This is a Request for Quote (RFQ) issued by the Department of Veterans Affairs for walk-in freezers and refrigerators for the Ann Arbor Healthcare System. The solicitation (36C25025Q0398) seeks equipment for five specific locations: N&FS Cooler (Room BB18C), N&FS Freezer (Room BB18A), Canteen Cooler (Room BB09A), Canteen Freezer (Room BB09B), and Morgue Cooler (Room FG101A). Vendors must provide complete walk-in cooler and freezer equipment for food service and mortuary purposes, with specific requirements including stainless steel panel skin, detailed electrical specifications, and comprehensive monitoring alarm systems.
Key procurement details include a site visit on March 27, 2025, at 2215 Fuller Road, Ann Arbor, MI, with all questions due by April 4, 2025. The equipment is needed for delivery by specific dates: Morgue Cooler, N&FS Cooler, and N&FS Freezer by August 4, 2025, and Canteen Cooler and Freezer by December 10, 2025. Vendors must submit technical capability documentation, past performance information for three similar contracts, and pricing details. The solicitation is a full and open competition with no specific small business set-aside, and the principal NAICS code is 333415 for Air-Conditioning and Commercial Refrigeration Equipment Manufacturing.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 28-AE111 - PHASE A2 NEW WORK PLAN.pdf | ||
| 1-AE115 - PHASE B1 NEW WORK PLAN R1.pdf | ||
| 36C25025Q0398 0002.docx | DOCX document | |
| 1-AE116 - PHASE B2 NEW WORK PLAN.pdf | ||
| 36C25025Q0398 0001.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36C25025Q0398
PAGE 1 OF
1. REQUISITION NO.
2. CONTRACT NO.
3. AWARD/EFFECTIVE DATE
4. ORDER NO.
5. SOLICITATION NUMBER
6. SOLICITATION ISSUE DATE
a. NAME
b. TELEPHONE NO. (No Collect Calls)
8. OFFER DUE DATE/LOCAL
TIME
9. ISSUED BY
CODE
10. THIS ACQUISITION IS
UNRESTRICTED OR
SET ASIDE:
% FOR:
SMALL BUSINESS
HUBZONE SMALL
BUSINESS
SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
WOMEN-OWNED SMALL BUSINESS
(WOSB) ELIGIBLE UNDER THE WOMEN-OWNED
SMALL BUSINESS PROGRAM
EDWOSB
8(A)
NAICS:
SIZE STANDARD:
11. DELIVERY FOR FOB DESTINA-
TION UNLESS BLOCK IS
MARKED
SEE SCHEDULE
12. DISCOUNT TERMS
13a. THIS CONTRACT IS A
RATED ORDER UNDER
DPAS (15 CFR 700)
13b. RATING
14. METHOD OF SOLICITATION
RFQ
IFB
RFP
15. DELIVER TO
CODE
16. ADMINISTERED BY
CODE
17a. CONTRACTOR/OFFEROR
CODE
FACILITY CODE
18a. PAYMENT WILL BE MADE BY
CODE
TELEPHONE NO.
UEI:
EFT:
PHONE:
FAX:
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN OFFER 18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK BELOW IS CHECKED
SEE ADDENDUM
19.
20.
21.
22.
23.
24.
ITEM NO.
SCHEDULE OF SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
(Use Reverse and/or Attach Additional Sheets as Necessary)
25. ACCOUNTING AND APPROPRIATION DATA
26. TOTAL AWARD AMOUNT (For Govt. Use Only) 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 AND 52.212-5 ARE ATTACHED. ADDENDA
ARE
ARE NOT ATTACHED.
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA
ARE
ARE NOT ATTACHED
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN _______________
29. AWARD OF CONTRACT: REF. ___________________________________ OFFER
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND
DATED ________________________________. YOUR OFFER ON SOLICITATION
DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY
(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE
ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED
SET FORTH HEREIN IS ACCEPTED AS TO ITEMS:
30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER) 30b. NAME AND TITLE OF SIGNER (TYPE OR PRINT) 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER (TYPE OR PRINT) 31c. DATE SIGNED
AUTHORIZED FOR LOCAL REPRODUCTION
(REV. NOV 2021)
PREVIOUS EDITION IS NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.212
7. FOR SOLICITATION
INFORMATION CALL:
STANDARD FORM 1449
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30
506-25-1-118-0013 36C25025Q0398 03-1 -2025 Kellie Konopinski 734-222-4330 04-18-2025 4:30 pm
EDT
36C250 Department of Veterans Affairs Ann Arbor Healthcare System Network Contracting Office 10 2215 Fuller Road Ann Arbor MI 48105 X 333415 1250 Employees N/A X 36C506 Department of Veterans Affair VA Ann Arbor Healthcare System 2215 Fuller Road Ann Arbor MI 48105 36C250 Department of Veterans Affairs Ann Arbor Healthcare System Network Contracting Office 10 2215 Fuller Road Ann Arbor MI 48105
Department of Veterans Affairs Financial Management System PO Box 149971 Austin TX 78714-9971 877-353-9791 512-460-5540 X See CONTINUATION Page RFQ for Walk-in Freezers and Refrigerators.
See SOW for site visit information.
All communication must be through the Contracting Officer.
All questions must be provided to the Contracting Officer, Kellie Konopinski, at Kellie.Konopinski@va.gov by April 4, 2025 at 11:59 pm.
