S06 - Att 1 A0002 - 556-24-102 Pre-Bid RFIs responses 14JUL25.pdf

PDF 545 KB Posted

Attached to
Y1DZ--B1 Interior Demo & Abatement 556-24-102
Solicitation number
36C25225B0019
Issued by

About this file

This document is a Pre-Bid Request for Information (RFI) response for a VA project involving interior demolition and asbestos abatement at the Captain James A. Lovell Federal Health Care Center. The solicitation (36C25225B0019) covers a comprehensive demolition and abatement project at Building 1, with a virtual bid opening scheduled for 7/24/2025 at 10:00 a.m. Key details include requirements for asbestos and lead-based paint removal, universal waste handling, utility service modifications, and specific demolition activities across multiple building areas.

The RFI responses address critical technical and procedural questions, including drawing scale discrepancies, flooring removal specifications, waste management protocols, safety requirements, and contractor responsibilities. Notable requirements include using an independent CPIH/CIH for asbestos abatement monitoring, handling universal wastes, managing potential quantity variations (±10%), and complying with specific demolition and abatement guidelines. The project will not involve occupied building spaces during demolition, and contractors must provide their own electricians and site safety personnel. The VA will provide abatement monitoring through a task order contract.

View the file

Other files

Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFI # Question/Comment Response (New are bolded)

Drawings missing information.

VA Confirmed this was a software issue on the users end. They were able to get the file to open and display all of the information.

While calibrating our Bluebeam take-offs, we found that sheets HA100 through HA104 do not land at the printed scale of 1/16" = 1'- 0". Field measurements and digital calibration both point to roughly 3/32" = 1'-0" (see the attached sheet at different scales for reference). Given this, could you please confirm the following two items:

1. Correct scale for sheets HA100-HA104.

2. Whether the quantified Keynotes and counts are correct as presently given. Specifically, if HA101 Keynotes H1–H10 should be priced exactly as listed, regardless of the scale discrepancy.

1. The scaling on these drawings is indeed 3/32" = 1'. This can be corrected without any other impacts.

2. Quantities were not based on the inaccurate 1/16" scaling, no quantity or pricing changes are anticipated

On page HA102 the area corridor CO-2-01 and Lobby 200-1 is noted H1 which is remove floor tile and mastic on concrete. That same area on page AD103 is calling for epoxy floor removal on concrete. Is the epoxy floor below the asbestos flooring and the mastic is on epoxy not on concrete?

For areas CO-2-01 and 200-1, we have determined that the asbestos flooring has indeed already been removed from these two areas. However, due to the widespread presence of residual asbestos black mastic throughout most of the building, the mastic in these areas will still require abatement.

On page AD101 rooms 123, 124, 129, 142 and 143 plans call for removal of floor tile. Those same rooms are listed on HA101 under H1. H1 is floor tile removal with black mastic on concrete. Is there a layer of flooring requiring removal after asbestos is abated?

See drawings on page 6 & 7

5 Under Summary Of Work-(02 82 11-3). Item 4 Special Wastes:

Are the Universal Wastes to be packaged by Contractor and then turn over to the VA for disposal/recycling? Yes. For more details, reference VHA Directive 1850.06(1)

Under Variations In Quantity (02 82 11-4) Item A:

Quantities at +/- of 10% are not change order amounts?

Contractor shall figure an additional 10% of spec quantities in contract price and timeframes?

Some allowances should always be given regarding estimates to material quantities. VA is not expecting to have much variation in the estimated amount of ACM. This does not mean overestimation or overinflation of costs is appropriate. The contract is a firm fixed price. The quote should be fair and reasonable. This verbage is in place to facilitate less red tape. The blade cuts both ways, underestimates of up to 10% will not seek a modification for a credit.

Under 1.5 Applicable Codes And Regulations (02 82 11-16) Item B: Asbestos Abatement Contractor Responsibility:

Is the Asbestos Contractor for hiring an independent CPIH/CIH to oversee abatement activities as well as perform sampling/analytical?

VA has a contract for asbestos abatement monitoring. There will be a task order issued to the abatement monitor after the contractor establishes the abatement schedule/duration.

This company will be under VA contract only.

