, E, or F, permanent non-structural components and their attachments, and the structure-supported attachments of permanent equipment shall be designed to resist total design forces prescribed in ASCE-7. |
| 3. | Seismic Control Specifications are Required- as this project location is in a medium low seismic activity area. |
| J. | Metering |
| 1. | The metered systems are specified under Section 25100 Advanced Utility Metering System. |
| 2.4.2 | APPLICABLE CODES |
| A. | ICC - International Building Codes |
| B. | NFPA – National Fire Protection Association - 90A, 96, 99, 101. |
| 2.4.3 | APPLICABLE STANDARDS |
| A. | HVAC Design Manual for New, Replacement, Addition and Renovation of Existing VA Facilities, Current edition. |
| B. | Facility Guidelines Institute (FGI) – 2010 |
| C. | ASHRAE 90.1 – 2013 Energy Standard for Buildings Except Low Rise Residential Buildings. |
| D. | ASHRAE Standard 170 – 2013 (Ventilation of Health Care Facilities) |
| E. | ASHRAE 62.1 - 2016 Ventilation for Acceptable Indoor Air Quality |
| 2.4.4 | OUTDOOR CLIMATE CONDITIONS: |
| A. | ASHRAE Climate Zone 4A (Moist) |
1. Weather Station: Forbes Field, KS - 724565
2. Topeka, KS (Shawnee County) B. VA HVAC Design Manual
1. Heating: 3.5°F (99.6% H DB)
2. Cooling (100% OA) - 0.4% Db/WB: 94.4°F DB / 60.8° MCWB, HR=104.4° / 70.4° MCDB
3. Cooling (minimum OA) - 1% Db/WB: 91.5°F DB / 60.2° MCWB, HR=97.8° / 70.0° MCDB
| 2.4.5 | INDOOR DESIGN CONDITIONS: |
| A. | The indoor design conditions are as defined by the VA HVAC Design manual for the individual spaces served by the air handling units described in the scope of work. |
| B. | See Division 23 appendices for indoor design conditions for the related spaces. |
| 2.4.6 | VENTILATION: |
| A. | Per VA Room Design Sheets and Related Standards (see appendix for HVAC Room Airflow Summary). |
| 2.4.7 | INTERNAL LOADS |
| 1. | See Division 23 appendices for internal load summaries for the related spaces. |
| 2.4.8 | ENERGY SUPPLY |
| A. | Electrical – see Electrical Scope for related information. |
| B. | Heating – heating will be hot water produced from central plant steam served by a steam to water heat exchanger. The piping is brought to and from the building through underground tunnels between buildings. |
| C. | Cooling - chilled water is provided from the central chilled water loop. The piping is brought to and from the building through underground tunnels between buildings. |
| 2.4.9 | HVAC LOAD ANALYSIS |
| A. | See Division 23 Appendices for HVAC load assumptions and HVAC load analysis. |
| 2.4.10 | HVAC SYSTEM OVERVIEW |
| A. | Overview |
The HVAC system will consist of two central VAV Air Handling Units with chilled water and heating hot water each serving a wing with single duct VAV air terminal units with hot water reheat coils serving their respective zones. Restroom exhaust, general exhaust, and relief air will be directed to Energy Recovery Ventilators (ERV), one per wing, serving their respective VAV Air Handling Units. Chilled water will be extended from the central campus chilled water loop. Steam will be extended to the building, pressure reduced to low pressure steam and converted to heating hot water with a steam to water heat exchanger.
| B. | Pumping |
| 1. | Heating Hot water Pumps – dual variable speed will be provided with the steam to water heat exchangers. |
| 2. | Chilled water pumps – dual variable speed tertiary pumps will circulate chilled water throughout the building. |
| C. | Central Utility Connections |
The central utility connections are existing system connections. It is also the requirement of the EKVAHCS maintenance staff to have this system operate off the central steam and chilled water system.
D. Roof Exhaust Fans Roof Exhaust Fans - will collect exhaust from areas not being fed to the energy recovery systems. Pre-existing ceiling penetrations will be used when possible.