See CONTINUATION Page 506-3650160-118-822300-3131 010044177 X X X Kellie Konopinski Contracting Officer Table of Contents
| SECTION A | 1 |
| A.1 SF 1449 SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES | 1 |
| SECTION B - CONTINUATION OF SF 1449 BLOCKS | 3 |
| B.1 CONTRACT ADMINISTRATION DATA | 3 |
| B.2 STATEMENT OF WORK | 4 |
| B.3 PRICE/COST SCHEDULE | 30 |
| ITEM INFORMATION | 30 |
| B.4 DELIVERY SCHEDULE | 31 |
| SECTION C - CONTRACT CLAUSES | 33 |
| C.1 52.212-4 CONTRACT TERMS AND CONDITIONS—COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (NOV 2023) | 33 |
| C.2 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018) | 38 |
| C.3 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018) | 39 |
| C.4 VAAR 852.242-71 ADMINISTRATIVE CONTRACTING OFFICER (OCT 2020) | 40 |
| C.5 VAAR 852.246-71 REJECTED GOODS (OCT 2018) | 40 |
| C.6 VAAR 852.247-71 DELIVERY LOCATION (OCT 2018) | 40 |
| C.7 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998) | 41 |
| C.8 52.212-5 CONTRACT TERMS AND CONDITIONS REQUIRED TO IMPLEMENT STATUTES OR EXECUTIVE ORDERS—COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (JAN 2025) | 41 |
| SECTION D - CONTRACT DOCUMENTS, EXHIBITS, OR ATTACHMENTS | 50 |
| SECTION E - SOLICITATION PROVISIONS | 51 |
| E.1 52.212-1 INSTRUCTIONS TO OFFERORS—COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (SEP 2023) | 51 |
| E.2 52.201-1 ACQUISITION 360: VOLUNTARY SURVEY (SEP 2023) | 55 |
| E.3 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (NOV 2021) | 55 |
| E.4 52.204-29 FEDERAL ACQUISITION SUPPLY CHAIN SECURITY ACT ORDERS—REPRESENTATION AND DISCLOSURES (DEC 2023) | 58 |
| E.5 52.233-2 SERVICE OF PROTEST (SEP 2006) | 59 |
| E.6 VAAR 852.215-72 NOTICE OF INTENT TO RE-SOLICIT (OCT 2019) | 60 |
| E.7 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018) | 60 |
| E.8 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998) | 60 |
| E.9 52.212-2 EVALUATION—COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (NOV 2021) | 61 |
| E.10 52.212-3 OFFEROR REPRESENTATIONS AND CERTIFICATIONS—COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (MAY 2024) | 62 |
SECTION B - CONTINUATION OF SF 1449 BLOCKS
B.1 CONTRACT ADMINISTRATION DATA
1. Contract Administration: All contract administration matters will be handled by the following individuals:
a. CONTRACTOR: __________________
| POC: | __________________ | |
| EMAIL: | __________________ | |
| PHONE: | __________________ |
b. GOVERNMENT: Contracting Officer 36C250 Kellie Konopinski 734-222-4330 Kellie.Konopinski@va.gov Department of Veterans Affairs Ann Arbor Healthcare System Network Contracting Office 10 2215 Fuller Road Ann Arbor MI 48105
2. CONTRACTOR REMITTANCE ADDRESS: All payments by the Government to the contractor will be made in accordance with:
| [X] |
| 52.232-33, Payment by Electronic Funds Transfer—System For Award Management, or |
| [] |
| 52.232-36, Payment by Third Party |
3. INVOICES: Invoices shall be submitted in arrears:
| a. Quarterly | [] |
| b. Semi-Annually | [] |
| c. Other | [X] After Delivery, inspection and acceptance. |
4. GOVERNMENT INVOICE ADDRESS: All Invoices from the contractor shall be submitted electronically in accordance with VAAR Clause 852.232-72 Electronic Submission of Payment Requests.
ACKNOWLEDGMENT OF AMENDMENTS: The offeror acknowledges receipt of amendments to the Solicitation numbered and dated as follows:
| AMENDMENT NO |
| DATE |
Page 1 of Page 1 of
B.2 STATEMENT OF WORK
PROJECT 506-20-102, UPGRADE BASEMENT, BUILDING 1W
1. GENERAL INTENT:
The Equipment Vendor shall provide complete walk-in cooler and freezer equipment for food and for mortuary service, as shown and specified.
2. LOCATION OF WORK:
Ann Arbor Medical Facility: Buildings 1W and 28 at Lieutenant Colonel Charles S. Kettles Veterans Affairs Medical Center 2215 Fuller Road, Ann Arbor, MI 48105.
3. DEFINITIONS:
| Equipment Vendor: | The manufacturer of the cooler and freezer equipment offering to provide equipment as described herein. | |
| Contractor: | General construction contractor, contracted under the Owner to build Project 506-20-102, Upgrade Basement, Building 1W. | |
| Owner: | The Federal Government, Department of Veterans Affairs | |
| AE: | Offices of FFE Inc., Architect/Engineer contracted by the Owner under Project 506-20-102, Upgrade Basement, Building 1W. As Architect/Engineers, FFE Inc. will render certain technical services to the Owner during procurement of the equipment. | |
| Others: | References to “Others” in these documents refer to any party other than the Equipment Vendor, which may include the Owner, Contractor, and the contractor’s subcontractors. |
3. DESCRIPTION OF WORK TO BE PERFORMED:
Provide all components for complete and functional walk-in coolers and freezers, delivered to the Ann Arbor Medical Facility in accordance with the requirements. The requirements are described in this Scope of Work document and in the attached drawings and specifications. The equipment is for the storage of food for the Nutrition and Food Service (N&FS) and Canteen Service (Canteen); and for storage of decedents for the Pathology and Laboratory Medicine Services (PALMS). The equipment to be provided is as follows:
· N&FS Cooler, Room BB18C
· N&FS Freezer, Room BB18A
· Canteen Cooler, Room BB09A
· Canteen Freezer, Room BB09B
· Morgue Cooler, Room FG101A Each cooler and freezer will be installed in interior spaces within existing facilities, started-up, and commissioned by Others.
The equipment will be incorporated into a renovation project that is currently under construction by the Contractor under Project 506-20-102, Upgrade Basement, Building 1W. The Contractor for that project will hire an installer certified to install the selected manufacturer’s equipment. The Contractor is responsible for installation, start-up, and commissioning of the equipment. Installation, start-up, and commissioning are not the responsibility of the Equipment Vendor.
Selected figures and specifications were taken from that construction project and adapted for this equipment procurement. Work to be performed by the Equipment Vendor is identified in this document.
The Equipment Vendor must meet all the requirements within this Scope of Work, including all components for complete and functional walk-in coolers and freezers, delivered to the Ann Arbor Medical Facility. That includes (but is not limited to) wall panels, ceiling panels, mechanical systems, ancillary components, accessories, etc. as specified, and as necessary for a complete and functional system. To be considered responsive to this procurement solicitation, the Equipment Vendor must provide the following information in their proposal which will be the basis for selection:
1. Price
2. Estimate of equipment delivery lead-time
3. Three reference contracts of similar type, scope, size, and complexity; including contact information for each contract and a listing of any notifications of citations.
4. A yes or no statement attesting whether the Equipment Vendor can, or cannot, meet the all the requirements listed within this Scope of Work and the attachments for the proposed price.
