Spec update.pdf

PDF 366 KB Posted

Attached to
J047--Medical Gas Deficiency 610A4-26-507 (VA-26-00058207)
Solicitation number
36C25026Q0452
Issued by

About this file

This is a federal construction contract specification document for replacing the medical gas system at Fort Wayne VA Medical Center. The contract encompasses comprehensive labor and materials for installing new air compressors, vacuum pumps, medical gas piping, valves, gages, alarm systems, and all associated equipment and accessories to replace existing systems.

Key deliverables include duplex medical air and vacuum pump systems with desiccant dryers, final line filters and regulators, dew point and carbon monoxide monitors, ASME-coded air receivers, pressure and vacuum gages, alarm panels with local and master alarm functions for oxygen, compressed air, and vacuum services, zone valves in cabinets, piping identification, low-voltage control wiring, conduit systems, and all necessary penetration sealing and firestopping. The contractor must comply with NFPA 99 standards and provide comprehensive testing and certification by an independent medical gas testing agency, including piping purge tests, purity tests, cross-connection tests, and contamination analysis. Installation must follow a phased approach with a 2-day hospital-wide medical air shutdown and a 2-week shutdown for final connections and testing. The contractor is required to provide four copies of maintenance and operating manuals, factory-trained instructors for equipment operation and maintenance training (minimum two 4-hour sessions), and OSHA compliance including a certified competent person on-site, 10-hour safety training for all personnel, and fire safety plans. All work must maintain existing utility services, minimize disruption to hospital operations, comply with VA security protocols, and coordinate with the Infection Control Risk Assessment team regarding dust control measures.

View the file

Other files

File Type Posted
36C25026Q0452 0005.docx DOCX document
36C25026Q0452 0004.docx DOCX document
FLR compressed MedGas Surgery.pdf PDF
610A4-26-507 Correct Med-Gas - Specs.pdf PDF
3Floor Architectural Original.pdf PDF
IMG_0706.jpg JPG image
IMG_0712.jpg JPG image
IMG_0713.jpg JPG image
IMG_0705.jpg JPG image
IMG_0709.jpg JPG image
IMG_0707.jpg JPG image
IMG_0714.jpg JPG image
Plumbing.pdf PDF
third floor compressed air-natural gs-oxygen-nitrous oxide-vacuum.pdf PDF
Site Visit Sign in Sheet.pdf PDF
36C25026Q0452 0003.docx DOCX document
36C25026Q0452 0002.docx DOCX document
36C25026Q0452 0001.docx DOCX document
Attachment IV - Specs.pdf PDF
Attachment I - Wage Determination.pdf PDF
Attachment II - VAAR 852.219-75 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING_CERTIFICATE OF COMPLIANCE.docx DOCX document
36C25026Q0452.docx DOCX document
Attachment V - RFI Template.doc DOC document
Attachment III - Med Gas System Maintenance Inspection.pdf PDF
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 01010

GENERAL REQUIREMENTS

1.1 GENERAL INTENTION

A. Contractor shall furnish labor and materials and perform work for Replace Medical Gas System, Ft. Wayne as required by drawings and specifications.

B. Visits to the site by Bidders may be made only by appointment with the Contracting Officer.

E. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.

F. Prior to commencing work, general contractor shall provide proof that a OSHA certified “competent person” (CP) (29 CFR 1926.20(b)(2) will maintain a presence at the work site whenever the general or subcontractors are present.

G. Training:

1. Beginning January 1, 2005, all employees of general contractor or subcontractors shall have the 10-hour OSHA certified Construction Safety course.

2. Submit training records of all such employees for approval before the start of work.

1.2 STATEMENT OF BID ITEM(S)

A. ITEM I, Work includes all items shown on the drawings and detailed in the specifications.

1.3 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

A. AFTER AWARD OF CONTRACT, 5 sets of specifications and drawings will be furnished. These drawings and specifications will consist of those returned by prospective bidders.

1.4 FIRE SAFETY

A. Applicable Publications: Publications listed below form part of this Article to extent referenced. Publications are referenced in text by basic designations only.

1. American Society for Testing and Materials (ASTM):

E84-2005 ..........................Surface Burning Characteristics of Building Materials

2. National Fire Protection Association (NFPA):

10-2002 ............................Standard for Portable Fire Extinguishers 30-2003 ............................Flammable and Combustible Liquids Code 51B-2003..........................Standard for Fire Prevention During Welding, Cutting and

Other Hot Work 70-2005 ............................National Electrical Code 241-2004 ..........................Standard for Safeguarding Construction, Alteration, and

Demolition Operations

3. Occupational Safety and Health Administration (OSHA):

29 CFR 1926 ....................Safety and Health Regulations for Construction

B. Fire Safety Plan: Establish and maintain a fire protection program in accordance with 29 CFR 1926. Prior to start of work, prepare a plan detailing project-specific fire safety measures, including periodic status reports, and submit to COTR for review for compliance with contract requirements in accordance with Section 01340, SAMPLES AND SHOP DRAWINGS. Prior to any worker for the contractor or subcontractors beginning work, they shall undergo a safety briefing provided by the general contractor’s competent person per OSHA requirements. This briefing shall include information on the construction limits, VAMC safety guidelines, means of egress, break areas, work hours, locations of restrooms, use of VAMC equipment, etc. Documentation shall be provided to the COTR that individuals have undergone contractor’s safety briefing.

C. Site and Building Access: Maintain free and unobstructed access to facility emergency services and for fire, police and other emergency response forces in accordance with

NFPA 241.