E. Scheduled Capacities and Approximate Weights See Drawings for scheduled capacities and approximate weights.
| 2.4.11 | AIR HANDLING UNITS |
| A. | Central AHU: |
| 1. | Custom modular rooftop air handling units will consist of relief exhaust fan, mixing and filter section, hot water pre-heat coil, humidifier section, chilled water-cooling section, supply fan section and discharge and final filter section. |
| 2. | Fan section will be a multi-fan array served by a single variable speed drive. |
| 3. | Pre-Filter section: slide out cartridge filters. |
| 4. | Final Filter section: slide out cartridge filters. |
| 2.4.12 | HUMIDIFIERS |
| A. | Electric immersion type humidifiers will be provided for the following spaces. |
| 1. | Med rooms |
| 2. | Med storage |
| B. | The humidifiers will be served with unsoftened domestic water with scale collected in a serviceable reusable tank. |
| C. | Deionized / RO water is not required or recommended with this type of system. RO water is not available in the building and would increase the complexity of the system. |
| 2.4.13 | AIR DISTRIBUTION SYSTEM |
| A. | All ductwork will be galvanized steel. |
| B. | Return air will be fully ducted from the ceiling space to the return side of the air handling unit. |
| C. | Supply air duct be externally insulated with duct wrap in compliance with the VA master specification. Internally insulated duct will not be used. |
| 2.4.14 | VAV TERMINAL UNITS |
| A. | Single duct variable air volume terminal units with hot water heating coil and DDC control will provide heating, ventilation, and cooling for the spaces shown. |
2.4.15 EXHAUST FANS
A. General exhaust
1. Toilet exhaust
2. Med/drug Storage
3. Break room
4. Housekeeping closet
2.4.16 FAN COIL UNITS
| A. | Consist of VRF DX Split system heat pump units with wall mounted or horizontal concealed indoor units with remote outdoor condensing unit. |
| 1. | IT Data Closets |
2.4.17 CONTROLS
| A. | The controls will be integrated with the current ECC system platform as part of this work. |
| B. | Building Automation System Platform: |
| 1. | ECC is Johnson Controls Inc. (Topeka) |
| 2. | The communications protocol will be BACnet. |
2.4.18 FAN COIL UNITS
A. Consist of VRF DX Split system heat pump units with wall mounted or horizontal concealed indoor units with remote outdoor condensing unit.
1. IT Data Closets
2.4.19 CONTROLS
| A. | The controls will be integrated with the current ECC system platform as part of this work. |
| B. | Building Automation System Platform: |
| 1. | ECC is Johnson Controls Inc. (Topeka) |
| 2. | The communications protocol will be BACnet. |
2.5 Plumbing:
2.5.1 All plumbing throughout the entire area of remodel will be removed and replaced. The new piping will be provided to all new plumbing fixtures throughout the entire area of remodel. The new mains to be extended from the existing mains located in the crawls space from the point of connection at the entrance of the mains into Wing C crawl space. New vent piping will be provided up through the roof.
Medical gases will be rerouted from the nearest branches to the new outlets and devices as needed for new floor plans and functions. Unused medical gases will be properly removed back to mains and capped.
| 2.5.2 | GENERAL |
| A. | Wings A and B of Building 6 and support areas of the Topeka VA are being renovated and will update all plumbing fixtures, replace domestic piping in areas of need, replace all medical oxygen piping, replace all sanitary piping except for the recently updated sanitary mains, replace all storm piping between roof drains and mains, provide an additional steam to domestic hot water heater, and provide new hot water heating to VAV terminal units through steam to hot water heat exchangers and circulation pumps to meet all standards and requirements. A conversion of Building 6 A and B wing into a Geriatric Community Living Center that fully meets current VA standards. |
| B. | New Plumbing Systems will include the following: |
| 1. | Sanitary waste minus the newer horizontal mains |
| 2. | Storm drainage minus horizontal mains and existing roof drains |
| 3. | Domestic cold water and recirculation system |
| 4. | Domestic hot water and recirculation system |
| 5. | Steam to domestic hot water heaters |
| 6. | Medical oxygen piping |
| 7. | Steam to hot water heat exchanger for air side heating and recirculation system |
| 8. | Humidifier Makeup water |
| 9. | Fire water service coordination |
| 10. | HVAC condensate drainage |
11. Hydronic system drainage
| C. | Selective Demolition | |
| 1. | B wing will be a full demolish with A Wing plumbing being removed everywhere except areas keeping certain structural and wall elements making in-wall piping removal inaccessible. Sanitary mains will remain that have been recently replaced with epoxy coated cast iron pipe. | |
| 2. | Roof and Storm drainage – demolished from the roof drain to the main in the pipe basement. | |
| 3. | Domestic Cold Water – demolished back to the service entrance and demarcation points as shown on the demolition drawings. | |
| 4. | Domestic hot water and recirculation system – will be demolished back to the existing steam-water heater. | |
| 5. | Medical gas system including (medical air, medical vacuum and oxygen) – will be | demolished back to the building service entrance for oxygen. All other existing medical gas systems that will not be used will be removed. |
| 6. | Natural Gas – no changes to the existing service are anticipated. | |
| 7. | Fire Water Service - not changes are anticipated. | |
| D. | Commissioning | |
| 1. | The system will be commissioned subject to the requirement of Section 01 91 00 General Commissioning Requirements. | |
| E. | Seismic Requirements | |
| 1. | Seismic controls, when required shall comply with VA Publication H-18-8 Seismic Design Requirements. | |
| 2. | Structures assigned to Seismic Design Category C, D, E, or F, permanent non-structural components and their attachments, and the structure-supported attachments of permanent equipment shall be designed to resist total design forces prescribed in ASCE-7. | |
| 3. | Seismic Control Specifications are Required- as this project location is in a medium low seismic activity area. | |
| F. | Freeze Protection | |
| 1. | Provide freeze protection methods as appropriate in climates with ASHRAE 99% Winter Design Condition is below 32°F. Project condition for location is 3.5°F. Therefore, freeze protection measures will be included where appropriate. |
G. Metering
| 1. | The domestic cold water and hot water will be metered for temperature and flow to provide monitoring components as required for compliance with VA Directive 1061. |
| H. | Tests Prior to design |
| 1. | Water analysis. |
| 2. | Hydrant test of the two nearest water hydrants. |
a) Static and residual pressure.
