S06-HVAC FILES.pdf
PDF 38 MB Posted
- Solicitation number
- 36C25225Q0188
About this file
This file is a Test, Adjust, and Balance (TAB) report from January 2025 documenting air flow measurements and system performance verification at Jesse Brown VA Medical Center in Chicago. The comprehensive report covers multiple areas including animal research labs, cardio-cath labs, endoscopy, isolation rooms, morgue/autopsy, surgical suites, and sterile processing services (SPS).
The report identifies several deficiencies and conditions requiring attention, including three spaces that failed negative pressure requirements (two isolation rooms in the ER and a secondary room in Dialysis on the 4th Floor Bed Tower), which were subsequently repaired. Other issues noted include manually overridden discharge air flows, rooms under construction preventing testing, equipment placement affecting temperature sensors, and dirty exhaust diffusers potentially restricting flow. The report includes detailed measurements of supply/return/exhaust air flows, room pressures, air changes per hour (ACH), and temperature/humidity levels across multiple hospital departments. All measurements were conducted according to National Environmental Balancing Bureau (NEBB) standards and procedures, with calibrated testing equipment documented in the report.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| P09-UPDATED SOW-PRICE SCHEDULE.docx | DOCX document | |
| P09-UPDATED SOW-PRICE SCHEDULE.docx | DOCX document | |
| S05-VENDOR QUESTIONS WITH RESPONSES.docx | DOCX document | |
| 36C25225Q0188 0001.docx | DOCX document | |
| 36C25225Q0188.docx | DOCX document | |
| P07 - Cook County WD 2015-5017 Rev-28 dated 12.23.2024.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
60612
TEST, ADJUST, AND BALANCE REPORT
JESSE BROWN VA
January 2025
Quarterly TAB Verification
VAMC Chicago, IL
820 S Damen Ave.
Corporate Office
1101 1st SW ∙ Ruskin, FL 33570 ∙ (813)641-2730
January 29, 2025
TAB REPORT SUMMARY
Addendum:
There were three spaces that failed their negative pressure. The two isolation rooms in the ER and the secondary room in Dialysis, 4th Floor Bed Tower. These rooms were checked and fixed by the facility, January 28th and 29th, after the report was completed.
The following pages are the repaired values.
What follows the addendum is the report as of January 27, 2025.
Addendum Page 1 of 4
BOX TEST
REPORT
PROJECT
LOCATION
Number Actual
Type 131 87%
Size Return Air CFM (L/S) 360 122%
DDC CF 26.1
DDC Address 64.3
ROOM FT
18.62 Exhaust
-0.011
Area
Served No Type AK* Velocity Flow Flow
1470Q SA 1 4-way 1 150 131 87%
1470Q EA 1 4-way 1 295 360 122%
REMARKS:
TEST DATE
Room Press. negative To corridor inwg. NA
24"X24"
ER
NA
6"
2.19
24"X24"
Design
VAV Outlet Data
VAV TERMINAL
Jessie Brown Quarterly TAB SYSTEM/UNIT
(Pressure Independent)
ER ROOM 14
Primary Maximum Airflow CFM (L/S)
Size
RH %
SIDES, BRADLEY1/29/2025
ACH1160 NA
FinalOutlet
Data value are "As-Is".
Setra Room Pressure Monitor: -0.009 Exhaust diffusers are very dirty may be causing flow restriction.
TECHNICIAN
Room Air Temp ⁰F
Design
Velocity
VAV Terminal Data
TU-1
CONSTANT VOLUME
NA
Addendum Page 2 of 4
PROJECT
LOCATION
Number Actual
Type 133 94%
Size Exhaust Air CFM (L/S) 424 91%
DDC CF 22.8
DDC Address 74.0
ROOM FT
13.59 Exhaust
-0.014
Area
Served No Type AK* Velocity Flow Flow
1470R SA 1 4-way 1 141 133 94%
1470R EA 1 4-way 1 468 424 91%
REMARKS:
TEST DATE
Data values are "As-Is".
Setra Room Pressure Monitor: -0.014 Exhaust diffusers are very dirty may be causing flow restriction.
TECHNICIAN
Room Air Temp ⁰F
Design
Velocity
VAV Terminal Data
TU-30
CONSTANT VOLUME
NA
Size
RH %
SIDES; BRADLEY1/29/2025
ACH1872 NA
FinalOutlet
VAV Outlet Data
VAV TERMINAL
Jessie Brown Quarterly TAB SYSTEM/UNIT
(Pressure Independent)
ER ROOM 15
Primary Maximum Airflow CFM (L/S)
ER
NA
7"
3.6
24"X24"
Design
Room Press. negative To corridor inwg. NA
24"X24"
Addendum Page 3 of 4
PROJECT
LOCATION
Number Actual
Type 279 64%
Size Exhaust Air CFM (L/S) 283 60%
DDC CF 12.2
DDC 77.5
ROOM FT
8.69 Exhaust
-0.010
Area
Served No Type AK* Velocity Flow Flow
4642 1 4-WAY 1 215 100 47%
4642 2 4-WAY 1 220 179 81%
4642 Rm Exh 3 4-WAY 1 475 250 53%
4642 RR Exh 4 4-WAY 1 100 33 33%
REMARKS:
TEST DATE
Velocity
VAV Terminal Data
4-#
CONSTANT VOLUME
NA
Size
NA
N/A
FinalOutlet
VAV Outlet Data
TECHNICIAN
Room Air Temp ⁰FN/A
24"x24"
24"x24"
Design
VAV TERMINAL
Jessie Brown Quarterly TAB SYSTEM/UNIT
(Pressure Independent)
4th Floor East
Primary Maximum Airflow CFM (L/S)
AHU-6
Design
NA
NA
Room Press. Neg to Ante-Room inwg. NA
RH %
ACH1953
24"x24"
24"x24"
Data values are "AS-IS". Pressure ratios are correct. No access to control system at this time. VAV Terminal unit number unavailable at this time.
Sectra Room Pressure Monitor: 4642 to 4641 ΔP -0.006
SIDES, BRADLEY1/29/2025
Room being used for Dialysis
Terminal Unit Coil
Check Report 3f-4-9B_4642 1-29-25
Addendum Page 4 of 4
DATE:
PROJECT:
ADDRESS:
Chicago, IL. 60612
ARCHITECT:
ENGINEER:
HVAC
CONTRACTOR
NEBB
TAB FIRM:
ADDRESS: P.O. BOX 1672
VAN BUREN, AR 72957
1/17/2025
CERTIFIED TEST, ADJUST, AND BALANCE REPORT
STAMP
Jesse Brown Quarterly TAB
820 S Damen Ave.
NA
NA
NA
TL SERVICES, INC.
TAB 1-91
NATIONAL ENVIRONMENTAL BALANCING BUREAU Page 1 of 119
Table of Contents Date: 1/17/2025
PROJECT:
2-3
8-16
18 - 20
21 - 33
Pressure Footprint Drawing 34
Summary 36
Under Construction - No Test Data
Isolation Rooms 37
Summary 38
Test Data 39 - 52
Morgue/Autopsy 53
Summary 54
Test Data 55 - 60
Autopsy Air Flow Footprint Drawing 61
Morgue Air Flow Footprint Drawing 62
Viewing Room Air Flow Footprint Drawing 63
Endoscopy
Test Data
Cardio-Cath
Summary
Test Data
Test Documentation
VMU Animal Research
Summary
Jesse Brown VAMC Quarterly TAB Report
Certification
Table of Contents
Cover Page
Abbreviations
Table of Contents
PROJECT:
66 - 82
85 - 92
Air Flow / Pressure Footprint Drawing 93
Exhaust Side-Vent Face Traverse 94 - 95
SPS-SPD Clean Storage/Soiled Utility Closets 96
VA Required data form 98 - 100
101 - 106
Instrument Calibration Report 107
Instrument Calibration Documentation 108 - 119
Jesse Brown VAMC Quarterly TAB Report
Summary
Test Data
Summary
Test Data
Surgical OR Suites
Summary
Test Data
SPS/SPD
CERTIFICATION
ADDRESS:
THE DATA PRESENTED IN THIS REPORT IS AN EXACT RECORD OF SYSTEM
PERFORMANCE AND WAS OBTAINED IN ACCORDANCE WITH NEBB STANDARD
PROCEDURES. ANY VARIANCES FROM DESIGN QUANTITIES WHICH EXCEED NEBB
TOLLERENCES ARE NOTED THROUGHOUT THIS REPORT.
THE AIR DISTRIBUTION SYSTEMS HAVE BEEN TESTED & BALANCED AND FINAL
ADJUSTMENTS HAVE BEEN MADE IN ACCORDANCE WITH NEBB "PROCEDURAL
STANDARDS FOR TESTING-ADJUSTING-BALANCE OF ENVIRONMENTAL SYSTEMS"
AND THE PROJECT SPECIFICATIONS.
NEBB CONTRACTOR:
REG. NO. 2932 CERTIFIED BY: DATE:
THE HYDRONIC DISTRIBUTION SYSTEMS HAVE BEEN TESTED & BALANCED AND FINAL
ADJUSTMENTS HAVE BEEN MADE IN ACCORDANCE WITH NEBB "PROCEDURAL
STANDARDS FOR TESTING-ADJUSTING-BALANCE OF ENVIRONMENTAL SYSTEMS"
AND THE PROJECT SPECIFICATIONS.
NEBB CONTRACTOR:
REG. NO. 2932 CERTIFIED BY: DATE:
SUBMITTED AND CERTIFIED BY:
NEBB CONTRACTOR:
TAB SUPERVISOR:
REG. NO. 2932 DATE:
TL SERVICES, INC.
JOHN SIDES JR. 1/31/2025
Jesse Brown Quarterly TAB Verification
Chicago, IL. 60612
820 S Damen Ave.
STAMP
TL SERVICES, INC.
1/31/2025
JOHN SIDES JR.
TL SERVICES, INC.