D. Means of Egress: Do not block exiting for occupied buildings, including paths from exits to roads. Minimize disruptions and coordinate with COTR.

E. Egress Routes for Construction Workers: Maintain free and unobstructed egress.

F. Existing Fire Protection: Do not impair automatic sprinklers, smoke and heat detection, and fire alarm systems.

G. Hot Work: Perform and safeguard hot work operations in accordance with NFPA 241 and

NFPA 51B. Coordinate with COTR. Obtain permits from COTR.

H. Smoking: Smoking is prohibited in and adjacent to gospital buildings except in designated areas.

I. Dispose of waste and debris in accordance with NFPA 241. Remove from buildings daily.

J. Perform other construction, alteration and demolition operations in accordance with 29

CFR 1926.

1.5 OPERATIONS AND STORAGE AREAS

A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.

B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the Contracting Officer, the buildings and utilities may be abandoned and need not be removed.

C. The Contractor shall, under regulations prescribed by the Contracting Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.

D. Working space and space available for storing materials shall be as determined by the

COTR.

E. Workmen are subject to rules of the Medical Center applicable to their conduct.

F. Execute work so as to interfere as little as possible with normal functioning of the

Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COTR where required by limited working space.

1. Do not store materials and equipment in other than assigned areas.

2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of Veterans Affairs in quantities sufficient for not more than two work days. Provide unobstructed access to Medical Center areas required to remain in operation.

G. Phasing.

1. Phase 1. Complete project within the contract completion time frame with the following constraints.

a. Installation/Demolition sequence of the major equipment/systems to be.

1. Install new medical air equipment in the penthouse.

2. Remove existing medical air equipment in the penthouse.

3. Install new medical vacuum equipment in the penthouse.

4. Remove existing medical vacuum equipment in the basement.

b. Connection of the new medical air equipment to the existing hospital piping distribution is to take place during a 2-day hospital-wide medical air shutdown.

During the 2-day shutdown the new equipment is to be piped, tested and certified for use. Shutdown not be begin on a Monday or a Friday. Provide a written 10-day notice of the shutdown and confirmation 3 days before the shutdown.

c. A 2-week hospital-wide medical air, medical vacuum ,oxygen, nitrogen and nitrous oxide shutdown to be scheduled by the contractor at which time all final connections, testing and certifications of the remaining equipment and alarms not installed during the 2-day shutdown is to take place. Provide a written 2-week notice of the shutdown and confirmation 1 week before the shutdown.

d. The contractor is to provide a 3-day notice prior to beginning pre-shutdown work in Emergency Entrance, Cardiopulmonary, 3-East, Surgery, ICU and 4-East areas.

e. No later than two (2) weeks prior to the first scheduled shutdown the contractor is to provide a comprehensive testing and certification procedure/sequence specific for this project prepared by a medical gas testing agency for approval.

H. Utilities Services: Maintain existing utility services for the Medical Center at all times.

1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COTR. Electrical work shall be accomplished with all affected circuits or equipment de-energized. When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without the Medical Center

Director’s prior knowledge and written approval. Refer to specification Section 16050 for additional requirements.

2. Contractor shall submit a request to interrupt any such services to COTR, in writing, 48 hours in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.

3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of the Medical Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.

4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COTR.

5. In case of a contract construction emergency, service will be interrupted on approval of COTR. Such approval will be confirmed in writing as soon as practical.

I. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, which are to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.

1.6 INFECTION PREVENTION MEASURES

A. Implement the requirements of VAMC’s Infection Control Risk Assessment (ICRA) team. ICRA Group may monitor dust in the vicinity of the construction work and require the Contractor to take corrective action immediately if the safe levels are exceeded.

B. Establish and maintain a dust control program as part of the contractor’s infection preventive measures in accordance with the guidelines provided by ICRA Group. Prior to start of work, prepare a plan detailing project-specific dust protection measures, including periodic status reports, and submit to the COTR for review for compliance with contract requirements in accordance with Section 01340, SAMPLES AND SHOP

DRAWINGS.

1. All personnel involved in the construction or renovation activity shall be educated and trained in infection prevention measures established by the medical center.

1.7 RESTORATION

A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the COTR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COTR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.

B. Upon completion of contract, deliver work complete and undamaged. Existing work disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.

C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workmen to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems.

D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES" (FAR 52.243-4 and VAAR 852.236-88) and "DIFFERING SITE CONDITIONS" (FAR 52.236-2) of Section 01001, GENERAL

CONDITIONS.

1.8 TESTS

A. Conduct final tests required in various sections of specifications in presence of an authorized representative of the Contracting Officer. Contractor shall furnish all labor, materials, equipment, instruments, and forms, to conduct and record such tests.

1.9 INSTRUCTIONS

A. Contractor shall furnish Maintenance and Operating manuals and verbal instructions when required by the various sections of the specifications and as hereinafter specified.

B. Manuals: Maintenance and operating manuals (four copies each) for each separate piece of equipment shall be delivered to the COTR coincidental with the delivery of the equipment to the job site. Manuals shall be complete, detailed guides for the maintenance and operation of equipment. They shall include complete information necessary for starting, adjusting, maintaining in continuous operation for long periods of time and dismantling and reassembling of the complete units and sub-assembly components.

Manuals shall include an index covering all component parts clearly cross-referenced to diagrams and illustrations. Illustrations shall include "exploded" views showing and identifying each separate item. Emphasis shall be placed on the use of special tools and instruments. The function of each piece of equipment, component, accessory and control shall be clearly and thoroughly explained. All necessary precautions for the operation of the equipment and the reason for each precaution shall be clearly set forth. Manuals must reference the exact model, style and size of the piece of equipment and system being furnished. Manuals referencing equipment similar to but of a different model, style, and size than that furnished will not be accepted.