5. List of any deviations from the requirements.
6. A statement attesting whether the panel skin material will be stainless steel, as specified in the requirements.
7. A statement attesting whether the dimensions of the proposed equipment match the requirements shown in Table 1 titled “Walk-in Freezer and Cooler Design Parameters”.
8. A statement attesting whether the proposed condenser types for the various freezers and coolers match the requirements, as specified in the Table 1 titled “Walk-in Freezer and Cooler Design Parameters”.
9. A statement attesting whether the proposed equipment meets the temperature capability requirements, as specified the Table 1 titled “Walk-in Freezer and Cooler Design Parameters”.
4. REQUIREMENTS AND PERFORMANCE STANDARDS:
The selected Equipment Vendor must coordinate with the Contractor for delivery times and locations. The Contractor does not have authority to change any requirements or make agreements that impact the cost to the Equipment Vendor. Please include Contracting Officer and VA Point of Contact on all communication. The intent is to time the delivery with the Contractor’s need. The timing will be based on when the Contractor is ready to install the equipment. The Contractor’s latest schedule shows that they will need equipment within the following timeframes. This is what the VA is trying to match:
· Morgue Cooler, N&FS Cooler, and N&FS Freezer: 8/4/2025
· Canteen Cooler and Canteen Freezer: 12/10/2025 Table 1. Walk-in Freezer and Cooler Design Parameters
· ACCU-1:
· Motor: 208V, 2-Pole, 1.98 kVA,
· Starter: At equipment control panel.
· Disconnect Switch, NEMA 3R, Locate near motor
· Controls: direct digital control.
· Feeder: 2 conductors, wire size 12, ground size 12, conduit size ¾”
· UC-1:
· Motor: 208V, 2-Pole, 0.37 kVA,
· Starter: EC Motor. At equipment control panel
· Disconnect: Switch, near motor. NEMA 3R, Disconnect size 30, Non-fused.
· Controls: direct digital control
· Feeder: 3 conductors, wire size 12, ground size 12, conduit size 3/4”.
· UC-1 Defrost Heater:
· Motor: 208V, 2-Pole, 2.48 kVA,
· Disconnect: Switch, near motor, NEMA 3R, Disconnect size 30, Non-fused.
· Controls: direct digital control
· Feeder: 3 conductors, wire size 12, ground size 12, conduit size 3/4”.
· UC-2:
· Motor: 120V, 1-Pole, 0.37 kVA,
· Starter: EC Motor. At equipment control panel
· Disconnect: Switch, near motor. NEMA 3R, Disconnect size 30, Non-fused.
· Controls: direct digital control
· Feeder: 3 conductors, wire size 12, ground size 12, conduit size 3/4”.
· UC-3:
· Motor: 120V, 1-Pole, 0.65 kVA,
· Starter: EC Motor. At equipment control panel
· Disconnect: Switch, near motor. NEMA 3R, Disconnect size 30, Non-fused.
· Controls: direct digital control
· Feeder: 2 conductors, wire size 12, ground size 12, conduit size 3/4”.
· UC-4 Defrost Heater
· Motor: 208V, 2-Pole, 3.22 kVA,
· Disconnect: Switch, near motor. NEMA 3R, Disconnect size 30, Non-fused.
· Controls: direct digital control
· Feeder: 2 conductors, wire size 12, ground size 12, conduit size 3/4”.
· UC-4 Fan
· Motor: 208V, 2-Pole, 0.25 kVA,
· Disconnect: Switch, near motor. NEMA 3R, Disconnect size 30, Non-fused.
· Controls: direct digital control
· Feeder: 2 conductors, wire size 12, ground size 12, conduit size 3/4”.
· UC-5:
· Motor: 120V, 1-Pole, 0.12 kVA,
· Starter: EC Motor. At equipment control panel
· Disconnect: Switch, near motor. NEMA 3R, Disconnect size 30, Non-fused.
· Controls: direct digital control
· Feeder: 3 conductors, wire size 12, ground size 12, conduit size 3/4”.
· WCCU-1
· Motor: 208V, 3-Pole, 7.71 kVA,
· Disconnect: Switch, near motor. NEMA 3R, Disconnect size 60, Non-fused.
· Controls: direct digital control
· Feeder: 3 conductors, wire size 8, ground size 10, conduit size 3/4”.
· WCCU-2
· Motor: 208V, 3-Pole, 2.59 kVA,
· Starter: EC Motor. At equipment control panel
· Disconnect: Switch, near motor. NEMA 3R, Disconnect size 30, Non-fused.
· Controls: direct digital control
· Feeder: 3 conductors, wire size 12, ground size 12, conduit size 3/4”.
· WCCU-4
· Motor: 208V, 3-Pole, 10.38kVA,
· Starter: EC Motor. At equipment control panel
· Disconnect: Switch, near motor. NEMA 3R, Disconnect size 60, Non-fused.
· Controls: direct digital control
· Feeder: 3 conductors, wire size 6, ground size 10, conduit size 1”.
· WCCU-3
· Motor: 208V, 3-Pole, 2.59 kVA,
· Starter: EC Motor. At equipment control panel
· Disconnect: Switch, near motor. NEMA 3R, Disconnect size 30, Non-fused.
· Controls: direct digital control
· Feeder: 3 conductors, wire size 12, ground size 12, conduit size 3/4”.
Figures 1 and 2 are provided to show the general shape and arraignment of the equipment after it is installed (by Others) within the facility. The equipment is highlighted in yellow for clarity. The yellow highlights do not relieve the Equipment Provider from providing equipment that is compliant with the requirements in this scope of work.
Figure 1: General Arrangement of N&FS Cooler, N&FS Freezer, Canteen Cooler, Canteen Freezer
Figure 2: General Arrangement of Morgue Cooler
A. Warranty Requirements
Furnish with each warranty the name, address and telephone number of each of the guarantor’s representatives nearest project location:
1. Listing and status of delivery of all Certificates of Warranty for extended warranty items to include pumps, motors, transformers and for all commissioned systems such as fire protection and alarm systems, sprinkler systems and lightning protection systems, etc.
