Wausau CBOC 11/15/2019 Appendix E: CBOC IT Specifications
LEASE NO. 36C252-20-R0001 LESSOR: ______ GOVERNMENT: ______ Page 1 of 5
Tomah VAMC OI&T Construction Standards 21 Jun 19
Overview.
The following is a guide designed to articulate OI&T requirements for new build or major remodeling projects. In some areas this document peripherally addresses Electronics and Biomed requirements, but those shops should be contacted directly to independently identify any requirements they have above and beyond the data presented here. Where applicable, the page number of the referenced document where the data can be found is identified with all bullets following also on the same page until a new page number is noted.
References.
• OIT Design Guide, Feb 2011
• Physical Security Design Manual for VA Mission Critical Facilities, Jan 2015
• OIT Infrastructure Standards for Telecommunications Spaces V2.2, 19 Feb 19
• Physical Security Design Manual, January 2015
• Telecommunications and Special Telecommunications Systems Design Manual, Feb
• PG-18-9: Space Planning Criteria, Chapter 232: Office of Information Technology, 3
Oct 16
OIT Design Guide.
1. Locate Comm rooms interior to facility. Pg 2-8
2. Locate Comm rooms above the Base Flood Elevation.
3. Comm Rooms shall not be located in patient care areas and shall not be located beneath toilets, showers, laboratories, kitchens, sinks, open courtyards, planters, roof drain leaders, or other areas where water service is provided.
4. Provide dedicated room(s); active voice, data, and special systems equipment is not allowed to be installed in elevator penthouses or mechanical rooms. Pg 2-9
5. Any pipe or duct system foreign to the telecommunications installation shall not enter or pass through a comm room.
6. Water and smoke detection devices are required beneath access floors. Pg 2-11
7. Provide an automatic wet-pipe sprinkler system throughout the building, including all
Demarc Rooms, Main Computer Rooms, and Telecommunications Rooms. Note:
Standard response fusible link sprinklers are permitted to be used in the Computer Area. These sprinklers will lessen the chance of a sprinkler being accidentally broken and will still provide structure protection since a standard response head is more robust and harder to break than a typical glass bulb quick response sprinkler.
Wausau CBOC 811/152019 Appendix E: CBOC IT Specifications
LEASE NO. 36C252-20-R0001 LESSOR: ______ GOVERNMENT: ______ Page 2 of 5
8. Provide clean agent fire suppression for the Main Computer Room and Backup Computer Room Pg 2-12
9. Maintain minimum of 20 foot separation (horizontally and vertically) from any high-induction electrical sources, i.e., electrical transformers, large motors, generators, radio transmitters, induction heating devices, photocopying equipment, radiology machines, variable frequency drives, and arc welding equipment. Pg 2.13
10. A minimum of one Telecommunications Room (TR) per floor is required, as is a minimum of one Telecommunications Room per 15,000 square feet of building gross floor area served.
11. Fiber/Copper Distribution. Telecommunications Rooms will be serviced by a minimum of 24 strands of Single Mode Fiber terminated LC and home run to the Main Computer Room (Bldg 32.) High computer density floors / facilities will likely require additional strands. Pg 2.18
NOTE: This fiber requirement does not include support for Cable TV or Patient Wireless systems.
Additionally, each Telecom Room will be serviced by a minimum of 50 pairs of CAT 3 home run to the Demarc Room in Bldg 32. All copper will be terminated through lightning protection.
12. Alternate Data Path Requirements. All Main telecom closets will have an alternate 12 strand single mode fiber feed to the Alternate Server Room in Building 408, Room 1884. The fiber will be terminated in a patch panel with LC connections at both ends.
13. Multiple Telecommunications Rooms are required if the horizontal cable length, routed parallel and perpendicular to the building geometry, between the Telecommunications Room and the furthest telecommunications outlet exceeds 262 feet (80 M). Pg 2-20
14. Telecommunications Rooms shall be aligned vertically (stacked) on multi-floor buildings.
15. HVAC. Maintain continuous and dedicated environmental control with limits for Telecommunications rooms of 65-80 degrees Fahrenheit and 40-60% humidity.
Server rooms will be maintained at 65-75 degrees Fahrenheit and 40-60% humidity.
If emergency power is available, connecting room HVAC to emergency power.
Maintain positive pressure with a minimum of one air change per hour. As part of the building energy management system, the Comm Room HVAC systems shall be alarmed for power loss, high and low temperature, high and low humidity, smoke detection, HVAC unit compressor failure (if applicable), and water flooding. Pg 2-21
16. Racks:
16.1. Each Telecommunication Room shall be equipped with a minimum of two racks. Racks will be open floor-mount, two-post systems that will support 19” rack-mountable equipment. The racks will be approximately 7 feet tall and will
LEASE NO. 36C252-20-R0001 LESSOR: ______ GOVERNMENT: ______ Page 3 of 5 have both horizontal and vertical wire management. An example of an appropriate rack can be found at: http://catalog.chatsworth.com/rack-systems/two-post-racks/35-x-3-889-mm-x-80-mm-universal-rack/46763-703.