JOHN SIDES JR. 1/31/2025
TAB 2-83
National Environmental Balancing Bureau
Report Not Valid Unless Stamped with Nebb Certification Seal
Table of Abbreviations
PROJECT:
L/S Liters Per Second kW Kilowatt
GPM Gallons Per Minute W Watt
Min Minimum MBH Thousand British Thermal
Min Alt for Minute Units Per Hour
Max Maximum BTU British Thermal Units
CFM Cubic Feet Per Minute CAL Calibration
PSI Pounds Per Square Inch
PSF Pounds Per Square Foot
Pa Pascales
In Inch
Ft Foot
M Meter
VFD/VSD Variable Frequency (Speed) Drive
No. Number
N/A / NA Not Applicible
RPM Revolutions Per Minute
S.P. Static Pressure
H.P. Horse Power
A Amps
V Volts
Damp / Dmp Damper
OSA Outside Air
RA Return Air
RTN Return
SA Supply Air
MA Mixed Air
VAV Variable Air Volume
CORR Correction (Factor)
Zn Zone
S.F. Service Factor
Ent Entering
Lvg Leaving
Temp Temperature
Press Pressure
Dischg Discharge
Cond Condenser
ChW Chilled Water
Htr Heater
L.P. Low Pressure
H.P. High Pressure
Quarterly TAB Verification
ADDRESS:
Chicago, IL. 60612
ARCHITECT:
ENGINEER:
HVAC
CONTRACTOR
NEBB
TAB FIRM:
ADDRESS: 1101 1st SW
Ruskin, FL 33570
1/8/2025
CERTIFIED TEST, ADJUST, AND BALANCE REPORT
STAMP
Jesse Brown Animal Research Labs, Veterinary Medical Unit
7th Floor Building 11, Taylor
820 S Damen Ave.
NA
NA
NA
TL SERVICES, INC.
NATIONAL ENVIRONMENTAL BALANCING BUREAU Page 6 of 119
August 29, 2024
TAB REPORT SUMMARY
7th Floor Animal Labs, Taylor (Building 11)
General:
All data is in an “AS-IS” condition. The control system is JCI Metasys.
Room 7330 had been reset to a positive pressure room for research purposes. Per the request of the area management, this room is to be returned to negative pressure.
While the new cage wash and bottle wash systems are not installed completely, air flow measurements have been taken at the duct inlet:
Cage Wash – 6” duct – 3651 FPM, 718 CFM Bottle Wash – 3” duct – 672 FPM, 33 CFM
Deficiencies:
Some areas have changed purpose, and this is not afforded in the design parameters. Room use designations have been updated and will be listed in the report.
Jan-25 Room Total Total
Volume Supply Exhaust VA
Room # Room Use FT3 CFM CFM Supply Exhaust Required Notes
1 7300 ANIMAL ROOM 942 136 277 8.7 17.6 - 15
2 7301 STERIL PREP 2012 203 263 6.1 7.8 - 15
3 7302 ANIMAL ROOM 929 149 242 9.6 15.6 - 15
4 7305 ANIMAL ROOM 2468 245 460 6.0 11.2 - 15
5 7306 ANIMAL ROOM 865 137 207 9.5 14.4 - 15
6 7310 BEDDING 1930 388 121 12.1 3.8 + 15
7 7312 CLEAN CAGE 2084 248 246 7.1 7.1 + 15
8 7315 BREAKROOM 989 56 57 3.4 3.5 - 6
9 7323 RESTROOM (WOMEN) 1084 0 0 0.0 0.0 6
10 7325 SLOP CLOSET 192 0 0.0 0.0 6
11 7330 ANTE-ANIMAL ROOM 1696 187 161 6.6 5.7 + 6 See Notes
12 7330A ANIMAL ROOM 1029 151 277 8.8 16.2 - 15
13 7330B ANIMAL ROOM 1156 256 282 13.3 14.6 - 15
14 7330C ANIMAL ROOM 1134 170 303 9.0 16.0 - 15
15 7331 DIRTY CAGE STORAGE 640 43 106 4.0 3.8 - 15 see notes
16 7332 CLEAN CAGE 2241 257 188 6.9 5.0 + 15 see notes
17 7332 DIRTY CAGE 2242 309 424 8.3 11.3 - 15
18 7333 ANIMAL ROOM 641 206 138 19.3 12.9 + 6
19 7335 ANIMAL ROOM 647 20 79 1.9 7.3 - 15
20 7337 ANIMAL ROOM 648 69 109 6.4 10.1 - 15
21 7338 LAB 1253 214 618 10.2 29.6 - 15
Lab Hood provides exhaust 117 ft/min
(defuser 33cfm)
22 7339
ANIMAL ROOM
(UNUSED)
648 197 170 18.2 15.7 + 15
23 7340 WASH ROOM 452 209 239 27.7 31.7 - 15
24 7342 ANIMAL ROOM 645 392 151 36.5 14.0 + 6
25 7343 FEED ROOM 615 115 159 11.2 15.5 - 15
26 7344 ANIMAL ROOM 2474 393 699 9.5 17.0 - 6
27 7350 OFFICE 1088 108 93 6.0 5.1 + 15
Air Changes / Hour (ACH)
Jesse Brown Animal Research ACH calculations with current conditions
28 7352 OFFICE 665 87 102 7.8 9.2 - 6
29 7353 LAUNDRY 750 263 21.0 0.0 + 6
30 7354 OFFICE 893 280 107 18.8 7.2 + 6
31 7356 OFFICE 925 231 141 15.0 9.1 + 6
32 7359 STORAGE 3841 632 1021 9.9 15.9 - 6
33 7368 RESTROOM (MEN) 1104 0 0 0.0 0.0 6
34 7369 PROCEDURE LAB 2346 505 580 12.9 14.8 - 15
35 7371
QUARANTINE (ANIMAL
PREP)
952 160 121 10.1 7.6 + 15
36 7372 WORK OFFICE 746 172 107 13.8 8.6 + 6
37 7373 OR 1631 408 819 15.0 30.1 - 15
38 7374 METABOLIC 833 74 200 5.3 14.4 - 15
39 7375 OPERATIONS 1089 304 173 16.7 9.5 + 15
40 7377 OR 1257 835 730 39.9 34.8 + 15
41 7378 LAB (HOOD) 1497 341 510 13.7 20.4 - 15 Has Lab Hood 102 ft/min
42 7380 NECROPSY 1100 262 495 14.3 27.0 - 15
Animal Research Area 52373 9412 11175 10.8 12.8 12.6 Average ACH for entire area.
Room 7330 was previously converted to a positive pressure room, the VA would like this room to be returned to negative pressure. Inside the cage cleaning room 6" exhaust cart wash 3651 FPM, 718 CFM. and 3" exhaust bottle wash 672 FPM, 33 CFM.
All spaces are currently supplied by a constant volume system. The rooms have hard ceilings with few access points. Also, some areas are not being used for the same applications and may need to have their requirements altered.
AIR OUTLET
TEST REPORT
(Flow Hood)
PROJECT SYSTEM Supply Page 1
AREA Animal Research
OUTLET MANUFACTURER TEST APPRATUS TSI Flow Hood
AREA DESIGN PRELIMINARY PERCENT OF
SERVED AIRFLOW CFM AIRFLOW CFM DESIGN
7300 Note 1 Note 1 7301 S1 Note 1 Note 1 7301 S2 Note 1 Note 1
7302 Note 1 Note 1 7305 S1 Note 1 Note 1 7305 S2 Note 1 Note 1
7306 Note 1 Note 1 7310 Note 1 Note 1 7312 Note 1 Note 1 7315 Note 1 Note 1 7323 Note 1 Note 1 7330 Note 1 Note 1
7330A Note 1 Note 1 7330B Note 1 Note 1 7330C Note 1 Note 1 7331 Note 1 Note 1
7332 S1 Note 2 Note 1 Note 1 7332 S2 Note 2 Note 1 Note 1 7332 S3 Note 2 Note 1 Note 1
7333 Note 1 Note 1 7335 Note 1 Note 1 7337 Note 1 Note 1
7338 S1 Note 1 Note 1 7338 S2 Note 1 Note 1
7339 Note 1 Note 1 7340 Note 1 Note 1
7342 S1 Note 1 Note 1 7342 S2 Note 1 Note 1
7343 Note 1 Note 1
REMARKS:
TEST DATE TECHNICIAN
Jessie Brown Quarterly TAB
FINAL
AIRFLOW CFM
1/6/2024
Note 1: No design airflow CFM data available at this time.
Note 2: 7332 is split into Clean and Dirty with the cartwash between. S1 is in the clean side. S2 and S3 are in the Dirty side.
STAMP
Bradley
(Flow Hood)
PROJECT SYSTEM Supply Page 2
AREA Animal Research
OUTLET MANUFACTURER TEST APPRATUS TSI Flow Hood
AREA DESIGN PRELIMINARY PERCENT OF
SERVED AIRFLOW CFM AIRFLOW CFM DESIGN
7344 S1 Note 1 Note 1 7344 S2 Note 1 Note 1
7350 Note 1 Note 1 7352 Note 1 Note 1 7353 Note 1 Note 1 7354 Note 1 Note 1 7356 Note 1 Note 1
E CORR 1 Note 1 Note 1 E CORR 2 Note 1 Note 1 N CORR 1 Note 1 Note 1 N CORR 2 Note 1 Note 1 N CORR 3 Note 1 Note 1 S CORR 1 Note 1 Note 1 S CORR 2 Note 1 Note 1 S CORR 3 Note 1 Note 1 S CORR 4 Note 1 Note 1 7359 S1 Note 1 Note 1 7359 S2 Note 1 Note 1
7368 Note 1 Note 1 7369 Note 1 Note 1 7371 Note 1 Note 1 7372 Note 1 Note 1 7374 Note 1 Note 1 7375 Note 1 Note 1
REMARKS:
TEST DATE TECHNICIAN BRADLEY1/6/2025
STAMP
Jessie Brown Quarterly TAB
AIRFLOW CFM
FINAL
Note 1: No design airflow CFM data available at this time.