2. A list for each warranted equipment item, feature of construction or system indicating:
a. Name of item.
b. Model and serial numbers.
c. Location where installed.
d. Name and phone numbers of manufacturers and suppliers.
e. Name and phone numbers of manufacturers or suppliers.
f. Names, addresses and phone numbers of sources of spare parts.
g. Warranties and terms of warranty. Include one-year overall warranty of construction, including the starting date of warranty of construction. Items which have extended warranties shall be indicated with separate warranty expiration dates.
h. Starting point and duration of warranty period.
i. Summary of maintenance procedures required to continue the warranty in force.
j. Cross-reference to specific pertinent Operation and Maintenance manuals.
k. Organizations, names and phone numbers of persons to call for warranty service.
l. Typical response time and repair time expected for various warranted equipment.
3. The plans for attendance at the 4 and 9-month post construction warranty inspections conducted by the government.
4. Procedure and status of tagging of all equipment covered by extended warranties.
5. Copies of instructions to be posted near selected pieces of equipment where operation is critical for warranty and/or safety reasons.
B. Operations and Maintenance Manuals
Equipment Vendor shall furnish Maintenance and Operating manuals (hard copies and electronic) and verbal instructions when required by the various sections of the specifications and as hereinafter specified.
Manuals: Maintenance and operating manuals and one compact disc (four hard copies and one electronic copy each) for each separate piece of equipment shall be delivered to the COR coincidental with the delivery of the equipment to the job site. Manuals shall be complete, detailed guides for the maintenance and operation of equipment. They shall include complete information necessary for starting, adjusting, maintaining in continuous operation for long periods of time and dismantling and reassembling of the complete units and sub-assembly components. Manuals shall include an index covering all component parts clearly cross-referenced to diagrams and illustrations. Illustrations shall include "exploded" views showing and identifying each separate item. Emphasis shall be placed on the use of special tools and instruments. The function of each piece of equipment, component, accessory and control shall be clearly and thoroughly explained. All necessary precautions for the operation of the equipment and the reason for each precaution shall be clearly set forth. Manuals shall reference the exact model, style and size of the piece of equipment and system being furnished. Manuals referencing equipment similar to but of a different model, style, and size than that furnished will not be accepted.
Instructions: Equipment Vendor shall provide qualified, factory-trained manufacturers' representatives to give detailed training to assigned Department of Veterans Affairs personnel in the operation and complete maintenance for each piece of equipment. All such training will be at the job site. These requirements are more specifically detailed in the various technical sections. Instructions for different items of equipment that are component parts of a complete system, shall be given in an integrated, progressive manner. All instructors for every piece of component equipment in a system shall be available until instructions for all items included in the system have been completed. This is to assure proper instruction in the operation of inter-related systems. All instruction periods shall be at such times as scheduled by the Government and shall be considered concluded only when the Government is satisfied in regard to complete and thorough coverage. The Equipment Vendor shall submit a course outline with associated material to the Government for review and approval prior to scheduling training to ensure the subject matter covers the expectations of the VA and the contractual requirements. The Government reserves the right to request the removal of, and substitution for, any instructor who, in the opinion of the Government, does not demonstrate sufficient qualifications in accordance with requirements for instructors above.
WALK-IN COOLERS AND FREEZERS FOR FOOD SERVICE
PART 1 GENERAL
1.1 DESCRIPTION:
| A. | This section specifies walk-in, site-assembled, coolers and freezers for food service, including: |
| 1. Nutrition and Food Service (N&FS) Cooler (Room BB18C) | |
| 2. N&FS Freezer (Room BB18A) | |
| 3. Canteen Cooler (Room BB09A) | |
| 4. Canteen Freezer (Room BB09B) |
1.2 WARRANTY:
A. Refrigeration Compressor Warranty: Equipment Vendor agrees to repair or replace compressors that fail in materials or workmanship within five (5) years from the date of final acceptance by the Government. Failure includes but is not limited to inability to maintain set temperature. Submit compressor warranty.
1.3 QUALITY ASSURANCE
Safety Standard: ASHRAE 15, describe requirements for refrigerant containing parts.
1.4 SUBMITTALS:
| A. | Once the contract is awarded to the successful Equipment Vendor, the Equipment Vendor must submit the following information for review and approval: | |
| B. | Provide manufacturer's Literature and Data: | |
| 1. | Walkin units, including assembly instructions and access panel location. | |
| 2. | Refrigeration equipment calculations per the design drawings. | |
| a. See mechanical schedules for cooler and freezer design conditions and setpoints. | ||
| b. Use ASHRAE recommendations for heat gain factors, load calculations and compressor running time while selecting equipment to maintain setpoints. | ||
| c. Provide calculation methods and results. | ||
| d. Provide the anticipated total water flow rate needed to serve all four water-cooled units. This will allow the Government to validate that the booster pump is adequately sized and make adjustments as necessary. Identify the entering water temperature (EWT) used in the calculations, as well as the differential temperature (dT) across the condenser. | ||
| e. | Provide head pressure drop through the condenser. Separately identify the pressure drop incurred by the any control/regulating valves. | |
| 3. | Condensing units, with mounting rack where required. | |
| 4. | Unit coolers. | |
| 5. | Temperature controls and alarms. | |
| 6. | Diagrams and details of piping, wiring and controls. | |
| 7. | Cutsheets and description of the operation of any control/regulating valves. Confirm whether there is constant (24/7) flow through the waterside of the condensers or if there are controls that will modulate or shut off the water through the condenser. Verify whether the water flow will be shut off when the unit is off and if there is an option to always keep a minimum flow through the condenser. | |