After you get to website, click “Documents and Tools”, then “Cut Sheet” for picture and more details.
16.2. High computer density floors / facilities may require up to four open racks;. On two racks are for horizontal passive distribution equipment, i.e., patch panels.
The other racks on are for active distribution equipment and termination of fiber backbone cables.
16.3. Power management will be included in each rack with two power supplies and associated, separate power distribution strips.
16.4. Vertical wire management will be attached to both sides of the rack and will run the full height of the rack. The approximate dimensions of the vertical wire management should be 84x6x24.5 and have doors that open on the front and back. The horizontal wire management will be approximately 2U in height and will run the width of the rack. They will have snap on covers over the front.
These will be installed between switches, patch panels, and other rack mountable devices. If angled patch panels are installed, then horizontal wire management is not required between them. A minimum of 5 per rack will be provided. An example of appropriate vertical and horizontal cable management can be found at: http://catalog.chatsworth.com/cable-management/vertical-cable-management/evolution-g2-double-sided-vertical-cable-manager/35521-
703. After you get to website, click “Documents and Tools”, then “Cut Sheet” for picture and more details.
17. Power.
17.1. UPS’s will be provided to all communications rooms with the following standards for full rated output: Demarc Room—4 hours of service (9.3.1.3), Main Computer Room—20 minutes of service (9.3.2.3), Telecommunications Rooms—4 hours of service (9.3.3.2)
17.2. Main Computer Rooms and Demarc rooms shall be provided with generator-backed HVAC service. 9.3.3.1
18. Additional Locally-Derived Telecom Room Standards.
18.1. Minimum size shall be 10’ x 10’ for two racks, 10’ x 13’ for three racks, and 10’ x 15’ for four racks.
18.2. The door to telecommunication closets will be offset to one side of the room.
18.3. Racks will be located perpendicular to the door entrance with them centered in the room between the door and the back wall and shifted to the side away from the door.
18.4. Room height shall be a minimum of 9’ above finished floor.
http://catalog.chatsworth.com/rack-systems/two-post-racks/35-x-3-889-mm-x-80-mm-universal-rack/46763-703 http://catalog.chatsworth.com/rack-systems/two-post-racks/35-x-3-889-mm-x-80-mm-universal-rack/46763-703 http://catalog.chatsworth.com/cable-management/vertical-cable-management/evolution-g2-double-sided-vertical-cable-manager/35521-703 http://catalog.chatsworth.com/cable-management/vertical-cable-management/evolution-g2-double-sided-vertical-cable-manager/35521-703 http://catalog.chatsworth.com/cable-management/vertical-cable-management/evolution-g2-double-sided-vertical-cable-manager/35521-703
LEASE NO. 36C252-20-R0001 LESSOR: ______ GOVERNMENT: ______ Page 4 of 5
18.5. All walls shall be lined with ¾” thick fire-rated plywood backboards, 4’ high, with the bottom located 3’ above the finished floor and painted white (4’ x 8’ sheets hung horizontally.)
18.6. Rooms shall not have a suspended ceiling.
18.7. Room entrances must have a minimum unobstructed area of 48” directly in front of the room door.
18.8. Room shall be enclosed with fire-rated construction IAW NFPA 75.
18.9. Rooms shall be provided with temperature and humidity monitoring and alarms.
18.10. Rooms shall be provided with one dedicated 208v circuit terminated at and grounded to each equipment rack. A minimum of four dedicated 120v circuits will be spaced on the walls around the room and terminated in four gang boxes.
A minimum of two 120v four gang box circuits will be placed (spaced out) on any wall longer than 10’.
18.11. Cable Colors.
18.11.1. Cables from room data jacks to the patch panel will be BLUE.
18.11.2. Guest Internet cables will be PURPLE.
18.11.3. VA Wireless patch panel cables will be ORANGE.
18.11.4. PC, Phone, and VTC patch panel cables will be YELLOW.
18.11.5. Electronics patch panel cables will be BLUE.
18.11.6. Biomed patch panel cables will be RED.
18.11.7. Johnson Controls / HVAC patch panel cables will be PINK.
18.12. Telecom Closets will have direct access at all times and will not be located off of conference rooms, offices, or other rooms whose occupancy would prevent access.
19. Additional Locally-Derived New Build / Remodel Standards for Data Drops and Cabling.
19.1. Data/power boxes will be provided and centered in each wall not containing a door in all occupied rooms (normally 3 boxes / room.) For walls longer than 15’, additional boxes will be located no greater than 15’ apart. Data/power boxes will also be installed on any wall containing a door with 8’ or more of free wall space.
19.2. Data boxes will consist of four RJ45 ports.
19.3. All data jacks will be wired back to the
Telecommunications Room via Cat 6A cables.
19.4. A data box meeting the standards
above will be installed in all locations identified for centralized printing stations.
LEASE NO. 36C252-20-R0001 LESSOR: ______ GOVERNMENT: ______ Page 5 of 5
19.5. CAT3/6A Patch Panel Specifications. Patch panels will be 48 port/connector angled devices, 2RUs in height—See picture at right for example.