(Flow Hood)
PROJECT SYSTEM Supply Page 3
AREA Animal Research
OUTLET MANUFACTURER TEST APPRATUS TSI Flow Hood
AREA DESIGN PRELIMINARY PERCENT OF
SERVED AIRFLOW CFM AIRFLOW CFM DESIGN
7373 S1 Note 2 Note 1 Note 1 7373 S2 Note 2 Note 1 Note 1 7373 S3 Note 2 Note 1 Note 1 7373 S4 Note 2 Note 1 Note 1 7373 S5 Note 2 Note 1 Note 1 7373 S6 Note 2 Note 1 Note 1 7373 S7 Note 2 Note 1 Note 1 7377 S1 Note 2 Note 1 Note 1 7377 S2 Note 2 Note 1 Note 1 7377 S3 Note 2 Note 1 Note 1 7377 S4 Note 2 Note 1 Note 1 7377 S5 Note 2 Note 1 Note 1 7377 S6 Note 2 Note 1 Note 1 7377 S7 Note 2 Note 1 Note 1 7377 S8 Note 2 Note 1 Note 1 7378 S1 Note 1 Note 1 7378 S2 Note 1 Note 1
7380 Note 1 Note 1
REMARKS:
TEST DATE TECHNICIAN
Note 2: 7373 and 7377 are Operating Room configuration with multiple diffusers.
BRADLEY1/6/2025
STAMP
AIRFLOW CFM
Note 1: No design airflow CFM data available at this time.
Jessie Brown Quarterly TAB
FINAL
(Flow Hood)
PROJECT SYSTEM Exhaust Page 1
AREA Animal Research
OUTLET MANUFACTURER TEST APPRATUS TSI Flow Hood
AREA DESIGN PRELIMINARY PERCENT OF
SERVED AIRFLOW CFM AIRFLOW CFM DESIGN
7300 Note 2 236 117% 7301 Note 2 503 52% 7302 Note 2 232 104% 7305 Note 2 617 75% 7306 Note 2 216 96% 7310 Note 2 483 25% 7312 Note 2 521 47% 7315 Note 2 99 58%
7323 E1 Note 2 108 0% 7323 E2 Note 2 108 0%
7325 Note 2 19 0% 7330 Note 2 170 95%
7330A Note 2 257 108% 7330B Note 2 289 98% 7330C Note 2 284 107% 7331 Note 2 560 19%
7332 Dirty Note 2 561 76% 7332 Clean Note 2 64 294%
7333 Note 2 162 85% 7335 Note 2 162 49% 7337 Note 2 162 67% 7338 Note 2 313 11% 7338 Note 1 Note 2 7339 Note 2 162 105% 7340 Note 2 113 212% 7342 Note 2 65 232% 7343 Note 2 138 115%
REMARKS:
TEST DATE TECHNICIAN
Jessie Brown Quarterly TAB
FINAL
AIRFLOW CFM
BRADLEY1/6/2025
STAMP
Note 1: 7338 has a hood. The hood had an exhaust readout, recorded here.
Note 2: The design Airflow CFM was calculated based on the Cubic Footage of the room and the required ACH.
(Flow Hood)
PROJECT SYSTEM Exhaust Page 2
AREA Animal Research
OUTLET MANUFACTURER TEST APPRATUS TSI Flow Hood
AREA DESIGN PRELIMINARY PERCENT OF
SERVED AIRFLOW CFM AIRFLOW CFM DESIGN
7344 Note 2 247 283% 7350 Note 2 272 34% 7352 Note 2 67 152% 7354 Note 2 89 120% 7356 Note 2 93 152% 7359 Note 2 384 266%
7368 E1 Note 2 60 0% 7368 E2 Note 2 50 0%
7369 Note 2 587 99% 7371 Note 2 238 51% 7372 Note 2 75 143%
7373 E1 Note 2 204 166% 7373 E2 Note 2 204 236%
7374 Note 2 360 56% 7375 Note 2 221 78%
7377 E1 Note 2 190 239% 7377 E2 Note 2 185 149%
7378 Note 2 Note3 374 136% 7380 E1 Note 2 137 88% 7380 E2 Note 2 138 271%
REMARKS:
TEST DATE TECHNICIAN BRADLEY
Note 2: The design Airflow CFM was calculated based on the Cubic Footage of the room and the required ACH.
Note 3: 7378 has a lab hood. The hood had an exhaust readout, recorded here. This is the only exhaust of the space.
1/6/2025 STAMP
Jessie Brown Quarterly TAB
FINAL
AIRFLOW CFM
AIR CHANGE
(Flow Hood)
PROJECT SYSTEM
CFM ACH VA ACH
136 9 15 203 6 15 149 10 15 245 6 15 137 10 15 388 12 15 248 7 15 56 3 6 0 0 6 0 0 6
187 7 6 151 9 15 256 13 15 170 9 15 43 4 15 257 7 15 309 8 15 206 19 6 20 2 15 69 6 15
214 10 15 197 18 15 209 28 15 392 36 6 115 11 15 393 10 6 108 6 6 87 8 6
REMARKS:
TEST DATE
Supply Exhaust
Exhaust Exhaust Exhaust Exhaust Exhaust Supply
Supply Supply
Exhaust Exhaust
Exhaust Exhaust
Exhaust
7352 665
Data values are "As-Is".
Exhaust Exhaust Exhaust Exhaust
Exhaust Supply
7343 615
7344 2474 7350 1088
7338 1253
7340 452 7342 645
7333 640 7335 647 7337 648
7330C 1134
7332 Clean 2241 7332 Dirty 2242
7331 640
7323 1084 7325 192 7330 1696
7310 1930 7312 2084 7315 989
Jessie Brown Quarterly TAB Animal Research
7302 929 7305 2468
7300 942
NOTE
Exhaust
BRADLEYTECHNICIAN1/6/2025 STAMP
ROOM CUBIC FT
7301 2012
7306 865
Exhaust Exhaust
Exhaust Exhaust Exhaust
Supply
7330A 1029 7330B
(Flow Hood)
PROJECT SYSTEM
CFM ACH VA ACH
263 21 6 280 19 6 231 15 6 632 10 6 0 0 6 0 0 6
505 13 15 160 10 15 172 14 6 408 15 15 74 5 15 304 17 15 835 40 15 341 14 15 262 14 15
REMARKS:
TEST DATE
Note 3: The supply/exhaust air flows fr 7369 have switched from last test. The space is slightly positive now.
Exhaust Supply
Exhaust
BRADLEYTECHNICIAN1/6/2024 STAMP
ROOM CUBIC FT
7354 893
7368 1104
Jessie Brown Quarterly TAB Animal Research
7356 925 7359 3841
7353 Note 1 750
NOTE
Supply
7369 Note 3 2346 7371 952 7372 746 7373 1631 7374 833 7375 1089
7378 Note 2 1497 7380 1100
Data values are "As-Is".
Note 1: This space is the laundry room. The exhaust for the room is the dryer vent, and only works when the dryer is running.
Exhaust Exhaust Supply
Exhaust
Supply Supply
Exhaust Exhaust
Exhaust Supply
73E2 192 Exhaust
Note 2: There is no exhaust in 7378 except for the Lab Hood. The hood will not draw enough air to alter the pressure profile to negative. This room would have to be re-engineered to add an exhaust diffuser and connect to the exhaust system.
ADDRESS:
Chicago, IL. 60612
ARCHITECT:
ENGINEER:
HVAC
CONTRACTOR
NEBB
TAB FIRM:
ADDRESS:
NA
NA
NA
TL SERVICES, INC.
1101 1st SW
Ruskin, FL 33570
1/7/2025
CERTIFIED TEST, ADJUST, AND BALANCE REPORT
STAMP
Jesse Brown Cardio-Cath Labs
5th Floor Damen Cardio-Cath
820 S Damen Ave.
NATIONAL ENVIRONMENTAL BALANCING BUREAU Page 17 of 119
January 7, 2025
TAB REPORT SUMMARY
5th Floor Cardio-Cath Labs, Damen
General:
The Cath Labs were done per the Quarterly TAB requirements.
Deficiencies:
The discharge air flows are manually set by VA Engineering, and not at the design specification. These values are left as is for the pressure relationships.
Return air flows are set to produce the proper pressure relationships, not at design.
The terminal VAV unit for the service corridor, C5506 VAV-5-4, has an issue. There is a blanket warmer next to the thermostat. This is artificially raising the temperature of the space above the actual space temperature. In the picture, the blanket warmer has been pushed directly up against the space sensor. The warmer is holding the blankets in the top chamber next to the space sensor at 136˚F. The space temperature at the space sensor is at 67.0˚F while the area is at 64.1˚F. The warmer should be moved to a different location. See pictures, next page. This issue is still there.
Jesse Brown VA Hospital TL Services, Inc.
P a g e | 2
Jesse Brown VA Hospital TL Services, Inc.