| 8. | Installations manuals for equipment. |
9. Drawings, to-scale, showing dimensions of the walk-in cooler and proposed locations of utility connections.
| C. | Operational test reports. |
| D. | Final field test reports. |
| E. | Maintenance and operating manuals |
| F. | Manufacturer’s compressor warranty. |
1.5 APPLICABLE PUBLICATIONS:
| A. | The publications listed below form a part of this specification to the extent referenced. The publications are referenced in the text by the basic designation only. |
| B. | Air-Conditioning and Refrigeration Institute (ARI): |
| 420-I-P-2016 | Unit Coolers for Refrigeration. |
| 520-04 | Performance Rating of Positive Displacement Condensing Units. |
| C. | American Society of Heating, Refrigerating and Air Conditioning Engineers (ASHRAE): |
| 15-22 | Safety Standard for Refrigeration Systems |
| D. | ASTM International (ASTM): |
| A240/A240M-22b | Chromium and Chromium-Nickel Stainless Steel Plate, Sheet, and Strip for Pressure Vessels and For General Applications |
| E84-22 | Surface Burning Characteristics of Building Materials |
| E. | National Sanitation Foundation/American National Standard (NSF/ANSI): |
| 7-21 | Commercial Refrigerators and Storage Freezers |
F. National Fire Protection Association (NFPA):
70-20 National Electric Code G. Underwriters Laboratories, Inc. (UL):
| 207- Edition 9, 2022 | Refrigerant-Containing Components and Accessories, Nonelectrical |
| 471-Edition 10, 2019 | Commercial Refrigerators and Freezers |
| 1598-Edition 5, 2021 | Luminaires |
PART 2 - PRODUCTS
2.1 performance requirements:
| A. | NSF Standards: Provide equipment that bears NSF Certification Mark certifying compliance with applicable standards. |
| B. | UL Certification: Provide electric and fuel-burning equipment and components that are evaluated by UL for fire, electric shock, and casualty hazards according to applicable safety standards, and that are UL certified for compliance and labeled for intended use. |
| C. | Regulatory Requirements: Install equipment to comply with the following: |
1. ASHRAE 15, “Safety Code for Mechanical Refrigeration.”
2. NFPA 70, “National Electric Code.”
2.2 WALK-IN REFRIGERATOR/FREEZER CONSTRUCTION:
| A. | General: Prefabricated, sectional, all-metal clad, modular, designed for easy accurate field assembly. |
| B. | Provide walk-in units manufactured for food service use conforming to NSF/ANSI 7, UL 207, and UL 471. |
| C. | Panel Construction: |
| 1. | General: Interchangeable, 1219 mm (48 inch) maximum width, 101 mm (4 inch) thick, filled with insulation. Double seal serrated neoprene rubber gaskets to assure air and vapor tight joints. |
| 2. | Panel skin: Stainless steel, min 0.85 mm thick (22 gauge), No. 3 finish, ASTM A167, Type 302B or ASTM A240, Type 304. |
| 2. | Corner panels: 90 degree angle, radiuses 15 mm (0.5 inch) inside and outside, with 305 mm (12inch) dimensions each side. |
| 3. | Panel edges: Foaminplace, tongueandgrooved urethane to assure tight joints. Provide double seal serrated neoprene rubber gaskets to assure air and vapor tight joints on the interior and exterior of each panel along every tongue. |
| 4. | Insulation: 101 mm (4 inch) minimum foamed-in-place polyurethane with manufacturer’s rated “K” factor of not more than 0.15, free rise design of not less than 27 kg per cubic meter (1.7 pounds per cubic foot), or in-place density of not less than 32 kg per cubic meter (2 pounds per cubic foot). Provide floor screeds with minimum of 63 mm (2-1/2 inches) of foamed insulation. |
| 5. | Door Panel and Door: |
| a. | Provide channel thermal breaker type reinforcing steel frame around the entire perimeter of the door opening. |
| b. | Door to be an in-fitting, flushmounted type with dual flexible blade wiper gasket on the bottom and a replaceable magnetic gasket on the top edge and along both vertical sides. |
| c. | Provide heated, double glass view windows in door. |
| d. | Door to be equipped with a minimum of three (3) hinges, for rough usage. |
| e. | Provide hydraulic exterior door closer to prevent slamming and assure secure closing. |
| f. | Door hinges and latch and strike assembly: Manufacturer's standard, selfclosing camlift type hinges, for 1219 mm (48 inch) door, chrome plated or stainless steel finish, made to provide for locking, but with an inside safety release mechanism to prevent anyone from being locked inside when door is locked from outside. |
| g. | Concealed, energy use selective, antisweat heater wire circuit: Provide sufficient heat to prevent condensation and frost formation at the door jambs and exterior edges of the door on all sides. |
| h. | Thermometer: Manufacturer's standard, 50 mm (2inch) minimum diameter, dial type, flush mounted in door panel. |
| i. | Door panel skin to be stainless steel to match wall panels. |
| 6. | Pressure relief port: Provide for all freezers operating at 18 degree C (0 degree F), or lower, twoway type ports, to allow for an increase or decrease of air pressure on the interior of the freezer to equalize with air pressure on the exterior. Provide ports with automatically controlled, UL approved antisweat heaters. Complete device to carry UL Label and be assembled ready for connection. Install port in a wall panel away from the direct air stream flowing from the coils. |
| 7. | Floor Panels |
| a. | Floor Panel Strength: Capable of withstanding 28.7 kPa (600 pounds per square foot) uniform load. Floor must be load-rated for use with a hand-operated (non-motorized) pallet jack. |
| b. | Provide prefabricated floor panels of the same construction as wall/ceiling. Floor shall be sealed watertight. Provide nonskid floor strips 101 x 915 mm (4 x 36 inch) and field apply at 305 mm (12 inch) spacing in all aisles. Provide prefabricated floor panels which are surfaced laid with sloping interior floor ramps at entrance doors. Furnish two (2) sets of erection tools, compatible with fasteners, with each unit. |
| D. | Wherever compartment dimension exceed clearspan ability of ceiling panels, provide Ibeam support on exterior of ceiling or spline-hangers. Install 13 mm (1/2 inch) diameter steel rods through beam/hangers and secure to structure above. Beams or posts within compartments are not acceptable. |
| E. | Rub rail wall protectors: Manufacturer’s standard, at floor line of walls exposed to traffic. |
| F. | Lights: Provide high-efficiency rated LED lamps in vapor-proof fixtures with safety shields. Lighting must conform with UL 1598. Provide lamps capable of operating in minus 29 degrees C (-20 degrees F) temperature. Lights must run full length of walk-in starting 610 mm (24 inches) from front panel and extending within 610 mm (24 inches) of back panel. Run between shelf rows to obtain 323 lux (30 foot-candles) at floor level regardless of any interior furnishings. |
2.3 CONDENSING UNITS
| A. | Comply with ARI Standard 520. Water cooled type as shown in construction documents. Sizing provided by Equipment Vendor in accordance with the design drawings. Selections subject to approval by the owner. |
| B. | Provide motor driven integral compressor, motor starter, condenser, receiver, common base, and safety/operational controls. |
| C. | Receiver capacity not to be less than 125 percent of system refrigerant charge. |
| D. | For units racked above each other and for units installed in a closet, provide a factory fabricated steel rack extending approximately 1143 mm (45 inches) above the floor. |
