Performance Work Statement Repair Emergency Power Phase 2 11 23 2026.pdf

PDF 285 KB Posted

Attached to
J061--Emergency Switchgear Repairs PWS 539
Solicitation number
36C25027Q0125
Issued by

About this file

Performance Work Statement Summary

This Performance Work Statement details a firm-fixed-price contract for emergency power system repairs at Cincinnati VA Medical Center, Building 1, Room B013. The Department of Veterans Affairs requires a qualified contractor to repair both emergency generators, replace damaged MFR13 and reverse power protective relays in the paralleling switchgear, modify switchgear doors and wiring, program and test replacement relays, perform load-bank testing on both generators, test paralleling operation, verify generator priority changes and load shedding, test control panels, and complete an operational test of the entire emergency power system. The two generators are Kohler units (Model 1500REOZDC, 1,560 kW each at 277/480V) powered by MTU Detroit Diesel T1238A36 engines.

The contract period of performance is 120 days, with generator work performed on two separate weekends—one generator per weekend—coordinated with and approved by the Government before work begins. Work shall be performed on Saturdays and Sundays unless otherwise approved in writing by the Contracting Officer. The contractor must provide all labor, supervision, materials, parts, equipment, tools, programming, testing equipment, load banks, and transportation. Load-bank testing requires a minimum of 4 hours per generator with loads at 30%, 50%, and 75% of nameplate kW rating for specified continuous durations. The contractor must obtain proper security clearance and VAMC/VAACC identification badges, maintain general liability insurance of at least $1,000,000 per occurrence, provide a licensed Professional Engineer for design-build oversight, submit a detailed work plan before mobilization, and deliver comprehensive documentation including repair reports, relay settings, updated ABB system drawings, individual load-bank test reports for each generator, and a final paralleling and functional test report. The place of performance is Cincinnati VA Medical Center, 3200 Vine Street, Cincinnati, Ohio 45220-2637.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Performance Work Statement Repair Emergency Power Phase 2

Cincinnati VA Medical Center

1. GENERAL

1.1. Purpose

The Department of Veterans Affairs requires the services of a qualified contractor to repair, program, modify, and test the emergency power generation and paralleling switchgear system serving at Building 1 at the Cincinnati VA Medical Center.

Last year, the lack of backup generators and emergency power led to operating room closures at

Cincinnati VA Medical Center. If the sole generator fails, critical care cannot be maintained onsite. As a result, all critical care would need to be diverted to other VA facilities or community care providers.

The system is currently operating with only one functional generator. This condition leaves the facility without the required redundancy in the event of a utility outage or failure of the remaining operational generator. The purpose of this requirement is to restore both generators to operational status, repair the associated paralleling switchgear, and verify that the emergency power system operates as designed.

1.2. Scope

The Contractor shall provide all labor, supervision, materials, parts, equipment, tools, programming, testing equipment, transportation, and incidental services necessary to:

1. Repair both emergency generators.

2. Replace damaged MFR13 and reverse power protective relays associated with the paralleling switchgear.

3. Modify the switchgear door and wiring as required to support the replacement relays.

4. Update applicable ABB system drawings.

5. Program and test the replacement relays.

6. Provide load-bank testing for both generators.

7. Test the paralleling operation of Generators 1 and 2.

8. Verify generator priority changes, automatic return to service, and load shedding.

9. Test the generator control panels.

10. Complete an operational test of the entire emergency power system following all repairs.

1.3. Period of Performance

The period of performance shall be 120 days.

Generator work shall be performed on two separate weekends, with one generator serviced during each weekend. Specific dates shall be coordinated with and approved by the

Government before work begins.

The Contractor shall perform work on Saturdays and Sundays unless otherwise approved in writing by the Contracting Officer or designated Government representative.