P a g e | 3
(Flow Hood)
PROJECT SYSTEM
CFM ACH
482 12.1 212 29.4 156 14.2 126 4.8 1945 20.6 615 25.2 2476 26.2
REMARKS:
TEST DATE BRADLEYTECHNICIAN1/7/2025 STAMP
ROOM CUBIC FT
5546A 432
5551 5670
Jessie Brown RTx Cardio-Cath 5th floor
5548 657 5550 1564
5546 2390
NOTE
Supply
5554 1462 5555 5670
Supply Exhaust Supply Supply Supply Supply
PROJECT
LOCATION
Number Actual Type 2476 144% Size Return Air CFM (L/S) 1285 71%
DDC CF 12.6
DDC Address 66
ROOM FT3 51.76
0.012
Area Served No Type AK* Velocity Flow Flow 5555 SA 1 Traverse 1 1725 2476 144%
5555 RA 1 1 Sidewall 1 900 671 75% 5555 RA 2 1 Sidewall 1 900 614 68%
REMARKS:
TEST DATE TECHNICIAN
Room Air Temp ⁰F
Design
Velocity
VAV Terminal Data EP Lab
VAV-5-1
CONSTANT VOLUME
NA
Size
RH %
BRADLEY1/7/2025
ACH2870 NA
FinalOutlet VAV Outlet Data
VAV TERMINAL
Jessie Brown Quarterly TAB SYSTEM/UNIT
(Pressure Independent)
Cath Lab 5th Floor
Primary Maximum Airflow CFM (L/S)
AHU-5
NA
15"x24"
14" 1.87
12"x30"
Design
15"x24"
Room Press. Postivie to corridor inwg. NA
Setpoint is overridden by VA Engineering. Setra Room Pressure Monitor: 0.005 "WC
RECTANGULAR DUCT
TRAVERSE REPORT
PROJECT SYSTEM/UNIT
LOCATION/ZONE SERVICE
VAV-5-1 Room 5555
S.P. AIR TEMP F ( C ) SCFM (sl/s) SCFM (sl/s) SIZE 30''X12'' AREA SQFT 2.5 FPM (ms) CFM FPM (ms) CFM
Distance Position 1 2 3 4 5 6 7 8 9 10 11 12 13 From Bottom
2.5 1 1344 1259 665 333
7.5 2 1296 1233 635 403
12.5 3 1287 1246 1015 298
17.5 4 1393 1298 1025 336
22.5 5 1383 1356 1138 466
27.5 6 1327 1303 1079 656
1.5 4.5 7.5 10.5
8030 7695 5557 2492 0 0 0 0 0 0 0 0 0
REMARKS:
1) Total CFM = Avg Velocity
TECHNICIAN: STAMP
Jesse Brown Quarterly TAB AHU-5
Cath Lab 5th Floor EP LAB
ACTUALDESIGN
23,774.00
Distance From # of Readings
1725 2,476
Sum of All Readings
Duct Edge
TEST DATE: 1/7/2025 BRADLEY
FPM
SUB-TOTALS
2,476 Due to proximity of the air flow from an elbow, more readings were taken to better qualify the air flow.
990.58
VAV-5-1_Supply_T&B_TRAVERSE 1-25 Page 23 of 119
PROJECT
LOCATION
Number Actual Type 1285 71% Size
DDC CF NA
DDC Address NA
ROOM FT3 NA
Area Served No Type AK* Velocity Flow Flow 5555 RA1 1 Sidewall 1 900 671 75% 5555 RA1 2 Sidewall 1 900 614 68%
REMARKS:
TEST DATE
Setpoint set by VA Engineering.
NA
12" 3.18
15"x24" 15"x24"
Design
VAV TERMINAL
Jessie Brown Quarterly TAB SYSTEM/UNIT
(Pressure Independent)
Cath Lab 5th Floor
Primary Maximum Airflow CFM (L/S)
AHU-5
RH %
BRADLEY1/7/2025
ACH2870 NA
FinalOutlet VAV Outlet Data
TECHNICIAN
Room Air Temp ⁰F
Design
Velocity
VAV Terminal Data EP Lab
VAV-5-1R
CONSTANT VOLUME
NA
Size
PROJECT
LOCATION
Number Actual Type 1945 113% Size Return Air CFM (L/S) 982 55%
DDC CF 10.6
DDC Address 70.1
ROOM FT3 35.58
0.024
Area Served No Type AK* Velocity Flow Flow 5551 SA 1 Traverse 1 1725 1945 113%
5551 RA1 1 Sidewall 1 900 393 44% 5551 RA2 1 Sidewall 1 900 589 65%
REMARKS:
TEST DATE
Setpoint is overridden by VA Engineering. Setra Room Pressure Monitor: 0.022 "WC
Room Press. Positive To corridor inwg. NA
15"x24"
NA
15"x24"
14" 2.00
12"x30"
Design
VAV TERMINAL
Jessie Brown Quarterly TAB SYSTEM/UNIT
(Pressure Independent)
Cath Lab 5th Floor
Primary Maximum Airflow CFM (L/S)
AHU-5
RH %
BRADLEY1/7/2025
ACH3280 NA
FinalOutlet VAV Outlet Data
TECHNICIAN
Room Air Temp ⁰F
Design
Velocity
VAV Terminal Data CATH Lab
VAV-5-2
CONSTANT VOLUME
NA
PROJECT SYSTEM/UNIT
LOCATION/ZONE SERVICE
VAV-5-2 Room 5551
S.P. AIR TEMP F ( C ) SCFM (sl/s) SCFM (sl/s) SIZE 30''X12'' AREA SQFT 2.5 FPM (ms) CFM FPM (ms) CFM
Distance Position 1 2 3 4 5 6 7 8 9 10 11 12 13 From Bottom
2.5 1 984 930 895 390
7.5 2 1008 916 831 360
12.5 3 993 915 801 323
17.5 4 992 964 814 234
22.5 5 1013 951 663 347
27.5 6 1005 961 852 533
1.5 4.5 7.5 10.5
5995 5637 4856 2187 0 0 0 0 0 0 0 0 0
REMARKS:
1) Total CFM = Avg Velocity
TECHNICIAN: STAMP
Jesse Brown Quarterly TAB AHU-5
Cath Lab 5th Floor CATH LAB
ACTUALDESIGN
18,675.00
Distance From # of Readings
1725 1,945
Sum of All Readings
Duct Edge
TEST DATE: 1/7/2025 BRADLEY
FPM
SUB-TOTALS
1,945 Due to proximity of the air flow from an elbow, more readings were taken to better qualify the air flow.
778.13
VAV-5-2_Supply_T&B_TRAVERSE 1-25 Page 26 of 119
PROJECT
LOCATION
Number Actual Type 982 55% Size
DDC CF NA
DDC Address NA
ROOM FT3 NA
Area Served No Type AK* Velocity Flow Flow 5551 RA 1 1 Sidewall 1 900 393 44% 5551 RA 2 2 Sidewall 1 900 589 65%
REMARKS:
TEST DATE TECHNICIAN
Room Air Temp ⁰F
Design
Velocity
VAV Terminal Data CATH Lab
VAV-5-2R
CONSTANT VOLUME
NA
Size
RH %
BRADLEY1/7/2025
ACH3280 NA
FinalOutlet VAV Outlet Data
VAV TERMINAL
Jessie Brown Quarterly TAB SYSTEM/UNIT
(Pressure Independent)
Cath Lab 5th Floor
Primary Maximum Airflow CFM (L/S)
AHU-5
NA
12" 9.89
15"x24" 15"x24"
Design
Setpoint set by VA Engineering.
PROJECT
LOCATION
Number Actual Type 615 65% Size Return Air CFM (L/S) 318 53%
DDC CF 12
DDC Address 67.8
ROOM FT3 12.11
0.008
Area Served No Type AK* Velocity Flow Flow 5554 SA1 1 4-way 1 650 407 63% 5554 SA2 1 4-way 1 300 208 69%
5554 RA1 1 4-way 1 600 318 53%
REMARKS:
TEST DATE TECHNICIAN
Room Air Temp ⁰F
Design
Velocity
VAV Terminal Data
VAV-5-3
CONSTANT VOLUME
NA
Size
RH %
BRADLEY1/7/2025
ACH2016 NA
FinalOutlet VAV Outlet Data
VAV TERMINAL
Jessie Brown Quarterly TAB SYSTEM/UNIT
(Pressure Independent)
Cath Lab 5th Floor
Primary Maximum Airflow CFM (L/S)
AHU-5
NA
9"
2.48
Design
Room Press. Positive To corridor inwg. NA
The Terminal unit is as set by VA Engineering.
Setra room pressure monitor reading +0.007
PROJECT
LOCATION
Number Actual Type 134 54% Size Exhaust Air CFM (L/S) 788 99%
DDC CF 10.3
DDC 69.6
ROOM FT3 NA
NA
Area Served No Type AK* Velocity Flow Flow C5506 SA 1 4-way 1 250 134 54%
C5506 RA 1 4-way 1 800 788 99%
REMARKS:
TEST DATE
Readings are "As-Is".
Terminal unit being influenced under a false load. A blanket warmer is up against the wall where the space sensor is mounted. Temperature is measuring 73.3 ⁰F at the side of the blanket warmer and the space sensor.
Room Press. Neutral To corridor inwg. NA
NA
5"
2.12
Design
VAV TERMINAL
Jessie Brown Quarterly TAB SYSTEM/UNIT
(Pressure Independent)
Cath Lab 5th Floor
Primary Maximum Airflow CFM (L/S)
AHU-5
RH %
BRADLEY1/7/2025
ACHNA NA
FinalOutlet VAV Outlet Data
TECHNICIAN
Room Air Temp ⁰F
Design
Velocity
VAV Terminal Data
VAV-5-4
VARIABLE VOLUME
NA
PROJECT
LOCATION
Number Actual Type 1528 113% Size
DDC CF NA
DDC Address NA
ROOM FT3 NA
NA
Area Served No Type AK* Velocity Flow Flow 5546 SA1 1 4-way 1 375 482 129% 5546 SA2 2 4-way 1 375 201 54% 5546A SA 3 4-way 1 75 212 283% 5548 SA 4 4-way 1 75 97 129% 5550 SA 5 4-way 1 150 126 84% C5505 SA 6 4-way 1 300 410 137%
C5505 RA 7 4-way 1 400 346 87% 5546 RA 8 4-way 1 175 521 298% 5546A RA 8 4-way 1 50 132 264% 5550 RA 9 4-way 1 150 54 36%
5548 EA 10 4-way 1 150 156 104%
REMARKS:
17.1 ACH
29.4 ACH
14.2 ACH
4.8 ACH
TEST DATE
5546 - 2390 FT3
BRADLEY1/7/2025 TECHNICIAN
5548 - 657 FT3
5550 - 1564 FT3
24"x24" 24"x24"
24"x24"
24"x24"
VelocitySize
24"x24"
24"x24"
Room Air Temp ⁰F38
24"x24" 24"x24"
Final
NARH %
Design
NA
Jessie Brown Quarterly TAB SYSTEM/UNIT
(Pressure Independent)
Cath Lab 5th Floor
Primary Maximum Airflow CFM (L/S)
AHU-5
Design
VAV TERMINAL
VAV Terminal Data
VAV-5-5
VARIABLE VOLUME
NA
Multiple Rooms
12"
ACH Multiple Rooms, see below.
