2026-7-27 ABB email with additional work required_Redacted.pdf
PDF 106 KB Posted
- Attached to
- J061--Emergency Switchgear Repairs PWS 539
- Solicitation number
- 36C25027Q0125
About this file
This document is an email correspondence regarding a federal facilities maintenance project at the Cincinnati VA.
The Department of Veterans Affairs (VA) has determined that an upgrade to the MFR13 Relay at the Cincinnati VA facility is the only viable solution to repair the Emergency Power Supply System. The scope of work extends beyond a simple relay replacement and includes programming of the upgraded relay to ensure proper system functionality, door modifications to support installation and operation, wiring modifications to accommodate the upgraded relay, and updates to existing systems drawings. Due to these additional labor and material requirements, the total project cost is higher than the initial estimate. The sender references a similar quote provided in 2025 for the relay upgrade and offers to prepare a detailed quote outlining the additional costs for review. The email indicates coordination among VA personnel, ABB (a service provider), Calvary Contracting, and Queen City Generator Service, suggesting this may involve contracted services for the emergency power system work.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Winslow, Juliet J. VHACIN
From:
Sent: Monday, July 27, 2026 6:20 PM
To:
Cc:
Subject: [EXTERNAL] Re: Cincinnati VA - Repair Emergency Power Supply System - Meeting minutes 7/22/2026- Relay still did not work
Julie, After reviewing the project requirements and available options, it has been determined that the only viable solution is to upgrade the MFR13 Relay.
The upgrade is expected to be more expensive than originally anticipated because the scope of work extends beyond simply replacing the relay. The upgrade will also require:
• Programming of the upgraded relay to ensure proper system functionality.
• Door modifications to support the installation and operation of the upgraded relay.
• Wiring modifications to accommodate the upgraded relay
• Changes to the existing systems drawings for the upgrade.
Due to these additional labor and material requirements, the total project cost will be higher than our initial estimate. While this was not anticipated as the solution, these modifications are necessary to ensure the system functions properly.
Please let us know if you would like us to prepare a quote outlining the additional costs associated with this work for your review. I believe a similar quote was provided in 2025 for the relay upgrade.
If you have any questions or would like to discuss the project in more detail, please feel free to reach out.
Thanks, From: Winslow, Juliet J. VHACIN <Juliet.Winslow@va.gov>
Sent: Wednesday, July 22, 2026 1:17 PM
To: Weidig, Jason H., VHACIN <Jason.Weidig@va.gov>; Kevin MILLER <kevin.miller@us.abb.com>; Smith, Chad A.
<Chad.Smith2@va.gov>; queencitygenservice@gmail.com <queencitygenservice@gmail.com>; Rodney Washburn
<rwashburn@calvarycontracting.com>; Eric Deaton [EXT] <eric.deaton@us.abb.com>; Brian Bednar
<brian.bednar@us.abb.com>
Cc: Fred Ervin <fred.ervin@us.abb.com>; John Moon <jmoon@calvarycontracting.com>; Appelgate, Conner VHACIN
File details come from the government source that posted it. Updated .