| E. | Provide two (2) condensing units and unit coolers with independent refrigeration systems for freezer when shown on construction documents or recommended by manufacturer due to size or freezer. |
| F. | Do not locate compressors on top of refrigerators or freezers. |
| G. | Provide positive oil lubrication and oil level indicating device for each compressor. Provide water regulating valve for water cooled unit. If a condenser water flow control valve is required, it shall be normally-open type. Water shall flow while the condenser is off. |
| H. | Compressor Motor: Squirrel cage induction type of ample size for continuous operating at maximum compressor performance. Provide inherent protection, in compressor terminal box, for each phase of motor. |
| I. | Pressure Switches: Automatic reset low pressure switch, and automatic or manual reset high pressure cutout. |
| J. | Valves: Valve components in contact with the process fluid shall be stainless steel. |
2.4 UNIT COOLERS:
| A. | Comply with ARI Standard 420. Units to be UL listed, forcedventilation type. Provide integral defrosting, internal or external refrigerant distributor, single or multiple fans and motors, drippan, deflectors, bakedenamel steel housing, hangers, and all accessories. Unit coolers for kitchen walkin units to be NSF approved. Sizing provided by Equipment Vendor in accordance with the design drawings. Selections subject to approval by the owner. |
| B. | Motors: Permanent split capacitor type. Provide motors with thermal overload protection and manual starting switch. |
| C. | Drain Pans: Galvanized sheet steel. Provide additional drain pans under uncovered refrigerant connections, and interconnect them with main drain pan. For freezer units provide electrically heated drain pan. |
| D. | Defrost Provision: |
| 1. | Refrigerators: Defrost to occur during compressor off cycle with evaporator fan running continuously. |
| 2. | Freezer defrost: Defrost by heating elements incorporated into coil and drain pan. Operation of evaporator fan to be delayed after defrost cycle until evaporator is cold enough to freeze any water droplets that are on evaporator coil. Defrosting unit to be automatically controlled by an electric clock, refrigerant suction gas pressure sensing device, or by means of sensing increased air resistance due to ice accumulation. |
2.5 monitoring alarm system:
| A. | Provide an electronic monitoring and alarm system for each section of each unit. |
| 1. | System Components: Detecting thermostat, master control panel, interconnecting wiring, remote audible alarm, and defrost compensator. Provide dials showing temperatures and pilot lights, warning lights, switches, transformer, and buzzer, all as a part of the master control panel. Locate master control panel and remote audible alarm as indicated on construction documents. Provide power fuse to protect system components. |
| 2. | System Operation: Set alarms at 5 degrees C (10 degrees F) above and below specified operating temperatures. |
| 3. | Communications: Electronic monitoring and alarm system must be compatible with Building Automation and Control Networks (BACnet) communication protocol. All points must be open for the VA to read and control parameters up to, and including, but not limited to, trending and status alarms, temperature settings, actual temperature, high temperature, and equipment status (on/off). The Ann Arbor Medical Facility uses Desigo, as manufactured by Siemens. |
| B. | Personnel Alarm: For each unit, provide separate audible alarm system operable from inside unit, for use of personnel unable to exit unit. Locate remote audible alarm where indicated on construction documents. |
2.6 EQUIPMENT IDENTIFICATION REQUIREMENTS:
A. Provide labels identifying all walkins coolers and freezers, refrigeration equipment, and alarm devices.
PART 3 EXECUTION
3.1 DELIVERY:
A. Equipment shall be delivered to the interior space in which the equipment will be installed.
3.2 INSTALLATION:
A. Installation will be performed by Others.
WALK-IN COOLER FOR MORGUE SERVICE
PART 1 GENERAL
1.1 DESCRIPTION
| A. | This section specifies walk-in, site-assembled, cooler mortuary service, including: |
| 1. Morgue Cooler (Room FG101A) |
1.2 WARRANTY:
A. Refrigeration Compressor Warranty: Equipment Vendor agrees to repair or replace compressors that fail in materials or workmanship within five (5) years from the date of final acceptance by the Government. Failure includes but is not limited to inability to maintain set temperature. Submit compressor warranty.
1.3 QUALITY ASSURANCE
Safety Standard: ASHRAE 15, describe requirements for refrigerant containing parts.
1.4 SUBMITTALS
| A. | Once the contract is awarded to the successful Equipment Vendor, the Equipment Vendor must submit the following information for review and approval: |
| B. | Manufacturer's Literature and Data: |
| 1. | Refrigeration equipment calculations per the design drawings. |
| a. See mechanical schedules for design conditions and setpoints. | |
| b. Use ASHRAE recommendations for heat gain factors, load calculations and compressor running time while selecting equipment to maintain setpoints. | |
| c. Provide calculation methods and results. | |
| d. Provide recommend range of airflow for exhaust air. | |
| 2. | Condensing units, with mounting rack where required. |
| 3. | Unit coolers. |
| 4. | Temperature controls and alarms. |
| 5. | Temperature recorders for mortuary refrigerators. |
| 6. | Mortuary walkin ventilation accessories. |
| 7. | Diagrams and details of piping, wiring and controls. |
| 8. | Drawings, to-scale, showing dimensions of the walk-in cooler and proposed locations of utility connections. |
| 9. | Installation Manuals of equipment. |
| C. | Operating Test Data. |
D. Final field test reports.
E. Maintenance and operating manuals F. Manufacturer’s compressor warranty
1.5 APPLICABLE PUBLICATIONS
| A. | The publications listed below form a part of this specification to the extent referenced. The publications are referenced in the text by the basic designation only. |
| B. | Air-Conditioning and Refrigeration Institute (ARI): |
| 420-I-P-2016 | Unit Coolers for Refrigeration. |
| 520-04 | Performance Rating of Positive Displacement Condensing Units. |
| C. | American Society of Heating, Refrigerating and Air Conditioning Engineers (ASHRAE): |
| 15-22 | Safety Standard for Refrigeration Systems |
| D. | ASTM International (ASTM): |
| A240/A240M-22b | Chromium and Chromium-Nickel Stainless Steel Plate, Sheet, and Strip for Pressure Vessels and For General Applications |
| E84-22 | Surface Burning Characteristics of Building Materials |
E. Underwriters Laboratories, Inc. (UL):
| 207- Edition 9, 2022 | Refrigerant-Containing Components and Accessories, Nonelectrical |
| 471-Edition 10, 2019 | Commercial Refrigerators and Freezers |
| 1598-Edition 5, 2021 | Luminaires |
PART 2 PRODUCTS
2.1 performance requirements:
| A. | UL Certification: Provide electric and fuel-burning equipment and components that are evaluated by UL for fire, electric shock, and casualty hazards according to applicable safety standards, and that are UL certified for compliance and labeled for intended use. |
| B. | Regulatory Requirements: Install equipment to comply with the following: |