C. Instructions: Contractor shall provide qualified, factory-trained manufacturers' representatives to give detailed instructions to assigned Department of Veterans Affairs personnel in the operation and complete maintenance for each piece of equipment. All such training will be at the job site. These requirements are more specifically detailed in the various technical sections. Instructions for different items of equipment that are component parts of a complete system, shall be given in an integrated, progressive manner. All instructors for every piece of component equipment in a system shall be available until instructions for all items included in the system have been completed. This is to assure proper instruction in the operation of inter-related systems. All instruction periods shall be at such times as scheduled by the COTR and shall be considered concluded only when the COTR is satisfied in regard to complete and thorough coverage.

The Department of Veterans Affairs reserves the right to request the removal of, and substitution for, any instructor who, in the opinion of the COTR, does not demonstrate sufficient qualifications in accordance with requirements for instructors above.

1.10 RELOCATED ITEMS

A. Contractor shall disconnect, dismantle as necessary, remove and reinstall in new location, all existing equipment shown to be relocated by the Contractor.

B. Perform relocation of such equipment or items at such times and in such a manner as directed by the COTR.

C. Suitably cap existing service lines, such as steam, condensate return, water, drain, gas, air, vacuum and/or electrical, whenever such lines are disconnected from equipment to be relocated. Remove abandoned lines in finished areas and cap as specified herein before under paragraph "Abandoned Lines".

D. Provide all mechanical and electrical service connections, fittings, fastenings and any other materials necessary for assembly and installation of relocated equipment; and leave such equipment in proper operating condition.

- - - E N D - - -

SECTION 01340

SAMPLES AND SHOP DRAWINGS

NOTE:

1. CONTRATOR TO PROVIDE 5 CIOPIES OF EACH SUBMITTAL. THE

GOVERNMENT WILL RETAIN 3 COPIES AND RETURN 2 FOR CONTRACTOR

USE.

2. SUBMITTALS ARE TO BE MAILED DIRECTLY TO THE COTR AT THE

ADDRESS NOTED BELOW.

1-1. Refer to Articles titled SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION

(FAR 52.236-21) and, SPECIAL NOTES (VAAR 852.236-91), in Section, GENERAL

CONDITIONS.

1-2. For the purposes of this contract, samples, test reports, certificates, and manufacturers' literature and data shall also be subject to the previously referenced requirements. The following text refers to all items collectively as SUBMITTALS.

1-3. Submit for approval, all of the items specifically mentioned under the separate sections of the specification, with information sufficient to evidence full compliance with contract requirements. Materials, fabricated articles and the like to be installed in permanent work shall equal those of approved submittals. After an item has been approved, no change in brand or make will be permitted unless:

A. Satisfactory written evidence is presented to, and approved by Contracting Officer, that manufacturer cannot make scheduled delivery of approved item or;

B. Item delivered has been rejected and substitution of a suitable item is an urgent necessity or;

C. Other conditions become apparent which indicates approval of such substitute item to be in best interest of the Government.

1-4. Forward submittals in sufficient time to permit proper consideration and approval action by Government. Time submission to assure adequate lead time for procurement of contract - required items. Delays attributable to untimely and rejected submittals will not serve as a basis for extending contract time for completion.

1-5. Submittals will be reviewed for compliance with contract requirements by COTR and action thereon will be taken on behalf of the Contracting Officer.

1-6. Upon receipt of submittals, COTR will assign a file number thereto. Contractor, in any subsequent correspondence, shall refer to this file and identification number to expedite replies relative to previously approved or disapproved submittals.

1-7. The Government reserves the right to require additional submittals, whether or not particularly mentioned in this contract. If additional submittals beyond those required by the contract are furnished pursuant to request therefore by Contracting Officer, adjustment in contract price and time will be made in accordance with Articles titled CHANGES (FAR 52.243-4) and CHANGES - SUPPLEMENT (VAAR 852.236-88) of the GENERAL CONDITIONS.

1-8. Schedules called for in specifications and shown on shop drawings shall be submitted for use and information of Department of Veterans Affairs and COTR. However, the Contractor shall assume responsibility for coordinating and verifying schedules. The Contracting Officer and Architect- Engineer assumes no responsibility for checking schedules or layout drawings for exact sizes, exact numbers and detailed positioning of items.

1-9. Submittals must be submitted by Contractor only and shipped prepaid. Contracting Officer assumes no responsibility for checking quantities or exact numbers included in such submittals.

A. Submittals will receive consideration only when covered by a transmittal letter signed by Contractor. Letter shall be sent via first class mail and shall contain the list of items, name of Medical Center, name of Contractor, contract number, applicable specification paragraph numbers, applicable drawing numbers (and other information required for exact identification of location for each item), manufacturer and brand, ASTM or Federal Specification Number (if any) and such additional information as may be required by specifications for particular item being furnished. In addition, catalogs shall be marked to indicate specific items submitted for approval.

1. A copy of letter must be enclosed with items, and any items received without identification letter will be considered "unclaimed goods" and held for a limited time only.

2. Each sample, certificate, manufacturers' literature and data shall be labeled to indicate the name and location of the Medical Center, name of Contractor, manufacturer, brand, contract number and ASTM or Federal Specification Number as applicable and location(s) on project.

3. Required certificates shall be signed by an authorized representative of manufacturer or supplier of material, and by Contractor.

B. If submittal samples have been disapproved, resubmit new samples as soon as possible after notification of disapproval. Such new samples shall be marked "Resubmitted Sample" in addition to containing other previously specified information required on label and in transmittal letter.