19.6. Patch Panel and Room Wall Jack Labeling Standards. 48 Port RJ-45 Patch Panel will be mounted starting at the top of the 19” Rack. The top/1st Patch Panel will be marked as “A”, then each Patch Panel installed under it will continue with markings: B, C, D… Additionally, patch panel ports will be labeled with the room number or other identifying information to indicate where the patched cable originates. Room Wall RJ-45 Jacks will correspond with the Rack RJ-45 Jack Plates (i.e. A-1, A-2, B-1, B-2…).
During installation the Technician will terminate the Room Wall RJ-45 Jacks in a Left to Right, Top to Bottom configuration as indicated in the figure to the right.
Physical Security Design Manual for VA Mission Critical Facilities.
20. Wireless. Provide a wireless data access system or install infrastructure (cabling) placed for later system installation. 9.3.4 (Wireless layout design to be provided by
OI&T)
Other.
21. Contractor will provide “As Built” drawings for all IT installed cabling and equipment.
Drawings will include, as a minimum, digital floorplans with data jack locations and identifications annotated.
22. Contractor will provide results of all fiber/copper cable and port testing.
OIT Infrastructure Standards for Telecommunications Spaces V2.2, 19 Feb 19
23. Current design standard is for Cat 6A horizontal distribution cabling. Pg 10, Table 3.
24. All racks will be grounded / bonded IAW ANSI/TIA-607-C. Pg 37, Table 18
25. Power Distribution Units (power strip) and UPS standards: See Table 28 and 29 on pgs 58-59.
26. Cable Tray standards: See table 31, pg 62.
A-1 A-2
A-3 A-4
Transforming Health Care for Veterans, Revolutionizing Health Care for All
OEHRM Site Infrastructure Requirements November 19, 2019 | Version 1.1
OEHRM SITE INFRASTRUCTURE REQUIREMENTS | ii
John Short Chief Technology & Integration Officer
Veterans Affairs Office of Electronic Health Record Modernization
Paul Tibbits, MD Executive Director, Office of Technology Integration
Veterans Affairs Office of Information and Technology
Edward A. Litvin, PE, CHFM Deputy to the Assistant Deputy Under Secretary for Health, Administrative Operations
Veterans Health Administration
OEHRM SITE INFRASTRUCTURE REQUIREMENTS | iii
Table of Contents 1 Overview
2 Requirements
2.1 Wide Area Networking (WAN)
2.1.1 WAN Requirements
2.1.2 WAN Implementation Specifications and Considerations
2.2 Local Area Networking (LAN)
2.3 Wireless LAN (WLAN) Design Requirements
2.4 Power and Space Design Requirements
2.5 Heating, Ventilation, and Air Conditioning (HVAC) Design Requirements
2.6 End-User Devices (EUD)
2.7 Voice Over Internet Protocol (VOIP) Device Requirements
2.8 Medical Device Requirements
2.9 Physical Security Design Requirements
2.10 Joint Security Architecture Design Requirements
Appendix A: Acronyms
Appendix B: References
OEHRM SITE INFRASTRUCTURE REQUIREMENTS | 1
1 Overview The Office of Electronic Health Record Modernization (OEHRM) Program is a large-scale, commercial Electronic Health Record (EHR) implementation. As such, the Department of Veterans Affairs (VA) must ensure that the new EHR is supported by both proper Information Technology (IT) infrastructure as well as physical (i.e., facilities) infrastructure. This document is intended to outline the current set of OEHRM requirements. Specific items evaluated within this document are: Wide Area Networking (WAN), Local Area Networking (LAN), Wireless LAN (WLAN), Power, Heating, Ventilation, and Air Conditioning (HVAC), End User Devices (EUD), Networking and Voice Over Internet Protocol (VOIP).
2 Requirements Sections 2.1 through 2.9 outline the initial set of requirements for support to OEHRM deployment at Initial Operating Capabilities (IOC) and subsequent wave deployments. These high-level requirements need to be communicated across all stakeholders.
This document provides requirements in addition to VA’s existing design guides and enterprise IT requirements. Additional requirements will supplement specific areas, such as wireless networking, that may require further details. Other site-specific requirements may be issued that develop from evaluation of individual locations. This document will be updated annually over the 10-year deployment schedule to incorporate both technology improvements and lessons learned from deployments. In any area of conflict, the more stringent of the two standards will apply.
2.1 Wide Area Networking (WAN)
2.1.1 WAN Requirements
WAN requirements are listed in the following table.
