About this file

This pre-solicitation announcement is for the replacement of elevators in five buildings at the Veterans Administration Medical Center in Battle Creek, Michigan. The project scope includes removing existing elevators and installing new equipment. A 100% small business set-aside will be in place, requiring offers only from verified Service-Disabled Veteran Owned Small Businesses. The solicitation is expected to be released on June 3rd, 2022 via the SAM.gov website. The period of performance is 730 calendar days. The estimated value is between $1 million and $5 million. Questions must be submitted in writing to the named contracting specialist by the specified date.

View the file

Other files for this federal contract opportunity

Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Battle Creek

VAMC

Project#: 515-21-103

Project Title: Replace Elevators, Building 2, 7, 13, 39, 82

The Contractor shall furnish all labor, material, equipment, supervision, As-Built Documentation, and all other related information for Project 515-21-103, Replace Elevators, Buildings 2, 7, 13, 39, 82, at the VA Medical Center in Battle Creek, Michigan. This project includes work, but is not limited to, the contractor furnishing all labor, materials, equipment, management, supervision, tools and all other necessary resources to complete project 515-21-103, Replace Elevators, Buildings 2, 7, 13, 39, 82 as required by the specifications and drawings.

Re-keying Phase, Re-key all existing fire fighter’s Service for elevators in Buildings: 5, 14, 22, 83, 84, 200 and elevator #2 in Building’s 39 & 82.

The contractor will receive a total of 730 days to complete the work.