C. Approved samples will be kept on file by the COTR at the site until completion of contract, at which time such samples will be delivered to Contractor as Contractor's property. Where noted in technical sections of specifications, approved samples in good condition may be used in their proper locations in contract work. At completion of contract, samples that are not approved will be returned to Contractor only upon request and at Contractor's expense. Such request should be made prior to completion of the contract. Disapproved samples that are not requested for return by Contractor will be discarded after completion of contract.

D. Submittal drawings (shop, erection or setting drawings) and schedules, required for work of various trades, shall be checked before submission by technically qualified employees of Contractor for accuracy, completeness and compliance with contract requirements.

These drawings and schedules shall be stamped and signed by Contractor certifying to such check.

1. For each drawing required, submit one legible photographic paper or vellum reproducible.

2. Reproducible shall be full size.

3. Each drawing shall have marked thereon, proper descriptive title, including Medical

Center, project number, manufacturer's number, reference to contract drawing number, detail Section Number, and Specification Section Number.

4. A space 120 mm by 125 mm (4-3/4 by 5 inches) shall be reserved on each drawing to accommodate approval or disapproval stamp.

5. Submit drawings, ROLLED WITHIN A MAILING TUBE, fully protected for shipment.

6. One reproducible print of approved or disapproved shop drawings will be forwarded to Contractor.

7. When work is directly related and involves more than one trade, shop drawings shall be submitted to COTR under one cover.

1-10. Samples, shop drawings, test reports, certificates and manufacturers' literature and data, shall be submitted for approval to VA Northern Indiana Health Care System

1700 E. 38th Street Marion, Indiana 46953

Attn: Sam Elkins (138B)

SECTION 07270

FIRESTOPPING SYSTEMS

PART 1 GENERAL

1.1 DESCRIPTION

A. Closures of openings in walls and floors against penetration of flame, heat, and smoke or gases in fire resistant rated construction.

B. Closure of openings in walls against penetration of gases or smoke in smoke partitions.

1.2 RELATED WORK

A. Sealants and application: Section 07920, SEALANTS AND CAULKING.

1.3 SUBMITTALS

A. Submit in accordance with Section 01340, SAMPLES AND SHOP DRAWINGS.

B. Manufacturers literature, data, and installation instructions for types of firestopping and smoke stopping used.

C. List of FM, UL, or WH classification number of systems installed.

1.4 DELIVERY AND STORAGE

A. Deliver materials in their original unopened containers with manufacturer’s name and product identification.

B. Store in a location providing protection from damage and exposure to the elements.

1.5 WARRANTY

Firestopping work subject to the terms of the Article “Warranty of Construction” of Section GENERAL CONDITIONS, except extend the warranty period to five years.

1.6 QUALITY ASSURANCE

FM, UL, or WH or other approved laboratory tested products will be acceptable.

1.7 APPLICABLE PUBLICATIONS

A. Publications listed below form a part of this specification to the extent referenced.

Publications are referenced in the text by the basic designation only.

B. American Society for Testing and Materials (ASTM):

E84-01 ....................................Surface Burning Characteristics of Building Materials E814-02 ..................................Fire Tests of Through-Penetration Fire Stops

C. Factory Mutual Engineering and Research Corporation (FM):

Annual Issue Approval Guide Building Materials D. Underwriters Laboratories, Inc. (UL):

Annual Issue Building Materials Directory

Annual Issue Fire Resistance Directory 1479-00 ..................................Fire Tests of Through-Penetration Firestops

E. Warnock Hersey (WH):

Annual Issue Certification Listings

PART 2 - PRODUCTS

2.1 FIRESTOP SYSTEMS

A. Use either factory built (Firestop Devices) or field erected (through-Penetration Firestop Systems) to form a specific building system maintaining required integrity of the fire barrier and stop the passage of gases or smoke.

B. Through-penetration firestop systems and firestop devices tested in accordance with ASTM E814 or UL 1479 using the "F" or "T" rating to maintain the same rating and integrity as the fire barrier being sealed. "T" ratings are not required for penetrations smaller than or equal to 100 mm (4 in) nominal pipe or 0.01 m2 (16 sq. in.) in overall cross sectional area.

C. Products requiring heat activation to seal an opening by its intumescence shall exhibit a demonstrated ability to function as designed to maintain the fire barrier.

D. Firestop sealants used for firestopping or smoke sealing shall have following properties:

1. Contain no flammable or toxic solvents.

2. Have no dangerous or flammable outgassing during the drying or curing of products.

3. Water-resistant after drying or curing and unaffected by high humidity, condensation or transient water exposure.

4. When used in exposed areas, shall be capable of being sanded and finished with similar surface treatments as used on the surrounding wall or floor surface.

E. Firestopping system or devices used for penetrations by glass pipe, plastic pipe or conduits, unenclosed cables, or other non-metallic materials shall have following properties:

1. Classified for use with the particular type of penetrating material used.

2. Penetrations containing loose electrical cables, computer data cables, and communications cables protected using firestopping systems that allow unrestricted cable changes without damage to the seal.

3. Intumescent products which would expand to seal the opening and act as fire, smoke, toxic fumes, and, water sealant.

F. Maximum flame spread of 25 and smoke development of 50 when tested in accordance with ASTM E84.

G. FM, UL, or WH rated or tested by an approved laboratory in accordance with ASTM E814.

H. Materials to be asbestos free.

2.2 SMOKE STOPPING IN SMOKE PARTITIONS

A. Use silicone sealant in smoke partitions as specified in section SEALANTS AND

CAULKING.

