S06_SF30 Continuation Page IFB Sol 36C25226B0027 A-0004 CON 556-23-104_07172026.pdf

PDF 207 KB Posted

Attached to
Y1DZ--556-23-104 CON: Chilled Water Piping from Bldg. 188 to Bldg. 3
Solicitation number
36C25226B0027
Issued by

About this file

This is an SF30 Amendment of Solicitation (Amendment 0004) for IFB Solicitation No. 36C25226B0027, a construction project for chilled water piping infrastructure at Captain James A. Lovell Federal Health Care Center in North Chicago, Illinois. The primary purpose of this amendment is to change the bid opening date to July 23, 2026, and establish virtual bid submission and opening procedures.

Bids must be submitted via email to the Contract Specialist (hudell.ballen@va.gov) and Contracting Officer (ryan.mcmillin@va.gov) no later than 9:00 AM CDT on Thursday, July 23, 2026. The virtual public bid opening will be conducted at 10:00 AM CDT on the same date via Microsoft Teams, with meeting access available 15 minutes prior. Hard copy submissions are not required. Bidders are strongly encouraged to submit bids at least one hour before the opening deadline to avoid transmission issues. The amendment also requires bidders to complete and submit the VAAR Clause 852.219-75 certification regarding limitations on subcontracting as an attachment; failure to include this required certification will render bids non-responsive and ineligible for evaluation and award. The successful low bidder must provide their original bid bond within five days after notification by the Contracting Officer. A third set of RFI responses has been published in conjunction with this amendment.

View the file

Other files

File Type Posted
36C25226B0027 0005.docx DOCX document
S06_SF30 Continuation Page IFB Sol 36C25226B0027 A-0005 CON 556-23-104_07222026.pdf PDF
S05_Ver4 RFI Pre-Bid IFB Sol 36C25226B0027 A-0005 CON 556-23-104 _07222026.xlsx XLSX spreadsheet
S05_Ver3 RFI Pre-Bid IFB Sol 36C25226B0027 A-0004 CON 556-23-104 _07172026.xlsx XLSX spreadsheet
36C25226B0027 0004.docx DOCX document
S06_Tramway Report Narrative RF1 No. 22 IFB Sol 36C25226B0027 A-0003 CON 556-23-104_12072011.pdf PDF
36C25226B0027 0003.docx DOCX document
S06_Post-CD Addendum Changed Sheets-SPECS IFB Sol 36C25226B0027 A-0003 CON 556-23-104_06302026.pdf PDF
S06_SF30 Continuation Page IFB Sol 36C25226B0027 A-0003 CON 556-23-104_07092026.pdf PDF
S06_SAM Wage Rates IL IFB Sol 36C25226B0027 A-0003 CON 556-23-104_current as of 07012026.pdf PDF
S06_Bldg. 3 Report Narrative RF1 No. 22 IFB Sol 36C25226B0027 A-0003 CON 556-23-104_12142011.pdf PDF
S05_Ver2 RFI Pre-Bid IFB Sol 36C25226B0027 A-0003 CON 556-23-104 _07092026.xlsx XLSX spreadsheet
S06_Bldg. 188 Report Narrative RF1 No. 22 IFB Sol 36C25226B0027 A-0003 CON 556-23-104_12092011.pdf PDF
S05_Ver1 RFI Pre-Bid IFB Sol 36C25226B0027 A-0002 CON 556-23-104 _06232026.xlsx XLSX spreadsheet
S06_SF30 Continuation Page IFB Sol 36C25226B0027 A-0002 CON 556-23-104_06232026.pdf PDF
36C25226B0027 0002.docx DOCX document
S04_Site Visit Sign-In-Sheet IFB Sol 36C25226B0027 A-0002 CON 556-23-104_06162026.pdf PDF
36C25226B0027 0001.docx DOCX document
S06_SF30 Continuation Page IFB Sol Amendment 0001 36C25226B0027 CON 556-23-104_06022026.pdf PDF
36C25226B0027_2.docx DOCX document
S02_Att3 CD Specifications 556-23-104 IFB Sol 36C25226B0027_07262024.pdf PDF
S02_Att1 852.219-75 VA Notice of Limitations on Subcontracting-Certificate DEVIATION_REQUIRED.pdf PDF
S02_Att2 CD Drawings 556-23-104 IFB Sol 36C25226B0027_07262024.pdf PDF
S02_Att4 SAM Wage Rates IL 556-23-104 IFB Sol 36C25226B0027 current as of 04162026.pdf PDF
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SF30 Block 14 Continuation Page