Project # 556-24-102 B1 INTERIOR DEMOLITION AND ABATEMENT Solicitation # 36C252-25-B-0019

Pre-Bid RFIs

S06 - Att 1 A0002 - 556-24-102 Pre-Bid RFIs responses 14JUL25 1 of 7

Under 3.1 Regulated Area Preparations (02 82 11-45) Item B: Signage and Power Management #2. The Contractor is responsible to shut down and lock out/tag out electric power to the regulated area?

Contractor to provide our own electrician?

VA electric shops personnel are not contracted to do the work of the contractor. VA may be consulted to help answer FHCC specific questions or help facilitate a lockdown. VA can advise on what might be affected in case of shutdowns.

In short, the contractor must provide their own electrician that will do the electrical work as specified in the contract.

Under 3.1 Auxiliary Generator (02 82 11-48) Item 7: Says if the building is occupied during abatement provide an auxiliary gasoline/diesel generator……..?

Will the building be occupied during demolition or abatement?

The building will not be occupied at time of demo/abatement.

10 Under Lead Based Paint Removal (02 83 33.13-14) Item D Waste Collection:

All lead contaminated materials are to be placed in drums? Follow the directions as laid out in the specs.

11 Under Demo: Does plaster ceilings stay where acoustical ceiling tile is removed?

No Plaster ceilings to also be removed. See General Demolition Note 6 Sheets AD102 AD104

& AD106

Page 9 of 83 please verify Experience Modification Rate (EMR) is required for the bid opening?

If we can produce a certification on insurance letterhead, is the form on page 10 Pre-award Contractor Safety and Environmental Record Evaluation Form still required for a submission at the time of bid opening?

EMR is required.

Please submit information with insurance letter.

13 Page 20 of 83 Please verify 852.219-75 General construction should be checked. Yes, General Construction (item 1.(ii)) Must be checked for this contract.

14 Please verify your DBW (IL20250008 04/25/2025) appears to be out of date, the new one from Lake County is: IL20250020 06/20/2025.

This updated after the solicitation was posted, an update is in Amendment 0001 and a second in Amendment 0002.

VHA Directive 1192.01 speaks to Health Care Personnel, Page 8(p) VA Contracting Officers: This section implies, “VA contracting officers responsible for on-site HCP contract will inform the contractors about this directive and its requirements.” However, this project is not an on-site contract for HCP. Section C page 3, indicated that flu season is between Dec 1 through March 31, please validate that is not a mandatory requirement per page 4 of the solicitation titled COMPLIANCE WITH VHA DIRECTIVE 1192.0.

Contracted personnel in this project will be located in Buiding 1. The issue of mandatory flu vaccinations is in following best practices here for the sake of the patients. B1 is an administrative building away from the main hospital and not likely to cause interaction with the patients.

The workers should stay on site and if they are not vaccinated, the directive is that they would be masked throughout the flu season if they leave the site for any reason and come in contact with any patients. If personnel have symptoms of flu, they should not interact with VA personnel or patients. The contractors that do get their flu shot do not require a mask.

16 Will the sign-in sheet from site visit be available in addendum? Yes, this is in the amendment 0001.

S06 - Att 1 A0002 - 556-24-102 Pre-Bid RFIs responses 14JUL25 2 of 7

17 Please clarify if a superintendent can be a dual hat to cover the requirements of SSHO?

This is already clarified in the specifications. See: 01 35 26 -

12. 1.7 "Site Safety and Health Officer" (SSHO) and "Competent Person"

The superintendent can act as the SSHO if VA determines them to have the proper qualifications and competency. The SSHO must remain on-site at all times during construction.

There is no case in which the SSHO can attend multiple projects at the same time.

18 If no to the question above, will the SSHO need to be full-time for this project? See answer to item 17

19 Please clarify if a superintendent can be a dual hat to cover the requirements of QA/QC? Superintendent may act as SSHO if qualified (see item 17) QA/QC can not be superintendent or SSHO.

20 If no to the question above, will the QA/QC need to be full time for this project?

QA/QC duties are typically fulilled by the PM if qualified or an outsourced licensed engineer. They should be available to complete the duties as laid out in the contract. If there is a line item for a full time QA/QC, they will be required to be onsite alongside the superintendent.