B. Use mineral fiber filler and bond breaker behind sealant.

C. Sealants shall have a maximum flame spread of 25 and smoke developed of 50 when tested in accordance with E84.

D. When used in exposed areas capable of being sanded and finished with similar surface treatments as used on the surrounding wall or floor surface.

PART 3 - EXECUTION

3.1 PREPARATION

A. Remove dirt, grease, oil, loose materials, or other substances that prevent adherence and bonding or application of the firestopping or smoke stopping materials.

B. Remove insulation on insulated pipe for a distance of 150 mm (six inches) on either side of the fire rated assembly prior to applying the firestopping materials unless the firestopping materials are tested and approved for use on insulated pipes.

3.2 INSTALLATION

A. Do not begin work until the specified material data and installation instructions of the proposed firestopping systems have been submitted and approved.

B. Install firestopping systems with smoke stopping in accordance with FM, UL, WH, or other approved system details and installation instructions.

C. Install smoke stopping seals in smoke partitions.

3.3 CLEAN-UP AND ACCEPTANCE OF WORK

A. As work on each floor is completed, remove materials, litter, and debris.

B. Do not move materials and equipment to the next-scheduled work area until completed work is inspected and accepted by the Resident Engineer.

C. Clean up spills of liquid type materials.

SECTION 07920

SEALANTS AND CAULKING

PART 1 - GENERAL

1.1 DESCRIPTION:

Section covers all sealant and caulking materials and their application, wherever required for complete installation of building materials or systems.

1.2 RELATED WORK:

A. Firestopping penetrations: Section 07270, FIRESTOPPING SYSTEMS.

B. Mechanical Work: Section 15050, BASIC METHODS AND REQUIREMENTS

(MECHANICAL).

1.3 SUBMITTALS:

A. Submit in accordance with Section 01340, SAMPLES AND SHOP DRAWINGS.

B. Manufacturer's installation instructions for each product used.

C. Manufacturer's Literature and Data:

1.4 DELIVERY, HANDLING, AND STORAGE:

A. Deliver materials in manufacturers' original unopened containers, with brand names, date of manufacture, shelf life, and material designation clearly marked thereon.

B. Carefully handle and store to prevent inclusion of foreign materials.

C. Do not subject to sustained temperatures exceeding 5 °C (90 °F) or less than 32 °C (40

°F).

1.5 APPLICABLE PUBLICATIONS:

A. Publications listed below form a part of this specification to extent referenced.

Publications are referenced in text by basic designation only.

B. American Society for Testing and Materials (ASTM):

C509-00..................................Elastomeric Cellular Preformed Gasket and Sealing

Material.

C612-00..................................Mineral Fiber Block and Board Thermal Insulation.

C717-03..................................Standard Terminology of Building Seals and Sealants.

C834-00..................................Latex Sealants.

C919-02..................................Use of Sealants in Acoustical Applications.

C920-02..................................Elastomeric Joint Sealants.

C1021-01................................Laboratories Engaged in Testing of Building Sealants C1193-00................................Standard Guide for Use of Joint Sealants.

C1330-02................................Specification for Cylindrical Sealant Backing for Use with

Cold Liquid Applied Sealants.

D1056-00 ...............................Specification for Flexible Cellular Materials—Sponge or Expanded Rubber.

E84-03 ....................................Surface Burning Characteristics of Building Materials.

C. Sealant, Waterproofing and Restoration Institute (SWRI).

The Professionals’ Guide

2.1 SEALANTS:

A. S-1:

1. ASTM C920, polyurethane or polysulfide.

2. Type M.

3. Class 25.

4. Grade NS.

5. Shore A hardness of 20-40

B. S-2:

1. ASTM C920, polyurethane or polysulfide.

2. Type M.

3. Class 25.

4. Grade P.

5. Shore A hardness of 25-40.

C. S-3:

1. ASTM C920, polyurethane or polysulfide.

2. Type S.

3. Class 25, joint movement range of plus or minus 50 percent.

4. Grade NS.

5. Shore A hardness of 15-25.

6. Minimum elongation of 700 percent.

2.2 CAULKING COMPOUND:

A. C-1: ASTM C834, acrylic latex.

B. C-2: One component acoustical caulking, non drying, non hardening, synthetic rubber.

2.3 COLOR:

A. Sealants used with exposed masonry shall match color of mortar joints.

B. Color of sealants for other locations shall be light gray or aluminum, unless specified otherwise.

D. Caulking shall be a neutral color.

2.4 JOINT SEALANT BACKING:

A. General: Provide sealant backings of material and type that are nonstaining; are compatible with joint substrates, sealants, primers, and other joint fillers; and are approved for applications indicated by sealant manufacturer based on field experience and laboratory testing.

B. Cylindrical Sealant Backings: ASTM C1330, of type indicated below and of size and density to control sealant depth and otherwise contribute to producing optimum sealant performance:

1. Type C: Closed-cell material with a surface skin.

C. Elastomeric Tubing Sealant Backings: Neoprene, butyl, EPDM, or silicone tubing complying with ASTM D1056, nonabsorbent to water and gas, and capable of remaining resilient at temperatures down to minus 32 °C (minus 26 °F). Provide products with low compression set and of size and shape to provide a secondary seal, to control sealant depth, and otherwise contribute to optimum sealant performance.

D. Bond-Breaker Tape: Polyethylene tape or other plastic tape recommended by sealant manufacturer for preventing sealant from adhering to rigid, inflexible joint-filler materials or joint surfaces at back of joint where such adhesion would result in sealant failure. Provide self-adhesive tape where applicable.