2.29
NA
12"x24"
5546A - 432 FT3
NA
24"x24" 24"x24"
5548 - ΔP Room -0.001 "WC
- ΔP Setra -0.002 "WC
C5505-C5506
- ΔP Room 0.012 "WC
- ΔP Setra 0.012 "WC
Room Press.
Outlet VAV Outlet Data
(Flow Hood)
PROJECT SYSTEM Supply AHU-5
LOCATION Cardio-Cath 5th Floor
OUTLET MANUFACTURER TEST APPRATUS TSI Flow Hood
AREA DESIGN PRELIMINARY PERCENT OF
SERVED AIRFLOW CFM AIRFLOW CFM DESIGN
5555A Note 2 Note 1 300 0%
REMARKS:
TEST DATE TECHNICIAN
1/7/2025
Jessie Brown RTx
FINAL
AIRFLOW CFM
BRADLEY
Note 1: Supply flow is "AS-IS". No adjustments available.
Note 2: This unit is a Fan Coil. It cycles with temperature. Assume design air flow at 300 CFM. Fan Coil unit is off at the time of testing.
STAMP
(Flow Hood)
PROJECT SYSTEM Return AHU-5
LOCATION Cardio-Cath 5th Floor
OUTLET MANUFACTURER TEST APPRATUS TSI Flow Hood
AREA DESIGN PRELIMINARY PERCENT OF
SERVED AIRFLOW CFM AIRFLOW CFM DESIGN
5546 Note 1 50 1024% 5546A Note 1 50 264% 5550 Note 1 150 36%
C5505 Note 1 400 87% 5555A Note 3 Note 1 1200 5% 5554 Note 1 600 53% 5551 Note 2 Note 1 1800 55% 5555 Note 2 Note 1 1800 71%
REMARKS:
TEST DATE TECHNICIAN
Jessie Brown RTx
FINAL
AIRFLOW CFM
BRADLEY
Note 3: 5555A is the mechanical area off Rm 5555. Controlled by a Fan Coil unit.
Unit is off at the time of testing.
1/7/2025
STAMP
Note 1: Return flows are "AS-IS". No adjustments available.
Note 2: Lab returns are maxed out. Setpoints have been overridden by VA Engineering.
(Flow Hood)
PROJECT SYSTEM Exhaust AHU-5
LOCATION Cardio-Cath 5th Floor
OUTLET MANUFACTURER TEST APPRATUS TSI Flow Hood
AREA DESIGN PRELIMINARY PERCENT OF
SERVED AIRFLOW CFM AIRFLOW CFM DESIGN
5548 Note 1 150 104%
TOTALS
REMARKS:
TEST DATE TECHNICIAN
Jessie Brown RTx
FINAL
AIRFLOW CFM
1/7/2025
Note 1: Exhaust flows are "AS-IS". No adjustments available.
STAMP BRADLEY
ADDRESS:
Chicago, IL. 60612
ARCHITECT:
ENGINEER:
HVAC
CONTRACTOR
NEBB
TAB FIRM:
ADDRESS:
NA
NA
NA
TL SERVICES, INC.
P.O. BOX 1672
VAN BUREN, AR 72957
1/7/2024
CERTIFIED TEST, ADJUST, AND BALANCE REPORT
STAMP
Jesse Brown Endoscopy
5th Floor Damen
820 S Damen Ave.
NATIONAL ENVIRONMENTAL BALANCING BUREAU Page 35 of 119
January 7, 2025
TAB REPORT SUMMARY
5th Floor Endoscopy, Damen Jessie Brown Quarterly TAB
General:
No report for this cycle. The area is shut down for construction. The replacement of the air handler.
ADDRESS:
Chicago, IL. 60612
ARCHITECT:
ENGINEER:
HVAC
CONTRACTOR
NEBB
TAB FIRM:
ADDRESS:
1/17/2025
CERTIFIED TEST, ADJUST, AND BALANCE REPORT
STAMP
Jesse Brown
Isolation Rooms
820 S Damen Ave.
NA
NA
NA
TL SERVICES, INC.
P.O. BOX 1672
VAN BUREN, AR 72957
NATIONAL ENVIRONMENTAL BALANCING BUREAU Page 37 of 119
1/20/2025
TAB REPORT SUMMARY
Negative Air Isolation Rooms
General:
All data is in an “AS-IS” condition. Area was tested for supply and exhaust air flows along with room pressure. Air changes per hour were calculated based off air flow for the greatest flow CFM (Supply, Return, or Exhaust) and room volume in cubic feet.
Deficiencies:
The systems have been adjusted for pressure control, so the setpoints are “AS-IS”.
Several Isolation Rooms were occupied, and not available for testing, are listed in the table below.
Data from the Setra Room Pressure Monitors were recorded:
ROOM NUMBER DIFF PRESSURE TEMPERATURE HUMIDITY
4698 -0.013 “WC 70.9 ˚F 16.8 %RH
5649 -0.006 “WC 76.7 ˚F 0.56 %RH
5656 -0.002 “WC 73.0 ˚F 17.8 %RH
5657 -0.012 “WC 77.4 ˚F 11.2 %RH
6646 -0.006 “WC 75.7 ˚F 12.8 %RH
6648 -0.006 “WC 74.3 ˚F 15.0 %RH
6659 -0.011 “WC 72.9 ˚F 20.2 %RH
Exhaust air in the ER area, rooms 14 and 15 is almost “0”. The supply air is normal. Without the exhaust air, the spaces are not viable for use as an isolation room. 4642 is being used for dialysis the room is currently positively pressured.
PROJECT
LOCATION
Number Actual Type 104 69% Size Return Air CFM (L/S) 21 7%
DDC CF 20.1
DDC Address 69.2 ROOM FT3 1.09 Exhaust
0.003
Area Served No Type AK* Velocity Flow Flow 1470Q SA 1 4-way 1 150 104 69%
1470Q EA 1 4-way 1 295 21 7%
REMARKS:
TEST DATE
Room Press. negative To corridor inwg. NA
24"X24"
ER
NA
6"
2.19
24"X24"
Design VAV Outlet Data
VAV TERMINAL
Jessie Brown Quarterly TAB SYSTEM/UNIT
(Pressure Independent)
ER ROOM 14
Primary Maximum Airflow CFM (L/S)
Size
RH %
SIDES, BRADLEY1/8/2025
ACH1160 NA
FinalOutlet
Data value are "As-Is".
Setra Room Pressure Monitor: +0.003 (- port in room + port in corridor) Exhaust diffusers are very dirty may be causing flow restriction.
TECHNICIAN
Room Air Temp ⁰F
Design
Velocity
VAV Terminal Data
TU-1
CONSTANT VOLUME
PROJECT
LOCATION
Number Actual Type 124 88% Size Exhaust Air CFM (L/S) 40 9%
DDC CF 30.5
DDC Address 72.1 ROOM FT3 1.28 Exhaust
0.003
Area Served No Type AK* Velocity Flow Flow 1470R SA 1 4-way 1 141 124 88%
1470R EA 1 4-way 1 468 40 9%
REMARKS:
TEST DATE
Data values are "As-Is".
Setra Room Pressure Monitor: +0.003 (- port in room + port in corridor) Exhaust diffusers are very dirty may be causing flow restriction.
TECHNICIAN
Room Air Temp ⁰F
Design
Velocity
VAV Terminal Data
TU-30
CONSTANT VOLUME
NA
Size
RH %
SIDES; BRADLEY1/8/2025
ACH1872 NA
FinalOutlet VAV Outlet Data
VAV TERMINAL
Jessie Brown Quarterly TAB SYSTEM/UNIT
(Pressure Independent)
ER ROOM 15
Primary Maximum Airflow CFM (L/S)
ER
NA
7" 3.6
24"X24"
Design
Room Press. negative To corridor inwg. NA
24"X24"
PROJECT
LOCATION
Number Actual Type 633 111% Size Exhaust Air CFM (L/S) 498 105%
DDC CF 9.1
DDC 73.1
ROOM FT3 15.30 Exhaust
-0.011
Area Served No Type AK* Velocity Flow Flow
4640 1 4-WAY 1 215 268 125%
4640 2 4-WAY 1 220 213 97%
4641 2 4-WAY 1 135 152 113%
4640 Rm Exh 3 4-WAY 1 475 450 95% 4640 RR Exh 4 4-WAY 1 100 48 48%
REMARKS:
TEST DATE
24"x24"
TECHNICIAN
Room Air Temp ⁰F
Design
Velocity
VAV Terminal Data 4-9
CONSTANT VOLUME
NA
Size
RH %
SIDES, BRADLEY1/8/2025
ACH1953 NA
FinalOutlet VAV Outlet Data
VAV TERMINAL
Jessie Brown Quarterly TAB SYSTEM/UNIT
(Pressure Independent)
4th Floor East
Primary Maximum Airflow CFM (L/S)
AHU-6
NA
NA
N/A N/A
24"x24"
24"x24"
Design
24"x24" 24"x24"
Room Press. Neg to Ante-Room inwg. NA
Data values are "AS-IS". No access to control system at this time.
4641 - Temp 74.1; RH% 9
4641 to Corridor ΔP 0.004 Setra Room Pressure Monitor 4640 -0.002 Setra Room Pressure Monitor 4641 0.007
4640 to 4641 ΔP -0.011
Terminal Unit Coil Check Report
3d-4-9_4640 1-25 ok
PROJECT
LOCATION
Number Actual Type 334 77% Size Exhaust Air CFM (L/S) 280 59%
DDC CF 8.6
DDC 74.7
ROOM FT3 8.60 Exhaust
0.005
Area Served No Type AK* Velocity Flow Flow
4642 1 4-WAY 1 215 119 55%
4642 2 4-WAY 1 220 215 98%
4642 Rm Exh 3 4-WAY 1 475 244 51% 4642 RR Exh 4 4-WAY 1 100 36 36%
REMARKS:
ΔP to corridor:
0.001
TEST DATE
Data values are "AS-IS". Pressure ratios are correct. This system has been negative in the past.