21 Can a superintendent be a triple hat to cover the requirements of SSHO and QA/QC? Absolutely not.

22 Please confirm if the current prevailing wages will be consistent for the life of the project with no escalation? Yes that is correct.

23 Is the use of temporary plastic wall panels (such as STARC panels) acceptable to meet ICRA requirements? If the panels are installed per the manufacturer's guidelines then inspected and approved by VA IC, yes.

24 Will shutdowns be required to be done during off hours or weekends?

Not always. Since this building is separate from the main hospital and there will be no personnel occupying the building, that requirement is rather moot. The exception would come if any utility shutdowns affect the rest of the facility and not solely building 1.

25 Will a full-time fire watch be required during activities such as cutting and welding?

How long after such activities are completed?

See specification 01 35 26 - 19-22 1.16 Fire Safety Follow all requirements as outlined here.

26 Is there a particular vendor or contractor currently servicing and maintaining the Building Automation System or Temperature Controls System? Automated Logic Controls (ALC)

27 Please confirm if we will be allowed to keep a locked storage container or conex box within the grounds. You will have an entire building for storage throughout the project. No, there is no need for an additional conex box.

28 Will this project requires phasing to maintain occupancy in any part of the building or will the contractor have full access for demolition activities?

The building will not be occupied at time of demo/abatement.

29 Are there any power, mechanical, telecommunications, etc extending from or passing through this building that should be noted to keep active?

See the drawings and specs for utilities that must remain active.

S06 - Att 1 A0002 - 556-24-102 Pre-Bid RFIs responses 14JUL25 3 of 7

30 To allow sufficient time to review responses and prepare our bid we kindly request that you please extend the bid date.

Due date was extend out to 7/24/25 in Amendment 0001.

The existing 4020 panel is obsolete and should be upgraded, as it does not support synchronization and cannot accommodate additional internal cards required for the new design.

Would you like to proceed with upgrading the panel at this time?

If not, and you still want the strobes to be synchronized, all signal circuits will need to be connected to new NAC panels.

In that case, the main panel will only support the addressable devices.

See specs: 28 31 00 - 11 2.4 Fire Alarm Control Unit(FACU) A.

32 Under Summary Of Work (02 82 11-3). Item 4 Special Wastes:

Are the Universal Wastes to be packaged by the Contractor and then turn over to the VA for disposal/recycling? Duplicate: See item 5

Under Variations In Quantity (02 82 11-4) Item A:

Quantities at +/- of 10% are not change order amounts?

Contractor shall figure an additional 10% of spec quantities in contract price and timeframes?

Duplicate: See item 6

Under 1.5 Applicable Codes and Regulations (02 82 11-16) Item B: Asbestos Abatement Contractor Responsibility:

Is the Asbestos Contractor responsible for hiring an independent CPIH/CIH to oversee abatement activities as well as perform sampling/analytical?

Duplicate: See item 7

35 Under 3.1 Regulated Area Preparations (02 82 11-45) Item B: Signage and Power Management #2. The Contractor is responsible to shut down and lock out/tag out electric power to the regulated area? Is the Contractor to provide its own electrician? Duplicate: See Item 8

Under 3.1 Auxiliary Generator (02 82 11-48) Item 7: Says if the building is occupied during abatement provide an auxiliary gasoline/diesel generator…?

Will the building be occupied during demolition or abatement?

Duplicate: See Item 9

37 Under Lead Based Paint Removal (02 83 33.13-14) Item D Waste Collection:

All lead contaminated materials are to be placed in drums? Duplicate: See Item 10

38 Under Demo: Does plaster ceilings stay where acoustical ceiling tile is removed? Duplicate: See Item 11

39 Demo 02 41 00 – 3, requirements 1.4 Utilities Services Where are the outside utility lines to abandoned and removed?

No exterior work in scope. All utilities are to be capped inside building at wall/foundation entry.

Is the crawl space considered a confined space?

The dirt in the space is currently not level, is the Contractor responsible for removing the uneven soil/dirt to ensure that the liner has a tight seal?

Yes and Yes.

41 Are we required to use chemical removal of the asbestos mastic, even though we can remove it cheaper by mechanical methods and this will give the floor a better quality. Yes, mechanical means are prohibited.