2.5 FILLER:

A. Mineral fiber board: ASTM C612, Class 1.

B. Thickness same as joint width.

C. Depth to fill void completely behind back-up rod.

2.6 PRIMER:

A. As recommended by manufacturer of caulking or sealant material.

B. Stain free type.

2.7 CLEANERS-NON POUROUS SURFACES:

A. Chemical cleaners acceptable to manufacturer of sealants and sealant backing material, free of oily residues and other substances capable of staining or harming joint substrates and adjacent non-pourous surfaces and formulated to promote adhesion of sealant and substrates.

3.1 INSPECTION:

A. Inspect substrate surface for bond breaker contamination and unsound materials at adherent faces of sealant.

B. Coordinate for repair and resolution of unsound substrate materials.

C. Inspect for uniform joint widths and that dimensions are within tolerance established by sealant manufacturer.

3.2 PREPARATIONS:

A. Prepare joints in accordance with manufacturer's instructions and SWRI.

B. Clean surfaces of joint to receive caulking or sealants in accordance with manufacturers instructions.

3.3 INSTALLATION:

A. General:

1. Apply sealants and caulking only when ambient temperature is between

5 degrees C and 38 degrees C (40 and 100 degrees F).

2. Do not use polysulfide base sealants where sealant may be exposed to fumes from bituminous materials, or where water vapor in continuous contact with cementitious materials may be present.

3. Do not use sealant type listed by manufacture as not suitable for use in locations specified.

4. Apply caulking and sealing compound in accordance with manufacturer's printer instructions.

5. Avoid dropping or smearing compound on adjacent surfaces.

6. Fill joints solidly with compound and finish compound smooth.

7. Tool joints to concave surface unless shown or specified otherwise.

8. Finish paving or floor joints flush unless joint is otherwise detailed.

9. Apply compounds with nozzle size to fit joint width.

10. Test sealants for compatibility with each other and substrate. Use only compatible sealant.

B. For application of sealants, follow requirements of ASTM C1193 unless specified otherwise.

C. Where gypsum board partitions are of sound rated, fire rated, or smoke barrier construction, follow requirements of ASTM C919 only to seal all cut-outs and intersections with the adjoining construction unless specified otherwise.

1. Apply a 6 mm (1/4 inch) minimum bead of sealant each side of runners (tracks), including those used at partition intersections with dissimilar wall construction.

2. Coordinate with application of gypsum board to install sealant immediately prior to application of gypsum board.

3. Partition intersections: Seal edges of face layer of gypsum board abutting intersecting partitions, before taping and finishing or application of veneer plaster-joint reinforcing.

4. Openings: Apply a 6 mm (1/4 inch) bead of sealant around all cut-outs to seal openings of electrical boxes, ducts, pipes and similar penetrations. To seal electrical boxes, seal sides and backs.

5. Control Joints: Before control joints are installed, apply sealant in back of control joint to reduce flanking path for sound through control joint.

3.4 LOCATIONS:

A. Exterior Building Joints, Horizontal and Vertical:

1. Metal to Metal: Type S-1, S-2

2. Metal to Masonry or Stone: Type S-1

3. Masonry to Masonry or Stone: Type S-1

4. Stone to Stone: Type S-1

5. Cast Stone to Cast Stone: Type S-1

6. Threshold Setting Bed: Type S-1, S-3, S-4

7. Masonry Expansion and Control Joints: Type S-6

8. Wood to Masonry: Type S-1

SECTION 15050

BASIC METHODS AND REQUIREMENTS (MECHANICAL)

A. Basic methods and requirements for Division 15, MECHANICAL, applies to all sections of Division 15.

1.2 RELATED WORK

A. Section 01001, GENERAL CONDITIONS.

B. Section 01010, GENERAL REQUIREMENTS.

C. Section 01340, SAMPLES AND SHOP DRAWINGS.

D. Section 15200, NOISE AND VIBRATION CONTROL E. Section 07270, FIRESTOPPING.

F. Section 07920, SEALANTS AND CAULKING.

G. Section 16050, BASIC METHODS AND REQUIRMENTS (ELECTRICAL)

1.3 QUALITY ASSURANCE

A. Products Criteria:

1. Standard Products: Material and equipment shall be the standard products of a manufacturer regularly engaged in the manufacture of the products for at least 3 years. See other specification sections for any exceptions.

2. Equipment Service: Products shall be supported by a service organization which maintains a complete inventory of repair parts and is located reasonably close to the site.

3. Multiple Units: When two or more units of materials or equipment of the same type or class are required, these units shall be products of one manufacturer.

4. Assembled Units: Manufacturers of equipment assemblies, which use components made by others, assume complete responsibility for the final assembled product.

5. Nameplates: Nameplate bearing manufacturer's name or identifiable trademark shall be securely affixed in a conspicuous place on equipment, or name or trademark cast integrally with equipment, stamped or otherwise permanently marked on each item of equipment.

6. Asbestos products or equipment or materials containing asbestos shall not be used.

B. Manufacturer's Recommendations: Where installation procedures or any part thereof are required to be in accordance with the recommendations of the manufacturer of the material being installed, printed copies of these recommendations shall be furnished to the COTR prior to installation. Installation of the item will not be allowed to proceed until the recommendations are received. Failure to furnish these recommendations can be cause for rejection of the material.

1.4 SUBMITTALS

A. Submit in accordance with Section 01340, SAMPLES AND SHOP DRAWINGS.

1.5 APPLICABLE PUBLICATIONS

A. The publications listed below form a part of this specification to the extent referenced.

The publications are referenced in the text by the basic designation only.