Setra Room Pressure Monitor: 4642 to 4641 ΔP -0.003
SIDES, BRADLEY1/8/2025
Room being used for Dialysis
24"x24" 24"x24"
NA
NA
Room Press. Neg to Ante-Room inwg. NA
RH %
ACH1953
VAV TERMINAL
Jessie Brown Quarterly TAB SYSTEM/UNIT
(Pressure Independent)
4th Floor East
Primary Maximum Airflow CFM (L/S)
AHU-6
Design
FinalOutlet VAV Outlet Data
TECHNICIAN
Room Air Temp ⁰FN/A
24"x24" 24"x24"
Design Velocity
VAV Terminal Data 4-#
CONSTANT VOLUME
NA
Size
NA
N/A
Terminal Unit Coil Check Report
3f-4-9B_4642 1-25 nogo
PROJECT
LOCATION
Number Actual Type 334 77% Size Exhaust Air CFM (L/S) 280 59%
DDC CF 13
DDC 67.3
ROOM FT3 8.60 Exhaust
-0.003
Area Served No Type AK* Velocity Flow Flow
4642 1 4-WAY 1 215 119 55%
4642 2 4-WAY 1 220 215 98%
4642 Rm Exh 3 4-WAY 1 475 244 51% 4642 RR Exh 4 4-WAY 1 100 36 36%
REMARKS:
TEST DATE
Velocity
VAV Terminal Data 4-#
CONSTANT VOLUME
NA
Size
NA
N/A
FinalOutlet VAV Outlet Data
TECHNICIAN
Room Air Temp ⁰FN/A
24"x24" 24"x24"
Design
VAV TERMINAL
Jessie Brown Quarterly TAB SYSTEM/UNIT
(Pressure Independent)
4th Floor East
Primary Maximum Airflow CFM (L/S)
AHU-6
Design
NA
NA
Room Press. Neg to Ante-Room inwg. NA
RH %
ACH1953
24"x24" 24"x24"
Data values are "AS-IS". Pressure ratios are correct. No access to control system at this time. VAV Terminal unit number unavailable at this time.
Sectra Room Pressure Monitor: 4642 to 4641 ΔP --0.003
SIDES, BRADLEY1/8/2025
Room being used for Dialysis
Terminal Unit Coil Check Report
3f-4-9B_4642 1-25
PROJECT
LOCATION
Number Actual Type 546 88% Size Exhaust Air CFM (L/S) 653 121%
DDC CF 6.7
DDC 76.9
ROOM FT3 12.80 Exhaust
-0.015
Area Served No Type AK* Velocity Flow Flow 4657 1 4-way 1 265 316 119% 4657 2 4-way 1 265 93 35% 4657B ante-rm 3 4-way 1 90 137 152%
4657 Rm Exh 4 4-way 1 555 448 81% 4657 RR Exh 5 4-way 1 100 205 205%
REMARKS:
TEST DATE
Velocity
VAV Terminal Data 4-#
CONSTANT VOLUME
NA
Size
NA
N/A
FinalOutlet VAV Outlet Data
TECHNICIAN
Room Air Temp ⁰FN/A
24"x24" 24"x24"
Design
Jessie Brown Quarterly TAB SYSTEM/UNIT
(Pressure Independent)
4th Floor West ICU
Primary Maximum Airflow CFM (L/S)
4th floor west AHU-7
Design
ACH2100
24"x24" 24"x24"
VAV TERMINAL
NA
NA
Room Press. Negative to Ante-Rm inwg. NA
RH %
24"x24"
SIDES, BRADLEY1/8/2025
Data values are "AS-IS". No access to control system at this time.
Pressure from Ante-Room to the Corridor, Meter 0.001. Setra 0.005 Room Setra -0.015 Supply air flows adjusted for negative pressure of room.
Ante Room:: 75.7⁰F, RH% 26.1
3g-4-20_4657 1-25 ok
PROJECT
LOCATION
Number Actual Type 451 105% Size Return Air CFM (L/S) 634 117%
DDC CF 15.1
DDC 75.3
ROOM FT3 26.42
-0.016
Area Served No Type AK* Velocity Flow Flow 5648 1 4-way 1 300 302 101% 5648B AnteRm 2 4-way 1 130 149 115%
5648 Rm Exh 3 4-way 1 500 436 87% 5648 RR Exh 4 4-way 1 100 198 198%
REMARKS:
TEST DATE
Velocity
VAV Terminal Data 5-6
CONSTANT VOLUME
NA
Size
NA
N/A
FinalOutlet VAV Outlet Data
TECHNICIAN
Room Air Temp ⁰FN/A
24"x24" 24"x24"
Design
Jessie Brown Quarterly TAB SYSTEM/UNIT
(Pressure Independent)
5th Floor East
Primary Maximum Airflow CFM (L/S)
AHU-6
Design
ACH1440
24"x24"
VAV TERMINAL
NA
24"x24"
NA
Ante-Room to Corridor inwg. NA
RH %
Data values are "AS-IS".
Anteroom 5648B: Room Air Temp ⁰F 74.1 RH % 15.2 Pressure from Ante-Room to the Corridor, Meter 0.000 Setra RPM: 0.004 Room Pressure Setra, -0.008, SIDES, BRADLEY1/17/2025
Terminal Unit Coil Check Report
4a-5-6_5648 1-25
PROJECT
LOCATION
Number Actual Type 515 94% Size Return Air CFM (L/S) 591 109%
DDC CF 9.1
DDC 74.3
ROOM FT3 24.63 Exhaust
-0.006
Area Served No Type AK* Velocity Flow Flow 5646 1 4-way 1 445 424 95% 5646B Ante 2 4-way 1 100 91 91%
5646 Rm Exh 3 4-way 1 429 430 100% 5646 RR Exh 4 4-way 1 162 161 99%
REMARKS:
TEST DATE
Anteroom 5646B: Room Air Temp ⁰F 73.4 RH % 10.6
Data values are "AS-IS".
Pressure from Ante-Room to the Corridor, Neutral -0.000 Setra RPM: 0.001 Room Pressure Setra, +0.006
Stamp
SIDES, BRADLEY1/13/2025
NA
NA
Room Press. Neg to AnteRm inwg. NA
RH %
ACH1440
24"x24" 24"x24"
VAV TERMINAL
Jessie Brown Quarterly TAB SYSTEM/UNIT
(Pressure Independent)
5th Floor East
Primary Maximum Airflow CFM (L/S)
AHU-6
Design
FinalOutlet VAV Outlet Data
TECHNICIAN
Room Air Temp ⁰FN/A
24"x24" 24"x24"
Design Velocity
VAV Terminal Data 5-9
CONSTANT VOLUME
NA
Size
NA
N/A
Terminal Unit Coil Check Report
4b-5-9_5646 1-25 ok
PROJECT
LOCATION
Number Actual Type 563 104% Size Return Air CFM (L/S) 540 82%
DDC CF 12.6
DDC 74.1
ROOM FT3 18.37
-0.011
Area Served No Type AK* Velocity Flow Flow 5660 1 4-way 1 400 389 97% 5660B AnteRm 2 4-way 1 140 174 124%
5660 Rm Exh 3 4-way 1 555 354 64% 5660 RR Exh 4 4-way 1 100 186 186%
REMARKS:
TEST DATE
Data values are "AS-IS".
Pressure from Ante-Room to the Corridor, Meter 0.001 Setra RPM: 0.007 Anteroom 5660B: Room Air Temp ⁰F 73.0 RH % 9.6
SIDES, BRADLEY1/9/2025
Room Pressure Setra, -0.010
NA
NA
Ante-Room to Corridor inwg. NA
RH %
ACH1764
24"x24" 24"x24"
VAV TERMINAL
Jessie Brown Quarterly TAB SYSTEM/UNIT
(Pressure Independent)
5th Floor West
Primary Maximum Airflow CFM (L/S)
AHU-8
Design
FinalOutlet VAV Outlet Data
TECHNICIAN
Room Air Temp ⁰FN/A
24"x24" 24"x24"
Design Velocity
VAV Terminal Data 5-10
CONSTANT VOLUME
NA
Size
NA
N/A
Terminal Unit Coil Check Report
4e-5-10_5660 1-25 ok
PROJECT
LOCATION
Number Actual Type 0 0% Size Return Air CFM (L/S) 0 0%
DDC CF 15
DDC 74.3
ROOM FT3 0.00
0.006
Area Served No Type AK* Velocity Flow Flow 6648 1 4-way 1 510 0% 6648B 1 4-way 1 140 0%
6648 Return 3 4-way 1 615 0% 6648 RR Exh 4 4-way 1 100 0%
REMARKS:
TEST DATE
Ante-Room Setra Room Pressure Monitor: +0.002 Ante-Room: Room Air Temp ⁰F 76.9: RH % 13.8 6648 Setra Room Pressure Monotor: -0.016
NA
DesignOutlet
24"x24" 24"x24"
24"x24" 24"x24"
AHU-8
NA
NA
N/A N/A
6-#
CONSTANT VOLUME
Size
VAV TERMINAL
Jessie Brown Quarterly TAB SYSTEM/UNIT
(Pressure Independent)
6th Floor East
VAV Terminal Data
Primary Maximum Airflow CFM (L/S)
RH %
ACH2268 NA
VAV Outlet Data
NA
Room Press. Neg. to Anteroom inwg.
