2023-3-11 ABB Y1284 VA Cincinnati PSG Rebuild MOP Rev 3_Redacted.pdf

PDF 6 MB Posted

Attached to
J061--Emergency Switchgear Repairs PWS 539
Solicitation number
36C25027Q0125
Issued by

About this file

This is a Method of Procedure (MOP) document for a low voltage switchgear preventive maintenance, controls rebuild, and testing project at VA Hospital Cincinnati, Ohio. The service was performed by ABB EP-Industrial Solutions from February 21, 2023 through March 11, 2023 on a GE Zenith Paralleling Switchgear system rated at 480VAC, 5000A, 3-phase, 4-wire, 60Hz, along with associated circuit breakers, PLCs, HMI/ACS units, generator controllers, meters, and protective relays.

The project encompassed four primary procedures: (1) LV Switchgear Preventive Maintenance & Services including inspection, cleaning, drying of cubicle devices, busbar, isolators, and instrument transformers, plus removal and testing of all breakers; (2) LV Switchgear Controls Rebuild involving replacement of damaged PLC components, HMI, VICOR, relays, and bases, with PLC HMI program downloads; (3) Controls Energization, I/O Checks, and Generator Alarm/Shutdown testing; and (4) Final System Testing per approved sequence of operations. The estimated project duration was 15 days, with operation risk classified as MEDIUM for work hazards and LEVEL 2 for end-user facility impact. Critical pre-conditions required customer provision of a portable generator to support life safety loads during procedures 1-3 when the standby power system would be unavailable. The document includes detailed step-by-step procedures, component inspection and rebuild tasks, testing protocols including individual ATS tests with load shed/add priority, loss and return of normal power scenarios, and site photographs demonstrating system operation post-commissioning. The project was successfully completed with the system placed in AUTOMATIC mode and no punch list items outstanding as of March 14, 2023.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Y1284 VA Hospital Cincinnati PSG Mod MOP, Rev 3, 03-14-2023 1

ABB

EP-Industrial Solutions

Method of Procedure PSG PM, Rebuild & Testing – Field Service

Project Information:

Project Name Y1284 VA Cincinnati, OH

Project Description LV Switchgear Preventive Maintenance & Services / Controls Rebuild & Testing

ABB Order Number Sales: -- Service: --

ABB Dates of Service 02/21/2023 thru 03/11/2023

End User Information:

Account Company Name Duns# VA Cincinnati, OH

Physical Address – City, State, Country, Zip 3200 Vine St, Cincinnati, OH, 45220

Contact Name – Title, Email, Phone

Purchaser Information:

Account Company Name Duns#

Physical Address – City, State, Country, Zip

Contact Name – Title, Email, Phone

Purchaser PO

ABB Quote#

Contractor Information:

Account Company Name Duns#

Physical Address – City, State, Country, Zip

Contact Name – Title, Email, Phone

Report Prepared by:

ABB FE/Tech Name

ABB FE/Tech Email

ABB FE/Tech Phone

Revision Number 3

Issue Date 03/14/2023

Y1284 VA Hospital Cincinnati PSG Mod MOP, Rev 3, 03-14-2023 2

EP-Industrial Solutions

Contents

1. Notice of Intent

2. Objective

3. Equipment Serviced

4. Statement of Work

4.1 Emergency/Standby Power System - Modifications & Testing

4.1.1 Purpose (Scope of Work)

4.1.2 Estimated Schedule

4.1.3 MOP Revision Notes

4.1.4 System Impact

4.1.5 Work Risk Assessment

4.1.6 End User Operations Risk Assessment

4.1.7 Pre-Conditions

4.1.8 MOP Procedure Notes

5. Procedures

5.1 PROCEDURE # 1 & 2 LV Switchgear Preventive Maintenance & Services / Controls Rebuild

5.2 Procedure #1 & 2 Prep Work

5.3 Procedure #1 & 2 Estimated Duration, Operation Risk & Emergency Standby Options

5.4 Procedure #1 & 2 LV Switchgear Preventive Maintenance & Services / Controls Rebuild

5.5 Procedure #3 Controls Energization, Program Downloads, I/O Checks, Gen AL/SD & Basic System Testing

5.6 Procedure #3 Prep Work

5.7 Procedure #3 Estimated Duration, Operation Risk & Emergency Standby Options

5.8 Procedure #3

5.9 Procedure #4 Final Testing

5.10 Procedure #4 Prep Work

5.11 Procedure #4 Estimated Duration, Operation Risk & Emergency Standby Options

5.12 Final System Testing

5.10 Final Software Record & Storage

6. Sign Off

Y1284 VA Hospital Cincinnati PSG Mod MOP, Rev 3, 03-14-2023 3

1. Notice of Intent

This document contains proprietary information and is submitted upon the express condition that the information contained herein will not be used directly or indirectly in any way detrimental to the interest of the ABB Company.

Specific technical data forms submitted to you are for ABB employees use during performance of service contracts and are not released as general industry information. These include engineering standards and engineering appraisals.

Good engineering practice dictates during the application of these generalized technical forms that specific exclusions or the service engineer assigned may make additional evaluations. Therefore, such individualization of the generic service content will be furnished automatically within the scopes of all service contracts without further notice.

Contributors

Brad Wieskus

Y1284 VA Hospital Cincinnati PSG Mod MOP, Rev 3, 03-14-2023 4

EP-Industrial Solutions

2. Objective

The Industrial Engineering Services Department of ABB Company has been authorized to perform a Paralleling Switchgear rebuild at the Y1286 VA Hospital located in Cincinnati, OH. The intent of this document is to provide a method of procedure for the ABB field service engineer. The procedures identify the steps to Rebuild the existing system and test for the emergency/Standby Power System.

3. Equipment Serviced

Equipment Tag/Designation

Equipment Type Mfgr& Model of Equipment ABB Shop

Order#

Nameplate Serial Number

Volts/Amps/HP/Unit Rating

Software/HMI /IO Type

480V Switchgear & Controls

Paralleling Switchgear

GE Zenith Paralleling Switchgear

-- Y1284 480VAC, 5000A

3-phase, 4-wire, 60Hz

-- Circuit Breaker Entilligurard CB -- Y1284 480V, 60HZ, 3200AF --

-- PLC GE-IP -

Versamax

-- Y1284 24VDC GE Proficy Machine Edition

-- HMI/ACS 15” ACS, Quick Panel Industrial

PC

-- Y1284 24VDC GE Proficy Machine Edition

-- Generator Controllers

Woodward -

25A, LSM

-- Y1284 24VDC --

-- Meters Multilin - PQMII -- Y1284 24VDC Multilin Enervista

-- Protective Relays Woodward -

MFR13

-- Y1284 24VDC Multilin Enervista

Y1284 VA Hospital Cincinnati PSG Mod MOP, Rev 3, 03-14-2023 7

EP-Industrial Solutions

4.1.5 Work Risk Assessment: MEDIUM

Definitions:

1. Low: Indicates the level of exposure to electrical arc-flash hazards or other safety concerns are reduced to a minimal safety requirement. For example, hard hats, safety glasses, boots, etc. Usually, low work risks involve activities near non-energized electrical equipment.

2. Medium: Indicates the level of exposure to electrical arc-flash hazards or other safety concerns are present and additional precautions are required. For example, face shields, or additional Personnel Protection Equipment (PPE) are required. Usually, medium work risks involve activities near energized electrical equipment.

3. High: Indicates the level of exposure to electrical arc-flash hazards or other safety concerns are elevated and additional precautions are required. For example, arc flash suits, certified safety personnel on-site, etc. Usually, high work risks involve activities on energized electrical equipment.

4.1.6 End User Operations Risk Assessment: LEVEL 2

Definitions:

1. Level 1: Indicates the level of operational risk to the facility due to the MOP activities have the greatest potential for immediate impact to building operations. For example, activities involving UPS System, or sub-systems that will eliminate the level of on-line redundancy. Owner personnel are requested on-site during these activities.

2. Level 2: Indicates the level of operational risk to the facility due to the MOP activities have some potential for immediate impact to building operations. For example, activities involving HVAC system that could delay cooling, or sub-systems that would reduce the level on on-line redundancy. Owner personnel are requested on-site during these activities.

3. Level 3: Indicates the level of operational risk to the facility due to the MOP activities have minimal potential for immediate impact to building operations. For example, activities involving routine maintenance or equipment, or sub-systems that would not reduce the level on on-line redundancy.

Y1284 VA Hospital Cincinnati PSG Mod MOP, Rev 3, 03-14-2023 8

EP-Industrial Solutions

4.1.7 Pre-Conditions:

NOTE: The following are the Customer’s responsibility. These must be completed PRIOR to the PM.

Responsibility of tasks below may be delegated to the electrical contractor, general contractor, generator technician or other vendors approved by the customer.

• Standby Power system won`t be available during procedure 1, 2 & 3 in manual or in auto so prior to the ABB`s arrival portable generator will have to be provided to support critical and life safety load in hospital.

• Temporarily connected Load Bank cables should be properly routed for safe access and away from ABB`s work area.

• Temporarily connected portable Gen cables should be properly routed for safe access and away from ABB`s work area.

• For safe work environment 24VDC Control power will be turned off, GEN Set will be disable/LOTO, and emergency start will be disabled before 1 and 2 starts.

• Any component that is functioning currently but have an accusive water damage will have to be replaced for safe working condition.

• Any component is functioning currently but compromised by water damage will be advised to replace in future. ABB will provide the list upon completion of project.

• All material and equipment that was shipped to site is available and placed near the existing switchgear.

• Fuel available to the engines.

• Engine-Generator batteries are properly charged and connected to battery chargers.

• Local authority and area notifications of engine-generator operations (noise, exhaust, etc.), if required.

• Notification and schedule issued to Owner regarding system modification, testing, outages, and times when the control system will be in Manual or not available.

• Copy of customer’s O&M and interconnections made available at site for ABB Field Engineer to use for mark ups during startup, testing and commissioning.

• If final commissioning tests are required, provide script to ABB prior to arriving on site.

4.1.8 MOP Procedure Notes:

• The “Customer”, as used throughout the MOP, is defined as the end user of the Emergency/Standby Power System or any contractor designated by the customer to act on their behalf.

Y1284 VA Hospital Cincinnati PSG Mod MOP, Rev 3, 03-14-2023 10

EP-Industrial Solutions

ATS-1 – CC1::1,2 Calvary/United Jeff 02/20/2023

ATS-2 – CC1::3,4 Calvary/United Jeff 02/20/2023

ATS-3 – CC1::5,6 Calvary/United Jeff 02/20/2023

ATS-4 – CC1::7,8 Calvary/United Jeff 02/20/2023

ATS-5 – CC1::9,10 Calvary/United Jeff 02/20/2023

ATS-6 – CC1::11,12 Calvary/United Jeff 02/20/2023

ATS-7 – CC1::13,14 Calvary/United Jeff 02/20/2023

ATS-8 – CC1::15,16 Calvary/United Jeff 02/20/2023

ATS-9 – CC1::17,18 Calvary/United Jeff 02/20/2023

ATS-10 – CC1::19,20 Calvary/United Jeff 02/20/2023

ATS-11 – CC1::21,22 Calvary/United Jeff 02/20/2023

ATS-12 – CC1::23,24 Calvary/United Jeff 02/20/2023

ATS-13 – CC1::25,26 Calvary/United Jeff 02/20/2023

ATS-14 – CC1::27,28 Calvary/United Jeff 02/20/2023

ATS-15 – CC1::29,30 Calvary/United Jeff 02/20/2023

ATS-16 – CC2::1,2 Calvary/United Jeff 02/20/2023

ATS-17 – CC2::3,4 Calvary/United Jeff 02/20/2023

ATS-18 – CC2::5,6 Calvary/United Jeff 02/20/2023

ATS-FIREPUMP – CC2::7,8 Calvary/United Jeff 02/20/2023

ATS-19 – CC2::9,10 Calvary/United Jeff 02/20/2023

ATS-20 – CC2::11,12 Calvary/United Jeff 02/20/2023

ATS-21 – CC2::13,14 Calvary/United Jeff 02/20/2023

ATS-22 – CC2::15,16 Calvary/United Jeff 02/20/2023

ATS-23 – CC2::17,18 Calvary/United Jeff 02/20/2023

ATS-24 – CC2::19,20 Calvary/United Jeff 02/20/2023

ATS-25 – CC2::21,22 Calvary/United Jeff 02/20/2023

ATS-26 – CC2[RTU]::35,36 Calvary/United Jeff 02/20/2023

ATS-27 – CC2[RTU]::37,38 Calvary/United Jeff 02/20/2023

ATS-28 – CC2[RTU]::39,40 Calvary/United Jeff 02/20/2023

ATS-29 – CC2[RTU]::41,42 Calvary/United Jeff 02/20/2023

ATS-30 – CC2[RTU]::43,44 Calvary/United Jeff 02/20/2023

ATS-31 – CC2[RTU]::45,46 Calvary/United Jeff 02/20/2023

ATS-32 – CC2[RTU]::47,48 Calvary/United Jeff 02/20/2023

ATS-33 – CC2[RTU]::49,50 Calvary/United Jeff 02/20/2023

NOTE: In the following MOP steps, the standby generator system will be placed into MANUAL and the ATS start signals will be transferred to the temporary generator. If emergency/standby power is needed during this transfer, the existing generators will have to be operated manually. Once the temporary generator is connected into the ATS’, testing will occur to confirm the operation of the temporary generator before the modification begins.

2 System In Manual Perform the following to place the paralleling switchgear controls in MANUAL:

At Section 101, place the Auto-Manual Switch (AUMS) in MANUAL.

Calvary/United Jeff 02/20/2023

At Section 102, place the Gen 1 Engine Control Switch (ECS) in MANUAL.

Calvary/United Jeff 02/20/2023

At Section 103, place the Gen 2 Engine Control Switch (ECS) in MANUAL.

Calvary/United Jeff 02/20/2023

At the Gen 1 on-board controller, place the generator in MANUAL.

Calvary/United Jeff 02/20/2023

At the Gen 2 on-board controller, place the generator in MANUAL.

Calvary/United Jeff 02/20/2023

3 Remove 24VDC Control Power

At Section 101, open fuse block F14 (10A) to remove control power to the ATS start signals going to the PLC.

Verify the CC1, CC2 (in Master) and CC2[RTU] (in RTU Panel) terminals have zero voltage before proceeding.

Calvary/United Jeff 02/20/2023

Y1284 VA Hospital Cincinnati PSG Mod MOP, Rev 3, 03-14-2023 12

EP-Industrial Solutions

5 Install CC1, CC2 & CC2[RTU] Jumpers

Install temporary jumper wires between the following terminal blocks:

CC1::2 → CC1::4

CC1::4 → CC1::6

CC1::6 → CC1::8

CC1::8 → CC1::10

CC1::10 → CC1::12

CC1::12 → CC1::14

CC1::14 → CC1::16

CC1::16 → CC1::18

CC1::18 → CC1::20

CC1::20 → CC1::22

CC1::22 → CC1::24

CC1::24 → CC1::26

CC1::26 → CC1::28

CC1::28 → CC1::30

CC1::30 → CC2::2

Calvary/United Jeff 02/20/2023

CC2::2 → CC2::4

CC2::4 → CC2::6

CC2::6 → CC2::8

CC2::8 → CC2::10

CC2::10 → CC2::12

CC2::12 → CC2::14

CC2::14 → CC2::16

CC2::16 → CC2::18

CC2::18 → CC2::20

CC2::20 → CC2::22

CC2::22 → CC2[RTU]::36

Calvary/United Jeff 02/20/2023

CC2::36 → CC2[RTU]::38

CC2::38 → CC2[RTU]::40

CC2::40 → CC2[RTU]::42

CC2::42 → CC2[RTU]::44

CC2::44 → CC2[RTU]::46

CC2::46 → CC2[RTU]::48

CC2::48 → CC2[RTU]::50

Calvary/United Jeff 02/20/2023

6 Interconnect Wiring to Temporary Generator

Instruct the contractor to install the temporary generator ATS gen start interconnect wires on CC1::1 & CC1::2.

NOTE THE CONTACT IS

NORMALLY CLOSED

Calvary Contracting/United

JEFF 02/20/2023

7 ATS’ Feeds to Temporary Generator

Verify with the contractor that the ATS power cables feeding their emergency source have been moved to be fed by the temporary generator.

Calvary Contracting/United

JEFF 02/20/2023

8 Testing Testing will be performed by the customer and/or contractor.

Note the following recommendations & information to assist with the testing as needed:

NOTE: Load Add/Shed operation from the existing controls WILL NOT be available while connected to the temporary generator.

Verify each ATS is setup to transfer staggered since Load Control will not active during temporary generator testing.

Calvary Contracting/United

JEFF 02/20/2023

Verify each ATS does not have an Inhibit signal or Load Shed signal connected to it from the existing controls.

Calvary Contracting/United

JEFF 02/20/2023

Y1284 VA Hospital Cincinnati PSG Mod MOP, Rev 3, 03-14-2023 15

EP-Industrial Solutions needs replacement are provided in spare parts.

In GEN controls, assess all the components for water damage and make a list. Make sure all the damage parts that needs replacement are provided in spare parts.

ABB JD 02/23/2023

Remove VICOR/booster assembly for clean and rebuild.

ABB JD 02/23/2023

Inspect all the water damaged Ice cube relays and bases.

ABB JD 02/23/2023

Clean all the control wire has water residue if required re strip all for use.

ABB JD 02/23/2023

Inspect all fuse bases are rust free. Clean or replace if need.

ABB JD 02/23/2023

2 Master PLC Replacements & Components inspection

Unwire Primary and Secondary PLC CPU Power Supply. Unwire Primary and Secondary PLC bases for Input, Output, and analog cards.

ABB JD 02/24/2023 –

02/27/2023

Clean cubicle as require ABB JD 02/23/2023

Install new, rewire Primary and Secondary PLC CPU Power Supply. Install new, rewire Primary and Secondary PLC bases for Input, Output, and analog cards.

ABB JD 02/24/2023 –

02/27/2023

Install new Ice cube relays and rewire bases as per drawings.

ABB JD 02/24/2023

As per information, there is no damage in Crompton, AUX CTs, Annunciator, PQM and HMI. Confirm information.

ABB JD 02/23/2023

3 GEN PLC & Components inspection

As per information, there is no damage in GEN PLC, Voltage Conditioners, Woodward 25A & LSM, MFR13 and Basler Relay.

Confirm information.

ABB JD 02/23/2023

Inspect all the water damaged Ice cube relays and bases. Install new Ice cube relays and rewire bases as per drawings.

ABB JD 02/24/2023

Make sure VICOR is still functional. ABB JD 02/24/2023

Note -

- Procedure 1 & 2 will start and be performed simultaneously.

- Load Bank will be required at the end of the procedure 1 & 2 and before procedure 3 starts.

Y1284 VA Hospital Cincinnati PSG Mod MOP, Rev 3, 03-14-2023 17

EP-Industrial Solutions

3 Communication establishments & PLC redundancy Checks

Make sure all the TCP/IP and Modbus devices on the network are communicating with both master PLCs and Communication status are green on HMI. Make sure ANN Box Working.

ABB JD 02/28/2023

Power down Primary PLC and mase sure Secondary PLC takes over all the comm devices and controls. Restore the Power back to Primary PLC and repeat same test for Secondary PLC.

ABB JD 02/28/2023

4 Generators Start Up Remove LOTO from each GEN set and perform GEN Startup.

Secure rear doors at switch gear. Make sure all PT, CPT and PTVC fuses are ok.

ABB JD 03/01/2023

Ask customer if GEN SETs are ready for startup & GEN Tech is available on site.

Preform GEN AL/SD with GEN TECH.

Perform GEN manual start & stop then Estop. Perform metering checks while GEN is running.

ABB JD 03/01/2023

Close GEN Bkr on a dead bus then perform more metering checks.

ABB JD 03/01/2023

Ask customer if Load Bank is connected and verified.

ABB JD 03/01/2023

Keep Load bank Bkr in test position and check Bkr open, close and charge works.

ABB JD 03/01/2023

Ask customer if Load Bank is ready and load bank operator is available on site.

ABB JD 03/01/2023

Open GEN Bkr, Stop the GEN and rack in Load bank Bkr.

ABB JD 03/01/2023

Start the GEN close Gen bkr on dead Bus then close LB Bkr and apply Load then perform Metering checks.

ABB JD 03/01/2023

Stop the Gen then perform LB Test while system is in Auto.

ABB JD 03/01/2023

Repeat same tests for all the GENs individually.

ABB JD 03/01/2023

5 Feeder Bkr Checks Keep all the feeder Bkrs in test position and while Bus is energized make sure Bkrs open, close and charge works.

ABB JD 02/28/2023

6 Generators Manual & Auto Synchronizations.

Keep second GEN Bkr in test position.

Start first GEN and close the bkr to connect to dead BUS. Start second GEN and perform six points GEN Synchronization checks.

ABB JD 03/01/2023 –

03/02/2023

Stop both GENs then rack in second GEN bkr. Start both GENs follow manual synchronization process. Check for circulating current and KVAR. Apply load using load bank and check for load sharing between GENs.

ABB JD 03/01/2023 –

03/02/2023

Follow O&M perform Sequence of Ops testing, failure modes, TNL and GEN Opt.

ABB JD 03/03/2023

At this point customer can connect cables for feeder Bkrs.

ABB JD 03/03/2023

Note: GEN Tech will be required to be on site for GENs AL/SD Checks.

Y1284 VA Hospital Cincinnati PSG Mod MOP, Rev 3, 03-14-2023 20

EP-Industrial Solutions

Re-land R-I40 wires on CC2::50 Calvary/United JEFF 03/11/2023

8 Restore 24VDC Control Power

At Section 101, close fuse block F14 to restore control power to the ATS start signals going to the PLC.

Calvary/United JEFF 03/11/2023

9 System In Auto Perform the following to place the paralleling switchgear controls in AUTO:

At the Gen 1 on-board controller, place the generator in AUTO.

ABB JD 03/11/2023

At the Gen 2 on-board controller, place the generator in AUTO.

ABB JD 03/11/2023

At Section 102, place the Gen 1 Engine Control Switch (ECS) in AUTO.

ABB JD 03/11/2023

At Section 103, place the Gen 2 Engine Control Switch (ECS) in AUTO.

ABB JD 03/11/2023

At Section 101, reset any alarms and place the Auto-Manual Switch (AUMS) in

AUTO.

ABB JD 03/11/2023

10 Proceed with Testing Verify with the customer that final system testing can begin.

ABB JD 03/11/2023

Y1284 VA Hospital Cincinnati PSG Mod MOP, Rev 3, 03-14-2023 25

6. Sign Off

By signing this form, it is agreed and accepted that the applicable ABB equipment has been tested to the fullest allowable extent. All tests performed tested with satisfactory results and have been approved by the customer or a representative of the customer.

If any further tests are requested or are required but were not allowed to be performed during the process of startup on site and the ABB field service engineer has departed the site, a purchase order will be required for a return site visit with a minimum of five (5) business days’ notice.

If system operation training requires another site visit a purchase order will be required unless training is specified for another site visit in the original quotation.

Warranty on the ABB equipment will begin from this date of signature and will expire on this date based on the duration of the warranty contract stated in the original quotation.

☒ System is in AUTOMATIC; startup is complete and no punch list items exist.

☐ System is NOT in AUTOMATIC; startup is complete and no punch list items exist.

☐ System is AUTOMATIC; startup is considered Substantially Complete however punch list items exist (as listed below). The job will be complete when contractual responsibilities have been met and the final bill issued.

☐ System is NOT in AUTOMATIC; startup is considered Substantially Compete however punch list items exist (as listed below). The job will be complete when contractual responsibilities have been met and the final bill issued.

Y1284 VA Hospital Cincinnati PSG Mod MOP, Rev 3, 03-14-2023 26

COMMENTS/RECOMMENDATIONS:

• Customer would like to order two (2) spare Annunciator Boxes for Remote Annunciator (RA) Panel located in the basement.

• This RA panel was powered on and downloaded RA PLC program.

• Provided missing 24 VDC to TBDC terminal block from SOLA power supply 24 VDC output for PLC I/O cards

• It is now functioning and communicating with Master PLC on 1st floor.

• Remote Terminal Unit with ATS start signals wiring was removed. Now they are communicating with Ethernet between PLCs.

• It is highly recommended to replace Generator Protection relays (MFR1, Analog Reverse Power Relay) with Multilin (SR 489) or ABB (REG) relays for both generators. MFR1 are obsolete by manufacturer.

• Arc Flash study is expiring this year and needs to be updated on the LV switchgear

AGREED AND ACCEPTED BY:

COMPANY COMPANY

COMPANY REPRESENATIVE REPRESENTATIVE

NAME (PRINTED) (SIGNATURE) TITLE DATE

_ABB___________ _Jagdeep (JD) Chahal ___________________ Senior Field Engineer __________

03/14/23

Y1284 VA Hospital Cincinnati PSG Mod MOP, Rev 3, 03-14-2023 27

SITE PICTURES

Y1284 VA Hospital Cincinnati PSG Mod MOP, Rev 3, 03-14-2023 28

Y1284 VA Hospital Cincinnati PSG Mod MOP, Rev 3, 03-14-2023 29

Y1284 VA Hospital Cincinnati PSG Mod MOP, Rev 3, 03-14-2023 30

Y1284 VA Hospital Cincinnati PSG Mod MOP, Rev 3, 03-14-2023 31

Y1284 VA Hospital Cincinnati PSG Mod MOP, Rev 3, 03-14-2023 32

Y1284 VA Hospital Cincinnati PSG Mod MOP, Rev 3, 03-14-2023 33

Y1284 VA Hospital Cincinnati PSG Mod MOP, Rev 3, 03-14-2023 34

Y1284 VA Hospital Cincinnati PSG Mod MOP, Rev 3, 03-14-2023 37

Y1284 VA Hospital Cincinnati PSG Mod MOP, Rev 3, 03-14-2023 38

File details come from the government source that posted it. Updated .