Federally Recognized Holidays: The contractor is not anticipated but may be required to provide service on Federally recognized holidays in accordance with the terms and conditions established in this PWS to include but not limited to the following:

New Year’s Day Labor Day Martin Luther King Jr.’s Birthday Columbus Day President’s Day Veteran’s Day Memorial Day Thanksgiving Day Juneteenth Christmas Day Independence Day

1.4. Place of Performance

Cincinnati VA Medical Center

3200 Vine Street

Cincinnati, Ohio 45220-2637

The work is in building 1 room B013 on the main Cincinnati VA campus.

1.5. Type of Contract

The Government intends to award a firm-fixed-price contract for the services described in this

Performance Work Statement.

Security Requirements and Background Checks: All contractor and subcontractor employees must comply with Federal, State, Local, and Department of Veterans Affairs security requirements and background checks to perform services in support of VA medical facilities in the states of Ohio and Kentucky. Services must be performed in accordance with contract terms at the contractor’s facility unless otherwise required (e.g., meetings, site visits), which must be coordinated with the Government Program Manager. Personnel requiring access to any VAMC property must consent to background checks or will be denied facility access. Required information for background checks includes: full name, driver’s license number and/or social security number, date of birth, and a completed background check questionnaire.

AMC/VAACC Identification Badges: The contractor shall ensure that all personnel obtain

VAMC/VAACC identification badges from the VAMC/VAACC security personnel office as appropriate in compliance with all federal and local VAMC/VAACC facility policies in coordination with the government program manager if required.

Employment Eligibility and Credentialing Requirements: Contractors shall ensure their employees and those of their Subcontractors possess proper credentials allowing them to work in the United States. No compensation will be provided for delays or expenses related to compliance with this requirement. Contractors are not excused from proceeding with the

Contract due to credentialing issues.

POST AWARD CONFERENCE/PERIODIC PROGRESS MEETINGS: The contractor agrees to attend any post award conference convened by the contracting activity or contract administration office in accordance with Federal Acquisition Regulation Subpart 42.5. The contracting officer, government program manager, and other government personnel, as appropriate, may meet periodically with the contractor to review the contractor's

1.6. Hours and Scheduling

A majority of the generator and emergency power system work shall be performed during weekends to minimize disruption to medical center operations.

The Contractor shall coordinate all work dates, system outages, switching activities, and testing with the Government Program Manager, COR, Engineering Service, and other designated VA personnel before mobilization.

The Contractor shall provide the Government with proposed work dates at least 14 business days before the planned work, unless otherwise directed by the Contracting Officer.

1.7. Contractor Furnished Items

The Contractor shall furnish all labor, supervision, materials, replacement parts, tools, equipment, programming devices, test instruments, load banks, transportation, and other items necessary to complete the work.

The Contractor shall provide a load bank for testing both generators during each scheduled weekend of work. The load bank shall be capable of providing the required test load, including the specified 125-percent load-bank requirement, as confirmed by the Government before testing.

1.8. Coordination with the Government

The Contractor shall coordinate all work with the Government before de-energizing, isolating, modifying, testing, or returning any generator, control panel, or paralleling switchgear to service.

The Contractor shall not interrupt electrical service or place the facility at increased risk without prior approval from the Government representative.

The Government may defer or reschedule work based on patient-care needs, facility operations, emergency conditions, or other mission requirements.

2. DEFINITIONS AND ACRONYMS

2.1. Definitions

Contractor: The firm awarded the contract to perform the required services.

Contracting Officer (CO): The Government official authorized to enter into, administer, modify, and terminate the contract.

Contracting Officer’s Representative (COR): The individual appointed in writing by the

Contracting Officer to monitor technical performance under the contract.

Emergency Power System: The generators, paralleling switchgear, protective relays, control panels, wiring, programming, and associated components that provide emergency electrical power to the facility.

Load Bank: A portable or permanently installed test device used to apply a controlled electrical load to a generator.

Paralleling Switchgear: The switchgear and associated controls that allow two or more generators to operate in parallel and share or transfer electrical load.

Protective Relay: A device that monitors electrical system conditions and initiates protective action when abnormal conditions occur.