Table 1. VA WAN Requirements for Multiple Locations
Location Community Based Outpatient Clinics (CBOCs) and other non- VA Medical Centers (VAMCs)
Specification
Minimum single 100 Megabits per second (Mbps) (1 x 100 Mbps) circuit with ≥ 50 Mbps committed information rate (CIR) or bandwidth allocation of peak usage plus 50%, whichever is greater for IOC, Wave 1, 2, and 3
Notes After installation, OIT, OEHRM, and Cerner will reassess these sites and the enterprise
OEHRM SITE INFRASTRUCTURE REQUIREMENTS | 2
Location VAMCs
Specification
Minimum dual 1 Gigabits per second (Gbps) interface available with ≥ 500 Mbps CIR (2 x 500 Mbps) circuits or bandwidth allocation of peak usage plus 50%, whichever is greater for IOC, Wave 1, 2, and 3. After that OIT, OEHRM, and Cerner will reassess for these sites and the enterprise
Notes After installation OIT, OEHRM, and Cerner will reassess for these sites and the enterprise
Location VAMCs
Specification
Shall have end-to-end, geographically diverse and carrier-diverse circuits with minimum fiber pathways separation:
service provider public rights-of-way 75 ft, Egress 20 ft, and cabinet 10 ft. See below Figure 1 The preferred entry points 180° apart, or 90° acceptable (protected preferred, unprotected acceptable), with the caveat of VHA providing space; all variances to be approved by OEHRM Chief Technology & Integration Officer. See below Figure 2 (when ordering diverse circuits, it is standard acceptable practice to request diversity, provide the alternate diverse carrier, and request route map to validate route diversity)
Location VA Enterprise Cloud (VAEC), Austin Information Technology
Center (AITC), Philadelphia Information Technology Center
(PITC)
Specification Dual 10 Gbps circuit with 1 Gbps CIR minimum from the facility to the Cerner Data Center (2 x 1 Gbps)
OEHRM SITE INFRASTRUCTURE REQUIREMENTS | 3
The physical configuration of circuits entering medical facilities is shown in the following figure.
Figure 1: Minimum Geographic Diversity Circuits with Entry Points
OEHRM SITE INFRASTRUCTURE REQUIREMENTS | 1
Figure 2: Preferred Geographic Diversity Circuits with Entry Points
2.1.2 WAN Implementation Specifications and Considerations
A. Details on Quality of Service (QoS) can be reference in the existing VA document: *Veterans Affairs Enterprise Infrastructure Standard: Quality of Service (QoS)
B. Active-Active High Availability (HA) Redundancy in accordance with facility type per the VA Enterprise Local Area Network (LAN) Technical Architecture Standard Version 2.1, February 13, C. Encryption Protocol: OEHRM requires an end-to-end WAN encryption solution such that traffic from VA locations can go directly to Cerner enclave without having the encryption broken and re-encrypted
D. Power / Environmental / Switching / Topology TIA-942Tier 3 E. Performance Service Level Agreements (SLA) 99.99% (per Networx SLA)
2.2 Local Area Networking (LAN)
A. Category 6A cable (CAT6A) unshielded twisted pair (UTP), with additional slack, as required, to relocate if telecommunications room (TR) wiring closet pending move. Otherwise, normal Building Industry Consulting Service International (BICSI) Standards; CAT6 will be grandfathered;
OEHRM SITE INFRASTRUCTURE REQUIREMENTS | 2
CAT5e is addressed per Electronic Health Record Modernization Cabling Infrastructure (VIEWS 01426385) per the Assistant Secretary and Chief Information Officer for Office of Information and Technology decision memorandum, September 23, 2019
1. Additional cabling (for closet relocation) in ceiling terminated to a CAT6A RJ-45 patch panel in closet and CAT6A RJ-45 Jack at wall plate
2. Consideration must be given to not add additional room cabling that might interfere with cooling/airflow or other environmental factors
3. All new cabling in the building will come with an electronic and paper as-built configuration, for the cable plant in AutoCAD
4. Each TR wiring closets cable plant as-built configuration will be maintained in a folder on the back of the door
B. Compliant with the BICSI standards (ANSI/NECA/BICSI 568, Standard for Installing Commercial Building Telecommunications Cabling and ANSI/TIA-1179-A Healthcare Facility Telecommunications Infrastructure for new installations)
C. 1 GbE connectivity to desktops, and other EUD D. Utilize high-performance network switches with low latency and minimal packet loss for appropriate infrastructure job function and growth per VA business growth forecast. (No site should go-live with any switch that is within one (1) year of Last Day of Support (LDoS) or End of Software Maintenance (EoSW))
E. A cable analyzer will be used to determine cable length (max cable length 90M/295Ft), and certify that cable meets or exceeds TIA-EIA-568-D
F. In areas where there are environmental issues (e.g., steam pipes, lack of ventilation, etc.), the use of thermal curtains and additional vents will be considered as a temporary alternative, if not permanent resolution
G. TR Wiring Closet Environmental Monitoring Solution for temperature and humidity (e.g.
Uninterruptible Power Supply (UPS) with Network Management Card, Temperature & Humidity Sensor, and Central Monitoring by way of a single network connection is required using a RJ-45 Patch Cable) Note: It is the responsibility of Facility Engineering to monitor and control the TR wiring closet environment. They must select the proper unit to accomplish the required monitoring
H. LAN topology from OIT I. Intra-building Fiber (Horizontal and First Level Backbone)
1. Performance Category: OM4 Laser Enhanced to 40 GbE; OM3 will be grandfathered
2. Performance Specifications: Laser Optimized 50/125 μm fibers with effective modal bandwidth of at least 4,700 MHz∙km at 850 nm
3. Mode: Multimode
4. Smoke Rating
i. Riser cable for vertical runs through floors
ii. Plenum rated for plenum spaces
iii. Not rated for other applications
iv. Or as per AHJ requirement
5. Jacket Color: Aqua
OEHRM SITE INFRASTRUCTURE REQUIREMENTS | 3
6. Termination Method: Pre-terminated with MPO (Long run cables and campus network cables will have terminations completed in the field, as required)
7. Strand Count: 12 or 24 per assembly
8. Bundling: Loose Tube
9. Polarity: Straight (or Type A-Key up one end, and key down on the other)
J. Campus Area Network (CAN) connection by Single Mode (SM) OS2 Fiber 10 GbE or better for building-to-building
1. Single Jacket Non-armored Loose Tube fiber cable for running in conduit
2. Armored fiber for direct-buried or aerial runs
3. All dielectric
4. Outside Plant, Communications Multipurpose Cable, Riser (CMR) “riser-rated cable”
Rating
5. 96 Count (if not enough room, smaller count cables can be used)
6. Field-Terminated
K. All CAN fiber connections may be homerun back to intermediate distribution switch/fiber distribution panel (FDP). Fiber connections at building should not be run through additional buildings unless pass-through or mesh; no “daisy chain”"
L. CAN – minimum of 10 Gbps LAN links or Small Coarse wavelength division multiplexing (CWDM);
VHA responsible for Fiber and OEHRM will fund small form pluggable (SFP); NOTE: Not required for Go Live at IOC facilities
M. Connections for Core, Distribution and uplink from Access Switch shall provide a minimum of 10 GbE Fiber or better; VHA responsible for Fiber and OEHRM will fund small form pluggable (SFP);
NOTE: Not required for Go Live at IOC facilities
N. Power / Environmental / Switching / TopologyTIA-942 Rating 3 O. Performance Service Level Agreements (SLA) 99.9% excluding scheduled downtime; assumption facility infrastructure supports the SLA P. Network Infrastructure devices connected to UPS and on Emergency Power / Backup Generator
2.3 Wireless LAN (WLAN) Design Requirements
This section covers VA secure WLAN. Detailed WLAN requirements will be contained in a supplemental document, VA OEHRM Wireless Network Infrastructure - Requirements Specification Document.
A. 802.11ac Wave 2 & when commercially available next-generation 802.11ax B. Power over Ethernet (PoE), 802.3at PoE+ C. CAT6A cable to access point (AP) D. VAMC POE Switch connected to UPS and on Emergency Power/Backup Generator E. CBOC POE Switch connected to UPS with 30-minute run-time F. Compliant with VA Telecommunications and Special Telecommunications Systems Design
Manual and TIA TBS-162-A, Telecommunication Cabling Guidelines for Wireless Access Points
OEHRM SITE INFRASTRUCTURE REQUIREMENTS | 4
2.4 Power and Space Design Requirements
A. Required Forward Deployed Server Power and Space Design Requirements
1. Specific power requirements for each Forward Deployed Server Stack are specified in the signed IOC Forward Deployed Rack Power Memo, dated April 19, 2019
2. As a guideline, previous installations required 208V,60A supply of 9.984W per circuit (with 2N redundancy) per stack and a total of two stacks. The maximal power required for each stack is estimated to be 14.1kW
3. Racks will be installed at the VAMC Server Rooms only and not needed at leased facilities unless required by Cerner for biomedical equipment / systems
4. Forward Deployed Server cabinets provided by Cerner (45RU, 24" nominal width)
5. Site-specific cabinet requirements will be determined by Cerner and may deviate from this guidance B. UPS Functional Requirements
1. All UPS units to be functional and adequate in all Telecommunication Rooms (VAMC with 20-minute run-time; CBOC with 30-minute run-time) (Reference. The U.S.
Department of Veterans Affairs, Physical Security Design Manual (PSDM) for Mission Critical Facilities, January 2015)
2. All units within one (1) year of end of life by IOC (Go-Live) are to be replaced with new units
i. End of Life for stand-alone units assumed to be six (6) years from date placed into service
ii. End of Life for UPS batteries assumed to be three (3) years from date replaced C. VAMC – Per section 8.2.2 of the Telecommunications Design Manual, Emergency Power /
Backup Generator used in all Telecommunication Rooms Equipment in TR Wiring Closet shall be connected to the critical electrical branch, where required
D. New equipment install must comply with Single point grounding per ANSI/NECA/BICSI 607-C, Generic Telecommunications Bonding and Grounding (Earthing) for Customer Premises November 2015
E. The main facility power feed must meet additional power requirements listed above at paragraph 2.4.A.1
2.5 Heating, Ventilation, and Air Conditioning (HVAC) Design
Requirements
A. The new total cooling (N+1 Redundancy) shall be equal to the existing requirements plus the additional heat releases from the following additional equipment
1. Cerner Forward Deployed Server cooling requirements will be calculated based on the power requirements provided by Cerner in the IOC Forward Deployed Rack Power Memo, dated April 19, 2019
2. As a guideline, previous installations required 208V,60A supply of 9,984W per circuit (with 2N redundancy) per stack and a total of two stacks. The maximal power required for each stack is estimated to be 14.1kW
OEHRM SITE INFRASTRUCTURE REQUIREMENTS | 5
B. Room temperature and relative humidity values should adhere to the U.S. Department of Veterans Affairs Office of Construction & Facilities Management HVAC Design Manual, dated May 1, 2019
1. VA data center environmental requirements are classified as Environmental Class A1 per American Society of Heating, Refrigerating and Air-Conditioning Engineers (ASHRAE) TC9.9 modified for the VA operating environment, IT equipment inlet temperature range of 72°F to 81°F, humidity ≤ 60 percent
2. TR Wiring Closet Class B space temperature range 41°F to 95°F, relative humidity: 8 to 80%
C. Blank panels shall be installed in all open rack units, in Data Center cabinet and racks, to prevent hot exhaust air recirculating to the cold air equipment intake side of the rack. This requirement is shown in the following figure
Figure 2. Blanking Panel Applications
Reference: Section 3.1.3.1, Data Center Facility Environment Conditioning Standards, Figure 8, page 42, Office of Information & Technology (OIT) Infrastructure Standards for Telecommunications Spaces, Version 2.2, April 10, 2019
2.6 End-User Devices (EUD)
This section describes specifications for Desktop, Laptop, Tablet, Document and Scanner and Printers.