B. Air Conditioning and Refrigeration Institute (ARI):

430-99 ....................................Central Station Air-Handling Units

C. American National Standard Institute (ANSI):

B31.1-2001.............................Power Piping

D. Rubber Manufacturers Association (ANSI/RMA):

IP-20-2001 .............................Drives Using Classical V-Belts and Sheaves IP-21-88 .................................Drives Using Double-V (Hexagonal) Belts IP-22-91 .................................Drives Using Narrow V-Belts and Sheaves

E. Air Movement and Control Association (AMCA):

410-96 ....................................Recommended Safety Practices for Air Moving Devices

F. American Society of Mechanical Engineers (ASME):

Boiler and Pressure Vessel Code (BPVC):

SEC IX-98 ..............................Qualifications Standard for Welding and Brazing

Procedures, Welders, Brazers, and Welding and Brazing Operators

G. American Society for Testing and Materials (ASTM):

A36/A36M-2001 ....................Carbon Structural Steel A575-96 .................................Steel Bars, Carbon, Merchant Quality, M-Grades R (2002) E84-2003 ................................Standard Test Method for Burning Characteristics of

Building Materials E119-2000 ..............................Standard Test Method for Fire Tests of Building

Construction and Materials H. Manufacturers Standardization Society (MSS) of the Valve and Fittings Industry, Inc:

SP-58-93 ................................Pipe Hangers and Supports-Materials, Design and Manufacture

SP-69-96 ................................Pipe Hangers and Supports-Selection and Application I. National Association of Plumbing - Heating - Cooling Contractors (NAPHCC):

1996........................................National Standard Plumbing Code J. National Fire Protection Association (NFPA):

90A-96 ...................................Installation of Air Conditioning and Ventilating Systems 101-97 .............................................Life Safety Code

2.1 BELT DRIVES

A. Type: ANSI/RMA standard V-belts with proper motor pulley and driven sheave. Belts shall be constructed of reinforced cord and rubber.

B. Dimensions, rating and selection standards: ANSI/RMA IP-20 and IP-21.

C. Minimum Horsepower Rating: Motor horsepower plus recommended ANSI/RMA service factor (not less than 20 percent) in addition to the ANSI/RMA allowances for pitch diameter, center distance, and arc of contact.

D. Maximum Speed: 25 m/s (5000 feet per minute).

E. Adjustment Provisions: For alignment and ANSI/RMA standard allowances for installation and take-up.

F. Drives may utilize a single V-Belt (any cross section) when it is the manufacturer's standard.

G. Multiple Belts: Matched to ANSI/RMA specified limits by measurement on a belt measuring fixture. Seal matched sets together to prevent mixing or partial loss of sets.

Replacement, when necessary, shall be an entire set of new matched belts.

H. Sheaves and Pulleys:

1. Material: Pressed steel, or close grained cast iron.

2. Bore: Fixed or bushing type for securing to shaft with keys.

3. Balanced: Statically and dynamically.

4. Groove spacing for driving and driven pulleys shall be the same.

5. Minimum Diameter of V-Belt Sheaves (ANSI/RMA recommendations)in millimeters and inches:

Fractional

Horsepower Standard High Capacity

Cross Section

Min. od mm (in)

Cross Section

Min. od mm (in)

Cross Section

Min. od mm (in)

2L 20 (0.8) A 83 (3.25) 3V 67 (2.65)

3L 38 (1.5) B 146 (5.75) 4V 180 (7.10)

4L 64 (2.5) C 239 (9.40) 5V 318 (12.50)

5L 89 (3.5) D 345 (13.60)

E 554 (21.80)

I. Drive Types, Based on ARI 435:

1. Provide adjustable-pitch or fixed-pitch drive as follows:

a. Fan speeds up to 1800 RPM: 7.5 kW (10 horsepower) and smaller.

b. Fan speeds over 1800 RPM: 2.2 kW (3 horsepower) and smaller.

2. Provide fixed-pitch drives for drives larger than those listed above.

3. The final fan speeds required to just meet the system CFM and pressure requirements, without throttling, shall be determined by adjustment of a temporary adjustable-pitch motor sheave or by fan law calculation if a fixed-pitch drive is used initially.

2.2 DRIVE GUARDS

A. For machinery and equipment, provide guards as shown in AMCA 410 for belts, chains, couplings, pulleys, sheaves, shafts, gears and other moving parts regardless of height above the floor. Drive guards may be excluded where motors and drives are inside factory fabricated air handling unit casings.

B. Materials: Sheet steel, cast iron, expanded metal or wire mesh rigidly secured so as to be removable without disassembling pipe, duct, or electrical connections to equipment.

C. Access for Speed Measurement: 25 mm (One inch) diameter hole at each shaft center.

2.3 PIPE AND EQUIPMENT SUPPORTS AND RESTRAINTS

A. Vibration Isolators: Refer to Section 15200, NOISE AND VIBRATION CONTROL.

3.1 INSTALLATION

A. Coordinate location of piping, sleeves, inserts, hangers, and equipment. Locate piping, sleeves, inserts, hangers, and equipment clear of windows, doors, openings, light outlets, and other services and utilities. Follow manufacturer's published recommendations for installation methods not otherwise specified.

3.2 PIPE AND EQUIPMENT SUPPORTS

A. Where hanger spacing does not correspond with joist or rib spacing, use structural steel channels secured directly to joist and rib structure that will correspond to the required hanger spacing, and then suspend the equipment and piping from the channels. Drill or burn holes in structural steel only with the prior approval of the Resident Engineer.