Generator 1 and Generator 2: The two emergency generators located at Building #1 Room

B013.

2.2. Acronyms

ABB — Asea Brown Boveri

CO — Contracting Officer

COR — Contracting Officer’s Representative

OEM — Original Equipment Manufacturer

PWS — Performance Work Statement

VA — Department of Veterans Affairs

VAMC — Veterans Affairs Medical Center

3. GOVERNMENT-FURNISHED ITEMS AND SERVICES

3.1. Access

The Government shall provide reasonable access to the generators, control panels, paralleling switchgear, and associated equipment located on VA property.

3.2. Information and Existing Documentation

The Government shall provide available equipment information, existing ABB documentation, system drawings, and prior diagnostic or repair reports relevant to the work.

3.3. Utilities

The Government shall provide access to existing electrical utilities required to perform the work, subject to facility approval and operational limitations.

3.4. Government Personnel

The Government shall identify the authorized Contracting Officer, COR, Program Manager, and other personnel responsible for coordinating access, outages, switching, and acceptance of completed work.

3.5 ABB Personnel

ABB personnel who have worked on Phase 1 of this project is Fred Ervin, ABB Business

Development Manager Mobile: 614.560.9216

4. CONTRACTOR RESPONSIBILITIES AND REQUIREMENTS

4.1. General Responsibilities

The Contractor shall:

A. Provide qualified personnel experienced in the repair, programming, testing, and commissioning of emergency generators and ABB paralleling switchgear.

B. This is a Design- Build project. Contractor shall provide all required engineering oversight with a licensed Professional Engineer for all aspects of this project.

C. Provide all required supervision, labor, tools, equipment, parts, materials, programming, testing, and incidental services.

D. Perform the work in accordance with applicable manufacturer recommendations, applicable codes and standards, and accepted industry practices.

E. Protect Government property, equipment, personnel, patients, and visitors during performance.

F. Coordinate all work and testing with the Government.

G. Immediately notify the COR of any condition that could affect system safety, reliability, schedule, or facility operations.

H. Not alter equipment or system settings outside the approved scope without prior written authorization from the Contracting Officer.

4.2. Qualifications

The Contractor shall use personnel who are qualified and experienced in:

• Emergency generator repair and testing;

• Protective relay replacement and programming;

• Generator paralleling systems;

• ABB switchgear and control systems;

• Load-bank testing;

• Electrical safety and energized equipment procedures; and

• Functional testing and commissioning of emergency power systems.

Upon request, the Contractor shall provide documentation of technician qualifications, training, certifications, and experience.

4.3. Worksite Conduct and Security

Contractor personnel shall:

• Comply with VA access, identification, security, safety, infection-control, and conduct requirements;

• Wear appropriate identification while on VA property;

• Identify themselves as contractor personnel;

• Maintain a professional appearance and conduct;

• Follow all facility rules and instructions provided by the COR or authorized VA personnel;

and

• Obtain any required site access approval before beginning work.

4.4. Safety

The Contractor shall comply with all applicable Federal, State, and local safety requirements, including applicable OSHA, NFPA, electrical safety, lockout/tagout, and VA requirements.

The Contractor shall:

A. Submit and follow a job hazard analysis or equivalent safety plan when requested by the Government.

B. Use appropriate personal protective equipment.

C. Implement lockout/tagout and electrical safe-work practices.

D. Protect personnel and equipment during switching and testing activities.

E. Obtain any required VA permits before performing hot work, energized work, or other controlled activities.

F. Immediately report accidents, injuries, equipment damage, hazardous conditions, or system failures to the COR.

G. Stop work when directed by the COR, Safety Officer, or Contracting Officer because of an unsafe condition.

4.5. Clean-Up and Restoration

The Contractor shall remove all debris, packaging, discarded components, wiring, and waste generated by the work.

At the completion of each work period, the Contractor shall leave the work area clean and safe and shall restore all equipment covers, guards, doors, labels, and protective devices.