b) Water quality analysis (pH, bacterial count, residual chlorine, total hardness as CaCO3, total dissolved solids, alkalinity).
c) Recommended water treatment for systems included in the proposed design.
| I. | Equipment supports and pads. |
| 1. | Indoor equipment will be provided with 3-1/2” minimum thickness concrete housekeeping pads or equipment supports with seismic restraints and anchors as appropriate for the location. |
2.5.3 NATIONAL CODES AND STANDARDS
| A. | VA Plumbing Design Manual – 2014 |
| B. | Legionella Control Measures – Subject to compliance with “VHA Directive 1061- “Prevention of Healthcare-Associated Legionella Disease and Scald Injury from Potable Water Distribution Systems.” |
| C. | International Plumbing Code (IPC) |
| D. | National Fire Protection Association (NFPA) |
1. NFPA 54 National Fuel Gas Code
2. NFPA 99 Health Care Facilities Code E. American Society of Heating Refrigeration and Air Conditioning Engineers (ASHRAE)
1. 90.1-2010 Energy Standard for Buildings Except Low-Rise Residential Buildings
2. ASHRAE Handbook HVAC Applications
3. America Society of Plumbing Engineers (ASPE) Data Books B. Legionella
2.5.4. UTILITY SERVICES
A. General – The existing utility services (sanitary, domestic, storm, steam, and chilled water) entering wings A and B will be reused with no new utility connections expected.
2.5.5 NATURAL GAS SERVICE
A. No changes to existing service. No new gas piping is anticipated.
2.5.6 PLUMBING PIPING GENERAL REQUIREMENTS
| A. | Plumbing Valves |
| 1. | General Isolation: Provided at the base of each riser, branch to floor and plumbing fixture group to allow servicing without disrupting water flow to entire facility. |
a) Ball valves, full port, extended stem, with drain fittings; material type consistent with piping material.
| 2. | Thermostatic Mixing Valves: Local mixing valves will be provided on all lavatory and sink faucets. A master mixing valve is not anticipated to be used. | |
| 3. | Flow Control: Provided on Auto-flow control valves on recirculation lines. | |
| B. | Water Hammer Arresters – will be installed on all domestic water piping in accordance with PDI (Plumbing and Drainage Institute) Standards. | |
| C. | Equipment and Materials Identification | |
| 1. | All equipment and piping will be identified in accordance with section 220511 Common | Work Results for plumbing. |
| D. | Plumbing Insulation: | |
| 1. | All new piping will be insulated with insulation material and thickness as scheduled in Section 220711 Plumbing insulation. | |
| 2. | All existing piping to remain within the scope area where piping modifications will take place will be reinsulated. |
2.5.7 WATER SERVICE
| A. | Domestic Cold-Water Service Entrance |
| 1. | Water service size will be an existing 3-1/2” line entering basement mechanical room. |
| 2. | Pipe material will be Type K copper. |
| B. | Domestic Cold Water |
| 1. | Piping: Type L copper with soldered fittings. |
| 2. | Cold water piping will be extended to the plumbing fixture with cold water connections. |
| 3. | The cold water piping system will consist of a recirculation loop with recirculation pump and flow control valves. |
| 4. | Recirculated cold water piping will be looped within the wall as close as possible to the point of fixture connection before branching off to serve the fixture, maximizing recirculation of the cold- water system and minimizing fixture run-out distances. |
| 5. | New piping will be designed in compliance with VHA Directive 1061. |
| 6. | All domestic cold water piping will be insulated per VA specifications. |
| C. | Irrigation water |
| 1. | There will be no new exterior irrigation connections. |
| 2. | Existing exterior non-freeze wall hydrants will be retained and reused. New water supply piping will be connected at the pipe basement level. |
| D. | Domestic Hot Water |
| 1. | Piping: Type L copper with soldered fittings. |
| 2. | Hot water piping will be extended to the plumbing fixtures with hot water outlets. The branch connection take-off as close to the outlet termination to minimize the branch piping water volume. |
| 3. | Point-of-use thermostatic mixing valves will be provided at each fixture to reduce the hot water supply to 110-degree F. |
| 4. | New piping will be designed in compliance with VHA Directive 1061. |
| 5. | All Domestic hot water piping will be insulated per VA specifications. |
| 6. | The existing steam to hot water heater will be removed. Two (2) steam to hot water heaters will be added to provide N+1 operation. The new water heaters will be sized to match the previous water heater. |
| E. | HVAC Condensate |
| 1. | Piping: Type M copper with soldered fittings. |
| 2. | HVAC condensate will be either taken by gravity or condensate pump to the nearest floor drain or mop sink for disposal. |
a) HVAC condensate will discharge into the receptor with an air gap.
