This document is Solicitation Attachment 11 for Safety or Environmental Violations and Experience Modification Rate for Solicitation 36C25224R0015, which is a Multiple Award Task Order Contract (MATOC) opportunity for the repair of parking lots at the Iron Mountain VA Medical Center.
The attachment requires all bidders/offerors to submit information on their past safety and environmental records, including any OSHA or EPA violations within the past 3 years and their current Experience Modification Rate (EMR) from their insurance carrier. If a bidder's EMR is above 1.0, they must provide an explanation from the insurance carrier. Self-insured contractors or those without an EMR on insurance letterhead must obtain the rating from the National Council on Compensation Insurance (NCCI). This information, along with other data from government systems, will be used to make an initial determination of responsibility. This requirement applies to all subcontractors as well. The attachment includes a Pre-Award Contractor Safety and Environmental Record Evaluation Form for bidders to complete.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25224R0015 2024-06-21 FINAL_amended.pdf | ||
| 36C25224R0015 0002.docx | DOCX document | |
| 585-23-106 sidewalk detail.pdf | ||
| 36C25224R0015 0001.docx | DOCX document | |
| S02 SOL-Att-01-SEED PROJECT SOW Repair Parking Lots.pdf | ||
| S02 SOL_Att09_SEED PROJECT Prints.pdf | ||
| S02 SOL-Att-06 Past Performance Client Questionnaire.docx | DOCX document | |
| S02 SOL_Att08_SEED PROJECT Specs Repair Parking Lots.pdf | ||
| S02 SOL_Att07_SEED PROJECT Pricing Schedule.docx | DOCX document | |
| S02 SOL-Att-03 Financial Disclosure Questionnaire.docx | DOCX document | |
| S02 SOL-Att-11 Contractor Safety and EMR.docx | DOCX document | |
| S02 SOL-Att-04 Contractor Surety Limitations.docx | DOCX document | |
| S02 SOL-Att-12 VAAR 852.219-75 Certification 585-MATOC.docx | DOCX document | |
| S02 SOL-Att-05 Sub-contractor Info Consent.docx | DOCX document | |
| 36C25224R0015_2.docx | DOCX document | |
| S02 SOL-Att-02 Contractor General Information.docx | DOCX document | |
| S02 SOL-Att-10-SEED PROJECT WD MI20240117 06.14.2024.pdf |
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Multiple Award Task Order Contract (MATOC) 36C25224R0015 Solicitation Attachment 11 Safety or Environmental Violations and Experience Modification Rate
All Bidders/Offerors shall submit information pertaining to their past Safety and Environmental record. The information must contain a certification that the bidder/offeror has no more than three (3) serious, or one (1) repeat or one (1) willful OSHA or any EPA violation(s) in the past three years. If such certification cannot be made, a Bidder/Offeror shall explain why and submit as much information as possible regarding the circumstances of its past safety and environmental record, including the number of EPA violations and/or the number of serious, repeat, and/or willful OSHA violations, along with a detailed description of those violations.
All Bidders/Offerors shall submit information regarding their current Experience Modification Rate (EMR). This information shall be obtained from the Bidder’s/Offeror’s insurance carrier and be furnished on the insurance carrier’s letterhead. If a Bidder/Offeror’s EMR is above 1.0, Bidder/Offeror must submit a written explanation of the EMR from its insurance carrier furnished on the insurance carrier’s letterhead, describing the reasons for the EMR, and the anticipated date the EMR may be reduced to 1.0 or below.
Self insured contractors or other contractors that cannot provide their EMR rating on insurance letterhead must obtain a rating from the National Council on Compensation Insurance, Inc. (NCCI) by completing/submitting form ERM-6 and providing the rating on letterhead from NCCI. Note: Self insured contractors or other contractors that cannot provide EMR rating on insurance letterhead from the states or territories of CA, DE, MI, NJ, ND, OH, PA, WA, WY, and PR shall obtain their EMR rating from their state run worker’s compensation insurance rating bureau.
If the NCCI cannot issue an EMR because the Bidder/Offeror lacks insurance history, Bidder/Offeror shall submit a letter indicating so from its insurance carrier furnished on the insurance carrier’s letterhead, and include a letter from the NCCI indicating that is has assigned Bidder/Offeror a Unity Rating of 1.0.
The above information, along with other information obtained from Government systems, such as the OSHA and EPA online inspection history databases, will be used to make an initial Determination of Responsibility.
This requirement is applicable to all subcontracting tiers, and prospective prime contractors are responsible for determining the responsibility of their prospective subcontractors.
Solicitation Attachment 11 Revision 2 Safety or Environmental Violations and Experience Modification Rate
Pre-Award Contractor Safety and Environmental Record Evaluation Form Company Name: ______________________________________________ Address: _____________________________________________________ Telephone: ______________________ Fax: ________________________ Email: _______________________________________________________ Contact: ______________________________________________________
1. Utilizing your OSHA 300 Forms, please complete the following information:
| Category |
| 2021 |
| 2022 |
| 2023 |
Number of man hours (jobsite and office).
Number of cases involving days away from work, restricted activity, or both (Column H and I of OSHA 300).
Days away, restricted, or transferred rate (# of days away, restricted, or transferred cases x 200,000/# of man hours) (DART Rate).
Number of serious, willful, or repeat violations from OSHA within the last 4 years. Please attach explanation for any violations.
Please attach copies of the following documents: OSHA 300 and 300a Forms. These forms can be accessed through the OSHA publications search page: http://www.osha.gov/pls/publications/publication.html.
| 2. | Provide your six-digit North American Industrial Classification System (NAICS) Code for this acquisition: __________________________________ |
| 3. | Who administers your company’s Safety and Health Program? __________________________________ |
| 4. | Company’s Insurance Experience Modification Rate (EMR): _____________ |