5. SPECIFIC TASKS

5.1. Task 1 — Pre-Work Inspection and Coordination

Before beginning repair work, the Contractor shall:

A. This is a Design- Build project. Contractor shall provide all required engineering oversight with a licensed Professional Engineer for all aspects of this project.

B. Inspect Generators 1 and 2, the associated control panels, and the paralleling switchgear.

C. Review the ABB diagnostic and repair report provided by the Government.

D. Confirm the equipment configuration, existing deficiencies, required replacement parts, and planned testing sequence.

E. Verify that the planned work can be performed safely during the approved weekend outage or testing period.

F. Provide the Government with a written work plan, including:

• Planned work dates;

• Work sequence;

• Personnel and contact information;

• Required outages or equipment isolations;

• Required load-bank equipment;

• Required Government coordination;

• Safety procedures;

• Testing procedures; and

• Anticipated restoration time.

No repair work shall begin until the work plan has been coordinated with the Government.

5.2. Task 2 — Protective Relay Replacement

The Contractor shall perform the following work for both generators:

A. Remove the damaged MFR13 relay and reverse-power relay.

B. Furnish and install new protective relays approved for use with the existing ABB paralleling switchgear and generator system.

C. Install all required mounting hardware, wiring, terminals, labels, and associated components.

D. Perform all required installation inspections and electrical tests.

E. Verify that the replacement relays are properly integrated with the generator controls and paralleling switchgear.

F. Provide documentation identifying the manufacturer, model, serial number, and settings for each replacement relay.

5.3. Task 3 — Relay Programming and System Configuration

The Contractor shall:

A. Program the replacement protective relays in accordance with the approved system design, manufacturer requirements, and ABB diagnostic recommendations.

B. Transfer or establish all required protection, control, alarm, communication, and trip settings.

C. Verify coordination between the replacement relays, generator control panels, paralleling switchgear, and facility emergency power system.

D. Back up and provide electronic copies of final relay settings and programming files.

E. Document all changes made to the relay programming and system configuration.

5.4. Task 4 — Switchgear Door Modifications

The Contractor shall modify the paralleling switchgear door as required to support the installation and operation of the upgraded protective relays.

The work shall include:

A. Cutting, drilling, mounting, or other required door modifications;

B. Installation of required mounting hardware;

C. Installation of labels and identification plates;

D. Verification of adequate clearance and access;

E. Verification that the door opens, closes, latches, and operates safely; and

F. Restoration of the enclosure to a safe and suitable condition.

5.5. Task 5 — Wiring Modifications

The Contractor shall perform all wiring modifications required to accommodate the replacement protective relays.

The work shall include:

A. Removal, rerouting, replacement, or installation of wiring as necessary.

B. Installation of properly sized conductors, terminals, ferrules, labels, and wire-management components.

C. Verification of wire identification and termination.

D. Continuity, insulation, polarity, and functional testing as applicable.

E. Correction of loose, damaged, mislabeled, or improperly terminated wiring identified during the work.

5.6. Task 6 — ABB System Drawing Updates

The Contractor shall update the applicable ABB system drawings to reflect all modifications made under this requirement, including:

A. Protective relay replacements;

B. Relay wiring;

C. Door modifications;

D. Control and communication wiring;

E. Terminal changes;

F. Programming or configuration changes; and

G. Other changes necessary to accurately document the completed system.

The Contractor shall provide final marked-up and electronic drawings to the Government.

5.7. Task 7 — Generator Work

Generator work shall be performed on two separate weekends, with one generator addressed during each weekend.

For each generator, the Contractor shall:

A. Complete the approved repairs and modifications.

B. Test the associated control panel.

C. Verify generator start, stop, emergency shutdown, alarms, and protective functions.

D. Verify voltage, frequency, phase rotation, and other applicable operating parameters.

E. Verify that the generator can connect to and disconnect from the emergency power system as designed.

F. Verify that the generator returns to service following testing or an interruption.

G. Correct deficiencies identified during testing before the generator is returned to normal operation.

The Contractor shall coordinate all generator work with the Government because the facility will temporarily have reduced emergency-power redundancy while one generator is unavailable.