Data values are "AS-IS". NO ACCESS TO PAITENT ROOM Pressure fro Anteroom to the Corridor, Meter reads:
TECHNICIAN
Room Air Temp ⁰F
Design
Velocity
SIDES, BRADLEY1/17/2025
Final
Terminal Unit Coil Check Report
5a-6-B_6648 1-25
PROJECT
LOCATION
Number Actual
Type 327 64%
Size Return Air CFM (L/S) 728 118%
DDC CF 14.2
DDC 73.1
ROOM FT
19.45 Exhaust
-0.017
Area
Served No Type AK* Velocity Flow Flow
6650 1 4-way 1 510 327 64%
6650 Rm Exh 2 4-way 24"x24" 1 615 220 36%
6650 RR Exh 3 4-way 24"x24" 1 100 508 508%
REMARKS:
TEST DATE TECHNICIAN
Room Air Temp ⁰F
Design
Velocity
SIDES, BRADLEY1/17/2025
Size
RH %
2246 NA
VAV TERMINAL
Jessie Brown Quarterly TAB SYSTEM/UNIT
(Pressure Independent)
6th Floor East
VAV Terminal Data
Primary Maximum Airflow CFM (L/S)
AHU-8
NA
NA
N/A
N/A
6-#
CONSTANT VOLUME
NA
Outlet Design
Room Press. neg. to Ante-Room inwg. NA
ACH
Final
VAV Outlet Data
Data values are "AS-IS".
6650 Setra Room Pressure Monitor: -0.017
Terminal Unit Coil
Check Report 5c-6-C_6650 1-25
PROJECT
LOCATION
Number Actual Type 611 120% Size Return Air CFM (L/S) 764 124%
DDC CF 9.4
DDC 73.9
ROOM FT3 20.21 Exhaust
-0.012
Area Served No Type AK* Velocity Flow Flow 6658 1 4-way 1 510 496 97% anti room 1 4-way 1 140 115 82%
6658 Rm Exh 2 4-way 24"x24" 1 615 534 87% 6658 RR Exh 3 4-way 24"x24" 1 100 230 230%
REMARKS:
TEST DATE
Room Air Temp ⁰F
SIDES, BRADLEY1/19/2024
VAV TERMINAL
Jessie Brown Quarterly TAB SYSTEM/UNIT
Final
NA
(Pressure Independent)
AHU-8
Design
NA
NA
N/A
Room Press. neg. to Ante-Room inwg.
CONSTANT VOLUME
NA
6th Floor West
VAV Terminal Data 6-14
Design
Primary Maximum Airflow CFM (L/S)
Size
RH %
ACH
NA
8''
N/A
Outlet VAV Outlet Data
Velocity
TECHNICIAN
6658 Setra Room Pressure Monitor: -0.005 "WC
Data values are "AS-IS". No access to control system at this time.
Pressure from Ante-Room to the Corridor, Meter reads; -0.010 Ante-Room: Room Air Temp ⁰F 73.9: RH % 12.0 Ante-Room Setra Room Pressure Monitor: -0.005
Terminal Unit Coil Check Report
6a-6-14_6658 1-25
PROJECT
LOCATION
Number Actual Type 0 0% Size Return Air CFM (L/S) 0 0%
DDC CF 20.2
DDC 72.9
ROOM FT3 0.00 Exhaust
-0.011
Area Served No Type AK* Velocity Flow Flow 6659 1 4-way 1 450 0%
6659 Return 3 4-way 24"x24" 1 555 0% 6659 RR Exh 4 4-way 24"x24" 1 100 0%
REMARKS:
TEST DATE
Data values are "AS-IS". No access to control system at this time.
6659 Setra Room Pressure Monitor: -0.011
NO ACCESS
Stamp
NA
VAV Outlet Data
Design
AHU-8
NA
NA
N/A N/A
VAV TERMINAL
Jessie Brown Quarterly TAB SYSTEM/UNIT
(Pressure Independent)
6th Floor West
Primary Maximum Airflow CFM (L/S)
VAV Terminal Data
CONSTANT VOLUME
NA
Size
RH %
ACH2268 NA
Room Press. neg. to Ante-Room inwg.
TECHNICIAN
Room Air Temp ⁰F
Design
Velocity
SIDES, BRADLEY1/17/2025
FinalOutlet
6-13
Terminal Unit Coil Check Report
6b-6-13_6659 1-25
PROJECT
LOCATION
Number Actual Type 631 117% Size Exhaust Air CFM (L/S) 592 116%
DDC CF 12.8
DDC 73
ROOM FT3 21.40 Exhaust
-0.008
Area Served No Type AK* Velocity Flow Flow 6662 1 4-way 1 400 486 122% anti room 2 4-way 1 140 145 104%
6659 Return 3 4-way 1 510 360 71% 6659 RR Exh 4 4-way 1 100 232 232%
REMARKS:
TEST DATE
Data values are "AS-IS". No access to control system at this time.
Pressure from Ante-Room to the Corridor, 0.0050
TECHNICIAN
Room Air Temp ⁰F
Design
Velocity
SIDES, BRADLEY1/8/2025
CONSTANT VOLUME
NA
Size
RH %
ACH1660 NA
VAV Outlet Data Outlet
VAV TERMINAL
Jessie Brown Quarterly TAB SYSTEM/UNIT
(Pressure Independent)
VAV Terminal Data 6-8
6th Floor West
Primary Maximum Airflow CFM (L/S)
AHU-8
NA
NA
N/A N/A
24"x24" 24"x24"
Design Final
Room Press. To Ante-Room inwg. NA
6662 Setra Room Pressure Monitor: -0.004
Ante-Room: Room Air Temp ⁰F 72.7: RH % 13.9 Ante-Room Setra Room Pressure Monitor: 0.006
24"x24" 24"x24"
Terminal Unit Coil Check Report
6c-6-8_6662 1-25
ADDRESS:
Chicago, IL. 60612
ARCHITECT:
ENGINEER:
HVAC
CONTRACTOR
NEBB
TAB FIRM:
ADDRESS:
NA
NA
TL SERVICES, INC.
P.O. BOX 1672
VAN BUREN, AR 72957
1/7/2025
CERTIFIED TEST, ADJUST, AND BALANCE REPORT
STAMP
Jesse Brown Morgue/Autopsy
820 S Damen Ave.
NA
NATIONAL ENVIRONMENTAL BALANCING BUREAU Page 53 of 119
January 7, 2025
TAB REPORT SUMMARY
Morgue/Autopsy 2nd Floor, Damen
Jessie Brown Quarterly TAB
General:
The area was tested for supply and exhaust air flows. Air changes per hour were calculated based off air flows both supply and exhaust and room volume in cubic feet.
Deficiencies:
1. All data is “As-Is”.
PROJECT
LOCATION
Number Actual Type 1213 66% Size Exhaust Air CFM (L/S) 1371 65%
DDC CF 11.1
DDC 66.4
ROOM FT3 NA
-0.030
Area Served No Type AK* Velocity Flow Flow Supply 2497 1 4-way 1 525 381 73% 2497 2 4-way 1 525 372 71% 2497 3 Linear 1 150 43 29% 2497 4 Linear 1 150 70 47% 2497 5 Linear 1 150 82 55% 2497 6 Linear 1 150 77 51% 2457 7 4-way 1 200 188 94% Exhaust 2497 E1 8 SideWall 1 150 96 64% 2497 E2 9 SideWall 1 150 200 133% 2497 E3 10 SideWall 1 250 162 65% 2497 E4 11 SideWall 1 250 163 65% 2497 E8 12 Table 1 400 99 25% 2497 E9 13 Table 1 400 62 16% 2457 E5 14 SideWall 1 300 417 139% 2457 E6 15 SideWall 1 100 64 64% 2497A E7 16 SideWall 1 100 108 108%
REMARKS:
TEST DATE TECHNICIAN
8x8 8x8
5"x9"
3' 3' 3'
5"x9"
BRADLEY
N/A N/A
Room Press. to corridor inwg. NA VAV Outlet Data
Size Design
Room Air Temp ⁰F
VAV TERMINAL
Jessie Brown Quarterly TAB Report SYSTEM/UNIT
(Pressure Independent)
Autopsy
Primary Maximum Airflow CFM (L/S)
AHU-137A
1/7/2025
ACHsee ACH report NA
FinalOutlet
2'x4'
Data values are "AS-IS". Exhaust System is on-line and working.
Design
Velocity
VAV Terminal Data
RHU-1
CONSTANT VOLUME
NA
RH % NA
NA
16"x16" 5"x9"
2'x4' 3'
24"x24"
13x14 13x14
16"x16"
Terminal Unit Coil Check Report
2a-rhu-1_Report 1-25
PROJECT
LOCATION
Number Actual Type 664 74% Size Exhaust Air CFM (L/S) 0 0%
DDC CF 10.9
DDC 71
ROOM FT3 NA
-0.008
Area Served No Type AK* Velocity Flow Flow Supply 2496 1 4-way 1 300 202 67% 2496 2 4-way 1 300 251 84% 2496 3 4-way 1 300 211 70% Exhaust 2496 total 10 ea Sidewall 1 680 0 0%
REMARKS:
TEST DATE
Design
Velocity
VAV Terminal Data
RHU-2
CONSTANT VOLUME
NA
Size
NA
NA
BRADLEY1/7/2025
ACHsee ACH report NA
FinalOutlet VAV Outlet Data
TECHNICIAN
VAV TERMINAL
Jessie Brown Quarterly TAB Report SYSTEM/UNIT
(Pressure Independent)
Morgue
Primary Maximum Airflow CFM (L/S)
AHU-137A
N/A N/A
24x24
Room Air Temp ⁰F
Design
RH %
6x9
24x24
Room Press. to corridor inwg. NA
24x24
Data values are "AS-IS". No exhaust air flow in the header.
Terminal Unit Coil Check Report
2b-rhu-2_Report 1-25
PROJECT
LOCATION
Number Actual Type 594 118% Size Exhaust Air CFM (L/S) 106 39%
DDC CF 10.5
DDC 70.7
ROOM FT3 NA
Area Served No Type AK* Velocity Flow Flow 2457 1 4-way 1 255 218 85% 2459 2 4-way 1 250 376 150%
Exhaust 2459 3 4-way 1 270 106 39%
REMARKS:
TEST DATE
NA
24x24
AHU-137A
NA
NA
N/A N/A
24x24 24x24
Design VAV Outlet Data
VAV TERMINAL
Jessie Brown Quarterly TAB Report SYSTEM/UNIT
(Pressure Independent)
Viewing/Mechanical Room
Primary Maximum Airflow CFM (L/S)
Size
RH %
BRADLEY1/7/2025
ACHsee ACH report NA
FinalOutlet
Data values are "AS-IS".