1. ASHRAE 15, “Safety Code for Mechanical Refrigeration.”
2. NFPA 70, “National Electric Code.”
2.2 WALK-IN Morgue COOLER CONSTRUCTION:
| A. | General: Prefabricated, sectional, all-metal clad, modular, designed for easy accurate field assembly. |
| B. | Provide walk-in units manufactured for food service use conforming to NSF/ANSI 7, UL 207, and UL 471. |
C. Mortuary Cooler: Floorless, with insulated floor screeds.
| D. | Panel Construction: |
| 1. | General: Interchangeable, 1219 mm (48 inch) maximum width, 101 mm (4 inch) thick, filled with insulation. Double seal serrated neoprene rubber gaskets to assure air and vapor tight joints. |
| 2. | Panel skin: Stainless steel, min 0.85 mm thick (22 gauge), No. 3 finish, ASTM A167, Type 302B or ASTM A240, Type 304. |
| 2. | Corner panels: 90 degree angle, radiuses 15 mm (0.5 inch) inside and outside, with 305 mm (12inch) dimensions each side. |
| 3. | Panel edges: Foaminplace, tongueandgrooved urethane to assure tight joints. Provide double seal serrated neoprene rubber gaskets to assure air and vapor tight joints on the interior and exterior of each panel along every tongue. |
| 4. | Insulation: 101 mm (4 inch) minimum foamed-in-place polyurethane with manufacturer’s rated “K” factor of not more than 0.15, free rise design of not less than 27 kg per cubic meter (1.7 pounds per cubic foot), or in-place density of not less than 32 kg per cubic meter (2 pounds per cubic foot). Provide floor screeds with minimum of 63 mm (2-1/2 inches) of foamed insulation. |
| 5. | Door Panel and Door: |
| a. | Provide channel thermal breaker type reinforcing steel frame around the entire perimeter of the door opening. |
| b. | Door to be an in-fitting, flushmounted type with dual flexible blade wiper gasket on the bottom and a replaceable magnetic gasket on the top edge and along both vertical sides. |
| c. | Provide heated, double glass view windows in door. |
| d. | Door to be equipped with a minimum of three (3) hinges, for rough usage. |
| e. | Provide hydraulic exterior door closer to prevent slamming and assure secure closing. |
| f. | Door hinges and latch and strike assembly: Manufacturer's standard, selfclosing camlift type hinges, for 1219 mm (48 inch) door, chrome plated or stainless steel finish, made to provide for locking, but with an inside safety release mechanism to prevent anyone from being locked inside when door is locked from outside. |
| g. | Concealed, energy use selective, antisweat heater wire circuit: Provide sufficient heat to prevent condensation and frost formation at the door jambs and exterior edges of the door on all sides. |
| h. | Thermometer: Manufacturer's standard, 50 mm (2inch) minimum diameter, dial type, flush mounted in door panel. |
| i. | Door panel skin to be stainless steel to match wall panels. |
| 6. | Floor Panels (Food Service Coolers/Freezers Only): |
| a. | Floor Panel Strength: Capable of withstanding 28.7 kPa (600 pounds per square foot) uniform load. |
| b. | Provide prefabricated floor panels of the same construction as wall/ceiling. Floor shall be sealed watertight. Provide nonskid floor strips 101 x 915 mm (4 x 36 inch) and field apply at 305 mm (12 inch) spacing in all aisles. Provide prefabricated floor panels which are surfaced laid with sloping interior floor ramps at entrance doors. Furnish two (2) sets of erection tools, compatible with fasteners, with each unit. |
7. Floors:
a. Mortuary cooler walls will be installed on top of an existing resinous floor consisting of heavy-duty urethane and epoxy mortar. The floor will be installed by Others.
| E. | Wherever compartment dimensions exceed clearspan ability of ceiling panels, provide Ibeam support on exterior of ceiling or spline-hangers. Install 13 mm (1/2 inch) diameter steel rods through beam/hangers and secure to structure above. Beams or posts within compartments are not acceptable. |
| F. | Rub rail wall protectors: Manufacturer’s standard, at floor line of walls exposed to traffic. |
| G. | Lights: Provide high-efficiency rated LED lamps in vapor-proof fixtures with safety shields. Lighting must conform with UL 1598. Provide lamps capable of operating in minus 23 degrees C (10 degrees F) temperature. Lights must run full length of walk-in starting 610 mm (24 inches) from front panel and extending within 610 mm (24 inches) of back panel. Run between shelf rows to obtain 323 lux (30 foot-candles) at floor level regardless of any interior furnishings. |
2.1 CONDENSING UNITS
| A. | Comply with ARI Standard 520. Air cooled motor driven integral compressor, motor starter, condenser, receiver, common base, and safety/operational controls. Receiver capacity shall be not less than 125 percent of system refrigerant charge. For units racked one above the other and for units installed in a closet, provide a factory fabricated steel rack extending approximately 1150 mm (45 inches) above the floor.. Do not locate compressors on top of cooler. Sizing of the condensing unit(s) shall be determined by the Equipment Vendor. Selections subject to approval by the Owner. |
| B. | Provide positive oil lubrication and oil level indicating device for each compressor. |
| C. | Compressor Motor: Squirrel cage induction type of ample size for continuous operating at maximum compressor performance indicated. Provide inherent (Klixon) protection, in compressor terminal box, for each phase of motor. |
| D. | Pressure Switches: Automatic reset low pressure switch, and automatic or manual reset high pressure cutout. |
| E. | Valves: Valve components in contact with the process fluid shall be stainless steel. |
| E. | Air Cooled Condensing Units: |
| 1. | High efficiency type piped and automatically controlled to operate at lower head pressures during low ambient temperature conditions, designed and weatherproofed for outdoor installation, to operate satisfactorily at winter ambient temperatures down to -30 degrees C (-21 degrees F), and be provided with crankcase and receiver heaters. |
| 2. | The condenser fans shall be driven by permanent split capacitor motors. |
2.2 UNIT COOLERS
| B. | Comply with ARI Standard 420. Units shall be UL listed, forcedventilation type integral defrosting, internal or external refrigerant distributor, single or multiple fans and motors, drippan, deflectors, aluminum or bakedenamel steel housing, hangers, and all accessories. Sizing provided by Equipment Vendor in accordance with the requirements shown on the contract documents. Selections subject to approval by the owner. |
| C. | Motors: Permanent split capacitor type. Provide motors with thermal overload protection. Provide manual starting switch. |
| D. | Drain Pans: Galvanized sheet steel. Provide additional drain pans under uncovered refrigerant connections and interconnect them with main drain pan. |