5.8. Task 8 — Load-Bank Testing for the 2 Emergency Generators

The Contractor shall provide and operate a load bank for testing during each weekend of work.

The Contractor shall:

A. Contractor shall perform a 4 hour Load Bank testing on the 2 emergency generators listed in Appendix A. Testing shall be performed solely utilizing supplemental loads under the following conditions:

• NOT LESS THAN 30 percent of the generator nameplate kW rating for NOT LESS THAN 60 continuous minutes.

• NOT LESS THAN 50 percent of the generator nameplate kW rating for NOT LESS THAN 120 continuous minutes.

• NOT LESS THAN 75 percent of the generator nameplate kW rating for NOT LESS THAN 60 continuous minutes.

• Total load test duration shall exceed four (4) continuous hours plus documented fifteen (15) minute warm up and cool down periods.

B. During testing the following measurements shall be recorded at intervals not exceeding thirty (30) minutes and documented in every test report:

• Time of day

• Generator Run Hours

• KW

• Load percentage

• Frequency

• Phase to phase AC voltage (measured across all phases)

• DC Voltage

• AC Amps (all phases)

• Oil Pressure

• Engine Temperature

• Engine revolutions per minute

C. Individual test reports shall be submitted for each emergency generator and shall document the following:

• Date and time of testing

• Total duration of testing time

• Testing location

• Name, physical address, email, and phone number of company conducting testing

• Name of technician conducting the test

• Generator Common Name

• Generator Manufacturer

• Generator Model number

• Generator Serial number

• Generator Nameplate KW

• Generator Nameplate Voltage

• Generator Nameplate Current

• Generator Current at Unity Power Factor (3 Phase)

• Generator Hour Meter Start/Stop times

• Ambient Air Temperature

• Technician Comments

5.9. Task 9 — Paralleling and Load-Sharing Testing

The Contractor shall test the paralleling operation of Generators 1 and 2 using the required load bank.

Testing shall include:

A. Verification that both generators can start and operate in parallel.

B. Verification that the generators share load properly.

C. Verification that the protective relays operate as programmed.

D. Verification of reverse-power protection.

E. Verification of generator priority sequencing.

F. Verification that the generators return online in the intended order following an interruption or transfer.

G. Verification that the generators shed load as designed.

H. Verification of alarms, trips, interlocks, and shutdown functions.

I. Verification that the paralleling switchgear operates without abnormal alarms, trips, overheating, vibration, or other deficiencies.

5.10. Task 10 — Control Panel Testing

The Contractor shall coordinate testing of the two generator control panels.

One control panel has previously been tested and verified by the Government. The Contractor shall confirm its proper operation as part of the final system test.

The control panel associated with the previously inoperable generator shall be fully tested and verified, including:

A. Local start and stop;

B. Automatic start;

C. Emergency shutdown;

D. Alarm annunciation;

E. Voltage and frequency monitoring;

F. Protective shutdowns;

G. Remote signals;

H. Generator status indication;

I. Control interlocks; and

J. Communication with the paralleling switchgear.

If there are any issues with this control panel – the contractor shall provide any required repairs, including up to changing out the control panel.

5.11. Task 11 — Final Emergency Power System Test

After completing all repairs, programming, wiring modifications, relay replacement, and generator testing, the Contractor shall perform a complete functional test of the emergency power system.

The final test shall include, as applicable:

A. Generator start and stop;

B. Automatic operation;

C. Generator paralleling;

D. Load sharing;

E. Priority sequencing;

F. Load shedding;

G. Reverse-power protection;

H. Protective relay operation;

I. Control panel operation;

J. Alarm and shutdown functions;

K. Return to normal utility power;

L. Return of generators to standby status; and

M. Repeated operation as necessary to verify reliable performance.

The Contractor shall demonstrate to the Government that the complete emergency power system operates as intended.

6. DELIVERABLES

6.1. Work Plan

The Contractor shall submit a work plan before beginning onsite work. The plan shall include the schedule, work sequence, personnel, safety procedures, outage requirements, load-bank requirements, and testing procedures.

6.2. Repair and Installation Report

The Contractor shall provide a report describing all work performed, including:

A. Equipment serviced;

B. Date and time of work;

C. Personnel performing the work;

D. Parts and materials installed;

E. Protective relays replaced;

F. Door modifications;

G. Wiring modifications;

H. Programming changes;

I. Problems encountered;

J. Corrective actions taken; and

K. Remaining deficiencies, if any.

6.3. Relay Settings and Programming Files

The Contractor shall provide:

A. Final protective relay settings;

B. Configuration files;

C. Programming backups;

D. Applicable software-generated reports; and

E. A written description of all programming changes.

6.4. Updated Drawings

The Contractor shall provide final updated ABB system drawings reflecting the completed modifications.

Drawings shall be submitted electronically in a commonly used format and, if requested, in hard copy.

6.5. Load-Bank Test Reports

A separate load-bank test report shall be provided for each generator.

Each report shall include:

A. Generator identification;

B. Manufacturer, model, and serial number;

C. Date and location of testing;

D. Load-bank manufacturer, model, and capacity;

E. Technician name;

F. Start and stop times;

G. Applied load and test sequence;

H. Voltage;

I. Current;

J. Frequency;

K. Engine operating parameters;

L. Alarms, trips, or abnormal conditions;

M. Test results;

N. Deficiencies identified; and

O. Corrective actions taken.

6.6. Paralleling and Functional Test Report

The Contractor shall provide a report documenting the final emergency power system test, including:

A. Generator paralleling results;

B. Load-sharing results;

C. Generator priority sequence;

D. Return-to-service operation;

E. Load-shedding operation;

F. Protective relay operation;

G. Control panel testing;

H. Alarm and shutdown testing;

I. System deficiencies; and

J. Final acceptance status.

6.7. Service Tickets

The Contractor shall report to the COR or authorized VA representative upon arrival and departure from the facility.

7. INSURANCE REQUIREMENTS

7.1 General:

A. The Contractor shall procure and maintain, during the entire period of performance under this contract, the types and minimum amounts of insurance coverage set forth in this section. The cost of such insurance shall be borne by the Contractor.

B. Workers' Compensation and Employer's Liability: Contractor shall comply with all applicable Federal, State, and local laws with respect to liability for injuries or death to

Contractor personnel. The Contractor is required to provide workers’ compensation insurance as prescribed by applicable law.

C. General Liability Insurance: Contractor shall maintain commercial general liability insurance protecting the Government, its agents, officers, and employees against liability claims, including personal injury, death, and property damage, to a minimum limit of not less than $1,000,000 per occurrence.

D. Automobile Liability Insurance: If performance of this contract requires use of motor vehicles on-site, Contractor shall provide automobile liability insurance covering all vehicles used in the performance of this contract with minimum limits of $1,000,000 per occurrence for bodily injury and property damage.

E. Professional Liability Insurance: If any professional/clinical services are provided, the

Contractor shall maintain professional liability insurance with limits of at least $1,000,000 per occurrence.

F. Other Insurance: The Government reserves the right to require additional insurance coverage as may be appropriate for the specific requirements of this contract.

G. Proof of Insurance: Before commencing work under this contract, the Contractor shall furnish to the Contracting Officer certificates of insurance evidencing the required coverage. All such certificates shall provide that no insurance may be canceled, or materially changed, except after thirty (30) days’ written notice to the Contracting

Officer.

H. Notice of Cancellation: The Contractor shall notify the Contracting Officer in writing at least thirty (30) calendar days before any policy of insurance is cancelled or reduced in coverage.

I. Subcontractors: The Contractor shall require all subcontractors to carry insurance coverage meeting these requirements.

Appendix A: Emergency Generator Inventory

This inventory is subject to update by written modification and is controlling for contract services where referenced.

Generator Set Engine

Manufacturer Wattage Voltage Model # Manufacturer Model #

Gen 1 Kohler 1,560 KW 277/480 1500REOZDC MTU Detroit

Diesel T1238A36

Gen 2 Kohler 1,560 KW 277/480 1500REOZDC MTU Detroit

Diesel T1238A36

Appendix B: Attachments Note: All attachments are provided with the understanding that they were accurate at the time, however, the VA takes no responsibility for the accuracy at the current time and any items of concern need to be verified by the Contractors Professional Engineer as this is a Design Build project.

1. Electrical Deficiencies As-Builts 1

2. 2026-7-27 ABB email with additional work required

3. 2023-1-8 ABB CSR VA Hospital PSG Repairs

4. 2023-3-14 ABB VA Cincinnati Executive Summary

5. 2023-3-11 AAB VA Hospital Cincinnati LV Breaker Test Sheets

6. 2023-3-14 ABB Y1284 VA Cincinnati PSG Rebuild MOP Rev 3

7. 2015-9-4 ABB Y1284-1 drawings

8. 2017-4-18 ABB Y-1284-2-Schmatics

9. 2010-3-3 ABB Y1284-OUT_SCHEM

10. 2010-3-3 ABB Y-1284- Outline file:///C:/Users/VHACINWeidiJ/AppData/Local/Microsoft/Windows/INetCache/Content.MSO/%22S:/Eng/Engineering%20Shops/Equipment%20Maintenance%20Shop/Electric%20Shop/GENERATOR/Generator%20Nameplates/Generator%231%20Generator%20Nameplate.jpg%22 file:///C:/Users/VHACINWeidiJ/AppData/Local/Microsoft/Windows/INetCache/Content.MSO/%22S:/Eng/Engineering%20Shops/Equipment%20Maintenance%20Shop/Electric%20Shop/GENERATOR/Generator%20Nameplates/Generator%232%20Generator%20Nameplate.jpg%22

ABB point of contact is:

Fred Ervin

Business Development Manager

Mobile: 614-560-3216 fred.ervin@us.abb.com

Performance Work Statement Repair Emergency Power Phase 2
Cincinnati VA Medical Center
1. GENERAL
1.1. Purpose
1.2. Scope
1.3. Period of Performance
1.4. Place of Performance
1.5. Type of Contract
1.6. Hours and Scheduling
1.7. Contractor Furnished Items
1.8. Coordination with the Government
2. DEFINITIONS AND ACRONYMS
2.1. Definitions
2.2. Acronyms
3. GOVERNMENT-FURNISHED ITEMS AND SERVICES
3.1. Access
3.2. Information and Existing Documentation
3.3. Utilities
3.4. Government Personnel
3.5 ABB Personnel
4. CONTRACTOR RESPONSIBILITIES AND REQUIREMENTS
4.1. General Responsibilities
4.2. Qualifications
4.3. Worksite Conduct and Security
4.4. Safety
4.5. Clean-Up and Restoration
5. SPECIFIC TASKS
5.1. Task 1 — Pre-Work Inspection and Coordination
5.2. Task 2 — Protective Relay Replacement
5.3. Task 3 — Relay Programming and System Configuration
5.4. Task 4 — Switchgear Door Modifications
5.5. Task 5 — Wiring Modifications
5.6. Task 6 — ABB System Drawing Updates
5.7. Task 7 — Generator Work
5.8. Task 8 — Load-Bank Testing for the 2 Emergency Generators
5.9. Task 9 — Paralleling and Load-Sharing Testing
5.10. Task 10 — Control Panel Testing
5.11. Task 11 — Final Emergency Power System Test
6. DELIVERABLES
6.1. Work Plan
6.2. Repair and Installation Report
6.3. Relay Settings and Programming Files
6.4. Updated Drawings
6.5. Load-Bank Test Reports
6.6. Paralleling and Functional Test Report
6.7. Service Tickets