| F. | Water Heating |
| 1. | The domestic water heating system will consist of a steam to hot water heat exchanger and hot water recirculation pump. |
G. Fire Suppression Water Service Entrance – where new fire service entrance is required provide supply piping constructed of ductile iron, cement lined, pipe.
| H. | Back Flow Prevention |
| 1. | Backflow preventers and/or vacuum breakers will be provided at all interconnections between the domestic water system and points of possible contamination, including mechanical make-up water. |
| 2. | Domestic Water – backflow prevention will be provided at the domestic water entrance in compliance with the IPC and use a reduced pressure zone (RPZ) type backflow preventer. |
| 3. | Irrigation water – a double check valve (DCV) backflow preventer will be provided at the point of connection between the irrigation water and the domestic water systems. |
| 4. | Fire Suppression Water – will be provided with a double check valve (DCV) backflow preventer type backflow preventer. See Division 21 for related requirements. |
I. Legionella Control – Directive 1061
| 1. | Water monitoring station – Service Entry |
| a) | A water monitoring station will be provided at the building domestic water entry. |
| b) | The water monitoring station will record incoming water temperature, pH level, dissolved solids and oxidant residual per Directive 1061. |
| 2. | Water monitoring system – Building Level |
| a) | Per Directive 1061, domestic hot and cold Water temperature will be monitored at the following points in the distribution system: |
(1) At water heater entry and discharge.
(2) At each hot water recirculation loop.
(3) At the hot water recirculation pump.
(4) At each cold-water recirculation loop.
(5) At the cold-water recirculation pump.
b) Per Directive 1061, the potable water distribution temperature limits are as follows:
(1) Cold water: Maximum Temperature of 67°F.
(2) Hot water: Minimum temperature of 124°F.
c) Per Directive 1061 the monitoring system will record data every 30 minutes during normal operation and continuously during alarm conditions.
(1) Temperatures outside of the limits noted above will generate an alarm condition in the hospital BAS system.
(2) The requirement for continuous monitoring during alarm conditions is being interpreted as monitoring at an interval of once every 60 seconds during the alarm period.
| 3. | Recirculation |
| a) | Both domestic hot and cold-water systems will be recirculated to per VA design standards. |
| 4. | Water Temperature Maintenance |
| a) | The hot water loop temperature will be controlled by the water heater. |
| b) | The cold-water loop will be temperature controlled by an NSF rated heat exchanger served with chilled water from the central plant’s chilled water system. |
| 5. | Thermal Eradication |
| a) | The water heater will be selected for ability to provide 160°F hot water. |
| 6. | Scald Protection |
| a) | All lavatories, hand sinks, countertop sinks, and emergency fixtures will be provided with thermostatic mixing devices to protect against scald injury. |
2.5.8 MEDICAL GASES
A. Medical Oxygen
| 1. | The existing medical oxygen piping and associated accessories will be removed back to the mechanical room. |
| 2. | The new medical oxygen piping will connect to the existing medical oxygen line from Building 9 located in the Building 6 mechanical room. A new zone valve box and area alarm panel will be provided with the new system. |
| 3. | The medical oxygen system will provide oxygen to the patient headwall system. No ventilators will be served by this system. |
| B. | Medical Air |
| 1. | The existing medical air compressor and associated piping will be removed. |