| E. | Defrost Provision: |
1. Coolers: Defrost shall occur during compressor off cycle with evaporator fan running continuously.
| F. | Lights: Provide high-efficiency rated LED lamps in vapor-proof fixtures with safety shields. Lighting must conform with UL 1598. Provide lamps capable of operating in minus 23 degrees C (10 degrees F) temperature. Lights must run full length of walk-in starting 24 inches from front panel and extending within 24 inches of back panel. Provide two rows of lights to obtain 30 foot-candles at floor level regardless of any interior furnishings. |
| G. | Ceiling Access Panel: At general location shown on Drawings, provide flush-mounted ceiling access panel with hatch that opens into the cooler. |
2.4 EQUIPMENT IDENTIFICATION REQUIREMENTS
A. Provide labels identifying all walkins coolers and freezers, refrigeration equipment, and alarm devices.
2.5 AUTOPSY REFRIGERATOR SPECIAL ITEMS
| A. | Seven-day temperature recorder: Electric clock operated, wall mounted cabinet, mounted on or adjacent to the refrigerator approximately 1.5m (5'- 0") above the floor. |
| 1. | Sensing bulb: Remote type, mercury filled, located in refrigerators recommended by the manufacturer. |
| 2. | Charts: Approximately 200 mm (8inch) diameter with range of -18 to 38 degrees C (0 to 100 degrees F). Provide 100 charts, replacement pen and ink supply. |
| 3. | New Mortuary coolers provided in existing buildings shall be installed so that the finished floor levels of the refrigerators and the general floor levels are the same. This shall be accomplished by installing a prefabricated cooler enclosure, minus the installed enclosure floor, directly upon the floor slab. The enclosure perimeter shall be sealed against air and waste leakage. Insulation with vapor barrier will be placed below the existing floor slab by Others to avoid condensation. |
| B. | Exhaust ventilation provision: |
| 1. | Ceiling grille: 150 mm by 150 mm (6inch by 6inch), stainless steel, with 13 mm (1/2inch) bars at 45 degree angle to exhaust 50 CFM with make up air for exhaust through the open door. Provide stainless steel duct extension to six inches above the top of the ceiling panel. |
| 2. | Door switch: Mount switch in door frame and extend wiring to a junction box above the ceiling. The purpose of the switch is to activate an automatic exhaust damper when the door is open. |
| C. | No viewport required in entrance doors. |
2.6 monitoring alarm system:
| A. | Provide an electronic monitoring and alarm system for each section of each unit. |
| 1. | System Components: Detecting thermostat, master control panel, interconnecting wiring, remote audible alarm, and defrost compensator. Provide dials showing temperatures and pilot lights, warning lights, switches, transformer, and buzzer, all as a part of the master control panel. Locate master control panel and remote audible alarm as indicated on construction documents. Provide power fuse to protect system components. |
| 2. | System Operation: Set alarms at 5 degrees C (10 degrees F) above and below specified operating temperatures. |
| 3. | Communications: Electronic monitoring and alarm system must be compatible with Building Automation and Control Networks (BACnet) communication protocol. All points must be open for the VA to read and control parameters up to, and including, but not limited to, trending and status alarms, temperature settings, actual temperature, high temperature, and equipment status (on/off). The Ann Arbor Medical Facility uses Desigo, as manufactured by Siemens. |
| B. | Personnel Alarm: For each unit, provide separate audible alarm system operable from inside unit, for use of personnel unable to exit unit. Locate remote audible alarm where indicated on construction documents. |
2.6 EQUIPMENT IDENTIFICATION REQUIREMENTS:
A. Provide labels identifying all walkins coolers and freezers, refrigeration equipment, and alarm devices.
PART 3 EXECUTION
3.1 DELIVERY
A. Equipment shall be delivered to the interior space in which the equipment will be installed.
3.2 INSTALLATION:
A. Installation will be performed by Others.
PERIOD OF PERFORMANCE
Proposal must be provided within the timeframe indicated in the solicitation. Shop drawings must be provided within 21 days of the issuance of a Purchase Order.
6. SPECIAL REQUIREMENTS:
A. Site Inspections by the Equipment Vendor
Pre-Proposal Site Inspection: It is recommended that the Equipment Vendor shall inspect areas of buildings in which the equipment will be installed and the areas which are anticipated routes of access, noting the existing condition and types of doors, walls, and other surfaces that could pose an obstruction to delivery of the equipment throughout affected areas of buildings and noting any discrepancies between drawings and existing conditions at site.
Pre-Delivery Site Inspection: Thirty days before expected delivery date, the Equipment Vendor, Contractor and their mechanical and plumbing subcontractors, and Government must make a thorough re-survey of the areas of buildings involved to view the spaces that will receive the equipment, which is being built out by Others (the Contractor) and view the conditions under which the equipment will be installed (by Others). The Equipment Vendor shall note conditions of flooring, doors, walls, utility connections, clearances, laydown areas, and interferences as compared with conditions of same as noted herein and during the Pre-Proposal Site Inspection.
B. Physical Data
Data and information furnished or referred to herein is for the Equipment Vendor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Equipment Vendor. The Government does not guarantee that other materials will not be encountered nor that proportions, conditions or character of several materials will not vary from those indicated by explorations. Bidders are expected to examine site and, after investigation, decide for themselves character of materials and make their bids accordingly.
C. Operations and Storage Areas The VA cannot take early delivery or store the equipment because there is not adequate storage space. After award, the successful Equipment Vendor must coordinate with the Contractor for specific delivery times and locations within the timeframe listed above to ensure the Contractor and VA are ready to receive the equipment before it is delivered. The Contractor’s contact information will be provided to the successful Equipment Vendor after award.
Offloading of delivery vehicles must be performed immediately upon the vehicle parking at the loading dock, and the vehicle must be moved offsite immediately after offloading. Execute work to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. The Equipment Vendor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the COR.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .