36C25218B0596-00006002.docx

DOCX document 63 KB Posted

Attached to
Remediate Legionella Station-Wide Phase-1 550-15-107
Solicitation number
36C25218B0596
Issued by

About this file

36C25218B0596 00006 ADDITIONAL RFI RESPONSE.docx

View the file

Other files

File Type Posted
36C25218B0596-00006000.docx DOCX document
36C25218B0596-00006001.pdf PDF
36C25218B0596-00005055.pdf PDF
36C25218B0596-00005057.pdf PDF
36C25218B0596-00005052.docx DOCX document
36C25218B0596-00005053.pdf PDF
36C25218B0596-00005058.pdf PDF
36C25218B0596-00005056.pdf PDF
36C25218B0596-00005054.pdf PDF
36C25218B0596-00004000.docx DOCX document
36C25218B0596-00003001.pdf PDF
36C25218B0596-00003000.docx DOCX document
36C25218B0596-00003002.pdf PDF
36C25218B0596-00002001.pdf PDF
36C25218B0596-00002000.docx DOCX document
36C25218B0596-00001001.pdf PDF
36C25218B0596-00001000.docx DOCX document
36C25218B0596-003.pdf PDF
36C25218B0596-002.docx DOCX document
36C25218B0596-004.pdf PDF
36C25218B0596-001.docx DOCX document
36C25218B0596-000.docx DOCX document
Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

550-15-107: REMEDIATE LEGIONELLA STATION-WIDE PHASE-1

ADDITIONAL COTRACTOR RFI QUESTION AND GOVERNMENT RESPONSE

80-Q: The following has been noticed late in the game. There seemed to be a lot of injection ports so we sit back and researched the prints. The symbol page shows the injection points and the prints in minimal locations as balancing valves. We will have a lot of balancing valves or a lot of injection ports. PLEASE ADVISE!!!

P-001 Notes and Symbols

P-201 Plumbing Riser Diagrams

80-A: These are injection ports as per P-001 symbol.