| C. | Medical Vacuum |
1. The existing medical vacuum pump and associated piping will be removed.
2.5.9 SANITARY DRAINAGE SYSTEM
| A. | A new gravity drained sanitary system will be provided to the existing sanitary mains of Wings A and B. |
| B. | The material for all pipe and fittings shall be cast iron soil pipe and fittings and shall conform to the requirements of CISPI 301, ASTM A888, or ASTM A74. See Section 221300 Facility Sanitary and Vent piping for above and below slab applications. |
| C. | PVC piping is only allowed for special systems waste. See chemical resistant waste and vent piping in Section 226600 Chemical-Waste Systems for Laboratory and Healthcare Facilities. |
| D. | Vent stacks shall terminate above the roof a minimum of 10 feet from fresh air intakes. |
| E. | Trap Primers: Trap primers will be provided in lieu of trap seals. |
| F. | Cleanouts: Floor and wall cleanouts will be provided throughout the system. |
2.5.10 STORM DRAINAGE SYSTEM
A. The existing storm drainage system will be reused and piping will be replaced where necessary, especially in areas being demolished exposing pipe between the floor and roof areas.
2.5.11 PLUMBING FIXTURES
| A. | General | |
| 1. | See plumbing fixture schedule on drawings and plumbing fixture cut sheets in appendices. | |
| 2. | Plumbing fixtures will be located as indicated by VA Program guide PG-18-5 (Equipment | Guide List), PG-18-12 Design Guides and programming design requirements provided by user groups through the architectural program. |
| B. | Public Toilet Rooms | |
| 1. | Public Water Closet – floor mounted, bottom outlet water closets rated for bariatric use with hard-wired handsfree flush valves. | |
| 2. | Public Lavatory – Wall hung, goose neck, hard-wired hands-free wrist-blade faucet. | |
| 3. | Electric Water Coolers – with ADA accessible dual high/low wall mounted cabinet style. | |
| C. | Housekeeping Assistant Closet (HAC) | |
| 1. | Mop Sink- Corner terracotta mop sink with rectangular drop front, faucet with double lever handle and vacuum breaker. | |
| D. | Staff Lounge / Break Rooms | |
| 1. | Double compartment sink with no garbage disposer with single lever kitchen faucet | |
| 2. | Kitchen / Food Prep (nourishment area) | |
| 3. | Kitchenette/pantry sinks | |
| 4. | Water connection for ice maker with water filtration | |
| E. | Electric Water Coolers (Drinking Fountains) | |
| 1. | Where provided – Drinking fountains will be wall hung ADA compliant, single user, wall hung, push button operated and stainless-steel construction with integral chiller units. | |
| F. | Wall Hydrants (Non-Freeze) | |
| 1. | Non-Freeze Wall Hydrant – The existing non-freeze wall hydrants will be reused. No additional non-freeze wall hydrants will be added. | |
| G. | Non-Freeze Roof Hydrant – Roof hydrant(s) will be located on the roof within 30-feet of equipment forcleaning of rooftop equipment. | |
| H. | Hose Bibbs – will be provided in mechanical/plumbing equipment rooms and shall include integral vacuum breakers. |
2.5.12 INTERCEPTORS
| A. | Grease – not applicable. |
| B. | Oil/Water/Sand – not applicable. |
| C. | Acid Dilution – not applicable. |
2.5.13 PLUMBING PUMPS
| A. | Plumbing Circulation Pump – the hot and cold water systems will be provided with a recirculation pump back to the hot water generator and cold-water chiller. |
| B. | Sewage Ejector Sump Pump – may be required for condensate and floor drains in the basement level. An allowance will be made for a sump pump until it can be determined that the effluent can go by gravity to the sanitary sewer. |
2.5.14 WATER TREATMENT
A. Water Softener
2.5.15 INTERDISCIPLINARY COORDINATION
| A. | Building plumbing fixture count |
| B. | Plumbing chase wall inside dimension and construction type for adequate clearances |
| C. | Plumbing fixture heights and clearances – ABAAS |
| D. | Access doors (water hammer arrestors, valves, and air vents) |
| E. | Fire-stopping for penetrations |
| F. | Floor drains, liquid waste and supply connections for mechanical and medical equipment |
| G. | Fire protection drains |
| H. | Electrical power requirement for plumbing equipment |
| I. | Interface with energy management and control systems |
Exceptions:
Contractor shall be responsible for meeting all fire, safety and VA standards as specified in Statement of Work, Drawings, and Specifications. All testing shall be provided to COR in digital and paper copies. All products shall be submitted on to the COR and examples displayed prior to installation. Materials shall be onsite prior to starting the portion of the work. All utility outages shall be coordinated well in advance with the COR and shall be reflected on the contractors construction schedule.