All EUDs must meet the recommended or greater requirement levels. EUD requirements to be further detailed in a supplemental OEHRM End User Device Requirements document
OEHRM SITE INFRASTRUCTURE REQUIREMENTS | 6
A. General EUD:
1. Processor: Dual or more Core Processor (i5, i7 or equivalent) running at 2.0GHz or greater, Support for AES-NI
2. RAM: 16GB DDR4 SDRAM 2,400MHz
3. Hard Drive: 512 GB NVMe PCIe M.2 SSD
4. Display/Graphics: Integrated High Definition (HD) graphics with of 512 MB shared memory or more provided, dedicated memory preferred, Dual Monitor Support
5. Monitor: 22” (minimum) or 24” (recommended), Resolution of 1920 x 1080 or higher and 32-bit color
i. Appropriate monitor size for locations where physical limitations restrict the use of recommended monitor sizes will be determined on a case by case basis
ii. Display size for laptops shall meet the end user’s requirements for their intended laptop use
iii. If a docking station is provided the docked monitor shall meet the requirements stated above
6. Network: Network Port 1 GbE, RJ-45. Wireless interface shall support 802.11a/n/ac
(2x2) and, a FIPS-140-2 encrypted communications and 5 GHz support
7. Peripheral: 101-key keyboard and mouse or equivalent
8. O/S: Windows 10 Pro 64 with Internet Explorer 11
9. Citrix Receiver: 14.9 or later as required by TRM
10. Access: PIV Card Reader
11. Other Software: VA Image as appropriate
B. Clinical Imaging-Diagnostic Viewing EUD
1. Processor: Intel Skylake Hexa Core w/HT Technology 3.7GHz or better
2. RAM: 32GB
3. Hard Drive: 512 GB PCIe NVMe M.2 SSD
4. Display/Graphics: Barco MXRT-5600 or NVIDIA Quadro P2000, Dual Monitor Support
5. Monitor:
i. 22” (minimum), Resolution of 1920 x 1080 or higher, and 32-bit color
ii. 27” monitors, Resolution of 2560 x 1440 or higher, total of 3 monitors is suggested for the optimal workflow, 2 for viewing images and 1 for charting
iii. Appropriate monitor size for locations where physical limitations restrict the use of recommended monitor sizes will be determined on a case-by-case basis
6. Network: Network Port - 1 GbE RJ-45. Wireless is not recommended
7. Peripheral: 101-key keyboard and mouse or equivalent
8. O/S: Windows 10 64-bit
9. Access: PIV Card Reader
C. Clinical Imaging-Technologist EUD:
1. Processor: Intel Skylake Quad Core w/HT Technology 3.0GHz or better
2. RAM: 16GB
3. Hard Drive: 512 GB PCIe NVMe M.2 SSD
4. Display/Graphics: Barco MXRT-5600 or NVIDIA Quadro P2000, Dual Monitor Support
5. Monitor:
OEHRM SITE INFRASTRUCTURE REQUIREMENTS | 7
i. 22” (minimum), Resolution of 1920 x 1080 or higher, and 32-bit color
ii. 27” monitors, Resolution of 2560 x 1440 or higher
iii. Appropriate monitor size for locations where physical limitations restrict the use of recommended monitor sizes will be determined on a case-by-case basis
6. Network: Network Port - 1 GbE RJ-45. Wireless is not recommended
7. Peripheral: 101-key keyboard and mouse or equivalent
8. Operating system (OS): Windows 10 64-bit
9. Access: PIV Card Reader
2.7 Voice Over Internet Protocol (VOIP) Device Requirements
A. A POE Switch and Desktop phones feed to EUD B. VOIP Phone / Device capable of 1 GbE pass-through to support EUDs C. Zebra device require Session Initiation Protocol (SIP) trunk with dialing plan (two extension per device; one for the user and one for the device)
2.8 Medical Device Requirements
Additional Medical Device Requirements are to be determined by OEHRM in supplemental documentation
2.9 Physical Security Design Requirements
Rooms undergoing modifications and upgrades will comply with current physical security design requirements. References should be made to U.S. Department of Veterans Affairs Office of Construction & Facilities Management Telecommunications and Special Telecommunications Systems Design Manual, dated February 2016 and The U.S. Department of Veterans Affairs, Physical Security Design Manual (PSDM) for Mission Critical Facilities, January 2015
2.10 Joint Security Architecture Design Requirements