Amendment of Solicitation Amendment 0004 IFB Solicitation No. 36C25226B0027

Project No. 556-23-104: Chill Water Piping from Bldg. 188 to Bldgs. 1, 3 and 48 at Captain James A. Lovell FHCC, North Chicago, IL

The Purpose of this amendment 0004 is to publish the following in reference to IFB Solicitation request for bids 36C25226B0027:

1. THE BID OPENING DATE IS CHANGED TO: JULY 23, 2026 (SEE ADDITIONAL

INFORMATION BELOW IN RED)

VIRTUAL BID OPENING INFORMATION:

a. There will be no in-person public bid opening process. Bid opening will be conducted as a public virtual activity.

b. The virtual bid opening will be available to the public via Microsoft Teams at the following link and/or phone number.

MICROSOFT TEAMS MEETING:

Join: https://teams.microsoft.com/meet/224138103086373?p=LEYMPxLGfFOPZOfUdG

i. Meeting can be accessed 15 min prior to virtual bid opening

ii. Meeting ID: 224 138 103 086 373

iii. Passcode: Hf2w78Sk

iv. Dial-in by phone: +1 872-701-0185; Phone conference ID: 838 196 200#

c. IAW FAR 52.214-5 Submission of Bids and FAR 14.202-8 Electronic Bids;

Bids shall be provided via email to the Contract Specialist (CS) and Contracting Officer (CO) as follows, hudell.ballen@va.gov and ryan.mcmillin@va.gov.

BIDS DUE: Vendor bids are due via email to the CS and CO as noted above NO LATER THAN 9:00 AM (CDT) on Thursday, July 23, 2026.

The virtual public bid opening will be held at 10:00 AM (CDT) on Thursday, July 23, 2026, at the link and/or the phone number provided above.

A hard copy submission is not required. Any bids received after the date and https://teams.microsoft.com/meet/224138103086373?p=LEYMPxLGfFOPZOfUdG mailto:hudell.ballen@va.gov mailto:ryan.mcmillin@va.gov time specified for receipt of bids will be processed in accordance with FAR 52.214-7 Late Submissions, Modifications, and Withdrawals of Bids (Nov 1999).

It is highly recommended that Bidders submit their bid at least one hour prior to bid opening to avoid any transmission issues.

Ensure your complete bid including bid bond are provided in your submission.

The successful low bidder is required to furnish their original bid bond within five (5) days after notification by the Contracting Officer.

2. PUBLISH 3RD SET OF RFI RESPONSES:

a. See attached document: S05_Ver3 RFI Pre-Bid IFB Sol 36C25226B0027

A-0004 CON 556-23-104 _07172026.

3. COMPLETE AND RETURN CERTIFICATION OF VAAR CLAUSE 852.219-75:

a. Bidders are REQUIRED to complete certification for VAAR 852.219-75 included as an attachment (S02_Att1 852.219-75 VA Notice of Limitations on Subcontracting-Certificate DEVIATION_REQUIRED as stated in the original solicitation that posted to SAM.gov - Contract Opportunities on May 8, 2026). Failure to complete and submit with bid, will render bid submission non-responsive and not eligible for evaluation/award.

***NOTHING ELSE FOLLOWS***

mailto:kristi.kluck3@va.gov

MICROSOFT TEAMS MEETING:

File details come from the government source that posted it. Updated .