Drawing HA101 – Keyed note H10 (purple high light) refers to “non-ACM vinyl sheet flooring, adhesive and filler with underlying asbestos black mastic”.

This area is on the west side of the floor, and we did not have access to this area at the site visit.

This vinyl sheet flooring also appears to be on the walls of this space.

Is the ASBESTOS contractor to remove this as asbestos?

Yes, the abatement contractor should remove this asbestos as well.

43 Can another site visit be arranged to visit the basement crawl spaces and the level 1 west area that we did not have access to. No additonal site vists will be scheduled at this time.

44 Level 1 west area also has Keyed note K17 which has plaster ceiling we need to demo for acm duct pin insulation removal.

Plaster ceilings to also be removed. See General Demolition Note 6 Sheets AD102 AD104

& AD106

S06 - Att 1 A0002 - 556-24-102 Pre-Bid RFIs responses 14JUL25 4 of 7

45 Under Summary Of Work-(02 82 11-3). Item 4 Special Wastes:

Are the Universal Wastes to be packaged by Contractor and then turn over to the VA for disposal/recycling? Duplicate: See item 5

Under Variations In Quantity (02 82 11-4) Item A:

Quantities at +/- of 10% are not change order amounts?

Contractor shall figure an additional 10% of spec quantities in contract price and timeframes?

Duplicate: See item 6

Under 1.5 Applicable Codes And Regulations (02 82 11-16) Item B: Asbestos Abatement Contractor Responsibility:

Is the Asbestos Contractor for hiring an independent CPIH/CIH to oversee abatement activities as well as perform sampling/analytical?

Duplicate: See item 7

Under 3.1 Regulated Area Preparations (02 82 11-45) Item B: Signage and Power Management #2.

The Contractor is responsible to shut down and lock out/tag out electric power to the regulated area?

Contractor to provide our own electrician?

Duplicate: See Item 8

Under 3.1 Auxiliary Generator (02 82 11-48) Item 7:

Says if the building is occupied during abatement provide an auxiliary gasoline/diesel generator……..?

Will the building be occupied during demolition or abatement?

Duplicate: See Item 9

50 Under Lead Based Paint Removal (02 83 33.13-14) Item D Waste Collection:

All lead contaminated materials are to be placed in drums? Duplicate: See Item 10

51 Under Demo: Does plaster ceilings stay where acoustical ceiling tile is removed? Duplicate: See Item 11

52 Can the Superintendent fulfill the Quality Control Manager (QCM) role? Duplicate: See item 19 53 Can the Superintendent fulfill the Site Safety & Health (SSHO) role? Duplicate: See item 17

54 Is fire alarm equipment required to be tested and re-certified at the end of the project? See specifications(28 31 00) for fire alarm certifications and testing requirements.

55 Will the VA provide laydown/storage areas? If so, where will they be located? Building 1

56 Will the VA provide an area for a dumpster? If so, where will that be located?

Building 1, coordinate with COR for placement. Since the building will be unoccupied, the current dumpster location and loading dock will be best suited for these locations.

57 Are CAD files available for all of the issued drawings? Or will they be available after award is made? CAD files are available. They will be shared as requested after award. Revit model is also available.

For asbestos abatement, please confirm that contractor will only be responsible for monitoring within contract work area, and VA will monitor outside of construction area. Abatement monitoring is conducted by the VA Task Order.

Will the VA be providing an electronic submittal program, or is it expected that the general contractor provides this? Are there programs or software that are acceptable? VA has a contract for Submittal Exchange

60 Are there any requirements regarding photographic documentation? Please confirm if this will be required as part of this project?

If required, must this be a 3rd party service? Or can it be performed inhouse by general contractor?

Photographic documentation falls under daily logs. This is not required to be a 3rd party service.

END of RFI's

S06 - Att 1 A0002 - 556-24-102 Pre-Bid RFIs responses 14JUL25 5 of 7

Drawing sent for Question 2 at 1/16" Scale

Drawing sent for Question 2 at .08759" Scale

S05 - Pre-Bid RFIs 556-24-102 B1 Interior Demo question 60_combined responses 14JUL25.pdf
S05 - Pre-Bid RFIs 556-24-102 B1 Interior Demo question 60_combined responses 14JUL25 attachments.pdf