Specific requirement can be found in the OEHRM Joint Security Architecture (JSA) Requirements Specifications Document (RSD)
OEHRM SITE INFRASTRUCTURE REQUIREMENTS | 8
Appendix A: Acronyms
Acronym Description
AP Access point
AITC Austin Information Technology Center
ANSI American National Standards Institute
ASHRAE The American Society of Heating, Refrigerating and Air-Conditioning Engineers
BICSI Building Industry Consulting Service International
BTU British Thermal Unit
CAN Campus Area Network
CAT6A Category 6A cable
CBOC Community Based Outpatient Clinic
CIR Committed information rate
CMR Communications Multipurpose Cable, Riser
CWDM Coarse Wavelength Division Multiplexing
DoD Department of Defense
DWDM Dense Wavelength Division Multiplexing her Electronic Health Record
ELTE Ethernet Line Termination Equipment (a term of convenience)
EMCR Emergency Control Room
EoSW End of Software Maintenance
EUD End User Device
FDP Fiber Distribution Panel
Gbps Gigabits per second
HA High Availability
HD High Definition
HVAC Heating, Ventilation and Air Conditioning
OEHRM SITE INFRASTRUCTURE REQUIREMENTS | 9
ICT Information and Communications Technology
IOC Initial Operating Capabilities
IT Information Technology
ITU-T International Telecommunications Union – Transport Standardization Sector
LAN Local Area Network
LDoS Last Day of Support
MAC Media Access Control layer
MAN Metropolitan Area Network
Mbps Megabits per second
MDA Main Distribution Area
MIB Management Information Base
NECA National Electrical Contractors Association
OEHRM Office of Electronic Health Record Modernization
OI&T Office of Information & Technology
OS Operating system
OTN Optical Transport Network (defined by ITU-T)
PACs Physical Access Control Systems
PCR Police Control Room
PCS Physical Coding Sublayer
PHY Physical layer comprised of the PCS + PMA + PMD sublayers
PII Personally Identifiable Information
PITC Philadelphia Information Technology Center
PIV Personal Identification Verification
PMA Physical Medium Attachment sublayer
PMD Physical Medium Dependent sublayer
POE Power Over Ethernet
OEHRM SITE INFRASTRUCTURE REQUIREMENTS | 10
QoS Quality of Service
SDH Synchronous Digital Hierarchy (ITU-T term)
SFP Small Form Pluggable
SIP Session Initiation Protocol
SLA Service Level Agreements
SM Single Mode
SMS Security Management System
SONET Synchronous Optical Network (ANSI term)
TR Telecommunications room
UPS Uninterruptible Power Supply
UTP Unshielded twisted pair
VA Department of Veterans Affairs
VAEC VA Enterprise Cloud
VAMC VA Medical Centers
VOIP Voice Over Internet Protocol
WAN Wide Area Network
WIS WAN Interface Sublayer (distinguishes the WAN PHY from the LAN PHY)
WLAN Wireless LAN
OEHRM SITE INFRASTRUCTURE REQUIREMENTS | 11
Appendix B: References The following were used as references for this document:
1. U.S Department of Veterans Affairs Office of Construction & Facilities Management Telecommunications and Special Telecommunications Systems Design Manual February 2016 https://www.cfm.va.gov/til/dManual/dmTelecomm.pdf
2. U.S Department of Veterans Affairs Office of Information & Technology (OIT) Infrastructure Standards for Telecommunications Spaces Version 2.2 April 10, 2019 https://vaww.vashare.oit.va.gov/sites/itops/svcs/sma/BCM/Supporting_Documents/Infrastruct ure%20Standards%20for%20Telecommunications%20Spaces.pdf
3. ANSI/NECA/BICSI 568, Standard for Installing Commercial Building Telecommunications Cabling
4. ANSI/TIA-1179-A Healthcare Facility Telecommunications Infrastructure for new installations
5. TIA TBS-162-A, Telecommunication Cabling Guidelines for Wireless Access Points
6. ANSI/NECA/BICSI 607-C, Generic Telecommunications Bonding and Grounding (Earthing) for
Customer Premises November 2015
7. Joint Enterprise Architecture Working Group (J-EAWG) Architecture 1.0
8. OEHRM End User Device Deployment Plan
9. VA OEHRM Wireless Network Infrastructure - Requirements Specification Document - v 1.7
10. U.S Department of Veterans Affairs Office of Information and Technology CFM/OIT DESIGN
GUIDE TEMPLATES FOR CRITICAL TELECOMMUNICATIONS SPACES IN CLINICAL AND NON-
CLINICAL ENVIRONMENTS Dec 27, 2018
11. Cerner Forward Deployed Power Supply Decision Memo April 19, 2019 https://vaww.vashare.oit.va.gov/sites/ehrm/ProgramControl/QualityPerfMgmt/Deliverables/v1 -119461343- 20190506_Forward%20Deployed%20Power%20Supply%20Decision%20Memo_Signed.pdf
12. The U.S. Department of Veterans Affairs, Physical Security Design Manual (PSDM) for Mission Critical Facilities, January 2015 https://www.wbdg.org/FFC/VA/VAPHYS/dmphysecmc_2015.pdf
13. U.S Department of Veterans Affairs Enterprise Infrastructure Standard: Quality Of Service(QoS) https://vaww.vashare.oit.va.gov/sites/itops/svcs/sma/BCM/Approved_Baselines/VA%20Enterpr ise%20IT%20Infrastructure%20(QoS)_1-14.pdf
14. U.S. Department of Veterans Affairs Office of Construction & Facilities Management HVAC Design Manual dated Revised May 1, 2019
15. 14.15. VA Drawing Deliverable Requirements, November 2016 https://www.cfm.va.gov/til/bim/DwgDelivRqmts.pdf
16. U.S Department of Veterans Affairs Enterprise Local Area Network (LAN) Technical Architecture Standard, Version 2.1, February 13, 2019 https://vaww.vashare.oit.va.gov/sites/itops/svcs/sma/BCM/Supporting_Documents/Enterprise %20Local%20Area%20Network%20(LAN)%20Technical%20Architecture%20Standard_v2.1.pdf
17. OEHRM Joint Security Architecture (JSA) Requirements Specifications Document (RSD) https://www.cfm.va.gov/til/dManual/dmTelecomm.pdf https://vaww.vashare.oit.va.gov/sites/itops/svcs/sma/BCM/Supporting_Documents/Infrastructure%20Standards%20for%20Telecommunications%20Spaces.pdf https://vaww.vashare.oit.va.gov/sites/itops/svcs/sma/BCM/Supporting_Documents/Infrastructure%20Standards%20for%20Telecommunications%20Spaces.pdf https://vaww.vashare.oit.va.gov/sites/ehrm/ProgramControl/QualityPerfMgmt/Deliverables/v1-119461343-20190506_Forward%20Deployed%20Power%20Supply%20Decision%20Memo_Signed.pdf https://vaww.vashare.oit.va.gov/sites/ehrm/ProgramControl/QualityPerfMgmt/Deliverables/v1-119461343-20190506_Forward%20Deployed%20Power%20Supply%20Decision%20Memo_Signed.pdf https://vaww.vashare.oit.va.gov/sites/ehrm/ProgramControl/QualityPerfMgmt/Deliverables/v1-119461343-20190506_Forward%20Deployed%20Power%20Supply%20Decision%20Memo_Signed.pdf https://www.wbdg.org/FFC/VA/VAPHYS/dmphysecmc_2015.pdf https://vaww.vashare.oit.va.gov/sites/itops/svcs/sma/BCM/Approved_Baselines/VA%20Enterprise%20IT%20Infrastructure%20(QoS)_1-14.pdf https://vaww.vashare.oit.va.gov/sites/itops/svcs/sma/BCM/Approved_Baselines/VA%20Enterprise%20IT%20Infrastructure%20(QoS)_1-14.pdf https://www.cfm.va.gov/til/bim/DwgDelivRqmts.pdf https://vaww.vashare.oit.va.gov/sites/itops/svcs/sma/BCM/Supporting_Documents/Enterprise%20Local%20Area%20Network%20(LAN)%20Technical%20Architecture%20Standard_v2.1.pdf https://vaww.vashare.oit.va.gov/sites/itops/svcs/sma/BCM/Supporting_Documents/Enterprise%20Local%20Area%20Network%20(LAN)%20Technical%20Architecture%20Standard_v2.1.pdf
OEHRM SITE INFRASTRUCTURE REQUIREMENTS | 12
18. U.S Department of Veterans Affairs Electronic Health Record Modernization Cabling Infrastructure (VIEWS 01426385) Executive Decision Memorandum, dated September 23, 2019
VACOVogelA Stamp
| Appendix E - CBOC IT Construction Standards 20191115.pdf |
| S02- Exhibit E Additional OEHRM Site Infrastructure Requirements_v1.1 Signed |
| 1 Overview |
| 2 Requirements |
| 2.1 Wide Area Networking (WAN) |
| 2.1.1 WAN Requirements |
| 2.1.2 WAN Implementation Specifications and Considerations |
| 2.2 Local Area Networking (LAN) |
| 2.3 Wireless LAN (WLAN) Design Requirements |
| 2.4 Power and Space Design Requirements |
| 2.5 Heating, Ventilation, and Air Conditioning (HVAC) Design Requirements |
| 2.6 End-User Devices (EUD) |
| 2.7 Voice Over Internet Protocol (VOIP) Device Requirements |
| 2.8 Medical Device Requirements |
| 2.9 Physical Security Design Requirements |
| 2.10 Joint Security Architecture Design Requirements |
| Appendix A: Acronyms |
| Appendix B: References |