B. Use of chain, wire or strap hangers; wood for blocking, stays and bracing; or, hangers suspended from piping above will not be permitted. Replace or thoroughly clean rusty products and paint with zinc primer.

C. Use hanger rods that are straight and vertical. Turnbuckles for vertical adjustments may be omitted where limited space prevents use. Provide a minimum of 15 mm (1/2-inch) clearance between pipe or piping covering and adjacent work.

3.3 STARTUP AND TEMPORARY OPERATION

Start up equipment as described in equipment specifications. Verify that vibration is within specified tolerance prior to extended operation.

3.4 OPERATING AND PERFORMANCE TESTS

A. Should evidence of malfunction in any tested system, or piece of equipment or component part thereof, occur during or as a result of tests, make proper corrections, repairs or replacements, and repeat tests at no additional cost to the Government.

3.5 INSTRUCTIONS TO VA PERSONNEL

Provide in accordance with Article, INSTRUCTIONS, of Section 01010, GENERAL

REQUIREMENTS.

T-1

SECTION 15200

NOISE AND VIBRATION CONTROL

PART 1 - GENERAL

1.1 DESCRIPTION

A. Vibration isolation for compressors and air pumps.

1.2 RELATED WORK

C. Section 15050, BASIC METHODS AND REQUIREMENTS (MECHANICAL): General mechanical requirements and items, which are common to more than one section of Division 15.

1.3 QUALITY ASSURANCE

A. Refer to article, QUALITY ASSURANCE in specification Section 15050, BASIC

METHODS AND REQUIREMENTS (MECHANICAL).

B. Allowable Vibration Tolerances for Rotating, Non-reciprocating Equipment: Not to exceed a self-excited vibration maximum velocity of 5 mm per second (0.20 inch per second) RMS, filter in, when measured with a vibration meter on bearing caps of machine in vertical, horizontal and axial directions or measured at equipment mounting feet if bearings are concealed. Measurements for internally isolated fans and motors may be made at the mounting feet.

A. Submit in accordance with specification Section 01340, SAMPLES AND SHOP

DRAWINGS.

B. Manufacturer's Literature and Data:

1. Vibration isolators:

1.5 APPLICABLE PUBLICATIONS

A. The publications listed below form a part of this specification to the extent referenced.

The publications are referenced in the text by the basic designation only.

B. American Society for Testing and Materials (ASTM):

A123/A123M-00 ....................Zinc (Hot-Dip Galvanized) Coatings on Iron and Steel

Products A307-00 .................................Carbon Steel Bolts and Studs, 60,000 PSI Tensile Strength D2240-00 ...............................Standard Test Method for Rubber Property - Durometer

Hardness

PART 2 - PRODUCTS

2.1 VIBRATION ISOLATORS

A. Spring Isolators (Type S): Shall be free-standing, laterally stable and include acoustical friction pads and leveling bolts. Isolators shall have a minimum ratio of http://www.va.gov/facmgt/standard/spec/15050.doc http://www.va.gov/facmgt/standard/spec/15050.doc http://www.va.gov/facmgt/standard/spec/01340.doc

T-2 spring diameter-to-operating spring height of 1.0 and an additional travel to solid equal to 50 percent of rated deflection.

A. Vibration Isolation:

1. No metal-to-metal contact will be permitted between fixed and floating parts.

2. Connections to Equipment: Allow for deflections equal to or greater than equipment deflections. Electrical, drain, piping connections, and other items made to rotating or reciprocating equipment (pumps, compressors, etc.) which rests on vibration isolators, shall be isolated from building structure for first three hangers or supports.

3. Common Foundation: Mount each electric motor on same foundation as driven machine. Hold driving motor and driven machine in positive rigid alignment with provision for adjusting motor alignment and belt tension. Bases shall be level throughout length and width. Provide shims to facilitate pipe connections, leveling, and bolting.

4. Extend bases for pipe elbow supports at discharge and suction connections at pumps.

Pipe elbow supports shall not short circuit pump vibration to structure.

B. Inspection and Adjustments: Check for vibration transmission through connections, piping, ductwork, foundations, and walls. Adjust, repair, or replace isolators as required to reduce vibration and noise transmissions to specified levels.

SECTION 15491

MEDICAL GAS AND VACUUM SYSTEMS

A. Medical Gas and Vacuum Systems: Replacing existing air and vacuum source equipment, piping additions and revisions, valves, gages, alarms including low voltage wiring, air compressors, vacuum pumps, electric motors and starters, receivers, air dryers, filters, pressure regulators, dew point, carbon monoxide monitors and all necessary parts, accessories, connections and equipment.

B. Medical gas and vacuum system alarm wiring from equipment to alarm panels.

1.2 RELATED WORK

A. Sealing around pipe penetrations to maintain the integrity of time rated construction:

Section 07270, FIRESTOPPING.

B. Sealing around pipe penetrations through the floor to prevent moisture migration: Section

07920, SEALANTS AND CAULKING.

C. General requirements and items common to more than one section of Division 15:

Section 15050, BASIC METHODS AND REQUIREMENTS (MECHANICAL).

D. Conduit: Section 16111, CONDUIT SYSTEMS.

E. Control wiring: Section 16127, CABLES, LOW VOLTAGE (600 VOLTS AND

BELOW).

1.3 QUALITY ASSURANCE

A. Materials and Installation: In accordance with NFPA 99, and as specified.

B. Equipment Installer: Show technical qualifications of previous experience in installing medical gas equipment on three similar projects. Submit names and addresses of referenced projects.

C. Equipment Supplier: Show evidence of equivalent product installed at three installations similar to this project that has been in satisfactory and efficient operation…