This document provides clarification on an upcoming federal contract solicitation for HVAC upgrades at a Veterans Affairs medical center. The Department of Veterans Affairs intends to issue an invitation for bids around May 12, 2023 for HVAC upgrades in Phase II of Project 515-21-101 at its medical center in Battle Creek, Michigan. The estimated value of the firm fixed price contract is between $2 million and $5 million, with award intended within 120 days of bid opening. The work includes furnishing all labor, materials, equipment, and supervision specified in the drawings and specifications to complete the project. The North American Industry Classification Code is 238220 and it is reserved as a 100% set-aside for qualified Service-Disabled Veteran Owned Small Businesses. Offerors must be registered in the System for Award Management and Veteran Small Business Certification databases. Questions may be submitted to the specified contracting officer by email only.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| C08 Notice of Award email - Robbert Constr - 515-21-101.pdf | ||
| 515-21-101 Addendum 002.pdf | ||
| S06 515-21-101 Addendum 001.pdf | ||
| S06 36C25023B0045 0001 - 515-21-101.pdf | ||
| S06 Pre-Bid Site Visit Agenda - 515-21-101.pdf | ||
| S06 515-21-101 Addendum Dwgs.pdf | ||
| S06 02 82 11 - Traditional Asbestos Abatement.pdf | ||
| S06 Pre-bid attendance - 515-21-101.pdf | ||
| S06 01 35 26 - Safety Requirements.pdf | ||
| S02 Wage Determination - MI20230079 - 5-5-23 - Calhoun - 515-21-101.pdf | ||
| S02 Contractor EMR Certification Form - 515-21-101.docx | DOCX document | |
| S02 36C25023B0045_1 - 515-21-101.pdf | ||
| S02 Wage Determination - MI20230079 - 5-5-23 - Calhoun - 515-21-101.pdf | ||
| S02 Drawings - 515-21-101.pdf | ||
| S02 RFI Form - 515-21-101.doc | DOC document | |
| S02 Specifications - 515-21-101.pdf | ||
| 36C25023B0045.docx | DOCX document |
Show all 17
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36C25023B0045 0002 – HVAC Upgrades Phase II – 515-21-101 – VAMC Battle Creek, MI
5. PROJECT NUMBER (if applicable)
CODE 7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO. 1. CONTRACT ID CODE
FACILITY CODE CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30 PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243
(Type or print) (Type or print)
(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code)
(If other than Item 6)
(Specify type of modification and authority)
(such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer)
1 3
07-12-2023
515-23-3-155-0026
515-21-101
Department of Veterans Affairs Network Contracting Office (NCO) 10
5500 Armstrong Rd Battle Creek MI 49037
Same as Block 6
To all Offerors/Bidders
36C25023B0045
07-12-2023
X
X X
The purpose of the Amendment is to:
Provide answers to RFI questions and revisions to Drawings relating to mechanical systems, including duct static pressure sensors, concrete equipment pads/supports, OA dampers, and AHU capacities.
SCOTT D. BRENNAN
Contract Specialist
SF 30 CONTINUATION PAGE 36C25023B0045
AMENDMENT 0002
THE FOLLOWING ANSWERS TO REQUESTS FOR INFORMATION QUESTIONS ARE
HEREBY PROVIDED TO CLARIFY, UPDATE, REVISE, OR CORRECT CONTRACT
SPECIFICATIONS AND/OR DRAWINGS.
QUESTIONS AND ANSWERS
1. RFI #1 Question: On the drawings M702, M703 and M704, the AHU’s are shown having a duct static pressure sensor. The note next to them states “locate as shown on plans” but there doesn’t seems to be a location shown on the plans that I can see. Where are these to be located?
Answer 1: See attached addendum for clarification.
2. RFI #2 Question: On the drawings M703 and M704, these AHU’s are shown having a building differential static pressure sensor. The high-pressure reference states “Reference to room #” but there isn’t a location shown on the plans where the location is to reference. Where are these references to be located?
Answer 2: See attached addendum for clarification.
3. RFI #3 Question: In building 5 and 14 attics duct insulation. Would this call for
- flexible ductwrap insulation with FSK foil backing?
- Ridged board insulation with ASJ paper jacket?
- Ridged board FSK foil jacket?
Answer 3: Rigid board with ASJ per 23 07 11 (3.2)(A)(3).
4. RFI #4 Question: On the mechanical detail for building 5 and 14 note 7 says to put the unit on 6" rails will this leave enough room for the traps and drains? Also it not reflected in the total height of the unit.
Answer 4: See attached addendum for clarification.
5. RFI #5 Question: Building 83 ahu note 4 says to suspend from structure or a stand to keep 36" above floor but also has different a note to put on rails on M505?
Answer 5: The 6” base rail referenced on M505is for unit structural rigidity.
A.1 ADDITIONAL ATTACHMENTS
See attached document: 515-21-101 Addendum 002.
A.1 ADDITIONAL ATTACHMENTS