TECHNICIAN
Room Air Temp ⁰F
Design
Velocity
VAV Terminal Data
RHU-3
CONSTANT VOLUME
NA
Terminal Unit Coil Check Report
2c-rhu-3_Report 1-25
(Flow Hood)
PROJEC SYSTEM Exhaust
AREA Morgue/Autospy
OUTLET MANUFACTURER TEST APPRATUS TSI Flow Hood
AREA DESIGN PRELIMINARY PERCENT OF
SERVED AIRFLOW CFM AIRFLOW CFM DESIGN
2497 E1 Sidewall 5"x9" 150 64% 2497 E2 Sidewall 5"x9" 150 133% 2497 E3 Sink 13x14 250 65% 2497 E4 Sink 13x14 250 65% 2457 E5 Soiled Uitility 16"x16" 300 139% 2457 E6 Soiled Uitility 16"x16" 100 64%
2497A E7 Restroom 5"x9" 170 64% 2497 E8 Table 1 8x8 400 25% 2497 E9 Table 2 8x8 400 16%
2459 E1 Consolation 24"x24" 270 100%
REMARKS:
1/7/2025 TECHNICIAN
FINAL
AIRFLOW CFM
Jessie Brown Quarterly TAB
Data values are "AS-IS".
BRADLEY STAMPTEST DATE
(Flow Hood)
PROJEC SYSTEM Exhaust
AREA Morgue
OUTLET MANUFACTURER TEST APPRATUS TSI Flow Hood
AREA DESIGN PRELIMINARY PERCENT OF
SERVED AIRFLOW CFM AIRFLOW CFM DESIGN
2496 E1 SIDEWALL 6"X9" 68 0%
2496 E2 SIDEWALL 6"X9" 68 0%
2496 E3 SIDEWALL 6"X9" 68 0%
2496 E4 SIDEWALL 6"X9" 68 0%
2496 E5 SIDEWALL 6"X9" 68 0%
2496 E6 SIDEWALL 6"X9" 68 0%
2496 E7 SIDEWALL 6"X9" 68 0%
2496 E8 SIDEWALL 6"X9" 68 0%
2496 E9 SIDEWALL 6"X9" 68 0%
2496 E10 SIDEWALL 6"X9" 68 0%
REMARKS:
1/7/2025 TECHNICIANTEST DATE
Data values are "AS-IS". No exhaust air flow in header with sidewall vents.
SIDES, BRADLEY STAMP
Jessie Brown Quarterly TAB
FINAL
AIRFLOW CFM
(Flow Hood)
PROJECT SYSTEM
CFM ACH
108 14
1025 11 782 8 188 10 484 7 218 11 376 23 106 6
REMARKS:
TEST DATE
Supply Supply Supply
Exhaust
SIDES, BRADLEYTECHNICIAN1/7/2025 STAMP
ROOM CUBIC FT
2497 5762
2496 4096
Morgue/Autopsy
2497 5762 2457 1134
NOTE
Supply Exhaust Exhaust
Jessie Brown Quarterly TAB Report mech. Room 1232 2459 990 2459 990
2497A 467 Exhaust
Supply air systems are at maximum flows available. Data is "As-Is".
ADDRESS:
Chicago, IL. 60612
ARCHITECT:
ENGINEER:
HVAC
CONTRACTOR
NEBB
TAB FIRM:
ADDRESS:
1/10/2025
CERTIFIED TEST, ADJUST, AND BALANCE REPORT
STAMP
Jesse Brown VA Hospital
OR Quarterly Verification: Surgeries
820 S Damen Ave.
NA
NA
NA
TL SERVICES, INC.
P.O. BOX 1672
VAN BUREN, AR 72957
NATIONAL ENVIRONMENTAL BALANCING BUREAU Page 64 of 119
January 11, 2025
TAB REPORT SUMMARY
Quarterly Operational Verification
General:
The operating rooms are near specification. Data values are being left “As-Is” due to VA Engineering settings.
Deficiencies:
Day Surgery OR7 (1693) appears to be used as storage, but due to lack of air flow into the area it is not viable for any kind of surgical procedure. The Terminal unit is maxed out.
Most OR systems have been manually set to their current values. These manual overrides were not changed, but left “As-Is”, per engineering request and preference.
We were unable to access 5391, Eye Clinic OR.
TEST
PROJECT
LOCATION
Number Actual
752 80%
Returnt Air CFM (L/S) 304
VFD % 12.7
DDC Address 72.4
ROOM FT
16.1
0.101
Area
Served No Type AK* Velocity Flow Flow
1109 SA1 1 4-way 1 470 265 56%
1109 SA2 2 4-way 1 470 487 104%
1109 RA1 1 4-way 1 NA 164
1109 RA2 2 4-way 1 NA 140
REMARKS:
TEST DATE TECHNICIAN
Room Air Temp ⁰F
Design
Velocity
System Data
AHU S-10C
NA
Size
RH %
SIDES, BRADLEY1/9/2025
ACH2808 NA
FinalOutlet
Outlet Data
OUTLET
NA
Jessie Brown Quarterly TAB SYSTEM/UNIT
(Pressure Independent)
1st Floor GU Clinic
Primary Maximum Airflow CFM (L/S)
Urology Procedural OR
NA60% Overridden
Design
Room Press. Pos. To corridor inwg. NA
AHU-S10C supplies air for this space. To get 20 Air Changes per Hour
(ACH) we calculate a primary air flow of 940 CFM on a cubic footage of
2808. It has been set by VA Engineering. System being left "As-Is".
Setra Room Pressure Monitor: 0.058 "WC
PROJECT
LOCATION
Number Actual Type 833 102% Size Return Air CFM (L/S) 629 95%
DDC CF 10.3
DDC Address 74.8 ROOM FT3 20.68 Supply Dmp Pos 0.014
Area Served No Type AK* Velocity Flow Flow 1692 1 4-way 1 410 439 107% 1692 1 4-way 1 410 394 96%
1692 1 4-Way 665 629 95%
REMARKS:
TEST DATE
Stamp
Room Press. Positive To Ante-room inwg. NA
12"x24"
AHU 1 Bed Tower
NA
12"
Not Recalibrated 04-A8-F2-2A-01-00
24"x24" 24"x24"
DesignOutlet VAV Outlet Data
VAV TERMINAL
Jessie Brown Quarterly TAB SYSTEM/UNIT
(Pressure Independent)
Primary Maximum Airflow CFM (L/S)
Not Available
Size
RH %
SIDES. BRADLEY1/9/2025
ACH2417 NA
Final
Day Surgery - OR 5
JCI space sensors are temperature only. The system reads a general humidity level of the space at the Nurse's Station. Values given for humidity and temperature are from the test meter. System adjusted by VA Engineering. Leaving system "As-Is".
Setra Room Pressure Monitor: 0.014"WC
TECHNICIAN
Room Air Temp ⁰F
Design
Velocity
VAV Terminal Data
TU-1-1-25
VARIABLE VOLUME
PROJECT
LOCATION
Number Actual Type 544 81% Size Return Air CFM (L/S) 425 85%
DDC CF 11.2
DDC Address 75 ROOM FT3 16.19 Supply Dmp Pos 0.009
Area Served No Type AK* Velocity Flow Flow 1693 SA1 1 4-way 1 336 279 83% 1693 SA2 2 4-way 1 336 265 79%
1693 EA 3 4-way 1 500 425 85%
REMARKS:
TEST DATE
Day Surgery - OR 7
JCI space sensors are temperature only. Values here are from the testing meter. Terminal unit is maxed out. Unable to get more air flow. Floor plans show the Supply Air Flows original design was 295 CFM. Calculating for ACH of 20 (to allow the room to return to procedural operations) the values for the supply diffusers should be 672 CFM total. This would give a 20 ACH for the space.
Setra Room Pressure Monitor: 0.011"WC
TECHNICIAN
Room Air Temp ⁰F
Design
Velocity
VAV Terminal Data
TU-1-1-24
VARIABLE VOLUME
NA
Not Available
Size
RH %
SIDES/BRADLEY1/9/2025
ACH2016 NA
FinalOutlet VAV Outlet Data
VAV TERMINAL
Jessie Brown Quarterly TAB Report SYSTEM/UNIT
(Pressure Independent)
Primary Maximum Airflow CFM (L/S)
AHU 1 Bed Tower
NA
24"x24"
10"
IFU1K-R2AA-CPXZ
04-9F-AB-FC-01-00
24"x24" 24"x24"
Design
Room Press. Positive to Ante-room inwg. NA
PROJECT
LOCATION
Number Actual Type 2772 91% Size Return Air CFM (L/S) 1774
DDC CF 25.4
DDC Address 66.9 ROOM FT3 21.32 Supply
0.028
Area Served No Type AK* Velocity Flow Flow OR 1 2620 1 Perf 1 300 76 25% OR 1 2620 2 Perf 1 300 341 114% OR 1 2620 3 Perf 1 300 150 50% OR 1 2620 4 Perf 1 300 221 74% OR 1 2620 5 Perf 1 300 281 94% OR 1 2620 6 Perf 1 156 162 104% OR 1 2620 7 Perf 1 156 158 101% OR 1 2620 8 Perf 1 156 178 114% OR 1 2620 9 Perf 1 156 171 110% OR 1 2620 10 Perf 1 156 168 108% OR 1 2620 11 Perf 1 156 163 104% OR 1 2620 12 Perf 1 156 160 103% OR 1 2620 13 Perf 1 156 188 121% OR 1 2620 14 Perf 1 156 171 110% OR 1 2620 15 Perf 1 156 184 118%
REMARKS:
TEST DATE
Return air is modulated to maintain the space pressure. Data values are "As-Is".
Setra Room Pressure Monitor: 0.023 "WC
1'x5'
1"x4' 1'x5' 1'x5'
Room Press. Pos.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .