VASWT Submittal 221216-042-1 Water Tower Calcs and Drawings Approved.pdf
PDF 4 MB Posted
- Attached to
- 655-26-201 Repaint Water Tower
- Solicitation number
- 36C25026R0062
About this file
This document is a submittal transmittal and related engineering design documentation for a water tower replacement project at Aleda E. Lutz Veterans Affairs Medical Center in Saginaw, Michigan (VA Project #655-09-109). The project, identified as C2AE Project #11-0105 with Submittal #42R1, concerns the design and construction of a 250,000-gallon spheroid potable water storage tank under Specification Section 221216. The contractor is Daniels Building Company, Inc., with the project manager being Stephen Dickerson. The submittals include resubmitted structural design shop drawings and calculations for the water tower, with the design review dated March 6, 2012, and marked as "No Exception Taken" by C2AE engineer K. Homic. The Contracting Officer's Technical Representative (COTR) is Kevin Russell of the Aleda E. Lutz Medical Center.
The submittal package includes comprehensive engineering drawings and design calculations prepared by River Valley Engineering, Inc., and Maguire Iron, Inc. (the fabricator). The tank design conforms to AWWA D-100-2005 standards with a design capacity of 250,000 gallons and working capacity of 252,473 gallons. Key design parameters include a height to high water line of 151 feet, head range of 31.25 feet, free board of 6.6976 feet, snow load of 40 psf, and wind speed of 90 mph. The spheroid tank features detailed specifications for all structural components, including the roof, knuckles, pedestal, base cone, and foundation system with anchor bolts and supporting infrastructure. The documentation encompasses structural calculations, tank geometry specifications, section designs, and multiple shop drawings detailing the fabrication and assembly of the 250 MG (250,000-gallon) spheroid water storage tank for the VA Medical Center in Saginaw, Michigan.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Transmittal
(If enclosures are not as noted, kindly notify us at once)
Project #: 11-0105 Date: March 6, 2012 Project: Aleda E. Lutz Medical Center C2AE Submittal #: 42R1 Replace Water Tower & Bulk Oxygen Specification Section: 221216 Tank, VA Project #655-09-109 Specification Title: Facility Elevated, Potable-Water
Storage Tanks Project Manager: Stephen Dickerson To: Kevin Russell, COTR Aleda E. Lutz Medical Center Distribution:
1500 Weiss St Saginaw, MI 48602
Enclosures: Attached Change Order Specifications
Report Shop Drawings Under Separate Cover Other ________________
Letter Submittal Review Plans
Quantity Description/Document Title
1 Resubmittal of water tower structural design shop drawing, and structural design calculations
Action Requested:
For Review and Approval No Exception Taken See Comment Sheet for Notations
For Your Use Exception As Noted Resubmit _____ Copies for Review
As Requested Rejected Submit _____ Copies for Distribution
Revise and Resubmit Return _____ Corrected Prints
For Bids Due ______________________ Other_________________________
Notes: C2AE strongly recommends that the original engineer review this submittal.
Kristy P. Baisch, Administrative Assistant
C2AE
NO EXCEPTION TAKEN REVISE AND RESUBMIT
EXCEPTION AS NOTED REJECTED
SEE COMMENT SHEET FOR NOTATIONS
C2AE
By Date 3/6/2012K. Homic
This review is only for general conformance with the design concept and the information given in the Construction Documents. Corrections or comments made on the submittal during this review do not relieve the contractor from compliance with the requirements of the plans and specifications. Review of a specific item shall not include review of an assembly of which the item is a component. The Contractor is responsible for: dimensions to be confirmed and correlated at the jobsite; information that pertains solely to the fabrication processes or to the means, methods, techniques, sequences and procedures of construction; coordination of the Work with that of all other trades and performing all Work in a safe and satisfactory manner.3/13/2012 PLR x
VHASAGRusseK Approved kristy.baisch New Stamp
Text Box
SEE NOTE ON WATER TOWER PAGE.
Approved as Noted
Text Box DRAWING LOOKS DISPROPORTIONATE, BASE IS LISTED AS APPROX 30' DIAMETER, SPHERE IS LISTED AS 43' DIAMETER.
| REV 03 |
| VASWT Submittal 221216-042 Shop Drawings Approved as Noted |
File details come from the government source that posted it. Updated .